Tennessee Gas Pipeline Company, LLC ; Notice of Scoping Period Requesting Comments on Environmental Issues for the Planned Cumberland Project, 13286-13288 [2022-04964]
Download as PDF
13286
Federal Register / Vol. 87, No. 46 / Wednesday, March 9, 2022 / Notices
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, MD 20852. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 385.2010.
Locations of Notice of Intent: The
Commission provides all interested
persons an opportunity to view and/or
print the contents of this document via
the internet through the Commission’s
website at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket
number (i.e., CD22–4) in the docket
number field to access the document.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
Copies of the notice of intent can be
obtained directly from the applicant.
For assistance, call toll-free 1–866–208–
3676 or email FERCOnlineSupport@
ferc.gov. For TTY, call (202) 502–8659.
Dated: March 3, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–04958 Filed 3–8–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF22–2–000]
jspears on DSK121TN23PROD with NOTICES1
Tennessee Gas Pipeline Company,
LLC ; Notice of Scoping Period
Requesting Comments on
Environmental Issues for the Planned
Cumberland Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document that will
discuss the environmental impacts of
the Cumberland Project involving
construction and operation of facilities
by Tennessee Gas Pipeline Company,
LLC (TGP) in Dickson, Houston, and
Steward counties, Tennessee. The
Commission will use this environmental
document in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
VerDate Sep<11>2014
17:44 Mar 08, 2022
Jkt 256001
and interested agencies regarding the
project. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. The
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and Environmental Document section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on April
4, 2022. Comments may be submitted in
written form. Further details on how to
submit comments are provided in the
Public Participation section of this
notice.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
Your input will help the Commission
staff determine what issues they need to
evaluate in the environmental
document. Commission staff will
consider all comments during the
preparation of the environmental
document.
If you submitted comments on this
project to the Commission before the
opening of this docket on November 5,
2021, you will need to file those
comments in Docket No. PF22–2–000 to
ensure they are considered as part of
this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
agreement. You are not required to enter
into an agreement. However, if the
Commission approves the project, the
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
Natural Gas Act conveys the right of
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement between you and the
company, the pipeline company could
initiate condemnation proceedings in
court where compensation would be
determined in accordance with state
law. The Commission does not
subsequently grant, exercise, or oversee
the exercise of that eminent domain
authority. The courts have exclusive
authority to handle eminent domain
cases; the Commission has no
jurisdiction over these matters.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC website (www.ferc.gov). This
fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings.
Public Participation
There are three methods you can use
to submit your comments to the
Commission. Please carefully follow
these instructions so that your
comments are properly recorded. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (866) 208–3676
or FercOnlineSupport@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s website
(www.ferc.gov) under the link to FERC
Online (left side of screen). Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s website
(www.ferc.gov) under the link to FERC
Online. With eFiling, you can provide
comments in a variety of formats by
attaching them as a file with your
submission. New eFiling users must
first create an account by clicking on
‘‘eRegister.’’ You will be asked to select
the type of filing you are making; a
comment on a particular project is
considered a ‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (PF22–2–000) on
your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
E:\FR\FM\09MRN1.SGM
09MRN1
Federal Register / Vol. 87, No. 46 / Wednesday, March 9, 2022 / Notices
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, MD 20858.
Additionally, the Commission offers a
free service called eSubscription, which
makes it easy to stay informed of all
issuances and submittals regarding the
dockets/projects to which you
subscribe. These instant email
notifications are the fastest way to
receive notification and provide a link
to the document files which can reduce
the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
Land Requirements for Construction
Summary of the Planned Project
Any environmental document issued
by Commission staff will discuss
impacts that could occur as a result of
the construction and operation of the
planned project under the relevant
general resource areas:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• socioeconomics;
• environmental justice, and
• reliability and safety.
Commission staff will also evaluate
reasonable alternatives to the planned
project or portions of the project and
make recommendations on how to
lessen or avoid impacts on the various
resource areas. Your comments will
help Commission staff identify and
focus on the issues that might have an
effect on the human environment and
potentially eliminate others from further
study and discussion in the
environmental document.
Although no formal application has
been filed, we have already initiated our
NEPA review under the Commission’s
pre-filing process. The purpose of the
pre-filing process is to encourage early
involvement of interested stakeholders
and to identify and resolve issues before
the FERC receives an application. As
part of our pre-filing review, will
contact federal and state agencies to
discuss their involvement in the scoping
process and the preparation of the
environmental document.
