Download as PDF 8244 Federal Register / Vol. 87, No. 30 / Monday, February 14, 2022 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP22–24–000] Equitrans, L.P.; Notice of Schedule for the Preparation of an Environmental Assessment for the Truittsburg Well Conversion Project On December 2, 2021, Equitrans, L.P. filed an application in Docket No. CP22–24–000 requesting a Certificate of Public Convenience and Necessity pursuant to Section 7(c) of the Natural Gas Act to construct and operate certain natural gas pipeline facilities. The proposed project is known as the Truittsburg Well Conversion Project (Project), and would convert two observation wells into injection/ withdrawal (I/W) wells in the existing Truittsburg Storage Field in Clarion County, Pennsylvania. On December 13, 2021, the Federal Energy Regulatory Commission (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization within 90 days of the date of issuance of the Commission staff’s environmental document for the Project. This notice identifies Commission staff’s intention to prepare an environmental assessment (EA) for the Project and the planned schedule for the completion of the environmental review.1 Schedule for Environmental Review Issuance of EA March 7, 2022 90-day Federal Authorization Decision Deadline June 5, 2022 If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. jspears on DSK121TN23PROD with NOTICES1 Project Description 1 40 CFR 1501.10 (2020). 2 A ‘‘pig’’ is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes. 17:54 Feb 11, 2022 Additional Information In order to receive notification of the issuance of the EA and to keep track of formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This service provides automatic notification of filings made to subscribed dockets, document summaries, and direct links to the documents. Go to https:// www.ferc.gov/ferc-online/overview to register for eSubscription. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the ‘‘eLibrary’’ link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and ‘‘Docket Number’’ excluding the last three digits (i.e., CP22–24), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: February 8, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–03094 Filed 2–11–22; 8:45 am] BILLING CODE 6717–01–P Equitrans is proposing to add approximately 1,119 feet of 4-inchdiameter natural gas pipeline to convert Truittsburg wells 2483 and 2484 from observation wells to I/W wells and install pigging 2 valves at the wellheads and associated piping. VerDate Sep<11>2014 Background On January 5, 2022, the Commission issued a Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Truittsburg Well Conversion Project (Notice of Scoping). The Notice of Scoping was sent to affected landowners; federal, state, and local government agencies; elected officials; environmental and public interest groups; Native American tribes; other interested parties; and local libraries and newspapers. In response to the Notice of Scoping, the Commission received comments from one landowner in support of the Project. All substantive comments will be addressed in the EA. Jkt 256001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following Complaints and Compliance filings in EL Dockets: Docket Numbers: EL22–29–000; QF15–850–003. PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 Applicants: Magnolia Solar, LLC, Magnolia Solar, LLC. Description: Petition for Enforcement of the Public Utility Regulatory Policies Act of 1978 of Magnolia Solar, LLC. Filed Date: 2/8/22. Accession Number: 20220208–5101. Comment Date: 5 p.m. ET 3/1/22. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER22–680–001. Applicants: Southern California Edison Company. Description: Tariff Amendment: Revised WDAT Enhancements 2021 to be effective 4/10/2022. Filed Date: 2/8/22. Accession Number: 20220208–5067. Comment Date: 5 p.m. ET 3/1/22. Docket Numbers: ER22–821–001. Applicants: Spotlight Power LLC. Description: Tariff Amendment: Amended Spotlight Power LLC Baseline MBR Tariff & Application to be effective 3/16/2022. Filed Date: 2/8/22. Accession Number: 20220208–5060. Comment Date: 5 p.m. ET 3/1/22. Docket Numbers: ER22–1001–000. Applicants: Union Electric Company. Description: § 205(d) Rate Filing: Joint Ownership Agreement—UE–MJMEUCHannibal to be effective 1/1/2022. Filed Date: 2/8/22. Accession Number: 20220208–5000. Comment Date: 5 p.m. ET 3/1/22. Docket Numbers: ER22–1002–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original IISA, Service Agreement No. 6327; Queue Nos. AF1–130/AF1–162 to be effective 1/10/2022. Filed Date: 2/8/22. Accession Number: 20220208–5026. Comment Date: 5 p.m. ET 3/1/22. Docket Numbers: ER22–1003–000. Applicants: Southwestern Public Service Company. Description: § 205(d) Rate Filing: LPL Second Amended PR Agreement to be effective 2/9/2022. Filed Date: 2/8/22. Accession Number: 20220208–5087. Comment Date: 5 p.m. ET 3/1/22. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES22–29–000. Applicants: Consolidated Edison Company of New York, Inc. Description: Application Under Section 204 of the Federal Power Act for Authorization to Issue Securities of Consolidated Edison of New York Inc. Filed Date: 2/7/22. E:\FR\FM\14FEN1.SGM 14FEN1

Agencies

[Federal Register Volume 87, Number 30 (Monday, February 14, 2022)]
[Notices]
[Page 8244]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-03094]



[[Page 8244]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP22-24-000]


Equitrans, L.P.; Notice of Schedule for the Preparation of an 
Environmental Assessment for the Truittsburg Well Conversion Project

    On December 2, 2021, Equitrans, L.P. filed an application in Docket 
No. CP22-24-000 requesting a Certificate of Public Convenience and 
Necessity pursuant to Section 7(c) of the Natural Gas Act to construct 
and operate certain natural gas pipeline facilities. The proposed 
project is known as the Truittsburg Well Conversion Project (Project), 
and would convert two observation wells into injection/withdrawal (I/W) 
wells in the existing Truittsburg Storage Field in Clarion County, 
Pennsylvania.
    On December 13, 2021, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\
---------------------------------------------------------------------------

    \1\ 40 CFR 1501.10 (2020).
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA March 7, 2022
90-day Federal Authorization Decision Deadline June 5, 2022

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Equitrans is proposing to add approximately 1,119 feet of 4-inch-
diameter natural gas pipeline to convert Truittsburg wells 2483 and 
2484 from observation wells to I/W wells and install pigging \2\ valves 
at the wellheads and associated piping.
---------------------------------------------------------------------------

    \2\ A ``pig'' is a tool that the pipeline company inserts into 
and pushes through the pipeline for cleaning the pipeline, 
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------

Background

    On January 5, 2022, the Commission issued a Notice of Scoping 
Period Requesting Comments on Environmental Issues for the Proposed 
Truittsburg Well Conversion Project (Notice of Scoping). The Notice of 
Scoping was sent to affected landowners; federal, state, and local 
government agencies; elected officials; environmental and public 
interest groups; Native American tribes; other interested parties; and 
local libraries and newspapers. In response to the Notice of Scoping, 
the Commission received comments from one landowner in support of the 
Project. All substantive comments will be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP22-24), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

    Dated: February 8, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-03094 Filed 2-11-22; 8:45 am]
BILLING CODE 6717-01-P