Alabama Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 4577-4578 [2022-01756]
Download as PDF
Federal Register / Vol. 87, No. 19 / Friday, January 28, 2022 / Notices
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Dated: January 24, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–01752 Filed 1–27–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. IN17–4–000]
Rover Pipeline, LLC; Energy Transfer
Partners, L.P.; Updated Notice of
Designation of Commission Staff as
Non-Decisional
With respect to an order issued by the
Commission on December 16, 2021, in
the above-captioned docket, with the
exceptions noted below, the staff of the
Office of Enforcement are designated as
non-decisional in deliberations by the
Commission in this docket.1
Accordingly, pursuant to 18 CFR
385.2202 (2021), they will not serve as
advisors to the Commission or take part
in the Commission’s review of any offer
of settlement. Likewise, as nondecisional staff, pursuant to 18 CFR
385.2201 (2021), they are prohibited
from communicating with advisory staff
concerning any deliberations in this
docket.
Exceptions to this designation as nondecisional are:
jspears on DSK121TN23PROD with NOTICES1
Serrita Hill
Seema K. Jain
Grace Kwon
Gabriel Sterling
Dated: January 21, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–01679 Filed 1–27–22; 8:45 am]
BILLING CODE 6717–01–P
1 Rover Pipeline, LLC and Energy Transfer
Partners, L.P., 177 FERC ¶ 61,182 (2021).
VerDate Sep<11>2014
18:03 Jan 27, 2022
Jkt 256001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 349–166]
Alabama Power Company; Notice of
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Non-Project
Use of Project Lands and Waters.
b. Project No.: 349–166.
c. Date Filed: December 8, 2021.
d. Applicant: Alabama Power
Company.
e. Name of Project: Martin Dam
Hydroelectric Project.
f. Location: The Martin Dam
Hydroelectric Project is located on the
Tallapoosa River (Lake Martin), in
Tallapoosa, Elmore, and Coosa counties,
Alabama, and occupies federal land
administered by the U.S. Bureau of
Land Management; the non-project use
is located in Tallapoosa County.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Unzell Kelley,
Alabama Power Company at (205) 517–
0885 or ukelley@southernco.com.
i. FERC Contact: Shana High at (202)
502–8674 or shana.high@ferc.gov.
j. Deadline for filing motions to
intervene and protests: February 23,
2022.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
4577
page of any filing should include docket
number P–349–166. Comments emailed
to Commission staff are not considered
part of the Commission record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: Alabama
Power Company is requesting
Commission approval to permit Harbor
Pointe Marina to dredge approximately
1,492 cubic yards at its existing
commercial marina.
l. Locations of the Application: This
filing may be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. Agencies may
obtain copies of the application directly
from the applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
E:\FR\FM\28JAN1.SGM
28JAN1
4578
Federal Register / Vol. 87, No. 19 / Friday, January 28, 2022 / Notices
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
Dated: January 24, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–01756 Filed 1–27–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 11132–029]
jspears on DSK121TN23PROD with NOTICES1
KEI (USA) Power Management (I), LLC;
Notice of Intent To File License
Application, Filing of Pre-Application
Document, and Approving Use of the
Traditional Licensing Process
a. Type of Filing: Notice of Intent to
File License Application and Request to
Use the Traditional Licensing Process.
b. Project No.: 11132–029.
c. Date Filed: November 22, 2021.
d. Submitted By: KEI (USA) Power
Management (I), LLC (KEI).
e. Name of Project: Eustis
Hydroelectric Project (project).
f. Location: On the North Branch of
the Dead River in Franklin County,
Maine. No federal lands are occupied by
the project works or located within the
project boundary.
g. Filed Pursuant to: 18 CFR 5.3 and
5.5 of the Commission’s regulations.
h. Potential Applicant Contact: Mr.
Lewis C. Loon, KEI (USA) Power
Management (III) LLC.; 423 Brunswick
Avenue, Gardiner, ME 04345; (207)
203–3027; or email at LewisC.Loon@
kruger.com.
i. FERC Contact: Erin Kimsey at (202)
502–8621; or email at erin.kimsey@
ferc.gov.
j. KEI filed its request to use the
Traditional Licensing Process on
November 22, 2021, and provided
public notice of its request on November
16, 2021. In a letter dated January 21,
2022, the Director of the Division of
Hydropower Licensing approved KEI’s
request to use the Traditional Licensing
Process.
