Georgia Power Company; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 3293-3294 [2022-01174]

Download as PDF Federal Register / Vol. 87, No. 14 / Friday, January 21, 2022 / Notices jspears on DSK121TN23PROD with NOTICES1 Dated: January 14, 2022. Kimberly D. Bose, Secretary. Applicants: Spotlight Power LLC. Description: Baseline eTariff Filing: Spotlight Power LLC Baseline MBR Tariff & Application to be effective 2/1/ [FR Doc. 2022–01170 Filed 1–20–22; 8:45 am] 2022. BILLING CODE 6717–01–P Filed Date: 1/14/22. Accession Number: 20220114–5065. Comment Date: 5 p.m. ET 2/4/22. DEPARTMENT OF ENERGY Docket Numbers: ER22–822–000. Federal Energy Regulatory Applicants: Southwest Power Pool, Commission Inc. Description: § 205(d) Rate Filing: Combined Notice of Filings #1 3164R1 Milligan 3 Wind LLC GIA Cancellation to be effective 1/9/2022. Take notice that the Commission Filed Date: 1/14/22. received the following electric rate Accession Number: 20220114–5095. filings: Comment Date: 5 p.m. ET 2/4/22. Docket Numbers: ER17–1821–004. Docket Numbers: ER22–823–000. Applicants: Panda Stonewall LLC. Applicants: PJM Interconnection, Description: Refund Report: Potomac L.L.C. Energy Center, LLC submits tariff filing Description: § 205(d) Rate Filing: per 35.19a(b): Refund Report to be Amendment to ISA, Service Agreement effective N/A. No. 3761, Racine ISA (consent) to be Filed Date: 1/14/22. effective 12/31/2013. Accession Number: 20220114–5146. Filed Date: 1/14/22. Comment Date: 5 p.m. ET 2/4/22. Accession Number: 20220114–5129. Docket Numbers: ER22–46–003. Comment Date: 5 p.m. ET 2/4/22. Applicants: Parkway Generation Docket Numbers: ER22–824–000. Essex, LLC. Applicants: Mid-Atlantic Interstate Description: Tariff Amendment: Transmission, LLC, PJM Supplement to Petition for Order Interconnection, L.L.C. Accepting for Filing Market-Based Rate Description: § 205(d) Rate Filing: MidTariff to be effective 12/1/2021. Atlantic Interstate Transmission, LLC Filed Date: 1/14/22. submits tariff filing per 35.13(a)(2)(iii: Accession Number: 20220114–5122. Comment Date: 5 p.m. ET 2/4/22. MAIT submits SA No. 6148 Tipton ECSA to be effective 3/16/2022. Docket Numbers: ER22–186–001. Filed Date: 1/14/22. Applicants: Middletown Coke Accession Number: 20220114–5160. Company, LLC. Comment Date: 5 p.m. ET 2/4/22. Description: Tariff Amendment: Supplemental Filing to 187 to be Docket Numbers: ER22–825–000. effective 11/1/2021. Applicants: American Transmission Filed Date: 1/14/22. Systems, Incorporated, PJM Accession Number: 20220114–5100. Interconnection, L.L.C. Comment Date: 5 p.m. ET 2/4/22. Description: § 205(d) Rate Filing: American Transmission Systems, Docket Numbers: ER22–764–001. Incorporated submits tariff filing per Applicants: PJM Interconnection, 35.13(a)(2)(iii: ATSI submits two L.L.C. Description: Tariff Amendment: Errata ECSAs, SA Nos. 6142 Ivanhoe & 6149 Ontario to be effective 3/16/2022. to WMPA, SA No. 6273; Queue No. Filed Date: 1/14/22. AG2–422 in Docket No. ER22–764–000 Accession Number: 20220114–5167. to be effective 12/7/2021. Comment Date: 5 p.m. ET 2/4/22. Filed Date: 1/14/22. Accession Number: 20220114–5179. Docket Numbers: ER22–826–000. Comment Date: 5 p.m. ET 2/4/22. Applicants: Mid-Atlantic Interstate Transmission, LLC, Pennsylvania Docket Numbers: ER22–820–000. Electric Company, PJM Interconnection, Applicants: The Potomac Edison L.L.C. Company, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: MidDescription: § 205(d) Rate Filing: The Potomac Edison Company submits tariff Atlantic Interstate Transmission, LLC filing per 35.13(a)(2)(iii: Potomac Edison submits tariff filing per 35.13(a)(2)(iii: MAIT, Penelec and AEC submit SA No. submits Construction SA No. 6133 5775 Saltillo Construction Agreement to Hagerstown-Maple Ave Project to be be effective 3/16/2022. effective 3/15/2022. Filed Date: 1/14/22. Filed Date: 1/13/22. Accession Number: 20220114–5174. Accession Number: 20220113–5159. Comment Date: 5 p.m. ET 2/4/22. Comment Date: 5 p.m. ET 2/3/22. Docket Numbers: ER22–827–000. Docket Numbers: ER22–821–000. VerDate Sep<11>2014 17:39 Jan 20, 2022 Jkt 256001 PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 3293 Applicants: Kentucky Utilities Company. Description: § 205(d) Rate Filing: Amended and Restated Agreement for Borderline Service with Appalachian Power Co to be effective 1/17/2022. Filed Date: 1/14/22. Accession Number: 20220114–5178. Comment Date: 5 p.m. ET 2/4/22. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES22–25–000. Applicants: Union Electric Company d/b/a Ameren Missouri. Description: Application Under Section 204 of the Federal Power Act for Authorization to Issue Securities of Union Electric Company. Filed Date: 1/14/22. Accession Number: 20220114–5175. Comment Date: 5 p.m. ET 2/4/22. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: January 14, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–01172 Filed 1–20–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2336–101] Georgia Power Company; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. E:\FR\FM\21JAN1.SGM 21JAN1 jspears on DSK121TN23PROD with NOTICES1 3294 Federal Register / Vol. 87, No. 14 / Friday, January 21, 2022 / Notices a. Type of Application: New Major License. b. Project No.: 2336–101. c. Date Filed: January 3, 2022. d. Applicant: Georgia Power Company (Georgia Power). e. Name of Project: Lloyd Shoals Hydroelectric Project (Lloyd Shoals Project.) f. Location: The Lloyd Shoals Project is located on the Ocmulgee River in Butts, Henry, Jasper, and Newton Counties, Georgia. The project does not occupy any federal land. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Courtenay O’Mara, Hydro Licensing & Compliance Supervisor; Georgia Power Company; 241 Ralph McGill Boulevard NE; Bin 10193; Atlanta, Georgia 30308–3374; (404) 506–7219, or email at cromara@ southernco.com. i. FERC Contact: Navreet Deo at (202) 502–6304, or email at navreet.deo@ ferc.gov. j. This application is not ready for environmental analysis at this time. k. The Lloyd Shoals Project consists of: (1) The 4,750-acre Lake Jackson at normal pool elevation of 530 feet Plant Datum (PD) with a gross storage capacity of 107,000 acre-feet; (2) a 1,600-foot-long, 106-foot-high concrete gravity dam consisting of a 143-footlong non-overflow section, a 198-footlong powerhouse intake section with six, 12-foot-high by 12-foot-wide octagonal water passages supplying the generating units, a 728.5-foot-long spillway section consisting of a trash gate and an Obermeyer gate system, and a 530-foot-long earth embankment tiein; (3) a concrete and brick powerhouse containing six horizontal Francis turbine-generator units, each rated at 3.0-megawatts (MW), for a total authorized installed capacity of 18–MW; (4) a 2,100-foot-long saddle dike approximately 3,000 feet upstream of the east end of the main dam; (5) a 500foot-long auxiliary spillway, topped with 10-foot-high flashboards, located 900 feet southwest of the main dam, which includes a 560-foot-long, 6-foothigh sacrificial earth embankment; (6) two 2.3-kilovolt generator leads connecting the powerhouse to a substation located at the west dam abutment; and (7) appurtenant facilities. Georgia Power proposes no modifications to existing project facilities. The Lloyd Shoals Project operates in a modified run-of-river mode to generate power during peak demand. Reservoir elevations are maintained between 530 feet PD and 527 feet PD year-round, excluding planned drawdowns and VerDate Sep<11>2014 17:39 Jan 20, 2022 Jkt 256001 drought. The project provides a continuous minimum flow of 400 cubic feet per second (cfs), or inflow, to the Ocmulgee River downstream for the protection and enhancement of fish and wildlife resources and other downstream resources. Georgia Power proposes no changes to project operation. Georgia Power proposes environmental measures to improve and enhance water quality, aquatic habitat, and recreation facilities. Georgia Power also proposes plans for protection of shoreline resources and historic properties. l. A copy of the application can be viewed on the Commission’s website at https://www.ferc.gov, using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field, to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19) issued on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov, or call toll-free, (866) 208–3676 or (202) 502– 8659 (TTY). m. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Procedural schedule: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Milestone Target date Issue Deficiency Letter (if necessary). Request Additional Information (if necessary). Notice of Acceptance/Notice of Ready for Environmental Analysis. January 2022. February 2022. March 2022 Dated: January 14, 2022. Kimberly D. Bose, Secretary. Frm 00017 Fmt 4703 Sfmt 4703 Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP22–484–000. Applicants: Kinder Morgan Louisiana Pipeline LLC. Description: § 4(d) Rate Filing: NonConforming Negotiated Rate Agreement Filing-Sabine Pass Liquefaction, LLC to be effective 2/1/2022. Filed Date: 1/13/22. Accession Number: 20220113–5136. Comment Date: 5 p.m. ET 1/20/22. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: January 14, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–01171 Filed 1–20–22; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY Science Advisory Committee on Chemicals (SACC); Notice of Public Meeting and Request for Comments on Draft Toxic Substances Control Act (TSCA) Screening Level Approach for Assessing Ambient Air and Water Exposures to Fenceline Communities Environmental Protection Agency (EPA). ACTION: Notice. AGENCY: [FR Doc. 2022–01174 Filed 1–20–22; 8:45 am] PO 00000 Federal Energy Regulatory Commission [EPA–HQ–OPPT–2021–0415; FRL–9392–01– OCSPP] o. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. BILLING CODE 6717–01–P DEPARTMENT OF ENERGY E:\FR\FM\21JAN1.SGM 21JAN1

