Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene; City of Beaverton, Oregon, 72946-72947 [2021-27783]
Download as PDF
72946
Federal Register / Vol. 86, No. 244 / Thursday, December 23, 2021 / Notices
• Provide additional discussion and
examples of the critical load method to
estimate the likelihood of failure;
• Provide clarification and additional
guidance on estimating consequences
(e.g., life safety consequences, economic
consequences, financial consequences
for damage state potential failure modes,
and environmental and other nonmonetary consequences);
• Add a risk analysis matrix for
incremental financial/damage state
consequences; and
• Include background information on
developing hydrologic hazard curves for
semi-quantitative risk analyses.
All information related to ‘‘Chapter
18—Level 2 Risk Analysis,’’ including
the draft chapter, all submitted
comments, and the final chapter, can be
found on the FERC website
(www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on
‘‘General Search’’ and enter the docket
number, excluding the last three digits
in the Docket Number field (i.e., AD20–
23). Be sure you have selected an
appropriate date range. The Commission
also offers a free service called
eSubscription which allows you to keep
track of all formal issuances and
submittals in specific dockets. This can
reduce the amount of time you spend
researching proceedings by
automatically providing you with
electronic notification of these filings
and direct links to the documents. Go to
the Commission’s website
(www.ferc.gov), select the FERC Online
option from the left-hand column, and
click on eSubscription. Users must be
registered in order to use eSubscription.
The final version of Chapter 18 is also
available on the Commission’s Division
of Dam Safety and Inspections website
at: Engineering Guidelines for the
Evaluation of Hydropower Projects |
Federal Energy Regulatory Commission
(ferc.gov).
Information Collection Statement
DEPARTMENT OF ENERGY
Chapter 18 includes information
collection activities for which the
Paperwork Reduction Act, 44 U.S.C.
3501–3521, requires approval by the
Office of Management and Budget
(OMB). The Commission has included
the burden and cost estimates for
information collection activities related
to this chapter in the rulemaking
document (Docket No. RM20–9–000,
Order No. 880). The Commission has
designated the information collection
activities in the rule as FERC–517. Upon
final approval of FERC–517, OMB will
assign an OMB Control Number and
expiration date.
Send written comments on FERC–517
to the Office of Management and Budget
(OMB) through www.reginfo.gov/public/
do/PRAMain, Attention: Federal Energy
Regulatory Commission Desk Officer.
Please identify the OMB control number
(1902–TBD) in the subject line. Your
comments should be sent within 30
days of publication of this notice in the
Federal Register. OMB submissions
must be formatted and filed in
accordance with submission guidelines
at www.reginfo.gov/public/do/PRAMain.
Using the search function under the
‘‘Currently Under Review field,’’ select
Federal Energy Regulatory Commission;
click ‘‘submit’’ and select ‘‘comment’’ to
the right of the subject collection.
For assistance with any of the
Commission’s online systems, please
contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8258.
Federal Energy Regulatory
Commission
Dated: December 16, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–27779 Filed 12–22–21; 8:45 am]
BILLING CODE 6717–01–P
[Docket No. CD22–2–000]
Notice of Preliminary Determination of
a Qualifying Conduit Hydropower
Facility and Soliciting Comments and
Motions To Intervene; City of
Beaverton, Oregon
On December 7, 2021, as
supplemented on December 15, 2021,
the City of Beaverton, Oregon filed a
notice of intent to construct a qualifying
conduit hydropower facility, pursuant
to section 30 of the Federal Power Act
(FPA). The proposed Sexton Mountain
Pump Station Hydroelectric Project
would have an installed capacity of up
to 200 kilowatts (kW), and would be
located along an existing 30-inch
pipeline adjacent to the Sexton
Mountain Pumping Station in the City
of Beaverton, Washington County,
Oregon.
Applicant Contact: Ronan Igloria, GSI
Water Solutions, Inc., 55 SW Yamhill
St., Suite 300, Portland, OR 97204, 971–
200–8510, rigloria@gsiws.com.
