Eagle Creek Reusens Hydro, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 15236-15237 [2022-05580]
Download as PDF
15236
Federal Register / Vol. 87, No. 52 / Thursday, March 17, 2022 / Notices
Title: FERC–1000, Request for a
Medical Exception to the COVID–19
Vaccination Requirement.
OMB Control No.: 1902–0320.
Abstract: The purpose of this threeyear renewal of the information
collection is to allow the Federal Energy
Regulatory Commission to collect
information from FERC employees (and
their medical providers) applying for a
medical exception to the COVID–19
Vaccination Requirement as specified in
Part 2 of FERC Form No. 1000.1
Consistent with guidance from the
Centers for Disease Control and
Prevention (CDC), guidance from the
Safer Federal Workforce Task Force
established pursuant to Executive Order
13991 of January 20, 2021, Protecting
the Federal Workforce and Requiring
Mask-Wearing, and Executive Order
14043 of September 9, 2021, Requiring
Coronavirus Disease 2019 Vaccination
for Federal Employees, the request for
this information collection is essential
to implement the Commission’s health
and safety measures regarding the
federal employee medical exceptions to
the COVID–19 mandatory vaccinations.
In addition, the Rehabilitation Act of
1973, as amended, requires Federal
Agencies to provide reasonable
accommodations to qualified employees
with disabilities unless that reasonable
accommodation would impose an
undue hardship on the employee’s
Agency. See 29 U.S.C. 791 and 29 CFR
part 1614; see also 20 CFR part 1630 and
Executive Order 13164 of July 26, 2000,
Requiring Federal Agencies to Establish
Procedures to Facilitate the Provision of
Reasonable Accommodation. Section 2
of E.O. 14043 mandates that each
agency, ‘‘implement, to the extent
consistent with applicable law, a
program to require COVID–19
vaccination for all of its Federal
employees, with exceptions only as
required by law.’’ This medical
exception form (FERC Form No. 1000) is
necessary for the Commission to
determine whether to grant medical
exceptions to the vaccine requirement
under the Rehabilitation Act.
The information being requested
helps promote the safety of the Federal
workforce, Federal buildings, and others
on site at FERC facilities. This collection
is consistent with the COVID–19
Workplace Safety Agency Model Safety
Principles established by the White
House Safer Federal Workforce Task
Force and guidance from the Centers for
Disease Control and Prevention.
Type of Respondent: Medical
Providers.
Estimate of Annual Burden: 2 The
Commission estimates the annual public
reporting burden for the information
collection as:
FERC–1000: REQUEST FOR A MEDICAL EXCEPTION TO THE COVID–19 VACCINATION REQUIREMENT
Number of
respondents
Annual
number of
responses per
respondent
Total
number of
responses
Average
burden &
cost per
response 3
Total annual
burden hours &
total annual cost
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
khammond on DSKJM1Z7X2PROD with NOTICES
Medical Provider ...............
24
1
24
30 minutes (1⁄2 hour); $72 ..
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: March 11, 2022.
Kimberly D. Bose,
Secretary.
1 The vaccination requirement issued pursuant to
E.O. 14043, is currently the subject of a nationwide
injunction. While that injunction remains in place,
the Federal Energy Regulatory Commission (FERC)
will not process requests for a medical exception
from the COVID–19 vaccination requirement
pursuant to E.O. 14043. FERC will also not request
the submission of any medical information related
to a request for an exception from the vaccination
requirement pursuant to E.O. 14043 while the
injunction remains in place. But FERC may
nevertheless receive information regarding a
medical exception. That is because, if FERC were
to receive a request for an exception from the
COVID–19 vaccination requirement pursuant to
E.O. 14043 during the pendency of the injunction,
FERC will accept the request, hold it in abeyance,
and notify the employee who submitted the request
that implementation and enforcement of the
COVID–19 vaccination requirement pursuant to
E.O. 14043 is currently enjoined and that an
exception therefore is not necessary so long as the
injunction is in place. In other words, during the
pendency of the injunction, any information
collection related to requests for medical exception
from the COVID–19 vaccination requirement
pursuant to E.O. 14043 is not undertaken to
implement or enforce the COVID–19 vaccination
requirement.
VerDate Sep<11>2014
17:38 Mar 16, 2022
Jkt 256001
720 minutes (12 hours); $1,728.
DEPARTMENT OF ENERGY
[FR Doc. 2022–05641 Filed 3–16–22; 8:45 am]
Federal Energy Regulatory
Commission
[Project No. P–2376–052]
BILLING CODE 6717–01–P
Eagle Creek Reusens Hydro, LLC;
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
and Establishing Procedural Schedule
for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
2 ‘‘Burden’’ is the total time, effort, or financial
resources expended by persons to generate,
maintain, retain, or disclose or provide information
to or for a Federal agency. For further explanation
of what is included in the information collection
burden, refer to Title 5 Code of Federal Regulations
1320.3.
