Georgia Power Company; Notice of Intent to Prepare an Environmental Assessment, 49819 [2022-17366]

Download as PDF Federal Register / Vol. 87, No. 155 / Friday, August 12, 2022 / Notices Issue Acceptance Letter—December 2022 Issue Scoping Document 1 for comments—January 2023 Request Additional Information (if necessary)—February 2023 Issue Scoping Document 2—March 2023 Issue Notice of Ready for Environmental Analysis—April 2023 Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: August 8, 2022. Kimberly D. Bose, Secretary. Milestone Target date Commission issues EA ............... Comments on EA ........................ January 2023 1. February 2023. Any questions regarding this notice may be directed to Navreet Deo at (202) 502–6304, or navreet.deo@ferc.gov. Dated: August 8, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–17366 Filed 8–11–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [FR Doc. 2022–17367 Filed 8–11–22; 8:45 am] BILLING CODE 6717–01–P Combined Notice of Filings #1 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2336–094] jspears on DSK121TN23PROD with NOTICES Georgia Power Company; Notice of Intent to Prepare an Environmental Assessment On January 3, 2022, Georgia Power filed an application for a new, major license for the 18-megawatt Lloyd Shoals Hydroelectric Project (Lloyd Shoals Project; FERC No. 2336). The Lloyd Shoals Project is located on the Ocmulgee River in Butts, Henry, Jasper, and Newton Counties, Georgia. The project does not occupy federal lands. In accordance with the Commission’s regulations, on May 26, 2022, Commission staff issued a notice that the project was ready for environmental analysis (REA Notice). Based on the information in the record, including comments filed on the REA Notice, staff does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to relicense the Lloyd Shoals Project. The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by Commission staff and considered in the Commission’s final licensing decision. The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate. VerDate Sep<11>2014 17:38 Aug 11, 2022 Jkt 256001 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–2394–007; ER10–2395–007; ER11–3642–021. Applicants: Tanner Street Generation, LLC, Colorado Power Partners, BIV Generation Company, L.L.C. Description: Notice of Change in Status of BIV Generation Company, L.L.C., et al. Filed Date: 8/8/22. Accession Number: 20220808–5034. Comment Date: 5 p.m. ET 8/29/22. Docket Numbers: ER11–4666–005; ER11–4667–005; ER11–4670–010; ER12–295–004; ER13–1368–002. Applicants: NaturEner Wind Watch, LLC, NaturEner Rim Rock Wind Energy, LLC, NaturEner Power Watch, LLC, NaturEner Glacier Wind Energy 2, LLC, NaturEner Glacier Wind Energy 1, LLC. Description: Notice of Non-Material Change in Status of NaturEner Glacier Wind Energy 1, LLC, et al. Filed Date: 8/2/22. Accession Number: 20220802–5180. Comment Date: 5 p.m. ET 8/23/22. Docket Numbers: ER22–2618–000. Applicants: BIV Generation Company, L.L.C. Description: § 205(d) Rate Filing: Market-Based Rate Tariff Revisions to be effective 8/9/2022. Filed Date: 8/8/22. Accession Number: 20220808–5018. Comment Date: 5 p.m. ET 8/29/22. 1 The Council on Environmental Quality’s (CEQ) regulations under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 year of the federal action agency’s decision to prepare an EA. This notice establishes the Commission’s intent to prepare an EA for the Lloyd Shoals Project. Therefore, in accordance with CEQ’s regulations, the EA must be issued within 1 year of the issuance date of this notice. PO 00000 Frm 00021 Fmt 4703 Sfmt 9990 49819 Docket Numbers: ER22–2619–000. Applicants: Colorado Power Partners. Description: § 205(d) Rate Filing: Market-Based Rate Tariff Revisions to be effective 8/9/2022. Filed Date: 8/8/22. Accession Number: 20220808–5019. Comment Date: 5 p.m. ET 8/29/22. Docket Numbers: ER22–2620–000. Applicants: Avista Corporation. Description: § 205(d) Rate Filing: Avista Corp Engineering Service Agreement RS T1180 to be effective 9/ 7/2022. Filed Date: 8/8/22. Accession Number: 20220808–5064. Comment Date: 5 p.m. ET 8/29/22. Docket Numbers: ER22–2621–000. Applicants: Tri-State Generation and Transmission Association, Inc. Description: § 205(d) Rate Filing: Amendment to Tri-State WAPA–RMR Balancing Authority Service Agreement to be effective 7/7/2022. Filed Date: 8/8/22. Accession Number: 20220808–5112. Comment Date: 5 p.m. ET 8/29/22. Docket Numbers: ER22–2622–000. Applicants: Chaparral Springs, LLC. Description: Baseline eTariff Filing: Market-Based Rate Application to be effective 10/8/2022. Filed Date: 8/8/22. Accession Number: 20220808–5125. Comment Date: 5 p.m. ET 8/29/22. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: August 8, 2022. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2022–17353 Filed 8–11–22; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\12AUN1.SGM 12AUN1

Agencies

[Federal Register Volume 87, Number 155 (Friday, August 12, 2022)]
[Notices]
[Page 49819]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-17366]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2336-094]


Georgia Power Company; Notice of Intent to Prepare an 
Environmental Assessment

    On January 3, 2022, Georgia Power filed an application for a new, 
major license for the 18-megawatt Lloyd Shoals Hydroelectric Project 
(Lloyd Shoals Project; FERC No. 2336). The Lloyd Shoals Project is 
located on the Ocmulgee River in Butts, Henry, Jasper, and Newton 
Counties, Georgia. The project does not occupy federal lands.
    In accordance with the Commission's regulations, on May 26, 2022, 
Commission staff issued a notice that the project was ready for 
environmental analysis (REA Notice). Based on the information in the 
record, including comments filed on the REA Notice, staff does not 
anticipate that licensing the project would constitute a major federal 
action significantly affecting the quality of the human environment. 
Therefore, staff intends to prepare an Environmental Assessment (EA) on 
the application to relicense the Lloyd Shoals Project.
    The EA will be issued and circulated for review by all interested 
parties. All comments filed on the EA will be analyzed by Commission 
staff and considered in the Commission's final licensing decision.
    The application will be processed according to the following 
schedule. Revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
                Milestone                           Target date
------------------------------------------------------------------------
Commission issues EA....................  January 2023 \1\.
Comments on EA..........................  February 2023.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Navreet Deo 
at (202) 502-6304, or [email protected].
---------------------------------------------------------------------------

    \1\ The Council on Environmental Quality's (CEQ) regulations 
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 
year of the federal action agency's decision to prepare an EA. This 
notice establishes the Commission's intent to prepare an EA for the 
Lloyd Shoals Project. Therefore, in accordance with CEQ's 
regulations, the EA must be issued within 1 year of the issuance 
date of this notice.

    Dated: August 8, 2022.
Kimberly D. Bose,
Secretary.