Cameron LNG, LLC; Notice of Application for Amendment and Establishing Intervention Deadline, 6163-6165 [2022-02214]

Download as PDF Federal Register / Vol. 87, No. 23 / Thursday, February 3, 2022 / Notices to file protests, motions to intervene, and comments is explained below. khammond on DSKJM1Z7X2PROD with NOTICES Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,2 any person 3 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,4 and must be submitted by the protest deadline, which is March 29, 2022. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 5 and the regulations under the NGA 6 by the intervention deadline for the project, which is March 29, 2022. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. All timely, unopposed motions to intervene are automatically granted by 2 18 CFR 157.205. 3 Persons include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 4 18 CFR 157.205(e). 5 18 CFR 385.214. 6 18 CFR 157.10. VerDate Sep<11>2014 18:08 Feb 02, 2022 Jkt 256001 operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before March 29, 2022. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. How to File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP22–40–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 7 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP22–40– 000. To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426 To mail via any other courier, use the following address: Kimberly D. Bose, 7 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 6163 Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852 The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: Jeffrey R. Tietbohl, Vice President, Eastern Shore Natural Gas Company, 500 Energy Lane, Suite 200 Dover, Delaware 19901 at (302)-363– 4679 or email at jtietbohl@esng.com or pipelines@chpk.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: January 28, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–02218 Filed 2–2–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP22–41–000] Cameron LNG, LLC; Notice of Application for Amendment and Establishing Intervention Deadline Take notice that on January 18, 2021, Cameron LNG, LLC (Cameron LNG), E:\FR\FM\03FEN1.SGM 03FEN1 khammond on DSKJM1Z7X2PROD with NOTICES 6164 Federal Register / Vol. 87, No. 23 / Thursday, February 3, 2022 / Notices 2925 Briarpark Drive, Suite 1000, Houston, Texas 77042, filed an application under section 3(a) of the Natural Gas Act (NGA) requesting an amendment to its May 5, 2016 Order 1 (2016 Order) to site, construct, and operate facilities to provide additional natural gas processing, storage, and liquefaction capacity at the existing site of the Cameron LNG liquefied natural gas terminal located in Cameron and Calcasieu Parishes, Louisiana (Amended Expansion Project). The proposed enhancements will reduce greenhouse gas (GHG) emissions from Train 4, will allow to access carbon capture and sequestration (CCS) facilities that may be developed in the region in the future, and will enhance the production capacity of Train 4. Cameron LNG also proposes a partial vacatur of the 2016 Order to exclude the construction and operation of Train 5 and a fifth LNG storage tank.2 With the removal of Train 5, the overall maximum production capacity of the Amended Expansion Project will be reduced from 9.97 MTPA to 6.75 MTPA, sourced exclusively from Train 4. The resultant total output capacity of the Cameron LNG terminal would be reduced from 24.95 MTPA (in service Trains 1–3 and Trains 4 & 5 which are approved but not in-service) to 21.7 MTPA (in service Trains 1–3 and enhanced Train 4). In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions regarding the proposed project should be directed to Blair 1 Cameron LNG, LLC, 155 FERC ¶ 61,141 (2016). 2016 Order authorized Cameron LNG to construct and operate two additional liquefaction trains (Trains 4 and 5) and one additional storage tank that would increase the Cameron LNG Terminal’s maximum natural gas liquefaction capacity by 9.97 million tonnes per annum (MTPA) referred to as the Expansion Project. 2 The VerDate Sep<11>2014 18:08 Feb 02, 2022 Jkt 256001 Woodward, General Counsel, Cameron LNG, LLC, 2925 Briarpark Drive, Suite 1000 Houston, TX 77042, (832) 783– 5582, bwoodward@cameronlng.com; or Brett A. Snyder or Lamiya Rahman, 1825 Eye Street NW, Washington, DC 20006, (202) 420–2200, brett.snyder@ blankrome.com or lamiya.rahman@ blankrome.com. Pursuant to Section 157.9 of the Commission’s Rules of Practice and Procedure,3 within 90 days of this Notice the Commission staff will either: Complete its environmental review and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Public Participation There are two ways to become involved in the Commission’s review of this project: You can file comments on the project, and you can file a motion to intervene in the proceeding. There is no fee or cost for filing comments or intervening. The deadline for filing a motion to intervene is 5:00 p.m. Eastern Time on February 18, 2022. Comments Any person wishing to comment on the project may do so. Comments may include statements of support or objections to the project as a whole or specific aspects of the project. