Federal Register / Vol. 87, No. 23 / Thursday, February 3, 2022 / Notices
serve a copy of the document on that
resource agency.
k. Description of Request: Domtar
Paper Company, LLC (licensee) has
determined that the repair of five
inoperable turbine generating units
(Units 1, 2, 4, 5, and 6) is not cost
effective, and therefore, proposes to
retire the five units in place. The other
two turbine generating units at the
project (Units 3 and 7) would remain in
service, with no changes proposed by
the licensee. To retire the five units, the
licensee proposes to disconnect the
generator leads from the units. All
proposed activity would occur in the
powerhouse, with no ground disturbing
activity necessary. With both the
powerhouse and the spillway section of
the dam currently releasing flows into
the main channel of the Wisconsin
River downstream, the proposal would
result in a reduced flow through the
powerhouse and an increased flow over
the spillway. The proposal would
decrease the total authorized capacity of
the project from 3,708 to 948 kilowatts
and would decrease the hydraulic
capacity from 3,850 to 1,100 cubic feet
per second.
l. Locations of the Application: This
filing may be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. Agencies may
obtain copies of the application directly
from the applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
VerDate Sep<11>2014
18:08 Feb 02, 2022
Jkt 256001
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting, or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
Dated: January 27, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–02153 Filed 2–2–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP22–40–000]
Eastern Shore Natural Gas; Notice of
Request Under Blanket Authorization
and Establishing Intervention and
Protest Deadline
Take notice that on January 18, 2022
Eastern Shore Natural Gas (Eastern
Shore) filed a prior notice request for
authorization, in accordance with 18
CFR Sections 157.203(c),157.205(b),
157.208(c) and 157.210 of the Federal
Energy Regulatory Commission’s
(Commission) regulations under the
Natural Gas Act and Eastern Shore’s
blanket certificate issued in Docket Nos.
CP96–128–000, et al., to install an
additional compressor unit, adding
1,875 horse power of new compression
at Eastern Shore’s existing Bridgeville
Compressor Station site in Sussex
County, DE and appurtenant facilities
required to provide additional firm
natural gas transportation service of
7,300 dekatherms per day to an existing
shipper on Eastern Shore’s pipeline
system, and estimates that the cost of
the project will be about $14,026,800,
all as more fully set forth in the
application which is on file with the
Commission and open for public
inspection.
In addition to publishing the full text
of this document in the Federal
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions concerning this
application should be directed to Jeffrey
R. Tietbohl, Vice President, Eastern
Shore Natural Gas Company, 500 Energy
Lane, Suite 200 Dover, Delaware 19901
at (302)-363–4679 or email at jtietbohl@
esng.com or pipelines@chpk.com.
Pursuant to Section 157.9 of the
Commission’s Rules of Practice and
Procedure,1 within 90 days of this
Notice the Commission staff will either:
complete its environmental review and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or environmental assessment (EA) for
this proposal. The filing of an EA in the
Commission’s public record for this
proceeding or the issuance of a Notice
of Schedule for Environmental Review
will serve to notify federal and state
agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Public Participation
There are three ways to become
involved in the Commission’s review of
this project: you can file a protest to the
project, you can file a motion to
intervene in the proceeding, and you
can file comments on the project. There
is no fee or cost for filing protests,
motions to intervene, or comments. The
deadline for filing protests, motions to
intervene, and comments is 5:00 p.m.
Eastern Time on March 29, 2022. How
1 18
E:\FR\FM\03FEN1.SGM
CFR (Code of Federal Regulations) § 157.9.
03FEN1
Federal Register / Vol. 87, No. 23 / Thursday, February 3, 2022 / Notices
to file protests, motions to intervene,
and comments is explained below.
khammond on DSKJM1Z7X2PROD with NOTICES
Protests
Pursuant to section 157.205 of the
Commission’s regulations under the
NGA,2 any person 3 or the Commission’s
staff may file a protest to the request. If
no protest is filed within the time
allowed or if a protest is filed and then
withdrawn within 30 days after the
allowed time for filing a protest, the
proposed activity shall be deemed to be
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request for
authorization will be considered by the
Commission.
Protests must comply with the
requirements specified in section
157.205(e) of the Commission’s
regulations,4 and must be submitted by
the protest deadline, which is March 29,
2022. A protest may also serve as a
motion to intervene so long as the
protestor states it also seeks to be an
intervenor.
Interventions
Any person has the option to file a
motion to intervene in this proceeding.
Only intervenors have the right to
request rehearing of Commission orders
issued in this proceeding and to
subsequently challenge the
Commission’s orders in the U.S. Circuit
Courts of Appeal.