k. With this notice, we are initiating
informal consultation with the U.S. Fish
VerDate Sep<11>2014
18:03 Jan 27, 2022
Jkt 256001
and Wildlife Service and NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, part 402; and NOAA Fisheries
under section 305(b) of the MagnusonStevens Fishery Conservation and
Management Act and implementing
regulations at 50 CFR 600.920. We are
also initiating consultation with the
Maine State Historic Preservation
Officer, as required by section 106 of the
National Historic Preservation Act, and
the implementing regulations of the
Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. With this notice, we are designating
KEI as the Commission’s non-federal
representative for carrying out informal
consultation pursuant to section 7 of the
Endangered Species Act and section
305(b) of the Magnuson-Stevens Fishery
Conservation and Management Act; and
consultation pursuant to section 106 of
the National Historic Preservation Act.
m. On November 22, 2021, KEI filed
a Pre-Application Document (PAD;
including a proposed process plan and
schedule) with the Commission,
pursuant to 18 CFR 5.6 of the
Commission’s regulations.
n. A copy of the PAD may be viewed
and/or printed on the Commission’s
website (https://www.ferc.gov), using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY).
o. The licensee states its unequivocal
intent to submit an application for a
subsequent license for Project No.
11132. Pursuant to 18 CFR 16.20, each
application for a subsequent license and
any competing license applications
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license. All applications
for license for this project must be filed
by November 30, 2024.
p. Register online at https://
ferconline.ferc.gov/FERCOnline.aspx to
be notified via email of new filings and
issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
Dated: January 21, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–01682 Filed 1–27–22; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP22–2–000]
Gas Transmission Northwest LLC;
Notice of Intent To Prepare an
Environmental Impact Statement for
The Proposed GTN Xpress Project
Request for Comments on
Environmental Issues, and Schedule
for Environmental Review
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental impact statement (EIS)
that will discuss the environmental
impacts of the GTN XPress Project
(Project) involving the modification and
operation of existing compression
facilities by Gas Transmission
Northwest LLC (GTN) in Idaho,
Washington, and Oregon. The
Commission will use this EIS in its
decision-making process to determine
whether the Project is in the public
convenience and necessity. The
schedule for preparation of the EIS is
discussed in the Schedule for
Environmental Review section of this
notice.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
project. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. This
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and the EIS section of this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document, including
comments on potential alternatives and
impacts, and any relevant information,
studies, or analyses of any kind
concerning impacts affecting the quality
of the human environment.
To ensure that your comments are
timely and properly recorded, please
submit your comments so that the
Commission receives them in
Washington, DC on or before 5:00 p.m.
E:\FR\FM\28JAN1.SGM
28JAN1
Agencies
[Federal Register Volume 87, Number 19 (Friday, January 28, 2022)]
[Notices]
[Pages 4577-4578]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-01756]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 349-166]
Alabama Power Company; Notice of Application Accepted for Filing
and Soliciting Comments, Motions To Intervene, and Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Non-Project Use of Project Lands and
Waters.
b. Project No.: 349-166.
c. Date Filed: December 8, 2021.
d. Applicant: Alabama Power Company.
e. Name of Project: Martin Dam Hydroelectric Project.
f. Location: The Martin Dam Hydroelectric Project is located on the
Tallapoosa River (Lake Martin), in Tallapoosa, Elmore, and Coosa
counties, Alabama, and occupies federal land administered by the U.S.
Bureau of Land Management; the non-project use is located in Tallapoosa
County.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Unzell Kelley, Alabama Power Company at (205)
517-0885 or [email protected].
i. FERC Contact: Shana High at (202) 502-8674 or
[email protected].
j. Deadline for filing motions to intervene and protests: February
23, 2022.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, and protests using the Commission's
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may
submit a paper copy. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. The first page of any filing should
include docket number P-349-166. Comments emailed to Commission staff
are not considered part of the Commission record.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervenor files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency.
k. Description of Request: Alabama Power Company is requesting
Commission approval to permit Harbor Pointe Marina to dredge
approximately 1,492 cubic yards at its existing commercial marina.
l. Locations of the Application: This filing may be viewed on the
Commission's website at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. You may also register
online at https://www.ferc.gov/docs-filing/esubscription.asp to be
notified via email of new filings and issuances related to this or
other pending projects. For assistance, call 1-866-208-3676 or email
[email protected], for TTY, call (202) 502-8659. Agencies may
obtain copies of the application directly from the applicant.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214, respectively. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a party to the proceeding. Any comments,
protests, or motions to intervene must be received on or before the
specified comment date for the particular application.
o. Filing and Service of Documents: Any filing must (1) bear in all
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO
INTERVENE'' as applicable; (2) set forth in the heading the name of the
applicant and the project number of the application to which the filing
[[Page 4578]]
responds; (3) furnish the name, address, and telephone number of the
person commenting, protesting or intervening; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis. Any filing made by an intervenor must be accompanied
by proof of service on all persons listed in the service list prepared
by the Commission in this proceeding, in accordance with 18 CFR
385.2010.
Dated: January 24, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-01756 Filed 1-27-22; 8:45 am]
BILLING CODE 6717-01-P