Control of Heavy Loads at Nuclear Facilities, 72287-72288 [2021-27550]
Download as PDF
jspears on DSK121TN23PROD with NOTICES1
Federal Register / Vol. 86, No. 242 / Tuesday, December 21, 2021 / Notices
10 CFR 50.12 that apply to this exemption
request are 10 CFR 50.12(a)(2)(ii) and (v).
Special circumstances, per 10 CFR
50.12(a)(2)(ii), are present when:
‘‘Application of the regulation in the
particular circumstances would not serve the
underlying purpose of the rule or is not
necessary to achieve the underlying purpose
of the rule.’’ Section IV.F.2.c of 10 CFR part
50, Appendix E requires licensees to exercise
offsite plans biennially with full or partial
participation by each offsite authority having
a role under the plan. The underlying
purposes of 10 CFR part 50, Appendix E,
Section IV.F.2.c requiring licensees to
exercise offsite plans with offsite authority
participation is to ensure that the emergency
organization personnel are familiar with their
duties, to identify and correct any
weaknesses that may exist in the licensee’s
EP Program, and to test and maintain
interfaces among affected State and local
authorities, and the licensee. Although the
affected OROs and FEMA were unable to
participate in the scheduled exercise for
August 24, 2021, no NRC findings (ADAMS
Accession No. ML 19263A647) nor FEMA
deficiencies (ADAMS Accession No.
ML21307A042) were identified at the
previous biennial EP exercise conducted on
August 20, 2019. As previously discussed,
the licensee has conducted nine (9) full-scale,
integrated performance indicator drills as
well as numerous training sessions with the
State and local response organizations in
2019 through 2021. The NRC staff has
determined that the licensee’s drill
performances and training sessions have
been adequate to ensure that the emergency
organization personnel are familiar with their
duties, to identify and correct any
weaknesses that may exist in the licensee’s
EP Program, and to test and maintain
interfaces among affected State and local
authorities and the licensee during this
period, satisfying the underlying purpose of
the rule.
To accommodate the scheduling of
exercises, the NRC has allowed licensees the
flexibility to schedule their exercises at any
time during the biennial calendar year. This
provides a 13- to 35-month window to
schedule exercises while still meeting the
biennial requirement. This one-time change
in the exercise schedule increases the
interval between biennial exercises, however
conducting the postponed exercise on a date
prior to July 20, 2022, falls within the 35month window, thus meeting the intent of
the regulation.
Under 10 CFR 50.12(a)(2)(v), special
circumstances are present whenever the
exemption would provide only temporary
relief from the applicable regulation and the
licensee or applicant has made good faith
efforts to comply with the regulation. Exelon
requests a temporary, one-time exemption for
the evaluation of certain offsite elements/
objectives from the CY 2021 biennial EP
exercise at Ginna. Based on discussions
between Exelon, supporting OROs, and
Federal stakeholders, it was determined that
rescheduling participation to complete the
applicable offsite exercise objectives would
not be feasible prior to the end of CY 2021
due to the impacts on the availability of the
VerDate Sep<11>2014
19:15 Dec 20, 2021
Jkt 256001
OROs and Federal stakeholders caused by the
significant devastation from Hurricane/
Tropical Storm Henri and later Ida and the
continued COVID–19 public health
emergency. On September 1, 2021, a
teleconference was held with representatives
from the State of New York OEM, Exelon,
FEMA, and other supporting OROs related to
deferring/postponing the completion of ORO
exercise criteria/objectives until sometime in
CY 2022. Subsequently, in a telephone
conversation between Exelon and FEMA
representatives on October 1, 2021, FEMA
indicated that they were not opposed to
postponing FEMA-evaluated exercise
criteria/objectives until CY 2022. FEMA
noted that completion of the remaining
exercise criteria/objectives must occur prior
to July 20, 2022. Attachment two to the
licensee’s application documents that the
State of New York OEM was unable to find
a suitable window of available dates in CY
2021 to accommodate the offsite portions of
the Ginna biennial EP exercise. Attachment
four to the licensee’s application documents
the scheduling conflicts identified by the
State of New York OEM preventing the
exercise from occurring in CY 2021.