If a formal application is filed,
Commission staff will then determine
whether to prepare an Environmental
Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the
EIS will present our independent
analysis of the environmental issues. If
Commission staff prepares an EA, a
Notice of Schedule for the Preparation
of an Environmental Assessment will be
jspears on DSK121TN23PROD with NOTICES1
TGP plans to construct and operate
approximately 32 miles of new 30-inchdiameter natural gas pipeline
(Cumberland Pipeline) from its existing
Lines 100–3 and 100–4 to the Tennessee
Valley Authority’s (TVA) Cumberland
Fossil Plant. TVA is evaluating options
to replace capacity following the
proposed retirement of its existing coalfired Cumberland Fossil Plant. The
Cumberland Pipeline would be in
Dickson, Houston, and Steward
counties, Tennessee; and it would
provide about 245,000 dekatherms per
day of natural gas per day to TVA.
The Cumberland Project would
consist of the following facilities:
• Approximately 32 miles of new 30inch-diameter natural gas lateral
pipeline, as described above.
• New Pressure Regulation Station
comprised of bi-directional back
pressure regulation facilities (including
a new Mainline valve [MLV] on each of
TGP’s Lines 100–3 and 100–4 at the
origin of the newly planned
Cumberland Pipeline in Dickson
County, Tennessee.
• New Cumberland Meter Station at
the terminus of the planned
Cumberland Pipeline within TVA’s
newly proposed power plant in Steward
County, Tennessee.
• New in-line inspection traps at each
end of the planned Cumberland
Pipeline.
• New MLV located at an
intermediate location along the planned
Cumberland Pipeline.
The general location of the project
facilities is shown in appendix 1.1
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE, Washington, DC 20426, or call (202) 502–
8371. For instructions on connecting to eLibrary,
refer to the last page of this notice.
VerDate Sep<11>2014
17:44 Mar 08, 2022
Jkt 256001
Construction of the planned facilities
would disturb about 494 acres of land
for the aboveground facilities and the
pipeline. Following construction, TGP
would maintain about 192 acres for
permanent operation of the project’s
facilities; the remaining acreage would
be restored and revert to former uses.
About 85 percent of the planned
pipeline route parallels an existing TVA
overhead electric transmission line
right-of-way.
The NEPA Process and the
Environmental Document
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
13287
issued. The EA may be issued for an
allotted public comment period. The
Commission would consider timely
comments on the EA before making its
determination on the proposed project.
If Commission staff prepares an EIS, a
Notice of Intent to Prepare an EIS/
Notice of Schedule will be issued once
an application is filed, which will open
an additional public comment period.
Staff will then prepare a draft EIS that
will be issued for public comment.
Commission staff will consider all
timely comments received during the
comment period on the draft EIS, and
revise the document, as necessary,
before issuing a final EIS. Any EA or
draft and final EIS will be available in
electronic format in the public record
through eLibrary 2 and the
Commission’s natural gas
environmental documents web page
https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents) If
eSubscribed, you will receive instant
email notification when the
environmental document is issued.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues related to this
project to formally cooperate with us in
the preparation of the environmental
document.3 Agencies that would like to
request cooperating agency status
should follow the instructions for filing
comments provided under the Public
Participation section of this notice
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
potential effects on historic properties.4
The environmental document for this
project will document our findings on
the impacts on historic properties and
2 For instructions on connecting to eLibrary, refer
to the last page of this notice.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.8.
4 The Advisory Council on Historic Preservation
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
E:\FR\FM\09MRN1.SGM
09MRN1
13288
Federal Register / Vol. 87, No. 46 / Wednesday, March 9, 2022 / Notices
summarize the status of consultations
under section 106.
jspears on DSK121TN23PROD with NOTICES1
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; local
community groups, schools, churches,
and businesses; other interested parties;
and local libraries and newspapers. This
list also includes all affected
landowners (as defined in the
Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project (and includes
a mailing address with their comment).
Commission staff will update the
environmental mailing list as the
analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the planned project.
If you need to make changes to your
name/address, or if you would like to
remove your name from the mailing list,
please complete one of the following
steps:
(1) Send an email to
GasProjectAddressChange@ferc.gov
stating your request. You must include
the docket number PF22–2–000 in your
request. If you are requesting a change
to your address, please be sure to
include your name and updated
address. If you are requesting to delete
your address from the mailing list,
please include your name and address
as it appeared on this notice. This email
address is unable to accept comments.
OR
(2) Return the attached ‘‘Mailing List
Update Form’’ (appendix 2).
Becoming an Intervenor
Once TGP files its application with
the Commission, you may want to
become an ‘‘intervenor,’’ which is an
official party to the Commission’s
proceeding. Only intervenors have the
right to seek rehearing of the
Commission’s decision and be heard by
the courts if they choose to appeal the
Commission’s final ruling. An
intervenor formally participates in the
proceeding by filing a request to
intervene pursuant to Rule 214 of the
Commission’s Rules of Practice and
Procedures (18 CFR 385.214). Motions
to intervene are more fully described at
https://www.ferc.gov/resources/guides/
VerDate Sep<11>2014
17:44 Mar 08, 2022
Jkt 256001
how-to.asp. Please note that the
Commission will not accept requests for
intervenor status at this time. You must
wait until the Commission receives a
formal application for the project, after
which the Commission will issue a
public notice that establishes an
intervention deadline.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website (www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number, excluding the last three
digits in the Docket Number field (i.e.,
PF22–2). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public meetings or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Comment Date: 5 p.m. ET 3/14/22.
