Great River Hydro, LLC; Notice of Settlement Agreement and Soliciting Comments, 48657-48658 [2022-17152]

Download as PDF khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 87, No. 153 / Wednesday, August 10, 2022 / Notices i. FERC Contact: Jeremy Jessup, (202) 502–6779, Jeremy.Jessup@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: September 2, 2022. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include the docket number P–1218–050. Comments emailed to Commission staff are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: The applicant proposes a temporary variance from the target water surface elevation requirements of Article 401 of the license (181.8 ± 0.5 feet Plant Datum which is 0.37 foot above mean sea level) to facilitate a scheduled a drawdown of the project impoundment, Lake Worth. The purpose of the drawdown is to provide for installation of new shoreline structures and maintenance of existing shoreline structures. The licensee will lower Lake Worth approximately 3.5 feet from the lower limit of the normal target elevation range, 181.3 feet, to an elevation of 177.8 ± 0.5 feet. The drawdown is scheduled to begin on September 27, 2022, and the licensee VerDate Sep<11>2014 17:26 Aug 09, 2022 Jkt 256001 proposes to utilize a drawdown rate of one half-foot per day. The licensee anticipates reaching the target drawdown elevation of 177.8 feet on October 3, 2022 and remain at the target drawdown elevation for four weeks. The licensee plans to begin refilling Lake Worth on November 1, 2022. The licensee states that the completion of refilling the reservoir would be dependent on precipitation and the releases from the upstream Lake Blackshear Hydroelectric Project No. 659. The licensee will continue to operate to comply with Article 401 runof-river operations requirement when it reaches the target drawdown elevation of 177.8 feet. l. Locations of the Application: This filing may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 48657 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: August 3, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–17128 Filed 8–9–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 1892–030; Project No. 1855– 050; Project No. 1904–078] Great River Hydro, LLC; Notice of Settlement Agreement and Soliciting Comments Take notice that the following settlement agreement has been filed with the Commission and is available for public inspection. a. Type of Application: Settlement Agreement. b. Project Nos.: 1892–030, 1855–050, and 1904–078. c. Date filed: August 3, 2022. d. Applicant: Great River Hydro, LLC (Great River). e. Name of Projects: Wilder Hydroelectric Project, Bellows Falls Hydroelectric Project, and Vernon Hydroelectric Project (collectively, projects). f. Location: The existing projects are located on the Connecticut River in the counties of Orange, Windham, and Windsor, Vermont and Sullivan, Cheshire, and Grafton, New Hampshire. The projects do not affect federal land. g. Filed Pursuant to: Rule 602 of the Commission’s Rules of Practice and Procedure, 18 CFR 385.602. h. Applicant Contact: John Ragonese, FERC License Manager, Great River Hydro, LLC, 40 Pleasant Street, Suite 202, Portsmouth, NH 03801; (603) 498– 2851 or jragonese@greatriverhydro.com. i. FERC Contact: Steve Kartalia, (202) 502–6131 or stephen.kartalia@ferc.gov. j. Deadline for filing comments: September 2, 2022. Reply comments due September 17, 2022. The Commission strongly encourages electronic filing. Please file comments using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, E:\FR\FM\10AUN1.SGM 10AUN1 khammond on DSKJM1Z7X2PROD with NOTICES 48658 Federal Register / Vol. 87, No. 153 / Wednesday, August 10, 2022 / Notices without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket numbers P–1892–030, P–1855–050, and P–1904–078. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Great River filed the Settlement Agreement on behalf of itself, the U.S. Fish and Wildlife Service, the New Hampshire Fish and Game Department, and the Vermont Fish and Wildlife Department. The purpose of the Settlement Agreement is to resolve, among the signatories, issues related to fish passage associated with the issuance of any new licenses and fishway prescriptions under Section 18 of the FPA for the projects. Specifically, the Settlement Agreement includes proposed upstream and downstream fish passage facilities, fish passage studies, and fish passage operational measures. Great River requests that the Commission consider the Settlement Agreement in its environmental analyses of the proposed relicense applications, and incorporate the proposed measures into any new licenses issued. l. A copy of the settlement agreement may be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits, in the docket number field to access the document (i.e., P–1892, P–1855, and P– 1904). At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the VerDate Sep<11>2014 17:26 Aug 09, 2022 Jkt 256001 proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC Online Support. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Filed Date: 8/3/22. Accession Number: 20220803–5037. Comment Date: 5 p.m. ET 8/15/22. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. Dated: August 4, 2022. Kimberly D. Bose, Secretary. Filings in Existing Proceedings [FR Doc. 2022–17152 Filed 8–9–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP22–1102–000. Applicants: MOGAS PIPELINE LLC. Description: Annual Report on Revenue from Penalties Subject to Crediting of MoGas Pipeline LLC. Filed Date: 7/29/22. Accession Number: 20220729–5395. Comment Date: 5 p.m. ET 8/10/22. Docket Numbers: RP22–1105–000. Applicants: Anadarko US Offshore LLC, Murphy Exploration & Production Company—USA, Eni Petroleum US LLC, INPEX Americas, Inc. Description: Joint Petition for Temporary Waiver of Capacity Release Regulations, et al. of Anadarko US Offshore LLC, et al. Filed Date: 7/29/22. Accession Number: 20220729–5398. Comment Date: 5 p.m. ET 8/10/22. Docket Numbers: RP22–1106–000. Applicants: East Tennessee Natural Gas, LLC. Description: § 4(d) Rate Filing: MAD Service Charge and Action Alert Penalty Filing to be effective 10/1/2022, Filed Date: 8/3/22. Accession Number: 20220803–5015. Comment Date: 5 p.m. ET 8/15/22. Docket Numbers: RP22–1107–000. Applicants: El Paso Natural Gas Company, L.L.C. Description: § 4(d) Rate Filing: Negotiated Rate Agreement Update (SoCal August 2022) to be effective 8/3/ 2022. PO 00000 Frm 00040 Fmt 4703 Sfmt 4703 Docket Numbers: RP21–993–000. Applicants: Cove Point LNG, LP. Description: Report Filing: Cove Point—2022 Report of Operational Sales and Purchases of Gas to be effective N/ A. Filed Date: 7/29/22. Accession Number: 20220729–5055. Comment Date: 5 p.m. ET 8/10/22. Any person desiring to protest in any the above proceedings must file in accordance with Rule 211 of the Commission’s Regulations (18 CFR 385.211) on or before 5:00 p.m. Eastern time on the specified comment date. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: August 4, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–17149 Filed 8–9–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 298–083] Southern California Edison Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Temporary variance of license flow requirements. b. Project No.: 298–083. E:\FR\FM\10AUN1.SGM 10AUN1