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please submit your comments on or before February 18, 2021. There are three methods you can use to submit your comments to the Commission. In all instances, please reference the Project docket number CP22–41–000 in your submission. (1) You may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov 3 18 PO 00000 CFR (Code of Federal Regulations) § 157.9. Frm 00034 Fmt 4703 Sfmt 4703 under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project; (2) You may file your comments electronically by using the eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address below. Your written comments must reference the Project docket number (CP22–41–000). To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To mail via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission encourages electronic filing of comments (options 1 and 2 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Persons who comment on the environmental review of this project will be placed on the Commission’s environmental mailing list, and will receive notification when the nvironmental documents (EA or EIS) are issued for this project and will be notified of meetings associated with the Commission’s environmental review process. The Commission considers all comments received about the project in determining the appropriate action to be taken. However, the filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. For instructions on how to intervene, see below. Interventions Any person, which includes individuals, organizations, businesses, municipalities, and other entities,4 has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently 4 18 E:\FR\FM\03FEN1.SGM CFR 385.102(d). 03FEN1 khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 87, No. 23 / Thursday, February 3, 2022 / Notices challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 5 and the regulations under the NGA 6 by the intervention deadline for the project, which is February 18, 2022. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. [For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene.] For more information about motions to intervene, refer to the FERC website at https:// www.ferc.gov/resources/guides/how-to/ intervene.asp. There are two ways to submit your motion to intervene. In both instances, please reference the Project docket number CP22–41–000 in your submission. (1) You may file your motion to intervene by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Intervention.’’ The eFiling feature includes a document-less intervention option; for more information, visit https://www.ferc.gov/docs-filing/efiling/ document-less-intervention.pdf; or (2) You can file a paper copy of your motion to intervene, along with three copies, by mailing the documents to the address below . Your motion to intervene must reference the Project docket number CP22–41–000. To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To mail via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission encourages electronic filing of motions to intervene (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. 5 18 6 18 CFR 385.214. CFR 157.10. VerDate Sep<11>2014 19:04 Feb 02, 2022 Jkt 256001 Motions to intervene must be served on the applicant either by mail or email at: Cameron LNG, LLC, 2925 Briarpark Drive, Suite 1000, Houston, TX 77042, or at bwoodward@cameronlng.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Service can be via email with a link to the document. All timely, unopposed 7 motions to intervene are automatically granted by operation of Rule 214(c)(1).8 Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations.9 A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Intervention Deadline: 5:00 p.m. Eastern Time on February 18, 2022. Dated: January 28, 2022. Kimberly D. Bose, Secretary. BILLING CODE 6717–01–P 7 The applicant has 15 days from the submittal of a motion to intervene to file a written objection to the intervention. 8 18 CFR 385.214(c)(1). 9 18 CFR 385.214(b)(3) and (d). PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–463–000] Texas Eastern Transmission, LP Notice of Schedule for the Preparation of an Environmental Assessment for the Holbrook Compressor Units Replacement Project On June 17, 2021, Texas Eastern Transmission, LP (Texas Eastern) filed an application in Docket No. CP21–463– 000 requesting authorization and a Certificate of Public Convenience and Necessity pursuant to Sections 7(b) and 7(c) of the Natural Gas Act to abandon certain natural gas facilities, and construct, operate, and maintain certain natural gas facilities. The proposed project is known as the Holbrook Compressor Station Replacement Project (Project). Texas Eastern is requesting authorization to abandon twelve existing reciprocating compressor units installed in the 1950s at its Holbrook Compressor Station in Greene County, Pennsylvania, and replace them with two new, more efficient gas turbines. On July 2, 2021, the Federal Energy Regulatory Commission (FERC or Commission) issued its Notice of Application for the Project. Among other things, that notice alerted other agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on the request for a federal authorization within 90 days of the date of issuance of the Commission staff’s environmental document for the Project. This notice identifies the Commission staff’s intention to prepare an environmental assessment (EA) for the Project and the planned schedule for completion of the environmental review.1 Schedule for Environmental Review Issuance of EA—May 12, 2022 90-day Federal Authorization Decision Deadline 2—August 10, 2022 If a schedule change becomes necessary for the EA, an additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. 1 40 [FR Doc. 2022–02214 Filed 2–2–22; 8:45 am] 6165 CFR 1501.10 (2020) Commission’s deadline applies to the decisions of other federal agencies, and state agencies acting under federally delegated authority, that are responsible for federal authorizations, permits, and other approvals necessary for proposed projects under the Natural Gas Act. Per 18 CFR 157.22(a), the Commission’s deadline for other agency’s decisions applies unless a schedule is otherwise established by federal law. 2 The E:\FR\FM\03FEN1.SGM 03FEN1