To intervene, you must submit a
motion to intervene to the Commission
in accordance with Rule 214 of the
Commission’s Rules of Practice and
Procedure 5 and the regulations under
the NGA 6 by the intervention deadline
for the project, which is March 29, 2022.
As described further in Rule 214, your
motion to intervene must state, to the
extent known, your position regarding
the proceeding, as well as your interest
in the proceeding. For an individual,
this could include your status as a
landowner, ratepayer, resident of an
impacted community, or recreationist.
You do not need to have property
directly impacted by the project in order
to intervene. For more information
about motions to intervene, refer to the
FERC website at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
All timely, unopposed motions to
intervene are automatically granted by
2 18
CFR 157.205.
3 Persons include individuals, organizations,
businesses, municipalities, and other entities. 18
CFR 385.102(d).
4 18 CFR 157.205(e).
5 18 CFR 385.214.
6 18 CFR 157.10.
VerDate Sep<11>2014
18:08 Feb 02, 2022
Jkt 256001
operation of Rule 214(c)(1). Motions to
intervene that are filed after the
intervention deadline are untimely and
may be denied. Any late-filed motion to
intervene must show good cause for
being late and must explain why the
time limitation should be waived and
provide justification by reference to
factors set forth in Rule 214(d) of the
Commission’s Rules and Regulations. A
person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies (paper or electronic)
of all documents filed by the applicant
and by all other parties.
Comments
Any person wishing to comment on
the project may do so. The Commission
considers all comments received about
the project in determining the
appropriate action to be taken. To
ensure that your comments are timely
and properly recorded, please submit
your comments on or before March 29,
2022. The filing of a comment alone will
not serve to make the filer a party to the
proceeding. To become a party, you
must intervene in the proceeding.
How to File Protests, Interventions, and
Comments
There are two ways to submit
protests, motions to intervene, and
comments. In both instances, please
reference the Project docket number
CP22–40–000 in your submission.
(1) You may file your protest, motion
to intervene, and comments by using the
Commission’s eFiling feature, which is
located on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You will be
asked to select the type of filing you are
making; first select General’’ and then
select ‘‘Protest’’, ‘‘Intervention’’, or
‘‘Comment on a Filing’’; or 7
(2) You can file a paper copy of your
submission by mailing it to the address
below. Your submission must reference
the Project docket number CP22–40–
000.
To mail via USPS, use the following
address: Kimberly D. Bose, Secretary,
Federal Energy Regulatory
Commission, 888 First Street NE,
Washington, DC 20426
To mail via any other courier, use the
following address: Kimberly D. Bose,
7 Additionally, you may file your comments
electronically by using the eComment feature,
which is located on the Commission’s website at
www.ferc.gov under the link to Documents and
Filings. Using eComment is an easy method for
interested persons to submit brief, text-only
comments on a project.
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
6163
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852
The Commission encourages
electronic filing of submissions (option
1 above) and has eFiling staff available
to assist you at (202) 502–8258 or
FercOnlineSupport@ferc.gov.
Protests and motions to intervene
must be served on the applicant either
by mail or email (with a link to the
document) at: Jeffrey R. Tietbohl, Vice
President, Eastern Shore Natural Gas
Company, 500 Energy Lane, Suite 200
Dover, Delaware 19901 at (302)-363–
4679 or email at jtietbohl@esng.com or
pipelines@chpk.com.
Any subsequent submissions by an
intervenor must be served on the
applicant and all other parties to the
proceeding. Contact information for
parties can be downloaded from the
service list at the eService link on FERC
Online.
Tracking the Proceeding
Throughout the proceeding,
additional information about the project
will be available from the Commission’s
Office of External Affairs, at (866) 208–
FERC, or on the FERC website at
www.ferc.gov using the ‘‘eLibrary’’ link
as described above. The eLibrary link
also provides access to the texts of all
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. For more information and to
register, go to www.ferc.gov/docs-filing/
esubscription.asp.