Therefore, the licensee has made good faith
efforts to comply with the regulations.
Granting the requested exemption from the
10 CFR part 50, Appendix E, Section IV.F.2.c
requirement to conduct the specific offsite
portions of the biennial EP exercise in CY
2022, instead of CY 2021, would provide
only temporary relief from the applicable
regulations. Additionally, the licensee has
acknowledged returning to the previous
biennial EP exercise schedule of every odd
year and conducting the next follow-on
biennial EP exercise in CY 2023, which will
include both onsite and offsite participation.
Granting the exemption would still achieve
the underlying purpose of 10 CFR part 50,
Appendix E, Section IV.F.2.c, the licensee
has made a good faith effort to comply with
the regulation, and the exemption would
grant only temporary relief from the
applicable regulation. Therefore, the special
circumstances required by 10 CFR
50.12(a)(2)(ii) and (v) exist for the granting of
an exemption.
E. Environmental Considerations
NRC approval of the requested exemption
is categorically excluded under 10 CFR
51.22(c)(25), and there are no extraordinary
circumstances present that would preclude
reliance on this exclusion. The NRC staff
determined, per 10 CFR 51.22(c)(25)(vi)(E),
that the requirements from which the
exemption is sought involve education,
training, experience, qualification,
requalification, or other employment
suitability requirements.
The NRC staff also determined that
approval of this exemption involves no
significant hazards consideration because it
does not authorize any physical changes to
the facility or any of its safety systems,
change any of the assumptions or limits used
in the licensee’s safety analyses, or introduce
any new failure modes. There is no
significant change in the types or significant
increase in the amounts of any effluents that
may be released offsite because this
PO 00000
Frm 00085
Fmt 4703
Sfmt 4703
72287
exemption does not affect any effluent
release limits as provided in the licensee’s
technical specifications or by the regulations
in 10 CFR part 20, ‘‘Standards for Protection
Against Radiation.’’ There is no significant
increase in individual or cumulative public
or occupational radiation exposure because
this exemption does not affect limits on the
release of any radioactive material, or the
limits provided in 10 CFR part 20 for
radiation exposure to workers or members of
the public.
There is no significant construction impact
because this exemption does not involve any
changes to a construction permit. There is no
significant increase in the potential for or
consequences from radiological accidents
because the exemption does not alter any of
the assumptions or limits in the licensee’s
safety analysis. In addition, the NRC staff
determined that there would be no
significant impacts to biota, water resources,
historic properties, cultural resources, or
socioeconomic conditions in the region.
Therefore, pursuant to 10 CFR 51.22(b), no
environmental impact statement or
environmental assessment need be prepared
in connection with the approval of the
requested exemption.
IV. Conclusions
Accordingly, the Commission has
determined that, pursuant to 10 CFR 50.12,
the exemption is authorized by law, will not
present an undue risk to the public health
and safety, and is consistent with the
common defense and security. Also, special
circumstances are present. Therefore, the
Commission hereby grants Exelon Generation
Company, LLC an exemption from the
requirements of 10 CFR part 50, Appendix E,
Section IV.F.2.c. to conduct the specific
offsite portion of the Ginna biennial EP
exercise required for CY 2021, permitting
that part of the exercise to be conducted in
coordination with FEMA, NRC Region I and
Ginna by a date prior to July 20, 2022. This
exemption expires on July 20, 2022, or when
the offsite biennial EP exercise is performed
in CY 2022, whichever occurs first.
Dated at Rockville, Maryland, this 15th day
of December 2021.
For the Nuclear Regulatory Commission.
Bo M. Pham,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2021–27574 Filed 12–20–21; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2021–0096]
Control of Heavy Loads at Nuclear
Facilities
Nuclear Regulatory
Commission.
