Georgia Power Company; Notice of Intent to Prepare an Environmental Assessment, 49819 [2022-17366]
Download as PDF
Federal Register / Vol. 87, No. 155 / Friday, August 12, 2022 / Notices
Issue Acceptance Letter—December
2022
Issue Scoping Document 1 for
comments—January 2023
Request Additional Information (if
necessary)—February 2023
Issue Scoping Document 2—March 2023
Issue Notice of Ready for Environmental
Analysis—April 2023
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: August 8, 2022.
Kimberly D. Bose,
Secretary.
Milestone
Target date
Commission issues EA ...............
Comments on EA ........................
January 2023 1.
February 2023.
Any questions regarding this notice
may be directed to Navreet Deo at (202)
502–6304, or navreet.deo@ferc.gov.
Dated: August 8, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–17366 Filed 8–11–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[FR Doc. 2022–17367 Filed 8–11–22; 8:45 am]
BILLING CODE 6717–01–P
Combined Notice of Filings #1
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2336–094]
jspears on DSK121TN23PROD with NOTICES
Georgia Power Company; Notice of
Intent to Prepare an Environmental
Assessment
On January 3, 2022, Georgia Power
filed an application for a new, major
license for the 18-megawatt Lloyd
Shoals Hydroelectric Project (Lloyd
Shoals Project; FERC No. 2336). The
Lloyd Shoals Project is located on the
Ocmulgee River in Butts, Henry, Jasper,
and Newton Counties, Georgia. The
project does not occupy federal lands.
In accordance with the Commission’s
regulations, on May 26, 2022,
Commission staff issued a notice that
the project was ready for environmental
analysis (REA Notice). Based on the
information in the record, including
comments filed on the REA Notice, staff
does not anticipate that licensing the
project would constitute a major federal
action significantly affecting the quality
of the human environment. Therefore,
staff intends to prepare an
Environmental Assessment (EA) on the
application to relicense the Lloyd
Shoals Project.
The EA will be issued and circulated
for review by all interested parties. All
comments filed on the EA will be
analyzed by Commission staff and
considered in the Commission’s final
licensing decision.
The application will be processed
according to the following schedule.
Revisions to the schedule may be made
as appropriate.
VerDate Sep<11>2014
17:38 Aug 11, 2022
Jkt 256001
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2394–007;
ER10–2395–007; ER11–3642–021.
Applicants: Tanner Street Generation,
LLC, Colorado Power Partners, BIV
Generation Company, L.L.C.
Description: Notice of Change in
Status of BIV Generation Company,
L.L.C., et al.
Filed Date: 8/8/22.
Accession Number: 20220808–5034.
Comment Date: 5 p.m. ET 8/29/22.
Docket Numbers: ER11–4666–005;
ER11–4667–005; ER11–4670–010;
ER12–295–004; ER13–1368–002.
Applicants: NaturEner Wind Watch,
LLC, NaturEner Rim Rock Wind Energy,
LLC, NaturEner Power Watch, LLC,
NaturEner Glacier Wind Energy 2, LLC,
NaturEner Glacier Wind Energy 1, LLC.
Description: Notice of Non-Material
Change in Status of NaturEner Glacier
Wind Energy 1, LLC, et al.
Filed Date: 8/2/22.
Accession Number: 20220802–5180.
Comment Date: 5 p.m. ET 8/23/22.
Docket Numbers: ER22–2618–000.
Applicants: BIV Generation Company,
L.L.C.
Description: § 205(d) Rate Filing:
Market-Based Rate Tariff Revisions to be
effective 8/9/2022.
Filed Date: 8/8/22.
Accession Number: 20220808–5018.
Comment Date: 5 p.m. ET 8/29/22.
1 The Council on Environmental Quality’s (CEQ)
regulations under 40 CFR 1501.10(b)(1) require that
EAs be completed within 1 year of the federal
action agency’s decision to prepare an EA. This
notice establishes the Commission’s intent to
prepare an EA for the Lloyd Shoals Project.
Therefore, in accordance with CEQ’s regulations,
the EA must be issued within 1 year of the issuance
date of this notice.
PO 00000
Frm 00021
Fmt 4703
Sfmt 9990
49819
Docket Numbers: ER22–2619–000.
Applicants: Colorado Power Partners.
Description: § 205(d) Rate Filing:
Market-Based Rate Tariff Revisions to be
effective 8/9/2022.
Filed Date: 8/8/22.
Accession Number: 20220808–5019.
Comment Date: 5 p.m. ET 8/29/22.
Docket Numbers: ER22–2620–000.
Applicants: Avista Corporation.
Description: § 205(d) Rate Filing:
Avista Corp Engineering Service
Agreement RS T1180 to be effective 9/
7/2022.
Filed Date: 8/8/22.
Accession Number: 20220808–5064.
Comment Date: 5 p.m. ET 8/29/22.
Docket Numbers: ER22–2621–000.
Applicants: Tri-State Generation and
Transmission Association, Inc.
Description: § 205(d) Rate Filing:
Amendment to Tri-State WAPA–RMR
Balancing Authority Service Agreement
to be effective 7/7/2022.
Filed Date: 8/8/22.
Accession Number: 20220808–5112.
Comment Date: 5 p.m. ET 8/29/22.
Docket Numbers: ER22–2622–000.
Applicants: Chaparral Springs, LLC.
Description: Baseline eTariff Filing:
Market-Based Rate Application to be
effective 10/8/2022.
Filed Date: 8/8/22.
Accession Number: 20220808–5125.
Comment Date: 5 p.m. ET 8/29/22.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: August 8, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022–17353 Filed 8–11–22; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\12AUN1.SGM
12AUN1
Agencies
[Federal Register Volume 87, Number 155 (Friday, August 12, 2022)]
[Notices]
[Page 49819]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-17366]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2336-094]
Georgia Power Company; Notice of Intent to Prepare an
Environmental Assessment
On January 3, 2022, Georgia Power filed an application for a new,
major license for the 18-megawatt Lloyd Shoals Hydroelectric Project
(Lloyd Shoals Project; FERC No. 2336). The Lloyd Shoals Project is
located on the Ocmulgee River in Butts, Henry, Jasper, and Newton
Counties, Georgia. The project does not occupy federal lands.
In accordance with the Commission's regulations, on May 26, 2022,
Commission staff issued a notice that the project was ready for
environmental analysis (REA Notice). Based on the information in the
record, including comments filed on the REA Notice, staff does not
anticipate that licensing the project would constitute a major federal
action significantly affecting the quality of the human environment.
Therefore, staff intends to prepare an Environmental Assessment (EA) on
the application to relicense the Lloyd Shoals Project.
The EA will be issued and circulated for review by all interested
parties. All comments filed on the EA will be analyzed by Commission
staff and considered in the Commission's final licensing decision.
The application will be processed according to the following
schedule. Revisions to the schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Commission issues EA.................... January 2023 \1\.
Comments on EA.......................... February 2023.
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Navreet Deo
at (202) 502-6304, or [email protected].
---------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1
year of the federal action agency's decision to prepare an EA. This
notice establishes the Commission's intent to prepare an EA for the
Lloyd Shoals Project. Therefore, in accordance with CEQ's
regulations, the EA must be issued within 1 year of the issuance
date of this notice.
Dated: August 8, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-17366 Filed 8-11-22; 8:45 am]
BILLING CODE 6717-01-P