Northbrook Carolina Hydro II, LLC; HydroLand Carolinas I, LLC; Notice of Effectiveness of Withdrawal of Applications To Transfer Licenses, 8579-8580 [2022-03218]
Download as PDF
Federal Register / Vol. 87, No. 31 / Tuesday, February 15, 2022 / Notices
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’ or
‘‘MOTION TO INTERVENE;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
Agencies may obtain copies of the
application directly from the applicant.
A copy of any protest or motion to
intervene must be served upon each
representative of the applicant specified
in the particular application.
o. Procedural schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Issue Scoping Document 1 for
comments—April 2022
Request Additional Information (if
necessary)—June 2022
Issue Scoping Document 2 (if
necessary)—July 2022
Issue Notice of Ready for Environmental
Analysis—July 2022
Dated: February 9, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–03215 Filed 2–14–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–501–000]
lotter on DSK11XQN23PROD with NOTICES1
Texas Eastern Transmission, LP;
Notice of Request for Extension of
Time
Take notice that on February 7, 2022,
Texas Eastern Transmission, LP. (Texas
Eastern), requested that the Federal
Energy Regulatory Commission
(Commission) grant an extension of
time, until March 24, 2023, to complete
construction of the Bailey East Mine
Panel 11J Project (Project) and make the
Project available for service, as
authorized in the March 24, 2020 Order
Issuing Certificates (Certificate Order).1
Texas Eastern was granted
authorization to excavate, elevate, and
replace certain segments of four
different natural gas transmission
pipelines and appurtenant facilities, and
to monitor potential strains on the
pipeline sections due to anticipated
1 Texas Eastern Transmission, LP, 170 FERC
¶ 62,167 (2020)(Certificate Order).
VerDate Sep<11>2014
20:12 Feb 14, 2022
Jkt 256001
longwall mining activities planned by
CONSOL Energy, Inc. (CONSOL) in
Marshall County, West Virginia. The
Certificate Order required Texas Eastern
to complete construction of the Project
facilities and make them available for
service by March 24, 2022.2 Texas
Eastern has completed the reinstallation
of Lines 15 and 30 below ground and
placed those lines back into service in
December 2021. Due to delays in the
reinstallation and hydrostatic testing of
Lines 10 and 25, Texas Eastern now
request an additional year, until March
24, 2023, to complete construction of
the Project and place it into service.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Texas Eastern’s request for
an extension of time may do so. No
reply comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,3 the Commission will aim to
issue an order acting on the request
within 45 days.4 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.5 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.6 At the time
a pipeline requests an extension of time,
2 Certificate Order, 170 FERC ¶ 62,167 at ordering
para. (D).
3 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
4 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
5 Id. at P 40.
6 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
8579
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.7 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFile’’ link at https://www.ferc.gov.
Persons unable to file electronically may
mail similar pleadings to the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern
Time on February 24, 2022.
Dated: February 9, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–03217 Filed 2–14–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project Nos. 2601–068; 2603–050]
Northbrook Carolina Hydro II, LLC;
HydroLand Carolinas I, LLC; Notice of
Effectiveness of Withdrawal of
Applications To Transfer Licenses
On May 13, 2021, Northbrook
Carolina Hydro II, LLC (Northbrook) and
HydroLand Carolinas I, LLC
(Hydroland) jointly filed applications to
transfer the licenses for the Bryson
7 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
E:\FR\FM\15FEN1.SGM
15FEN1
8580
Federal Register / Vol. 87, No. 31 / Tuesday, February 15, 2022 / Notices
Hydroelectric Project No. 2601 and
Franklin Hydroelectric Project No. 2603.
On January 21, 2022, Northbrook and
HydroLand jointly filed a notice of
withdrawal of their applications to
transfer the licenses for the Bryson
Hydroelectric Project No. 2601 and
Franklin Hydroelectric Project No. 2603.
The projects are located on the
Oconaluftee and Little Tennessee rivers
in Swain and Macon counties, North
Carolina.
No motion in opposition to the notice
of the withdrawal has been filed, and
the Commission has taken no action to
disallow the withdrawal. Pursuant to
Rule 216(b) of the Commission’s Rules
of Practice and Procedure,1 the
withdrawal of the transfer of licenses
became effective on February 5, 2022,
and these proceedings are hereby
terminated.
Dated: February 9, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–03218 Filed 2–14–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP22–21–000; Docket No.
CP22–22–000]
lotter on DSK11XQN23PROD with NOTICES1
Venture Global CP2 LNG, LLC; Venture
Global CP Express, LLC; Notice of
Intent To Prepare an Environmental
Impact Statement for the Proposed
CP2 LNG and CP Express Project,
Request for Comments on
Environmental Issues, and Schedule
for Environmental Review
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental impact statement (EIS)
that will discuss the environmental
impacts of the CP2 LNG and CP Express
Project (Project) involving construction
and operation of facilities by Venture
Global CP2 LNG, LLC (CP2 LNG) and
Venture Global CP Express, LLC (CP
Express) in Jasper and Newton Counties,
Texas and Calcasieu and Cameron
Parishes, Louisiana. The Commission
will use this EIS in its decision-making
process to determine whether the
Project is in the public interest. The
schedule for preparation of the EIS is
discussed in the Schedule for
Environmental Review section of this
notice.