FERC Contact: Christopher Chaney,
202–502–6778, christopher.chaney@
ferc.gov.
Qualifying Conduit Hydropower
Facility Description: The proposed
project would consist of: (1) One Francis
turbine unit with a capacity of 100 kW,
with a second up to 100-kW unit
planned in the future; (2) intake and
discharge pipes connecting to the 30inch pipeline; and (3) appurtenant
facilities. The proposed project would
have an estimated annual generation of
approximately 392 megawatt-hours
during the first year of operation.
A qualifying conduit hydropower
facility is one that is determined or
deemed to meet all the criteria shown in
the table below.
TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
Statutory provision
Description
Satisfies
(Y/N)
FPA 30(a)(3)(A) .............
The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade
water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity.
The facility is constructed, operated, or maintained for the generation of electric power and uses for
such generation only the hydroelectric potential of a non-federally owned conduit.
The facility has an installed capacity that does not exceed 40 megawatts ...........................................
On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA.
Y
jspears on DSK121TN23PROD with NOTICES1
FPA 30(a)(3)(C)(i) ..........
FPA 30(a)(3)(C)(ii) .........
FPA 30(a)(3)(C)(iii) ........
Preliminary Determination: The
proposed Sexton Mountain Pump
Station Hydroelectric Project will not
VerDate Sep<11>2014
20:50 Dec 22, 2021
Jkt 256001
alter the primary purpose of the
conduit, which is to transport water for
municipal use. Therefore, based upon
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
Y
Y
Y
the above criteria, Commission staff
preliminarily determines that the
proposal satisfies the requirements for a
E:\FR\FM\23DEN1.SGM
23DEN1
jspears on DSK121TN23PROD with NOTICES1
Federal Register / Vol. 86, No. 244 / Thursday, December 23, 2021 / Notices
qualifying conduit hydropower facility,
which is not required to be licensed or
exempted from licensing.
Comments and Motions to Intervene:
Deadline for filing comments contesting
whether the facility meets the qualifying
criteria is 30 days from the issuance
date of this notice.
Deadline for filing motions to
intervene is 30 days from the issuance
date of this notice.
Anyone may submit comments or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210 and
385.214. Any motions to intervene must
be received on or before the specified
deadline date for the particular
proceeding.
Filing and Service of Responsive
Documents: All filings must (1) bear in
all capital letters the ‘‘COMMENTS
CONTESTING QUALIFICATION FOR A
CONDUIT HYDROPOWER FACILITY’’
or ‘‘MOTION TO INTERVENE,’’ as
applicable; (2) state in the heading the
name of the applicant and the project
number of the application to which the
filing responds; (3) state the name,
address, and telephone number of the
person filing; and (4) otherwise comply
with the requirements of sections
385.2001 through 385.2005 of the
Commission’s regulations.1 All
comments contesting Commission staff’s
preliminary determination that the
facility meets the qualifying criteria
must set forth their evidentiary basis.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and comments using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may send a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, MD 20852. A copy of all
other filings in reference to this
application must be accompanied by
1 18
CFR 385.2001–2005 (2020).
VerDate Sep<11>2014
20:50 Dec 22, 2021
Jkt 256001
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 385.2010.
Locations of Notice of Intent: The
Commission provides all interested
persons an opportunity to view and/or
print the contents of this document via
the internet through the Commission’s
website at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket
number (i.e., CD22–2) in the docket
number field to access the document.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
Copies of the notice of intent can be
obtained directly from the applicant.
For assistance, call toll-free 1–866–208–
3676 or email FERCOnlineSupport@
ferc.gov. For TTY, call (202) 502–8659.
