Georgia Power Company; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 3293-3294 [2022-01174]
Download as PDF
Federal Register / Vol. 87, No. 14 / Friday, January 21, 2022 / Notices
jspears on DSK121TN23PROD with NOTICES1
Dated: January 14, 2022.
Kimberly D. Bose,
Secretary.
Applicants: Spotlight Power LLC.
Description: Baseline eTariff Filing:
Spotlight Power LLC Baseline MBR
Tariff & Application to be effective 2/1/
[FR Doc. 2022–01170 Filed 1–20–22; 8:45 am]
2022.
BILLING CODE 6717–01–P
Filed Date: 1/14/22.
Accession Number: 20220114–5065.
Comment Date: 5 p.m. ET 2/4/22.
DEPARTMENT OF ENERGY
Docket Numbers: ER22–822–000.
Federal Energy Regulatory
Applicants: Southwest Power Pool,
Commission
Inc.
Description: § 205(d) Rate Filing:
Combined Notice of Filings #1
3164R1 Milligan 3 Wind LLC GIA
Cancellation to be effective 1/9/2022.
Take notice that the Commission
Filed Date: 1/14/22.
received the following electric rate
Accession Number: 20220114–5095.
filings:
Comment Date: 5 p.m. ET 2/4/22.
Docket Numbers: ER17–1821–004.
Docket Numbers: ER22–823–000.
Applicants: Panda Stonewall LLC.
Applicants: PJM Interconnection,
Description: Refund Report: Potomac
L.L.C.
Energy Center, LLC submits tariff filing
Description: § 205(d) Rate Filing:
per 35.19a(b): Refund Report to be
Amendment to ISA, Service Agreement
effective N/A.
No. 3761, Racine ISA (consent) to be
Filed Date: 1/14/22.
effective 12/31/2013.
Accession Number: 20220114–5146.
Filed Date: 1/14/22.
Comment Date: 5 p.m. ET 2/4/22.
Accession Number: 20220114–5129.
Docket Numbers: ER22–46–003.
Comment Date: 5 p.m. ET 2/4/22.
Applicants: Parkway Generation
Docket Numbers: ER22–824–000.
Essex, LLC.
Applicants: Mid-Atlantic Interstate
Description: Tariff Amendment:
Transmission, LLC, PJM
Supplement to Petition for Order
Interconnection, L.L.C.
Accepting for Filing Market-Based Rate
Description: § 205(d) Rate Filing: MidTariff to be effective 12/1/2021.
Atlantic Interstate Transmission, LLC
Filed Date: 1/14/22.
submits tariff filing per 35.13(a)(2)(iii:
Accession Number: 20220114–5122.
Comment Date: 5 p.m. ET 2/4/22.
MAIT submits SA No. 6148 Tipton
ECSA to be effective 3/16/2022.
Docket Numbers: ER22–186–001.
Filed Date: 1/14/22.
Applicants: Middletown Coke
Accession Number: 20220114–5160.
Company, LLC.
Comment Date: 5 p.m. ET 2/4/22.
Description: Tariff Amendment:
Supplemental Filing to 187 to be
Docket Numbers: ER22–825–000.
effective 11/1/2021.
Applicants: American Transmission
Filed Date: 1/14/22.
Systems, Incorporated, PJM
Accession Number: 20220114–5100.
Interconnection, L.L.C.
Comment Date: 5 p.m. ET 2/4/22.
Description: § 205(d) Rate Filing:
American Transmission Systems,
Docket Numbers: ER22–764–001.
Incorporated submits tariff filing per
Applicants: PJM Interconnection,
35.13(a)(2)(iii: ATSI submits two
L.L.C.
Description: Tariff Amendment: Errata ECSAs, SA Nos. 6142 Ivanhoe & 6149
Ontario to be effective 3/16/2022.
to WMPA, SA No. 6273; Queue No.
Filed Date: 1/14/22.
AG2–422 in Docket No. ER22–764–000
Accession Number: 20220114–5167.
to be effective 12/7/2021.
Comment Date: 5 p.m. ET 2/4/22.
Filed Date: 1/14/22.
Accession Number: 20220114–5179.
Docket Numbers: ER22–826–000.
Comment Date: 5 p.m. ET 2/4/22.
Applicants: Mid-Atlantic Interstate
Transmission, LLC, Pennsylvania
Docket Numbers: ER22–820–000.
Electric Company, PJM Interconnection,
Applicants: The Potomac Edison
L.L.C.
Company, PJM Interconnection, L.L.C.
Description: § 205(d) Rate Filing: MidDescription: § 205(d) Rate Filing: The
Potomac Edison Company submits tariff Atlantic Interstate Transmission, LLC
filing per 35.13(a)(2)(iii: Potomac Edison submits tariff filing per 35.13(a)(2)(iii:
MAIT, Penelec and AEC submit SA No.
submits Construction SA No. 6133
5775 Saltillo Construction Agreement to
Hagerstown-Maple Ave Project to be
be effective 3/16/2022.
effective 3/15/2022.
Filed Date: 1/14/22.