3 Cost estimates are based on industry costs for
general internal medicine physicians (29–1216)
defined by the Bureau of Labor Statistics. The cost
figure for the general internal medicine physicians
in 2021 was an average annual salary plus benefits
of $300,076/year or $144/hour.
E:\FR\FM\17MRN1.SGM
17MRN1
khammond on DSKJM1Z7X2PROD with NOTICES
Federal Register / Vol. 87, No. 52 / Thursday, March 17, 2022 / Notices
b. Project No.: 2376–052.
c. Date Filed: February 28, 2022.
d. Applicant: Eagle Creek Reusens
Hydro, LLC (Reusens Hydro).
e. Name of Project: Reusens
Hydroelectric Project (Reusens Project).
f. Location: The project is located on
the James River in Bedford and Amherst
Counties, Virginia. The project does not
occupy any federal land.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contacts: Ms. Joyce
Foster, Director, Licensing and
Compliance Eagle Creek Renewable
Energy, LLC, 7315 Wisconsin Avenue,
Suite 1100W, Bethesda, MD 20814;
Phone at (804) 338–5110 or email at
Joyce.Foster@eaglecreekre.co; and Ms.
Jody Smet, Vice President, Regulatory
Affairs, Eagle Creek Renewable Energy,
LLC, 7315 Wisconsin Ave., Suite
1100W, Bethesda, MD 20814; Phone at
(240) 482–2700 or email at jody.smet@
eaglecreekre.com.
i. FERC Contact: Laurie Bauer at (202)
502–6519, or laurie.bauer@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: April 29, 2022.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
VerDate Sep<11>2014
17:38 Mar 16, 2022
Jkt 256001
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. All filings must clearly identify
the project name and docket number on
the first page: Reusens Project (P–2376–
052).
m. This application is not ready for
environmental analysis at this time.
n. The Reusens Project consists of: (1)
A 24-foot-high, 416-foot-long concrete
dam and spillway containing eight
16.75-foot-high, 44-foot-wide floodgates;
(2) a 25-foot-high concrete curved
auxiliary spillway; (3) a 500-acre
impoundment with a gross storage
capacity of 6,869 acre-feet at the normal
pool elevation of 550.7 feet National
Geodetic Vertical Datum of 1929; (4) an
intake sction of Powerhouse A
containing three 6.83-foot-wide, 17.92foot-high steel, concrete, and timber
gates and Powerhouse B containing two
6.67-foot-wide, 17.5-foot-high timber
gates; (5) a 105.5-foot-long, 83-footwide, 86-foot-high steel frame, concrete
and brick Powerhouse A containing
three vertical Francis turbine-generator
units with a total installed capacity of
7.5 megawatts (MW); (5) a 55-foot-long,
27-foot-wide, 84-foot-high steel frame,
concrete and brick Powerhouse B
containing two vertical Francis turbinegenerator units with a total installed
capacity of 5 MW; (6) a 100-foot-wide,
250-foot-long tailrace below
Powerhouse A; (7) a 60-foot-wide, 50foot-long tailrace below Powerhouse B;
(8) a 280-foot-long transmission line to
three 5,210 kilovolt-ampere 4/34.5
kilovolt step-up transformers which are
connected to the grid via a 24-foot-long
overhead line; and (9) appurtenant
facilities.
The Reusens Project operates in a
peaking mode with an average annual
generation of 22,504 megawatt-hours
between 2018 and 2021.
o. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov, using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field, to access the
document (P–2376). For assistance,
contact FERC at FERCOnlineSupport@
ferc.gov, or call toll-free, (866) 208–3676
or (202) 502–8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
PO 00000
Frm 00047
Fmt 4703
Sfmt 4703
15237
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Issue Deficiency Letter (if necessary)—
April 2022
Request Additional Information—April
2022
Issue Acceptance Letter—July 2022
Issue Scoping Document 1 for
comments—August 2022
Request Additional Information (if
necessary)—September 2022
Issue Scoping Document 2—November
2022
Issue Notice of Ready for Environmental
Analysis—November 2022
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: March 10, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022–05580 Filed 3–16–22; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OPPT–2022–0132; FRL–9411–04–
OSCPP]
Certain New Chemicals; Receipt and
Status Information for February 2022
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
EPA is required under the
Toxic Substances Control Act (TSCA),
as amended by the Frank R. Lautenberg
Chemical Safety for the 21st Century
Act, to make information publicly
available and to publish information in
the Federal Register pertaining to
submissions under TSCA Section 5,
including notice of receipt of a
Premanufacture notice (PMN),
Significant New Use Notice (SNUN) or
Microbial Commercial Activity Notice
(MCAN), including an amended notice
or test information; an exemption
application (Biotech exemption); an
application for a test marketing
exemption (TME), both pending and/or
concluded; a notice of commencement
(NOC) of manufacture (including
import) for new chemical substances;
and a periodic status report on new
chemical substances that are currently
under EPA review or have recently
SUMMARY:
E:\FR\FM\17MRN1.SGM
17MRN1
Agencies
[Federal Register Volume 87, Number 52 (Thursday, March 17, 2022)]
[Notices]
[Pages 15236-15237]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-05580]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. P-2376-052]
Eagle Creek Reusens Hydro, LLC; Notice of Application Tendered
for Filing With the Commission and Soliciting Additional Study Requests
and Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
[[Page 15237]]
b. Project No.: 2376-052.
c. Date Filed: February 28, 2022.
d. Applicant: Eagle Creek Reusens Hydro, LLC (Reusens Hydro).
e. Name of Project: Reusens Hydroelectric Project (Reusens
Project).
f. Location: The project is located on the James River in Bedford
and Amherst Counties, Virginia. The project does not occupy any federal
land.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contacts: Ms. Joyce Foster, Director, Licensing and
Compliance Eagle Creek Renewable Energy, LLC, 7315 Wisconsin Avenue,
Suite 1100W, Bethesda, MD 20814; Phone at (804) 338-5110 or email at
[email protected]; and Ms. Jody Smet, Vice President,
Regulatory Affairs, Eagle Creek Renewable Energy, LLC, 7315 Wisconsin
Ave., Suite 1100W, Bethesda, MD 20814; Phone at (240) 482-2700 or email
at [email protected].
i. FERC Contact: Laurie Bauer at (202) 502-6519, or
[email protected].
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: April 29, 2022.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at [email protected], (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, you may submit a paper
copy. Submissions sent via the U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent
via any other carrier must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. All filings must clearly identify the
project name and docket number on the first page: Reusens Project (P-
2376-052).
m. This application is not ready for environmental analysis at this
time.
n. The Reusens Project consists of: (1) A 24-foot-high, 416-foot-
long concrete dam and spillway containing eight 16.75-foot-high, 44-
foot-wide floodgates; (2) a 25-foot-high concrete curved auxiliary
spillway; (3) a 500-acre impoundment with a gross storage capacity of
6,869 acre-feet at the normal pool elevation of 550.7 feet National
Geodetic Vertical Datum of 1929; (4) an intake sction of Powerhouse A
containing three 6.83-foot-wide, 17.92-foot-high steel, concrete, and
timber gates and Powerhouse B containing two 6.67-foot-wide, 17.5-foot-
high timber gates; (5) a 105.5-foot-long, 83-foot-wide, 86-foot-high
steel frame, concrete and brick Powerhouse A containing three vertical
Francis turbine-generator units with a total installed capacity of 7.5
megawatts (MW); (5) a 55-foot-long, 27-foot-wide, 84-foot-high steel
frame, concrete and brick Powerhouse B containing two vertical Francis
turbine-generator units with a total installed capacity of 5 MW; (6) a
100-foot-wide, 250-foot-long tailrace below Powerhouse A; (7) a 60-
foot-wide, 50-foot-long tailrace below Powerhouse B; (8) a 280-foot-
long transmission line to three 5,210 kilovolt-ampere 4/34.5 kilovolt
step-up transformers which are connected to the grid via a 24-foot-long
overhead line; and (9) appurtenant facilities.
The Reusens Project operates in a peaking mode with an average
annual generation of 22,504 megawatt-hours between 2018 and 2021.
o. A copy of the application can be viewed on the Commission's
website at https://www.ferc.gov, using the ``eLibrary'' link. Enter the
docket number, excluding the last three digits in the docket number
field, to access the document (P-2376). For assistance, contact FERC at
[email protected], or call toll-free, (866) 208-3676 or (202)
502-8659 (TTY).
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate.
Issue Deficiency Letter (if necessary)--April 2022
Request Additional Information--April 2022
Issue Acceptance Letter--July 2022
Issue Scoping Document 1 for comments--August 2022
Request Additional Information (if necessary)--September 2022
Issue Scoping Document 2--November 2022
Issue Notice of Ready for Environmental Analysis--November 2022
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: March 10, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022-05580 Filed 3-16-22; 8:45 am]
BILLING CODE 6717-01-P