Dated: December 16, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–27783 Filed 12–22–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP15–554–009 and CP15–555–
007]
Atlantic Coast Pipeline, LLC, Eastern
Gas Transmission and Storage, Inc.;
Notice of Availability of the Final
Supplemental Environmental Impact
Statement for the Proposed Atlantic
Coast Pipeline Restoration Project and
Supply Header Restoration Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared a final
supplemental environmental impact
statement (sEIS) for the Atlantic Coast
Pipeline, LLC’s (Atlantic) Atlantic Coast
Pipeline Restoration Project, and
Eastern Gas Transmission and Storage,
Inc.’s (EGTS) Supply Header Restoration
Project (Restoration Projects), in the
above-referenced dockets. Atlantic and
EGTS request authorization to
implement the Restoration Projects in
order to stabilize lands affected by
previous construction efforts for the
Atlantic Coast Pipeline and Supply
Header Project, respectively, and to
facilitate cessation of all project-related
activities. Implementation of the plans
is proposed because Atlantic and EGTS
have cancelled their respective projects
and do not intend to complete them.
The final sEIS assesses the potential
impacts that would result from the
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
72947
Restoration Projects, in accordance with
the requirements of the National
Environmental Policy Act (NEPA).1 The
FERC staff concludes that the proposed
actions, with the additional mitigation
measures recommended in the sEIS,
would continue to avoid or reduce
impacts to less than significant levels,
with the exception of climate change
impacts, for which FERC staff is unable
to determine significance.
The U.S. Department of Agriculture’s
Forest Service and the U.S. Department
of the Interior’s Fish and Wildlife
Service participated as cooperating
agencies in the preparation of the sEIS.
Cooperating agencies have jurisdiction
by law or special expertise with respect
to resources potentially affected by the
proposal and participate in the NEPA
analysis.
The sEIS addresses the potential
environmental effects of the following
activities:
• Atlantic proposes to leave all
installed pipeline in place
(approximately 31.4 miles of the
pipeline right-of-way), restore lands that
were cleared and graded (approximately
82.7 miles of the pipeline right-of-way),
and leave felled trees in place in areas
where trees have not yet been cleared
(approximately 25.2 miles of the
pipeline right-of-way). For aboveground
facilities, Atlantic proposes to restore
the sites and manage the disposition of
the materials and land through an
investment recovery process. Workspace
for these activities would occur in West
Virginia, Virginia, and North Carolina.
• EGTS proposes to leave all installed
pipeline in place (approximately 11.7
miles), leave approximately 0.13 mile of
felled trees in place, and complete final
restoration of approximately 9 miles of
the pipeline right-of-way that EGTS
previously cleared and/or graded. EGTS
proposes to stabilize all aboveground
facility sites and prepare assets for long
term preservation. Workspace for these
activities would occur in Pennsylvania
and West Virginia.
The Commission mailed a copy of the
Notice of Availability for the final sEIS
to federal, state, and local government
representatives and agencies; elected
officials; environmental and public
interest groups; Native American tribes;
potentially affected landowners and
other interested individuals and groups;
and newspapers and libraries in the
project areas. The final sEIS is only
available in electronic format. It may be
1 The construction and operation impacts of the
then-proposed Atlantic Coast Pipeline and Supply
Header Project were evaluated in a final EIS, which
was issued by the Commission on July 21, 2017, in
Docket Nos. CP15–554–00, CP15–554–001; and
CP15–555–000.
E:\FR\FM\23DEN1.SGM
23DEN1
Agencies
[Federal Register Volume 86, Number 244 (Thursday, December 23, 2021)]
[Notices]
[Pages 72946-72947]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-27783]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CD22-2-000]
Notice of Preliminary Determination of a Qualifying Conduit
Hydropower Facility and Soliciting Comments and Motions To Intervene;
City of Beaverton, Oregon
On December 7, 2021, as supplemented on December 15, 2021, the City
of Beaverton, Oregon filed a notice of intent to construct a qualifying
conduit hydropower facility, pursuant to section 30 of the Federal
Power Act (FPA). The proposed Sexton Mountain Pump Station
Hydroelectric Project would have an installed capacity of up to 200
kilowatts (kW), and would be located along an existing 30-inch pipeline
adjacent to the Sexton Mountain Pumping Station in the City of
Beaverton, Washington County, Oregon.