Docket Numbers: RP22–674–000.
Applicants: Texas Eastern
Transmission, LP.
Description: § 4(d) Rate Filing: Quality
of Gas—PTR Language Modification eff
4–1–22 to be effective 4/1/2022.
Filed Date: 3/2/22.
Accession Number: 20220302–5213.
Comment Date: 5 p.m. ET 3/14/22.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Kimberly D. Bose,
Secretary.
Dated: March 3, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022–04964 Filed 3–8–22; 8:45 am]
[FR Doc. 2022–04952 Filed 3–8–22; 8:45 am]
BILLING CODE 6717–01–P
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
Combined Notice of Filings
[Project No. 2955–000]
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
City of Watervliet, New York; Notice of
Authorization for Continued Project
Operation
Filings Instituting Proceedings
Docket Numbers: RP22–672–000.
Applicants: Bear Creek Storage
Company, L.L.C.
Description: Compliance filing:
Annual Report on Operational
Transactions 2022 to be effective N/A.
Filed Date: 3/2/22.
Accession Number: 20220302–5035.
Comment Date: 5 p.m. ET 3/14/22.
Docket Numbers: RP22–673–000.
Applicants: Rover Pipeline LLC.
Description: § 4(d) Rate Filing:
Summary of Negotiated Rate Capacity
Release Agreements on 3–2–22 to be
effective 3/1/2022.
Filed Date: 3/2/22.
Accession Number: 20220302–5052.
On February 28, 2020, the City of
Watervliet, New York, licensee for the
Normanskill Hydroelectric Project
No.2955, filed an Application for a
Subsequent Minor License for the
Normanskill Hydroelectric Project
pursuant to the Federal Power Act
(FPA) and the Commission’s regulations
thereunder. The Normanskill
Hydroelectric Project located on the
Normans Kill in Guilderland, Albany
County, New York
The license for Project No.2955 was
issued for a period ending February 28,
2022. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
E:\FR\FM\09MRN1.SGM
09MRN1
Agencies
[Federal Register Volume 87, Number 46 (Wednesday, March 9, 2022)]
[Notices]
[Pages 13286-13288]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-04964]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF22-2-000]
Tennessee Gas Pipeline Company, LLC ; Notice of Scoping Period
Requesting Comments on Environmental Issues for the Planned Cumberland
Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document that will discuss
the environmental impacts of the Cumberland Project involving
construction and operation of facilities by Tennessee Gas Pipeline
Company, LLC (TGP) in Dickson, Houston, and Steward counties,
Tennessee. The Commission will use this environmental document in its
decision-making process to determine whether the project is in the
public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers the
issuance of a Certificate of Public Convenience and Necessity. The
gathering of public input is referred to as ``scoping.'' The main goal
of the scoping process is to focus the analysis in the environmental
document on the important environmental issues. Additional information
about the Commission's NEPA process is described below in the NEPA
Process and Environmental Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on April 4, 2022. Comments may be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues they need to evaluate in the environmental document. Commission
staff will consider all comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on November 5, 2021, you will need to file
those comments in Docket No. PF22-2-000 to ensure they are considered
as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this planned
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the planned facilities. The company
would seek to negotiate a mutually acceptable agreement. You are not
required to enter into an agreement. However, if the Commission
approves the project, the Natural Gas Act conveys the right of eminent
domain. Therefore, if easement negotiations fail to produce an
agreement between you and the company, the pipeline company could
initiate condemnation proceedings in court where compensation would be
determined in accordance with state law. The Commission does not
subsequently grant, exercise, or oversee the exercise of that eminent
domain authority. The courts have exclusive authority to handle eminent
domain cases; the Commission has no jurisdiction over these matters.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC website (www.ferc.gov). This fact sheet addresses a
number of typically asked questions, including the use of eminent
domain and how to participate in the Commission's proceedings.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(866) 208-3676 or [email protected].
(1) You can file your comments electronically using the eComment
feature on the Commission's website (www.ferc.gov) under the link to
FERC Online (left side of screen). Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's website (www.ferc.gov) under the link to
FERC Online. With eFiling, you can provide comments in a variety of
formats by attaching them as a file with your submission. New eFiling
users must first create an account by clicking on ``eRegister.'' You
will be asked to select the type of filing you are making; a comment on
a particular project is considered a ``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (PF22-2-
000) on your letter. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose,
[[Page 13287]]
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, MD 20858.