Dated: January 28, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–02218 Filed 2–2–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP22–41–000]
Cameron LNG, LLC; Notice of
Application for Amendment and
Establishing Intervention Deadline
Take notice that on January 18, 2021,
Cameron LNG, LLC (Cameron LNG),
E:\FR\FM\03FEN1.SGM
03FEN1
Agencies
[Federal Register Volume 87, Number 23 (Thursday, February 3, 2022)]
[Notices]
[Pages 6162-6163]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-02218]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP22-40-000]
Eastern Shore Natural Gas; Notice of Request Under Blanket
Authorization and Establishing Intervention and Protest Deadline
Take notice that on January 18, 2022 Eastern Shore Natural Gas
(Eastern Shore) filed a prior notice request for authorization, in
accordance with 18 CFR Sections 157.203(c),157.205(b), 157.208(c) and
157.210 of the Federal Energy Regulatory Commission's (Commission)
regulations under the Natural Gas Act and Eastern Shore's blanket
certificate issued in Docket Nos. CP96-128-000, et al., to install an
additional compressor unit, adding 1,875 horse power of new compression
at Eastern Shore's existing Bridgeville Compressor Station site in
Sussex County, DE and appurtenant facilities required to provide
additional firm natural gas transportation service of 7,300 dekatherms
per day to an existing shipper on Eastern Shore's pipeline system, and
estimates that the cost of the project will be about $14,026,800, all
as more fully set forth in the application which is on file with the
Commission and open for public inspection.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact the Federal Energy
Regulatory Commission at [email protected] or call toll-free,
(886) 208-3676 or TYY, (202) 502-8659.
Any questions concerning this application should be directed to
Jeffrey R. Tietbohl, Vice President, Eastern Shore Natural Gas Company,
500 Energy Lane, Suite 200 Dover, Delaware 19901 at (302)-363-4679 or
email at [email protected] or pipeli[email protected].
Pursuant to Section 157.9 of the Commission's Rules of Practice and
Procedure,\1\ within 90 days of this Notice the Commission staff will
either: complete its environmental review and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or environmental
assessment (EA) for this proposal. The filing of an EA in the
Commission's public record for this proceeding or the issuance of a
Notice of Schedule for Environmental Review will serve to notify
federal and state agencies of the timing for the completion of all
necessary reviews, and the subsequent need to complete all federal
authorizations within 90 days of the date of issuance of the Commission
staff's FEIS or EA.
---------------------------------------------------------------------------
\1\ 18 CFR (Code of Federal Regulations) Sec. 157.9.
---------------------------------------------------------------------------
Public Participation
There are three ways to become involved in the Commission's review
of this project: you can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5:00 p.m. Eastern Time on March 29, 2022.
How
[[Page 6163]]
to file protests, motions to intervene, and comments is explained
below.
Protests
Pursuant to section 157.205 of the Commission's regulations under
the NGA,\2\ any person \3\ or the Commission's staff may file a protest
to the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the allowed
time for filing a protest, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request for authorization
will be considered by the Commission.
---------------------------------------------------------------------------
\2\ 18 CFR 157.205.
\3\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\4\ and must be submitted by
the protest deadline, which is March 29, 2022. A protest may also serve
as a motion to intervene so long as the protestor states it also seeks
to be an intervenor.
---------------------------------------------------------------------------
\4\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \5\ and the regulations under the NGA \6\ by the
intervention deadline for the project, which is March 29, 2022. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------
\5\ 18 CFR 385.214.
\6\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before March 29, 2022. The filing of a comment alone will not
serve to make the filer a party to the proceeding. To become a party,
you must intervene in the proceeding.
How to File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the Project docket number
CP22-40-000 in your submission.
(1) You may file your protest, motion to intervene, and comments by
using the Commission's eFiling feature, which is located on the
Commission's website (www.ferc.gov) under the link to Documents and
Filings. New eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing''; or \7\
---------------------------------------------------------------------------
\7\ Additionally, you may file your comments electronically by
using the eComment feature, which is located on the Commission's
website at www.ferc.gov under the link to Documents and Filings.
Using eComment is an easy method for interested persons to submit
brief, text-only comments on a project.
---------------------------------------------------------------------------
(2) You can file a paper copy of your submission by mailing it to
the address below. Your submission must reference the Project docket
number CP22-40-000.
To mail via USPS, use the following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426
To mail via any other courier, use the following address: Kimberly D.
Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852
The Commission encourages electronic filing of submissions (option
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected]
Protests and motions to intervene must be served on the applicant
either by mail or email (with a link to the document) at: Jeffrey R.
Tietbohl, Vice President, Eastern Shore Natural Gas Company, 500 Energy
Lane, Suite 200 Dover, Delaware 19901 at (302)-363-4679 or email at
[email protected] or [email protected].
Any subsequent submissions by an intervenor must be served on the
applicant and all other parties to the proceeding. Contact information
for parties can be downloaded from the service list at the eService
link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at www.ferc.gov using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
www.ferc.gov/docs-filing/esubscription.asp.
Dated: January 28, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-02218 Filed 2-2-22; 8:45 am]
BILLING CODE 6717-01-P