Applicant Contact: Ronan Igloria, GSI Water Solutions, Inc., 55 SW
Yamhill St., Suite 300, Portland, OR 97204, 971-200-8510,
[email protected].
FERC Contact: Christopher Chaney, 202-502-6778,
[email protected].
Qualifying Conduit Hydropower Facility Description: The proposed
project would consist of: (1) One Francis turbine unit with a capacity
of 100 kW, with a second up to 100-kW unit planned in the future; (2)
intake and discharge pipes connecting to the 30-inch pipeline; and (3)
appurtenant facilities. The proposed project would have an estimated
annual generation of approximately 392 megawatt-hours during the first
year of operation.
A qualifying conduit hydropower facility is one that is determined
or deemed to meet all the criteria shown in the table below.
Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
Statutory provision Description Satisfies (Y/N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A).......................... The conduit the facility uses is a tunnel, canal, Y
pipeline, aqueduct, flume, ditch, or similar
manmade water conveyance that is operated for the
distribution of water for agricultural, municipal,
or industrial consumption and not primarily for the
generation of electricity.
FPA 30(a)(3)(C)(i)....................... The facility is constructed, operated, or maintained Y
for the generation of electric power and uses for
such generation only the hydroelectric potential of
a non-federally owned conduit.
FPA 30(a)(3)(C)(ii)...................... The facility has an installed capacity that does not Y
exceed 40 megawatts.
FPA 30(a)(3)(C)(iii)..................... On or before August 9, 2013, the facility is not Y
licensed, or exempted from the licensing
requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------
Preliminary Determination: The proposed Sexton Mountain Pump
Station Hydroelectric Project will not alter the primary purpose of the
conduit, which is to transport water for municipal use. Therefore,
based upon the above criteria, Commission staff preliminarily
determines that the proposal satisfies the requirements for a
[[Page 72947]]
qualifying conduit hydropower facility, which is not required to be
licensed or exempted from licensing.
Comments and Motions to Intervene: Deadline for filing comments
contesting whether the facility meets the qualifying criteria is 30
days from the issuance date of this notice.
Deadline for filing motions to intervene is 30 days from the
issuance date of this notice.
Anyone may submit comments or a motion to intervene in accordance
with the requirements of Rules of Practice and Procedure, 18 CFR
385.210 and 385.214. Any motions to intervene must be received on or
before the specified deadline date for the particular proceeding.
Filing and Service of Responsive Documents: All filings must (1)
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as
applicable; (2) state in the heading the name of the applicant and the
project number of the application to which the filing responds; (3)
state the name, address, and telephone number of the person filing; and
(4) otherwise comply with the requirements of sections 385.2001 through
385.2005 of the Commission's regulations.\1\ All comments contesting
Commission staff's preliminary determination that the facility meets
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------
\1\ 18 CFR 385.2001-2005 (2020).
---------------------------------------------------------------------------
The Commission strongly encourages electronic filing. Please file
motions to intervene and comments using the Commission's eFiling system
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at [email protected], (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, you may send a
paper copy. Submissions sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, MD 20852. A copy of all other filings in reference
to this application must be accompanied by proof of service on all
persons listed in the service list prepared by the Commission in this
proceeding, in accordance with 18 CFR 385.2010.
Locations of Notice of Intent: The Commission provides all
interested persons an opportunity to view and/or print the contents of
this document via the internet through the Commission's website at
https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number
(i.e., CD22-2) in the docket number field to access the document. You
may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. Copies of the notice of
intent can be obtained directly from the applicant. For assistance,
call toll-free 1-866-208-3676 or email [email protected]. For
TTY, call (202) 502-8659.
Dated: December 16, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-27783 Filed 12-22-21; 8:45 am]
BILLING CODE 6717-01-P