Rover Pipeline LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Rover-Brightmark Receipt and Delivery Meter Station Project, 74078-74079 [2021-28294]
Download as PDF
khammond on DSKJM1Z7X2PROD with NOTICES
74078
Federal Register / Vol. 86, No. 247 / Wednesday, December 29, 2021 / Notices
Filed Date: 12/22/21.
Accession Number: 20211222–5117.
Comment Date: 5 p.m. ET 1/12/22.
Docket Numbers: ER22–708–000.
Applicants: Alabama Power
Company.
Description: Tariff Amendment:
Jefferson County Solar LGIA
Termination Filing to be effective 12/22/
2021.
Filed Date: 12/22/21.
Accession Number: 20211222–5128.
Comment Date: 5 p.m. ET 1/12/22.
Docket Numbers: ER22–709–000.
Applicants: Missouri Joint Municipal
Electric Utility Commission, Southwest
Power Pool, Inc.
Description: § 205(d) Rate Filing:
Missouri Joint Municipal Electric Utility
Commission submits tariff filing per
35.13(a)(2)(iii: Missouri Joint Municipal
Electric Utility Commission Formula
Rate to be effective 12/31/9998.
Filed Date: 12/22/21.
Accession Number: 20211222–5129.
Comment Date: 5 p.m. ET 1/12/22.
Docket Numbers: ER22–710–000.
Applicants: Alabama Power
Company.
Description: Tariff Amendment:
Sycamore Solar LGIA Termination
Filing to be effective 12/22/2021.
Filed Date: 12/22/21.
Accession Number: 20211222–5130.
Comment Date: 5 p.m. ET 1/12/22.
Docket Numbers: ER22–711–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Sawmill Junction Solar Park Amended
and Restated LGIA Filing to be effective
11/9/2021.
Filed Date: 12/22/21.
Accession Number: 20211222–5131.
Comment Date: 5 p.m. ET 1/12/22.
Docket Numbers: ER22–712–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, Service Agreement No.
6274; Queue No. AE2–133 to be
effective 11/23/2021.
Filed Date: 12/22/21.
Accession Number: 20211222–5138.
Comment Date: 5 p.m. ET 1/12/22.
Docket Numbers: ER22–713–000.
Applicants: American Transmission
Systems, Incorporated, PJM
Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
American Transmission Systems,
Incorporated submits tariff filing per
35.13(a)(2)(iii: ATSI submits one ECSA,
SA No. 6145 to be effective 2/21/2022.
Filed Date: 12/22/21.
Accession Number: 20211222–5164.
Comment Date: 5 p.m. ET 1/12/22.
VerDate Sep<11>2014
20:20 Dec 28, 2021
Jkt 256001
Docket Numbers: ER22–714–000.
Applicants: Mid-Atlantic Interstate
Transmission, LLC, PJM
Interconnection, L.L.C.
Description: § 205(d) Rate Filing: MidAtlantic Interstate Transmission, LLC
submits tariff filing per 35.13(a)(2)(iii:
MAIT submits two ECSAs, SA Nos.
6146 and 6147 to be effective 2/21/2022.
Filed Date: 12/22/21.
Accession Number: 20211222–5168.
Comment Date: 5 p.m. ET 1/12/22.
Docket Numbers: ER22–715–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: ISA,
SA No. 6276; Queue No. AE2–060 to be
effective 11/23/2021.
Filed Date: 12/22/21.
Accession Number: 20211222–5171.
Comment Date: 5 p.m. ET 1/12/22.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES22–18–000.
Applicants: Portland General Electric
Company.
Description: Amendment to
Application Under Section 204 of the
Federal Power Act for Authorization to
Issue Securities of Portland General
Electric Company.
Filed Date: 12/21/21.
Accession Number: 20211221–5222.
Comment Date: 5 p.m. ET 1/4/22.
Take notice that the Commission
received the following public utility
holding company filings:
Docket Numbers: PH22–3–000.
Applicants: Consumers Energy
Company.
Description: CMS Energy Corporation
submits FERC 65–B Notice of Change in
Fact to Waiver Notification.
Filed Date: 12/20/21.
Accession Number: 20211220–5273.