ACTION: Regulatory guide; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing Regulatory
SUMMARY:
E:\FR\FM\21DEN1.SGM
21DEN1
72288
Federal Register / Vol. 86, No. 242 / Tuesday, December 21, 2021 / Notices
Guide (RG) 1.244 (Revision 0), ‘‘Control
of Heavy Loads at Nuclear Facilities.’’
RG 1.244 is a new regulatory guide to
endorse selected national consensus
standards related to heavy load
handling that replace NRC technical
reports. The national consensus
standards provide greater flexibility in
the selection of lifting equipment and
have incorporated recent operating
experience to provide a more accurate
risk-informed perspective of heavy load
handling activities.
Revision 0 to RG 1.244 is
available on December 21, 2021.
DATES:
Please refer to Docket ID
NRC–2021–0096 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly available
information related to this document
using any of the following methods:
• Federal Rulemaking website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2021–0096. Address
questions about Docket IDs in
Regulations.gov to Stacy Schumann;
telephone: 301–415–0624; email:
Stacy.Schumann@nrc.gov. For technical
questions, contact the individuals listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to
PDR.Resource@nrc.gov. The ADAMS
accession number for each document
referenced (if it is available in ADAMS)
is provided the first time that it is
mentioned in this document.
• NRC’s PDR: You may examine and
purchase copies of public documents,
by appointment, at the NRC’s PDR,
Room P1 B35, One White Flint North,
11555 Rockville Pike, Rockville,
Maryland 20852. To make an
appointment to visit the PDR, please
send an email to PDR.Resource@nrc.gov
or call 1–800–397–4209 or 301–415–
4737, between 8:00 a.m. and 4:00 p.m.
(ET), Monday through Friday, except
Federal holidays.
Revision 0 to RG 1.244 and the
regulatory analysis may be found in
ADAMS under Accession Nos.
ML21006A346 and ML21006A337,
respectively.
jspears on DSK121TN23PROD with NOTICES1
ADDRESSES:
VerDate Sep<11>2014
18:02 Dec 20, 2021
Jkt 256001
Regulatory guides are not
copyrighted, and NRC approval is not
required to reproduce them.
FOR FURTHER INFORMATION CONTACT:
Steven R. Jones, Office of Nuclear
Reactor Regulation, telephone: 301–
415–2712, email: Steve.Jones@nrc.gov;
or Stanley Gardocki, Office of Nuclear
Regulatory Research, telephone: 301–
415–1067, email: Stanley.Gardocki@
nrc.gov. Both are staff members at the
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001.
SUPPLEMENTARY INFORMATION:
NML–1, ‘‘Rules for the Movement of
Loads Using Overhead Handling
Equipment in Nuclear Facilities,’’ 2019.
• ASME Std. NOG–1, ‘‘Rules for
Construction of Overhead and Gantry
Cranes (Top Running Bridge, Multiple
Girder),’’ 2020.
• ASME Std. BTH–1, ‘‘Design of
Below-the-Hook Lifting Devices,’’ 2017,
Chapters 1 through 3.
The use of consensus standards where
available is consistent with NRC
Commission Policy and provides
updated information reflecting
operating experience.
I. Discussion
III. Congressional Review Act
This RG is a rule as defined in the
Congressional Review Act (5 U.S.C.
801–808). However, the Office of
Management and Budget has not found
it to be a major rule as defined in the
Congressional Review Act.
The NRC is issuing a new guide in the
NRC’s ‘‘Regulatory Guide’’ series. This
series was developed to describe and
make available to the public information
regarding methods that are acceptable to
the NRC staff for implementing specific
parts of the agency’s regulations,
techniques that the NRC staff uses in
evaluating specific issues or postulated
events, and data that the NRC staff
needs in its review of applications for
permits and licenses.
RG 1.244 was issued with a temporary
identification of Draft Regulatory Guide,
DG–1381, ADAMS Accession No,
ML21006A335.
II. Additional Information
The NRC published a notice of the
availability of DG–1381 in the Federal
Register on May 5, 2021 (86 FR 23750)
for a 30-day public comment period.
The public comment period was
extended and closed on July 5, 2021.
Public comments and the staff responses
to the public comments on DG–1381 are
available in ADAMS under Accession
No. ML21244A455.