Additionally, the Commission offers a free service called
eSubscription, which makes it easy to stay informed of all issuances
and submittals regarding the dockets/projects to which you subscribe.
These instant email notifications are the fastest way to receive
notification and provide a link to the document files which can reduce
the amount of time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
Summary of the Planned Project
TGP plans to construct and operate approximately 32 miles of new
30-inch-diameter natural gas pipeline (Cumberland Pipeline) from its
existing Lines 100-3 and 100-4 to the Tennessee Valley Authority's
(TVA) Cumberland Fossil Plant. TVA is evaluating options to replace
capacity following the proposed retirement of its existing coal-fired
Cumberland Fossil Plant. The Cumberland Pipeline would be in Dickson,
Houston, and Steward counties, Tennessee; and it would provide about
245,000 dekatherms per day of natural gas per day to TVA.
The Cumberland Project would consist of the following facilities:
Approximately 32 miles of new 30-inch-diameter natural gas
lateral pipeline, as described above.
New Pressure Regulation Station comprised of bi-
directional back pressure regulation facilities (including a new
Mainline valve [MLV] on each of TGP's Lines 100-3 and 100-4 at the
origin of the newly planned Cumberland Pipeline in Dickson County,
Tennessee.
New Cumberland Meter Station at the terminus of the
planned Cumberland Pipeline within TVA's newly proposed power plant in
Steward County, Tennessee.
New in-line inspection traps at each end of the planned
Cumberland Pipeline.
New MLV located at an intermediate location along the
planned Cumberland Pipeline.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE, Washington,
DC 20426, or call (202) 502-8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the planned facilities would disturb about 494
acres of land for the aboveground facilities and the pipeline.
Following construction, TGP would maintain about 192 acres for
permanent operation of the project's facilities; the remaining acreage
would be restored and revert to former uses. About 85 percent of the
planned pipeline route parallels an existing TVA overhead electric
transmission line right-of-way.
The NEPA Process and the Environmental Document
Any environmental document issued by Commission staff will discuss
impacts that could occur as a result of the construction and operation
of the planned project under the relevant general resource areas:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
socioeconomics;
environmental justice, and
reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
planned project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before
the FERC receives an application. As part of our pre-filing review,
will contact federal and state agencies to discuss their involvement in
the scoping process and the preparation of the environmental document.
If a formal application is filed, Commission staff will then
determine whether to prepare an Environmental Assessment (EA) or an
Environmental Impact Statement (EIS). The EA or the EIS will present
our independent analysis of the environmental issues. If Commission
staff prepares an EA, a Notice of Schedule for the Preparation of an
Environmental Assessment will be issued. The EA may be issued for an
allotted public comment period. The Commission would consider timely
comments on the EA before making its determination on the proposed
project. If Commission staff prepares an EIS, a Notice of Intent to
Prepare an EIS/Notice of Schedule will be issued once an application is
filed, which will open an additional public comment period. Staff will
then prepare a draft EIS that will be issued for public comment.
Commission staff will consider all timely comments received during the
comment period on the draft EIS, and revise the document, as necessary,
before issuing a final EIS. Any EA or draft and final EIS will be
available in electronic format in the public record through eLibrary
\2\ and the Commission's natural gas environmental documents web page
https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents) If eSubscribed, you will receive instant email
notification when the environmental document is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues
related to this project to formally cooperate with us in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.8.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The environmental document for this
project will document our findings on the impacts on historic
properties and
[[Page 13288]]
summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; local
community groups, schools, churches, and businesses; other interested
parties; and local libraries and newspapers. This list also includes
all affected landowners (as defined in the Commission's regulations)
who are potential right-of-way grantors, whose property may be used
temporarily for project purposes, or who own homes within certain
distances of aboveground facilities, and anyone who submits comments on
the project (and includes a mailing address with their comment).
Commission staff will update the environmental mailing list as the
analysis proceeds to ensure that we send the information related to
this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
planned project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to [email protected] stating your
request. You must include the docket number PF22-2-000 in your request.
If you are requesting a change to your address, please be sure to
include your name and updated address. If you are requesting to delete
your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments. OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Becoming an Intervenor
Once TGP files its application with the Commission, you may want to
become an ``intervenor,'' which is an official party to the
Commission's proceeding. Only intervenors have the right to seek
rehearing of the Commission's decision and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in the proceeding by filing a request to
intervene pursuant to Rule 214 of the Commission's Rules of Practice
and Procedures (18 CFR 385.214). Motions to intervene are more fully
described at https://www.ferc.gov/resources/guides/how-to.asp. Please
note that the Commission will not accept requests for intervenor status
at this time. You must wait until the Commission receives a formal
application for the project, after which the Commission will issue a
public notice that establishes an intervention deadline.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., PF22-
2). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public meetings or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-04964 Filed 3-8-22; 8:45 am]
BILLING CODE 6717-01-P