Comment Date: 5 p.m. ET 1/10/22.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
PO 00000
Frm 00016
Fmt 4703
Sfmt 4703
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: December 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–28298 Filed 12–28–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–492–000]
Rover Pipeline LLC; Notice of
Schedule for the Preparation of an
Environmental Assessment for the
Rover-Brightmark Receipt and Delivery
Meter Station Project
On September 9, 2021, Rover Pipeline
LLC (Rover) filed an application in
Docket No. CP21–492–000 requesting a
Certificate of Public Convenience and
Necessity pursuant to Section 7(c) of the
Natural Gas Act to construct and operate
certain natural gas pipeline facilities in
Michigan. The proposed project is
known as the Rover-Brightmark Receipt
and Delivery Meter Station Project
(Project), and would allow Rover to
construct a new interconnect on its
existing mainline system to receive up
to 1,600 dekatherms per day of natural
gas from Brightmark SunRyz RNG LLC
while also allowing Rover to deliver up
to 100 dekatherms per day of natural gas
to Brightmark SunRyz RNG LLC for its
Brightmark Renewable Natural Gas
Facility.
On September 20, 2021 the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s environmental
document for the Project.
This notice identifies Commission
staff’s intention to prepare an
environmental assessment (EA) for the
Project and the planned schedule for the
completion of the environmental
review.1
Schedule for Environmental Review
Issuance of EA—February 22, 2022
90-day Federal Authorization Decision
Deadline—May 24, 2022
If a schedule change becomes
necessary, additional notice will be
1 40
E:\FR\FM\29DEN1.SGM
CFR 1501.10 (2020).
29DEN1
Federal Register / Vol. 86, No. 247 / Wednesday, December 29, 2021 / Notices
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
The Project would consist of Rover
constructing and operating a new
interconnect and meter station on its
existing Market Area Mainline at about
milepost 30.5 in Lenawee County,
Michigan. The proposed meter station
would include hot taps, valves, 65 feet
of interconnecting pipe, two meter
skids, a gas quality building, a
measurement building, and satellite
communications. Construction of the
proposed facilities would impact about
2.0 acres.
khammond on DSKJM1Z7X2PROD with NOTICES
Background
On October 26, 2021, the Commission
issued a Notice of Scoping Period
Requesting Comments on
Environmental Issues for the Proposed
Rover-Brightmark Receipt and Delivery
Meter Station Project and Notice of
Public Scoping Session (Notice of
Scoping). The Notice of Scoping was
sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers. In response to
the Notice of Scoping, the Commission
received comments from the U.S.
Environmental Protection Agency. The
U.S. Environmental Protection Agency
commented on identifying the Project
purpose and need; and assessing
impacts on socioeconomics and
environmental justice communities,
greenhouse gas emissions, climate
change, vegetation and wildlife, surface
and groundwater quality, and karst
terrain. All substantive comments will
be addressed in the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
service provides automatic notification
of filings made to subscribed dockets,
document summaries, and direct links
to the documents. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
VerDate Sep<11>2014
20:20 Dec 28, 2021
Jkt 256001
(i.e., CP21–492), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: December 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–28294 Filed 12–28–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2361–056]
Allete, Inc.; Notice of Application
Tendered for Filing With The
Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.a. Type of
Application: Subsequent License.b.
Project No.: 2361–056.c. Date filed:
December 20, 2021.d. Applicant: Allete,
Inc. (Allete).e. Name of Project: Prairie
River Hydroelectric Project (Prairie
River Project).f. Location: On the Prairie
River, near the Township of Arbo in
Itasca County, Minnesota. The project
does not include any federal lands.g.
Filed Pursuant to: Federal Power Act 16
U.S.C. 791(a)–825(r).h. Applicant
Contact: Mr. David R. Moeller, Senior
Attorney & Director of Regulatory
Compliance, ALLETE, Inc., d.b.a.
Minnesota Power, 30 West Superior
Street, Duluth, MN 55802, 218–723–
3963, dmoeller@allete.com.i. FERC
Contact: Laura Washington (202) 502–
6072, Laura.Washington@ferc.gov.j.
This application is not ready for
environmental analysis at this time.k.