This new regulatory guide provides
guidance for control of heavy loads at
nuclear facilities to provide reasonable
assurance safety functions would be
accomplished following handling
system equipment failure. The NRC has
provided guidance in technical reports
NUREG–0612, ‘‘Control of Heavy Loads
in Nuclear Power Plants,’’ dated August
1980 (ADAMS Accession No.
ML070250180) and NUREG–0554,
‘‘Single Failure-Proof Cranes for Nuclear
Power Plants,’’ dated May 1979
(ADAMS Accession No. ML110450636).
However, this guidance has not been
updated and does not reflect a current
risk-informed perspective regarding
heavy load handling activities. To
provide updated guidance, the NRC is
issuing RG 1.244 which endorses, with
clarifications, the following consensus
standards:
• American Society of Mechanical
Engineers (ASME) Standard (Std.)
PO 00000
Frm 00086
Fmt 4703
Sfmt 4703
IV. Backfitting, Forward Fitting, and
Issue Finality
Issuance of this RG does not
constitute backfitting as defined in
Section 50.109 of title 10 of the Code of
Federal Regulations (10 CFR),
‘‘Backfitting,’’ and as described in NRC
Management Directive (MD) 8.4,
‘‘Management of Backfitting, Forward
Fitting, Issue Finality, and Information
Requests’’; constitute forward fitting as
that term is defined and described in
MD 8.4; or affect issue finality of any
approval issued under 10 CFR part 52,
‘‘Licenses, Certificates, and Approvals
for Nuclear Power Plants.’’ As explained
in this regulatory guide, applicants and
licensees are not required to comply
with the positions set forth in this
regulatory guide.
Dated: December 15, 2021.
For the Nuclear Regulatory Commission.
Meraj Rahimi,
Branch Chief, Regulatory Guide and Programs
Management Branch, Division of Engineering,
Office of Nuclear Regulatory Research.
[FR Doc. 2021–27550 Filed 12–20–21; 8:45 am]
BILLING CODE 7590–01–P
PEACE CORPS
Information Collection Request;
Submission for OMB Review
Peace Corps.
30-day notice and request for
comments.
AGENCY:
ACTION:
The Peace Corps will submit
the following information collection
request to the Office of Management and
Budget (OMB) for review and approval.
In accordance with the Paperwork
Reduction Act of 1995, we are
SUMMARY:
E:\FR\FM\21DEN1.SGM
21DEN1
Agencies
[Federal Register Volume 86, Number 242 (Tuesday, December 21, 2021)]
[Notices]
[Pages 72287-72288]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-27550]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2021-0096]
Control of Heavy Loads at Nuclear Facilities
AGENCY: Nuclear Regulatory Commission.
ACTION: Regulatory guide; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing
Regulatory
[[Page 72288]]
Guide (RG) 1.244 (Revision 0), ``Control of Heavy Loads at Nuclear
Facilities.'' RG 1.244 is a new regulatory guide to endorse selected
national consensus standards related to heavy load handling that
replace NRC technical reports. The national consensus standards provide
greater flexibility in the selection of lifting equipment and have
incorporated recent operating experience to provide a more accurate
risk-informed perspective of heavy load handling activities.
DATES: Revision 0 to RG 1.244 is available on December 21, 2021.
ADDRESSES: Please refer to Docket ID NRC-2021-0096 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0096. Address
questions about Docket IDs in Regulations.gov to Stacy Schumann;
telephone: 301-415-0624; email: [email protected]. For technical
questions, contact the individuals listed in the FOR FURTHER
INFORMATION CONTACT section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or
by email to [email protected]. The ADAMS accession number for each
document referenced (if it is available in ADAMS) is provided the first
time that it is mentioned in this document.
NRC's PDR: You may examine and purchase copies of public
documents, by appointment, at the NRC's PDR, Room P1 B35, One White
Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. To make
an appointment to visit the PDR, please send an email to
[email protected] or call 1-800-397-4209 or 301-415-4737, between
8:00 a.m. and 4:00 p.m. (ET), Monday through Friday, except Federal
holidays.