Agencies

[Federal Register Volume 87, Number 14 (Friday, January 21, 2022)]
[Notices]
[Pages 3293-3294]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-01174]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2336-101]


Georgia Power Company; Notice of Application Tendered for Filing 
With the Commission and Establishing Procedural Schedule for Licensing 
and Deadline for Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.

[[Page 3294]]

    a. Type of Application: New Major License.
    b. Project No.: 2336-101.
    c. Date Filed: January 3, 2022.
    d. Applicant: Georgia Power Company (Georgia Power).
    e. Name of Project: Lloyd Shoals Hydroelectric Project (Lloyd 
Shoals Project.)
    f. Location: The Lloyd Shoals Project is located on the Ocmulgee 
River in Butts, Henry, Jasper, and Newton Counties, Georgia. The 
project does not occupy any federal land.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Courtenay O'Mara, Hydro Licensing & 
Compliance Supervisor; Georgia Power Company; 241 Ralph McGill 
Boulevard NE; Bin 10193; Atlanta, Georgia 30308-3374; (404) 506-7219, 
or email at [email protected].
    i. FERC Contact: Navreet Deo at (202) 502-6304, or email at 
[email protected].
    j. This application is not ready for environmental analysis at this 
time.
    k. The Lloyd Shoals Project consists of: (1) The 4,750-acre Lake 
Jackson at normal pool elevation of 530 feet Plant Datum (PD) with a 
gross storage capacity of 107,000 acre-feet; (2) a 1,600-foot-long, 
106-foot-high concrete gravity dam consisting of a 143-foot-long non-
overflow section, a 198-foot-long powerhouse intake section with six, 
12-foot-high by 12-foot-wide octagonal water passages supplying the 
generating units, a 728.5-foot-long spillway section consisting of a 
trash gate and an Obermeyer gate system, and a 530-foot-long earth 
embankment tie-in; (3) a concrete and brick powerhouse containing six 
horizontal Francis turbine-generator units, each rated at 3.0-megawatts 
(MW), for a total authorized installed capacity of 18-MW; (4) a 2,100-
foot-long saddle dike approximately 3,000 feet upstream of the east end 
of the main dam; (5) a 500-foot-long auxiliary spillway, topped with 
10-foot-high flashboards, located 900 feet southwest of the main dam, 
which includes a 560-foot-long, 6-foot-high sacrificial earth 
embankment; (6) two 2.3-kilovolt generator leads connecting the 
powerhouse to a substation located at the west dam abutment; and (7) 
appurtenant facilities. Georgia Power proposes no modifications to 
existing project facilities.
    The Lloyd Shoals Project operates in a modified run-of-river mode 
to generate power during peak demand. Reservoir elevations are 
maintained between 530 feet PD and 527 feet PD year-round, excluding 
planned drawdowns and drought. The project provides a continuous 
minimum flow of 400 cubic feet per second (cfs), or inflow, to the 
Ocmulgee River downstream for the protection and enhancement of fish 
and wildlife resources and other downstream resources. Georgia Power 
proposes no changes to project operation.
    Georgia Power proposes environmental measures to improve and 
enhance water quality, aquatic habitat, and recreation facilities. 
Georgia Power also proposes plans for protection of shoreline resources 
and historic properties.
    l. A copy of the application can be viewed on the Commission's 
website at https://www.ferc.gov, using the ``eLibrary'' link. Enter the 
docket number, excluding the last three digits in the docket number 
field, to access the document. At this time, the Commission has 
suspended access to the Commission's Public Reference Room due to the 
proclamation declaring a National Emergency concerning the Novel 
Coronavirus Disease (COVID-19) issued on March 13, 2020. For 
assistance, contact FERC at [email protected], or call toll-
free, (866) 208-3676 or (202) 502-8659 (TTY).
    m. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Procedural schedule: The application will be processed according 
to the following preliminary schedule. Revisions to the schedule will 
be made as appropriate.

------------------------------------------------------------------------
                Milestone                           Target date
------------------------------------------------------------------------
Issue Deficiency Letter (if necessary)..  January 2022.
Request Additional Information (if        February 2022.
 necessary).
Notice of Acceptance/Notice of Ready for  March 2022
 Environmental Analysis.
------------------------------------------------------------------------

    o. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: January 14, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-01174 Filed 1-20-22; 8:45 am]
BILLING CODE 6717-01-P