Agencies

[Federal Register Volume 87, Number 153 (Wednesday, August 10, 2022)]
[Notices]
[Pages 48657-48658]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-17152]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 1892-030; Project No. 1855-050; Project No. 1904-078]


Great River Hydro, LLC; Notice of Settlement Agreement and 
Soliciting Comments

    Take notice that the following settlement agreement has been filed 
with the Commission and is available for public inspection.
    a. Type of Application: Settlement Agreement.
    b. Project Nos.: 1892-030, 1855-050, and 1904-078.
    c. Date filed: August 3, 2022.
    d. Applicant: Great River Hydro, LLC (Great River).
    e. Name of Projects: Wilder Hydroelectric Project, Bellows Falls 
Hydroelectric Project, and Vernon Hydroelectric Project (collectively, 
projects).
    f. Location: The existing projects are located on the Connecticut 
River in the counties of Orange, Windham, and Windsor, Vermont and 
Sullivan, Cheshire, and Grafton, New Hampshire. The projects do not 
affect federal land.
    g. Filed Pursuant to: Rule 602 of the Commission's Rules of 
Practice and Procedure, 18 CFR 385.602.
    h. Applicant Contact: John Ragonese, FERC License Manager, Great 
River Hydro, LLC, 40 Pleasant Street, Suite 202, Portsmouth, NH 03801; 
(603) 498-2851 or [email protected].
    i. FERC Contact: Steve Kartalia, (202) 502-6131 or 
[email protected].
    j. Deadline for filing comments: September 2, 2022. Reply comments 
due September 17, 2022.
    The Commission strongly encourages electronic filing. Please file 
comments using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 
6,000 characters,

[[Page 48658]]

without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and 
contact information at the end of your comments. For assistance, please 
contact FERC Online Support at [email protected], (866) 208-
3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic 
filing, you may submit a paper copy. Submissions sent via the U.S. 
Postal Service must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, 
Washington, DC 20426. Submissions sent via any other carrier must be 
addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first 
page of any filing should include docket numbers P-1892-030, P-1855-
050, and P-1904-078.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. Great River filed the Settlement Agreement on behalf of itself, 
the U.S. Fish and Wildlife Service, the New Hampshire Fish and Game 
Department, and the Vermont Fish and Wildlife Department. The purpose 
of the Settlement Agreement is to resolve, among the signatories, 
issues related to fish passage associated with the issuance of any new 
licenses and fishway prescriptions under Section 18 of the FPA for the 
projects. Specifically, the Settlement Agreement includes proposed 
upstream and downstream fish passage facilities, fish passage studies, 
and fish passage operational measures. Great River requests that the 
Commission consider the Settlement Agreement in its environmental 
analyses of the proposed relicense applications, and incorporate the 
proposed measures into any new licenses issued.
    l. A copy of the settlement agreement may be viewed on the 
Commission's website at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number, excluding the last three digits, in the 
docket number field to access the document (i.e., P-1892, P-1855, and 
P-1904). At this time, the Commission has suspended access to the 
Commission's Public Reference Room, due to the proclamation declaring a 
National Emergency concerning the Novel Coronavirus Disease (COVID-19), 
issued by the President on March 13, 2020. For assistance, contact FERC 
Online Support.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.

    Dated: August 4, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-17152 Filed 8-9-22; 8:45 am]
BILLING CODE 6717-01-P