Revision 0 to RG 1.244 and the regulatory analysis may be found in
ADAMS under Accession Nos. ML21006A346 and ML21006A337, respectively.
Regulatory guides are not copyrighted, and NRC approval is not
required to reproduce them.
FOR FURTHER INFORMATION CONTACT: Steven R. Jones, Office of Nuclear
Reactor Regulation, telephone: 301-415-2712, email:
[email protected]; or Stanley Gardocki, Office of Nuclear Regulatory
Research, telephone: 301-415-1067, email: [email protected].
Both are staff members at the U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Discussion
The NRC is issuing a new guide in the NRC's ``Regulatory Guide''
series. This series was developed to describe and make available to the
public information regarding methods that are acceptable to the NRC
staff for implementing specific parts of the agency's regulations,
techniques that the NRC staff uses in evaluating specific issues or
postulated events, and data that the NRC staff needs in its review of
applications for permits and licenses.
RG 1.244 was issued with a temporary identification of Draft
Regulatory Guide, DG-1381, ADAMS Accession No, ML21006A335.
II. Additional Information
The NRC published a notice of the availability of DG-1381 in the
Federal Register on May 5, 2021 (86 FR 23750) for a 30-day public
comment period. The public comment period was extended and closed on
July 5, 2021. Public comments and the staff responses to the public
comments on DG-1381 are available in ADAMS under Accession No.
ML21244A455.
This new regulatory guide provides guidance for control of heavy
loads at nuclear facilities to provide reasonable assurance safety
functions would be accomplished following handling system equipment
failure. The NRC has provided guidance in technical reports NUREG-0612,
``Control of Heavy Loads in Nuclear Power Plants,'' dated August 1980
(ADAMS Accession No. ML070250180) and NUREG-0554, ``Single Failure-
Proof Cranes for Nuclear Power Plants,'' dated May 1979 (ADAMS
Accession No. ML110450636). However, this guidance has not been updated
and does not reflect a current risk-informed perspective regarding
heavy load handling activities. To provide updated guidance, the NRC is
issuing RG 1.244 which endorses, with clarifications, the following
consensus standards:
American Society of Mechanical Engineers (ASME) Standard
(Std.) NML-1, ``Rules for the Movement of Loads Using Overhead Handling
Equipment in Nuclear Facilities,'' 2019.
ASME Std. NOG-1, ``Rules for Construction of Overhead and
Gantry Cranes (Top Running Bridge, Multiple Girder),'' 2020.
ASME Std. BTH-1, ``Design of Below-the-Hook Lifting
Devices,'' 2017, Chapters 1 through 3.
The use of consensus standards where available is consistent with
NRC Commission Policy and provides updated information reflecting
operating experience.
III. Congressional Review Act
This RG is a rule as defined in the Congressional Review Act (5
U.S.C. 801-808). However, the Office of Management and Budget has not
found it to be a major rule as defined in the Congressional Review Act.
IV. Backfitting, Forward Fitting, and Issue Finality
Issuance of this RG does not constitute backfitting as defined in
Section 50.109 of title 10 of the Code of Federal Regulations (10 CFR),
``Backfitting,'' and as described in NRC Management Directive (MD) 8.4,
``Management of Backfitting, Forward Fitting, Issue Finality, and
Information Requests''; constitute forward fitting as that term is
defined and described in MD 8.4; or affect issue finality of any
approval issued under 10 CFR part 52, ``Licenses, Certificates, and
Approvals for Nuclear Power Plants.'' As explained in this regulatory
guide, applicants and licensees are not required to comply with the
positions set forth in this regulatory guide.
Dated: December 15, 2021.
For the Nuclear Regulatory Commission.
Meraj Rahimi,
Branch Chief, Regulatory Guide and Programs Management Branch, Division
of Engineering, Office of Nuclear Regulatory Research.
[FR Doc. 2021-27550 Filed 12-20-21; 8:45 am]
BILLING CODE 7590-01-P