The Prairie River Project consists of the
following existing facilities: (1) A 1,305acre reservoir; (2) a concrete dam; (3) a
reinforced-concrete penstock extending
from the forebay via a surge tank to the
powerhouse; (4) 2,500-foot-long bypass
reach; (5) a powerhouse containing two
generating units with a total installed
capacity of 1.1 megawatts; and (6) a 2.3/
23-kilovolt transmission bank.
The Prairie River Project is currently
operated in a run-of-river mode and
generates an annual average of
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
74079
approximately 3,087,000 kilowatt hours.
Allete proposes to continue operating
the project as a run-of-river facility and
does not propose any new construction
to the project.l. A copy of the
application can be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19) issued
on March 13, 2020. For assistance,
contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).m. You may also register
online at https://www.ferc.gov/docsfiling/esubscription.asp to be notified
via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.n. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Milestone
Target
date
Issue Deficiency Letter (if necessary).
Request Additional Information ..
January
2022.
February
2022.
June 2022.
Notice of Acceptance/Notice of
Ready for Environmental Analysis.
Dated: December 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–28297 Filed 12–28–21; 8:45 am]
BILLING CODE 6717–01–P795
E:\FR\FM\29DEN1.SGM
29DEN1
Agencies
[Federal Register Volume 86, Number 247 (Wednesday, December 29, 2021)]
[Notices]
[Pages 74078-74079]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-28294]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP21-492-000]
Rover Pipeline LLC; Notice of Schedule for the Preparation of an
Environmental Assessment for the Rover-Brightmark Receipt and Delivery
Meter Station Project
On September 9, 2021, Rover Pipeline LLC (Rover) filed an
application in Docket No. CP21-492-000 requesting a Certificate of
Public Convenience and Necessity pursuant to Section 7(c) of the
Natural Gas Act to construct and operate certain natural gas pipeline
facilities in Michigan. The proposed project is known as the Rover-
Brightmark Receipt and Delivery Meter Station Project (Project), and
would allow Rover to construct a new interconnect on its existing
mainline system to receive up to 1,600 dekatherms per day of natural
gas from Brightmark SunRyz RNG LLC while also allowing Rover to deliver
up to 100 dekatherms per day of natural gas to Brightmark SunRyz RNG
LLC for its Brightmark Renewable Natural Gas Facility.
On September 20, 2021 the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
environmental document for the Project.
This notice identifies Commission staff's intention to prepare an
environmental assessment (EA) for the Project and the planned schedule
for the completion of the environmental review.\1\
---------------------------------------------------------------------------
\1\ 40 CFR 1501.10 (2020).
---------------------------------------------------------------------------
Schedule for Environmental Review
Issuance of EA--February 22, 2022
90-day Federal Authorization Decision Deadline--May 24, 2022
If a schedule change becomes necessary, additional notice will be
[[Page 74079]]
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
The Project would consist of Rover constructing and operating a new
interconnect and meter station on its existing Market Area Mainline at
about milepost 30.5 in Lenawee County, Michigan. The proposed meter
station would include hot taps, valves, 65 feet of interconnecting
pipe, two meter skids, a gas quality building, a measurement building,
and satellite communications. Construction of the proposed facilities
would impact about 2.0 acres.
Background
On October 26, 2021, the Commission issued a Notice of Scoping
Period Requesting Comments on Environmental Issues for the Proposed
Rover-Brightmark Receipt and Delivery Meter Station Project and Notice
of Public Scoping Session (Notice of Scoping). The Notice of Scoping
was sent to affected landowners; federal, state, and local government
agencies; elected officials; environmental and public interest groups;
Native American tribes; other interested parties; and local libraries
and newspapers. In response to the Notice of Scoping, the Commission
received comments from the U.S. Environmental Protection Agency. The
U.S. Environmental Protection Agency commented on identifying the
Project purpose and need; and assessing impacts on socioeconomics and
environmental justice communities, greenhouse gas emissions, climate
change, vegetation and wildlife, surface and groundwater quality, and
karst terrain. All substantive comments will be addressed in the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of formal issuances and submittals in specific dockets, the
Commission offers a free service called eSubscription. This service
provides automatic notification of filings made to subscribed dockets,
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP21-492), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC
website also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rule makings.
Dated: December 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-28294 Filed 12-28-21; 8:45 am]