Filed Date: 1/13/22.
Accession Number: 20220114–5174.
Accession Number: 20220113–5159.
Comment Date: 5 p.m. ET 2/4/22.
Comment Date: 5 p.m. ET 2/3/22.
Docket Numbers: ER22–827–000.
Docket Numbers: ER22–821–000.
VerDate Sep<11>2014
17:39 Jan 20, 2022
Jkt 256001
PO 00000
Frm 00016
Fmt 4703
Sfmt 4703
3293
Applicants: Kentucky Utilities
Company.
Description: § 205(d) Rate Filing:
Amended and Restated Agreement for
Borderline Service with Appalachian
Power Co to be effective 1/17/2022.
Filed Date: 1/14/22.
Accession Number: 20220114–5178.
Comment Date: 5 p.m. ET 2/4/22.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES22–25–000.
Applicants: Union Electric Company
d/b/a Ameren Missouri.
Description: Application Under
Section 204 of the Federal Power Act for
Authorization to Issue Securities of
Union Electric Company.
Filed Date: 1/14/22.
Accession Number: 20220114–5175.
Comment Date: 5 p.m. ET 2/4/22.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number. Any person desiring to
intervene or protest in any of the above
proceedings must file in accordance
with Rules 211 and 214 of the
Commission’s Regulations (18 CFR
385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified
comment date. Protests may be
considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: January 14, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–01172 Filed 1–20–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2336–101]
Georgia Power Company; Notice of
Application Tendered for Filing With
the Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
E:\FR\FM\21JAN1.SGM
21JAN1
jspears on DSK121TN23PROD with NOTICES1
3294
Federal Register / Vol. 87, No. 14 / Friday, January 21, 2022 / Notices
a. Type of Application: New Major
License.
b. Project No.: 2336–101.
c. Date Filed: January 3, 2022.
d. Applicant: Georgia Power Company
(Georgia Power).
e. Name of Project: Lloyd Shoals
Hydroelectric Project (Lloyd Shoals
Project.)
f. Location: The Lloyd Shoals Project
is located on the Ocmulgee River in
Butts, Henry, Jasper, and Newton
Counties, Georgia. The project does not
occupy any federal land.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Courtenay
O’Mara, Hydro Licensing & Compliance
Supervisor; Georgia Power Company;
241 Ralph McGill Boulevard NE; Bin
10193; Atlanta, Georgia 30308–3374;
(404) 506–7219, or email at cromara@
southernco.com.
i. FERC Contact: Navreet Deo at (202)
502–6304, or email at navreet.deo@
ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. The Lloyd Shoals Project consists
of: (1) The 4,750-acre Lake Jackson at
normal pool elevation of 530 feet Plant
Datum (PD) with a gross storage
capacity of 107,000 acre-feet; (2) a
1,600-foot-long, 106-foot-high concrete
gravity dam consisting of a 143-footlong non-overflow section, a 198-footlong powerhouse intake section with
six, 12-foot-high by 12-foot-wide
octagonal water passages supplying the
generating units, a 728.5-foot-long
spillway section consisting of a trash
gate and an Obermeyer gate system, and
a 530-foot-long earth embankment tiein; (3) a concrete and brick powerhouse
containing six horizontal Francis
turbine-generator units, each rated at
3.0-megawatts (MW), for a total
authorized installed capacity of 18–MW;
(4) a 2,100-foot-long saddle dike
approximately 3,000 feet upstream of
the east end of the main dam; (5) a 500foot-long auxiliary spillway, topped
with 10-foot-high flashboards, located
900 feet southwest of the main dam,
which includes a 560-foot-long, 6-foothigh sacrificial earth embankment; (6)
two 2.3-kilovolt generator leads
connecting the powerhouse to a
substation located at the west dam
abutment; and (7) appurtenant facilities.
Georgia Power proposes no
modifications to existing project
facilities.
The Lloyd Shoals Project operates in
a modified run-of-river mode to generate
power during peak demand. Reservoir
elevations are maintained between 530
feet PD and 527 feet PD year-round,
excluding planned drawdowns and
VerDate Sep<11>2014
17:39 Jan 20, 2022
Jkt 256001
drought. The project provides a
continuous minimum flow of 400 cubic
feet per second (cfs), or inflow, to the
Ocmulgee River downstream for the
protection and enhancement of fish and
wildlife resources and other
downstream resources. Georgia Power
proposes no changes to project
operation.
Georgia Power proposes
environmental measures to improve and
enhance water quality, aquatic habitat,
and recreation facilities. Georgia Power
also proposes plans for protection of
shoreline resources and historic
properties.
l. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov, using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field, to access the
document. At this time, the Commission
has suspended access to the
Commission’s Public Reference Room
due to the proclamation declaring a
National Emergency concerning the
Novel Coronavirus Disease (COVID–19)
issued on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov, or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Milestone
Target date
Issue Deficiency Letter (if
necessary).
Request Additional Information (if necessary).
Notice of Acceptance/Notice
of Ready for Environmental Analysis.
January 2022.
February
2022.