As part of the National Environmental
Policy Act (NEPA) review process, the
1 18
CFR 385.216(b) (2021).
VerDate Sep<11>2014
20:12 Feb 14, 2022
Jkt 256001
Commission takes into account
concerns the public may have about
proposals and the environmental
impacts that could result whenever it
considers the issuance of an
authorization. This gathering of public
input is referred to as ‘‘scoping.’’ By
notice issued on April 27, 2021 in
Docket No. PF21–1–000, the
Commission opened a scoping period
during CP2 LNG and CP Express’
planning process for the Project and
prior to filing a formal application with
the Commission, a process referred to as
‘‘pre-filing.’’ CP2 LNG and CP Express
have now filed an application with the
Commission, and staff intends to
prepare an EIS that will address the
concerns raised during the pre-filing
scoping process and comments received
in response to this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document, including
comments on potential alternatives and
impacts, and any relevant information,
studies, or analyses of any kind
concerning impacts affecting the quality
of the human environment. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on March
11, 2022. Further details on how to
submit comments are provided in the
Public Participation section of this
notice.
As mentioned above, during the prefiling process, the Commission opened
a scoping period which expired on May
27, 2021; however, Commission staff
continued to accept comments during
the entire pre-filing process. Staff also
held three virtual scoping sessions to
take oral scoping comments. All
substantive written and oral comments
provided during pre-filing will be
addressed in the EIS. Therefore, if you
submitted comments on this Project to
the Commission during the pre-filing
process in Docket No. PF21–1–000, you
do not need to file those comments
again.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed pipeline facilities. The
company would seek to negotiate a
mutually acceptable easement
agreement. You are not required to enter
into an agreement. However, if the
Commission approves the Project, the
Natural Gas Act conveys the right of
eminent domain to the company.
Therefore, if you and the company do
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
not reach an easement agreement, the
pipeline company could initiate
condemnation proceedings in court. In
such instances, compensation would be
determined by a judge in accordance
with state law. The Commission does
not grant, exercise, or oversee the
exercise of eminent domain authority.
The courts have exclusive authority to
handle eminent domain cases; the
Commission has no jurisdiction over
these matters.
CP2 LNG and CP Express provided
landowners with a fact sheet prepared
by the FERC entitled ‘‘An Interstate
Natural Gas Facility On My Land? What
Do I Need To Know?’’ which addresses
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. This fact sheet along with
other landowner topics of interest are
available for viewing on the FERC
website (www.ferc.gov) under the
Natural Gas Questions or Landowner
Topics link.
Public Participation
There are three methods you can use
to submit your comments to the
Commission. The Commission
encourages electronic filing of
comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov. Please
carefully follow these instructions so
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is also located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP22–21–000
and CP22–22–000) on your letter.
Submissions sent via the U.S. Postal
Service must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
E:\FR\FM\15FEN1.SGM
15FEN1
Agencies
[Federal Register Volume 87, Number 31 (Tuesday, February 15, 2022)]
[Notices]
[Pages 8579-8580]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-03218]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project Nos. 2601-068; 2603-050]
Northbrook Carolina Hydro II, LLC; HydroLand Carolinas I, LLC;
Notice of Effectiveness of Withdrawal of Applications To Transfer
Licenses
On May 13, 2021, Northbrook Carolina Hydro II, LLC (Northbrook) and
HydroLand Carolinas I, LLC (Hydroland) jointly filed applications to
transfer the licenses for the Bryson
[[Page 8580]]
Hydroelectric Project No. 2601 and Franklin Hydroelectric Project No.
2603. On January 21, 2022, Northbrook and HydroLand jointly filed a
notice of withdrawal of their applications to transfer the licenses for
the Bryson Hydroelectric Project No. 2601 and Franklin Hydroelectric
Project No. 2603. The projects are located on the Oconaluftee and
Little Tennessee rivers in Swain and Macon counties, North Carolina.
No motion in opposition to the notice of the withdrawal has been
filed, and the Commission has taken no action to disallow the
withdrawal. Pursuant to Rule 216(b) of the Commission's Rules of
Practice and Procedure,\1\ the withdrawal of the transfer of licenses
became effective on February 5, 2022, and these proceedings are hereby
terminated.
---------------------------------------------------------------------------
\1\ 18 CFR 385.216(b) (2021).
Dated: February 9, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-03218 Filed 2-14-22; 8:45 am]
BILLING CODE 6717-01-P