Agencies

[Federal Register Volume 87, Number 23 (Thursday, February 3, 2022)]
[Notices]
[Pages 6163-6165]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-02214]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP22-41-000]


Cameron LNG, LLC; Notice of Application for Amendment and 
Establishing Intervention Deadline

    Take notice that on January 18, 2021, Cameron LNG, LLC (Cameron 
LNG),

[[Page 6164]]

2925 Briarpark Drive, Suite 1000, Houston, Texas 77042, filed an 
application under section 3(a) of the Natural Gas Act (NGA) requesting 
an amendment to its May 5, 2016 Order \1\ (2016 Order) to site, 
construct, and operate facilities to provide additional natural gas 
processing, storage, and liquefaction capacity at the existing site of 
the Cameron LNG liquefied natural gas terminal located in Cameron and 
Calcasieu Parishes, Louisiana (Amended Expansion Project). The proposed 
enhancements will reduce greenhouse gas (GHG) emissions from Train 4, 
will allow to access carbon capture and sequestration (CCS) facilities 
that may be developed in the region in the future, and will enhance the 
production capacity of Train 4.
---------------------------------------------------------------------------

    \1\ Cameron LNG, LLC, 155 FERC ] 61,141 (2016).
---------------------------------------------------------------------------

    Cameron LNG also proposes a partial vacatur of the 2016 Order to 
exclude the construction and operation of Train 5 and a fifth LNG 
storage tank.\2\ With the removal of Train 5, the overall maximum 
production capacity of the Amended Expansion Project will be reduced 
from 9.97 MTPA to 6.75 MTPA, sourced exclusively from Train 4. The 
resultant total output capacity of the Cameron LNG terminal would be 
reduced from 24.95 MTPA (in service Trains 1-3 and Trains 4 & 5 which 
are approved but not in-service) to 21.7 MTPA (in service Trains 1-3 
and enhanced Train 4).
---------------------------------------------------------------------------

    \2\ The 2016 Order authorized Cameron LNG to construct and 
operate two additional liquefaction trains (Trains 4 and 5) and one 
additional storage tank that would increase the Cameron LNG 
Terminal's maximum natural gas liquefaction capacity by 9.97 million 
tonnes per annum (MTPA) referred to as the Expansion Project.
---------------------------------------------------------------------------

    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact the Federal Energy 
Regulatory Commission at [email protected] or call toll-free, 
(886) 208-3676 or TYY, (202) 502-8659.
    Any questions regarding the proposed project should be directed to 
Blair Woodward, General Counsel, Cameron LNG, LLC, 2925 Briarpark 
Drive, Suite 1000 Houston, TX 77042, (832) 783-5582, 
[email protected]; or Brett A. Snyder or Lamiya Rahman, 1825 Eye 
Street NW, Washington, DC 20006, (202) 420-2200, 
[email protected] or [email protected].
    Pursuant to Section 157.9 of the Commission's Rules of Practice and 
Procedure,\3\ within 90 days of this Notice the Commission staff will 
either: Complete its environmental review and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or environmental 
assessment (EA) for this proposal. The filing of an EA in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
---------------------------------------------------------------------------

    \3\ 18 CFR (Code of Federal Regulations) Sec.  157.9.
---------------------------------------------------------------------------

Public Participation

    There are two ways to become involved in the Commission's review of 
this project: You can file comments on the project, and you can file a 
motion to intervene in the proceeding. There is no fee or cost for 
filing comments or intervening. The deadline for filing a motion to 
intervene is 5:00 p.m. Eastern Time on February 18, 2022.

