Texas Eastern Transmission, LP; Notice of Request for Extension of Time, 8579 [2022-03217]
Download as PDF
Federal Register / Vol. 87, No. 31 / Tuesday, February 15, 2022 / Notices
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’ or
‘‘MOTION TO INTERVENE;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
Agencies may obtain copies of the
application directly from the applicant.
A copy of any protest or motion to
intervene must be served upon each
representative of the applicant specified
in the particular application.
o. Procedural schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Issue Scoping Document 1 for
comments—April 2022
Request Additional Information (if
necessary)—June 2022
Issue Scoping Document 2 (if
necessary)—July 2022
Issue Notice of Ready for Environmental
Analysis—July 2022
Dated: February 9, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–03215 Filed 2–14–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–501–000]
lotter on DSK11XQN23PROD with NOTICES1
Texas Eastern Transmission, LP;
Notice of Request for Extension of
Time
Take notice that on February 7, 2022,
Texas Eastern Transmission, LP. (Texas
Eastern), requested that the Federal
Energy Regulatory Commission
(Commission) grant an extension of
time, until March 24, 2023, to complete
construction of the Bailey East Mine
Panel 11J Project (Project) and make the
Project available for service, as
authorized in the March 24, 2020 Order
Issuing Certificates (Certificate Order).1
Texas Eastern was granted
authorization to excavate, elevate, and
replace certain segments of four
different natural gas transmission
pipelines and appurtenant facilities, and
to monitor potential strains on the
pipeline sections due to anticipated
1 Texas Eastern Transmission, LP, 170 FERC
¶ 62,167 (2020)(Certificate Order).
VerDate Sep<11>2014
20:12 Feb 14, 2022
Jkt 256001
longwall mining activities planned by
CONSOL Energy, Inc. (CONSOL) in
Marshall County, West Virginia. The
Certificate Order required Texas Eastern
to complete construction of the Project
facilities and make them available for
service by March 24, 2022.2 Texas
Eastern has completed the reinstallation
of Lines 15 and 30 below ground and
placed those lines back into service in
December 2021. Due to delays in the
reinstallation and hydrostatic testing of
Lines 10 and 25, Texas Eastern now
request an additional year, until March
24, 2023, to complete construction of
the Project and place it into service.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Texas Eastern’s request for
an extension of time may do so. No
reply comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,3 the Commission will aim to
issue an order acting on the request
within 45 days.4 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.5 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.6 At the time
a pipeline requests an extension of time,
2 Certificate Order, 170 FERC ¶ 62,167 at ordering
para. (D).
3 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
4 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
5 Id. at P 40.
6 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
8579
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.7 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFile’’ link at https://www.ferc.gov.
Persons unable to file electronically may
mail similar pleadings to the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern
Time on February 24, 2022.
Dated: February 9, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–03217 Filed 2–14–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project Nos. 2601–068; 2603–050]
Northbrook Carolina Hydro II, LLC;
HydroLand Carolinas I, LLC; Notice of
Effectiveness of Withdrawal of
Applications To Transfer Licenses
On May 13, 2021, Northbrook
Carolina Hydro II, LLC (Northbrook) and
HydroLand Carolinas I, LLC
(Hydroland) jointly filed applications to
transfer the licenses for the Bryson
7 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
E:\FR\FM\15FEN1.SGM
15FEN1
Agencies
[Federal Register Volume 87, Number 31 (Tuesday, February 15, 2022)]
[Notices]
[Page 8579]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-03217]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP19-501-000]
Texas Eastern Transmission, LP; Notice of Request for Extension
of Time
Take notice that on February 7, 2022, Texas Eastern Transmission,
LP. (Texas Eastern), requested that the Federal Energy Regulatory
Commission (Commission) grant an extension of time, until March 24,
2023, to complete construction of the Bailey East Mine Panel 11J
Project (Project) and make the Project available for service, as
authorized in the March 24, 2020 Order Issuing Certificates
(Certificate Order).\1\
---------------------------------------------------------------------------
\1\ Texas Eastern Transmission, LP, 170 FERC ] 62,167
(2020)(Certificate Order).
---------------------------------------------------------------------------
Texas Eastern was granted authorization to excavate, elevate, and
replace certain segments of four different natural gas transmission
pipelines and appurtenant facilities, and to monitor potential strains
on the pipeline sections due to anticipated longwall mining activities
planned by CONSOL Energy, Inc. (CONSOL) in Marshall County, West
Virginia. The Certificate Order required Texas Eastern to complete
construction of the Project facilities and make them available for
service by March 24, 2022.\2\ Texas Eastern has completed the
reinstallation of Lines 15 and 30 below ground and placed those lines
back into service in December 2021. Due to delays in the reinstallation
and hydrostatic testing of Lines 10 and 25, Texas Eastern now request
an additional year, until March 24, 2023, to complete construction of
the Project and place it into service.
---------------------------------------------------------------------------
\2\ Certificate Order, 170 FERC ] 62,167 at ordering para. (D).
---------------------------------------------------------------------------
This notice establishes a 15-calendar day intervention and comment
period deadline. Any person wishing to comment on Texas Eastern's
request for an extension of time may do so. No reply comments or
answers will be considered. If you wish to obtain legal status by
becoming a party to the proceedings for this request, you should, on or
before the comment date stated below, file a motion to intervene in
accordance with the requirements of the Commission's Rules of Practice
and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
Natural Gas Act (18 CFR 157.10).
As a matter of practice, the Commission itself generally acts on
requests for extensions of time to complete construction for Natural
Gas Act facilities when such requests are contested before order
issuance. For those extension requests that are contested,\3\ the
Commission will aim to issue an order acting on the request within 45
days.\4\ The Commission will address all arguments relating to whether
the applicant has demonstrated there is good cause to grant the
extension.\5\ The Commission will not consider arguments that re-
litigate the issuance of the certificate order, including whether the
Commission properly found the project to be in the public convenience
and necessity and whether the Commission's environmental analysis for
the certificate complied with the National Environmental Policy Act.\6\
At the time a pipeline requests an extension of time, orders on
certificates of public convenience and necessity are final and the
Commission will not re-litigate their issuance.\7\ The OEP Director, or
his or her designee, will act on all of those extension requests that
are uncontested.
---------------------------------------------------------------------------
\3\ Contested proceedings are those where an intervenor disputes
any material issue of the filing. 18 CFR 385.2201(c)(1) (2019).
\4\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
\5\ Id. at P 40.
\6\ Similarly, the Commission will not re-litigate the issuance
of an NGA section 3 authorization, including whether a proposed
project is not inconsistent with the public interest and whether the
Commission's environmental analysis for the permit order complied
with NEPA.
\7\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://www.ferc.gov) using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to Commission's Public Reference
Room, due to the proclamation declaring a National Emergency concerning
the Novel Coronavirus Disease (COVID-19), issued by the President on
March 13, 2020. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFile'' link at
https://www.ferc.gov. Persons unable to file electronically may mail
similar pleadings to the Federal Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
Hand delivered submissions in docketed proceedings should be
delivered to Health and Human Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern Time on February 24, 2022.
Dated: February 9, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-03217 Filed 2-14-22; 8:45 am]
BILLING CODE 6717-01-P