March 2022
Dated: January 14, 2022.
Kimberly D. Bose,
Secretary.
Frm 00017
Fmt 4703
Sfmt 4703
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP22–484–000.
Applicants: Kinder Morgan Louisiana
Pipeline LLC.
Description: § 4(d) Rate Filing: NonConforming Negotiated Rate Agreement
Filing-Sabine Pass Liquefaction, LLC to
be effective 2/1/2022.
Filed Date: 1/13/22.
Accession Number: 20220113–5136.
Comment Date: 5 p.m. ET 1/20/22.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: January 14, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–01171 Filed 1–20–22; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
Science Advisory Committee on
Chemicals (SACC); Notice of Public
Meeting and Request for Comments on
Draft Toxic Substances Control Act
(TSCA) Screening Level Approach for
Assessing Ambient Air and Water
Exposures to Fenceline Communities
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
[FR Doc. 2022–01174 Filed 1–20–22; 8:45 am]
PO 00000
Federal Energy Regulatory
Commission
[EPA–HQ–OPPT–2021–0415; FRL–9392–01–
OCSPP]
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
E:\FR\FM\21JAN1.SGM
21JAN1
Agencies
[Federal Register Volume 87, Number 14 (Friday, January 21, 2022)]
[Notices]
[Pages 3293-3294]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-01174]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2336-101]
Georgia Power Company; Notice of Application Tendered for Filing
With the Commission and Establishing Procedural Schedule for Licensing
and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
[[Page 3294]]
a. Type of Application: New Major License.
b. Project No.: 2336-101.
c. Date Filed: January 3, 2022.
d. Applicant: Georgia Power Company (Georgia Power).
e. Name of Project: Lloyd Shoals Hydroelectric Project (Lloyd
Shoals Project.)
f. Location: The Lloyd Shoals Project is located on the Ocmulgee
River in Butts, Henry, Jasper, and Newton Counties, Georgia. The
project does not occupy any federal land.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Courtenay O'Mara, Hydro Licensing &
Compliance Supervisor; Georgia Power Company; 241 Ralph McGill
Boulevard NE; Bin 10193; Atlanta, Georgia 30308-3374; (404) 506-7219,
or email at [email protected].
i. FERC Contact: Navreet Deo at (202) 502-6304, or email at
[email protected].
j. This application is not ready for environmental analysis at this
time.
k. The Lloyd Shoals Project consists of: (1) The 4,750-acre Lake
Jackson at normal pool elevation of 530 feet Plant Datum (PD) with a
gross storage capacity of 107,000 acre-feet; (2) a 1,600-foot-long,
106-foot-high concrete gravity dam consisting of a 143-foot-long non-
overflow section, a 198-foot-long powerhouse intake section with six,
12-foot-high by 12-foot-wide octagonal water passages supplying the
generating units, a 728.5-foot-long spillway section consisting of a
trash gate and an Obermeyer gate system, and a 530-foot-long earth
embankment tie-in; (3) a concrete and brick powerhouse containing six
horizontal Francis turbine-generator units, each rated at 3.0-megawatts
(MW), for a total authorized installed capacity of 18-MW; (4) a 2,100-
foot-long saddle dike approximately 3,000 feet upstream of the east end
of the main dam; (5) a 500-foot-long auxiliary spillway, topped with
10-foot-high flashboards, located 900 feet southwest of the main dam,
which includes a 560-foot-long, 6-foot-high sacrificial earth
embankment; (6) two 2.3-kilovolt generator leads connecting the
powerhouse to a substation located at the west dam abutment; and (7)
appurtenant facilities. Georgia Power proposes no modifications to
existing project facilities.
The Lloyd Shoals Project operates in a modified run-of-river mode
to generate power during peak demand. Reservoir elevations are
maintained between 530 feet PD and 527 feet PD year-round, excluding
planned drawdowns and drought. The project provides a continuous
minimum flow of 400 cubic feet per second (cfs), or inflow, to the
Ocmulgee River downstream for the protection and enhancement of fish
and wildlife resources and other downstream resources. Georgia Power
proposes no changes to project operation.
Georgia Power proposes environmental measures to improve and
enhance water quality, aquatic habitat, and recreation facilities.
Georgia Power also proposes plans for protection of shoreline resources
and historic properties.
l. A copy of the application can be viewed on the Commission's
website at https://www.ferc.gov, using the ``eLibrary'' link. Enter the
docket number, excluding the last three digits in the docket number
field, to access the document. At this time, the Commission has
suspended access to the Commission's Public Reference Room due to the
proclamation declaring a National Emergency concerning the Novel
Coronavirus Disease (COVID-19) issued on March 13, 2020. For
assistance, contact FERC at [email protected], or call toll-
free, (866) 208-3676 or (202) 502-8659 (TTY).
m. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue Deficiency Letter (if necessary).. January 2022.
Request Additional Information (if February 2022.
necessary).
Notice of Acceptance/Notice of Ready for March 2022
Environmental Analysis.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: January 14, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-01174 Filed 1-20-22; 8:45 am]