Comments

    Any person wishing to comment on the project may do so. Comments 
may include statements of support or objections to the project as a 
whole or specific aspects of the project. The more specific your 
comments, the more useful they will be. To ensure that your comments 
are timely and properly recorded, please submit your comments on or 
before February 18, 2021.
    There are three methods you can use to submit your comments to the 
Commission. In all instances, please reference the Project docket 
number CP22-41-000 in your submission.
    (1) You may file your comments electronically by using the eComment 
feature, which is located on the Commission's website at www.ferc.gov 
under the link to Documents and Filings. Using eComment is an easy 
method for interested persons to submit brief, text-only comments on a 
project;
    (2) You may file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. With eFiling, you can provide 
comments in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; first select ``General'' and then select ``Comment on a 
Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address below. Your written comments must reference the 
Project docket number (CP22-41-000).
    To mail via USPS, use the following address: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.
    To mail via any other courier, use the following address: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852.
    The Commission encourages electronic filing of comments (options 1 
and 2 above) and has eFiling staff available to assist you at (202) 
502-8258 or [email protected]
    Persons who comment on the environmental review of this project 
will be placed on the Commission's environmental mailing list, and will 
receive notification when the nvironmental documents (EA or EIS) are 
issued for this project and will be notified of meetings associated 
with the Commission's environmental review process.
    The Commission considers all comments received about the project in 
determining the appropriate action to be taken. However, the filing of 
a comment alone will not serve to make the filer a party to the 
proceeding. To become a party, you must intervene in the proceeding. 
For instructions on how to intervene, see below.

Interventions

    Any person, which includes individuals, organizations, businesses, 
municipalities, and other entities,\4\ has the option to file a motion 
to intervene in this proceeding. Only intervenors have the right to 
request rehearing of Commission orders issued in this proceeding and to 
subsequently

[[Page 6165]]

challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
---------------------------------------------------------------------------

    \4\ 18 CFR 385.102(d).
---------------------------------------------------------------------------

    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \5\ and the regulations under the NGA \6\ by the 
intervention deadline for the project, which is February 18, 2022. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. [For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene.] For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \5\ 18 CFR 385.214.
    \6\ 18 CFR 157.10.
---------------------------------------------------------------------------

    There are two ways to submit your motion to intervene. In both 
instances, please reference the Project docket number CP22-41-000 in 
your submission.
    (1) You may file your motion to intervene by using the Commission's 
eFiling feature, which is located on the Commission's website 
(www.ferc.gov) under the link to Documents and Filings. New eFiling 
users must first create an account by clicking on ``eRegister.'' You 
will be asked to select the type of filing you are making; first select 
``General'' and then select ``Intervention.'' The eFiling feature 
includes a document-less intervention option; for more information, 
visit https://www.ferc.gov/docs-filing/efiling/document-less-intervention.pdf; or
    (2) You can file a paper copy of your motion to intervene, along 
with three copies, by mailing the documents to the address below . Your 
motion to intervene must reference the Project docket number CP22-41-
000.
    To mail via USPS, use the following address: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.
    To mail via any other courier, use the following address: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852.
    The Commission encourages electronic filing of motions to intervene 
(option 1 above) and has eFiling staff available to assist you at (202) 
502-8258 or [email protected]
    Motions to intervene must be served on the applicant either by mail 
or email at: Cameron LNG, LLC, 2925 Briarpark Drive, Suite 1000, 
Houston, TX 77042, or at [email protected]. Any subsequent 
submissions by an intervenor must be served on the applicant and all 
other parties to the proceeding. Contact information for parties can be 
downloaded from the service list at the eService link on FERC Online. 
Service can be via email with a link to the document.
    All timely, unopposed \7\ motions to intervene are automatically 
granted by operation of Rule 214(c)(1).\8\ Motions to intervene that 
are filed after the intervention deadline are untimely and may be 
denied. Any late-filed motion to intervene must show good cause for 
being late and must explain why the time limitation should be waived 
and provide justification by reference to factors set forth in Rule 
214(d) of the Commission's Rules and Regulations.\9\ A person obtaining 
party status will be placed on the service list maintained by the 
Secretary of the Commission and will receive copies (paper or 
electronic) of all documents filed by the applicant and by all other 
parties.
---------------------------------------------------------------------------

    \7\ The applicant has 15 days from the submittal of a motion to 
intervene to file a written objection to the intervention.
    \8\ 18 CFR 385.214(c)(1).
    \9\ 18 CFR 385.214(b)(3) and (d).
---------------------------------------------------------------------------

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Intervention Deadline: 5:00 p.m. Eastern Time on February 18, 2022.

    Dated: January 28, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-02214 Filed 2-2-22; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.