Northwestern Corporation; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 70835-70836 [2021-26895]
Download as PDF
khammond on DSKJM1Z7X2PROD with NOTICES
Federal Register / Vol. 86, No. 236 / Monday, December 13, 2021 / Notices
Applicants: ISO New England Inc.,
Fitchburg Gas and Electric Light
Company.
Description: Compliance filing: ISO
New England Inc. submits tariff filing
per 35: FG&E, Docket No. ER21–1154;
Amended Supplemental Order No. 864
Compliance Filing to be effective 1/1/
2020.
Filed Date: 12/7/21.
Accession Number: 20211207–5114.
Comment Date: 5 p.m. ET 12/17/21.
Docket Numbers: ER21–1241–001.
Applicants: ISO New England Inc.,
New England Power Company.
Description: Compliance filing: ISO
New England Inc. submits tariff filing
per 35: New England Power; ER21–1241
Amended Order 864 Compliance Filing
to be effective 1/1/2020.
Filed Date: 12/7/21.
Accession Number: 20211207–5094.
Comment Date: 5 p.m. ET 12/17/21.
Docket Numbers: ER21–2926–000.
Applicants: Caddo Wind, LLC.
Description: Filing Withdrawal:
Withdraw of Supplement to Application
for Market-Based Rate Authorization to
be effective N/A.
Filed Date: 12/7/21.
Accession Number: 20211207–5142.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–306–001.
Applicants: Duke Energy Carolinas,
LLC.
Description: Tariff Amendment: Errata
Filing—DEF Revised Depreciation Rates
to be effective 1/1/2022.
Filed Date: 12/7/21.
Accession Number: 20211207–5096.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–414–001.
Applicants: AES Marketing and
Trading, LLC.
Description: Tariff Amendment: AES
Marketing and Trading, LLC MBR
Supplement to be effective 11/17/2021.
Filed Date: 12/7/21.
Accession Number: 20211207–5053.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–46–002.
Applicants: Parkway Generation
Essex, LLC.
Description: Tariff Amendment:
Response to Deficiency Letter to be
effective 12/1/2021.
Filed Date: 12/6/21.
Accession Number: 20211206–5176.
Comment Date: 5 p.m. ET 12/27/21.
Docket Numbers: ER22–564–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original NSA, Service Agreement No.
6262; Queue No. K11 to be effective 11/
4/2021.
Filed Date: 12/6/21.
VerDate Sep<11>2014
16:50 Dec 10, 2021
Jkt 256001
Accession Number: 20211206–5206.
Comment Date: 5 p.m. ET 12/27/21.
Docket Numbers: ER22–566–000.
Applicants: Southern California
Edison Company.
Description: Compliance filing:
WDAT Storage Settlement Compliance
Filing to be effective 6/15/2021.
Filed Date: 12/7/21.
Accession Number: 20211207–5066.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–567–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Seminole Solar (Seminole I Solar) LGIA
Filing to be effective 11/22/2021.
Filed Date: 12/7/21.
Accession Number: 20211207–5081.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–568–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Seminole Solar (Seminole II Solar) LGIA
Filing to be effective 11/22/2021.
Filed Date: 12/7/21.
Accession Number: 20211207–5082.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–569–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Seminole Solar (Seminole III Solar)
LGIA Filing to be effective 11/22/2021.
Filed Date: 12/7/21.
Accession Number: 20211207–5086.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–570–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Seminole Solar (Seminole IV Solar)
LGIA Filing to be effective 11/22/2021.
Filed Date: 12/7/21.
Accession Number: 20211207–5087.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–571–000.
Applicants: Assembly Solar I, LLC.
Description: § 205(d) Rate Filing: COC
update 2021 to be effective 12/8/2021.
Filed Date: 12/7/21.
Accession Number: 20211207–5117.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–572–000.
Applicants: Assembly Solar II, LLC.
Description: § 205(d) Rate Filing: COC
update 2021 to be effective 12/8/2021.
Filed Date: 12/7/21.
Accession Number: 20211207–5121.
Comment Date: 5 p.m. ET 12/28/21.
Docket Numbers: ER22–573–000.
Applicants: Assembly Solar III, LLC.
Description: § 205(d) Rate Filing: COC
update 2021 to be effective 12/8/2021.
Filed Date: 12/7/21.
Accession Number: 20211207–5127.
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
70835
Comment Date: 5 p.m. ET 12/28/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at:https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: December 7, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–26897 Filed 12–10–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2188–259]
Northwestern Corporation; Notice of
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Temporary
Variance of Article 403.
b. Project No: 2188–259.
c. Date Filed: November 9, 2021, and
supplemented on November 12, 2021.
d. Applicant: Northwestern
Corporation (licensee).
e. Name of Project: Missouri-Madison
Hydroelectric Project.
f. Location: The project consists of
nine hydroelectric developments
located on the Madison and Missouri
Rivers in Gallatin, Madison, Lewis and
Clark, and Cascade counties, in
southwestern Montana.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Mary Gail
Sullivan, Director, Environmental and
Lands, Northwestern Corporation, 11
East Park Street, Butte, Montana 59701,
(406) 497–3382, marygail.sullivan@
northwestern.com.
E:\FR\FM\13DEN1.SGM
13DEN1
khammond on DSKJM1Z7X2PROD with NOTICES
70836
Federal Register / Vol. 86, No. 236 / Monday, December 13, 2021 / Notices
i. FERC Contact: Jeremy Jessup, (202)
502–6779, Jeremy.Jessup@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests:
January 6, 2022.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include the
docket number P–2188–259. Comments
emailed to Commission staff are not
considered part of the Commission
record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: The
licensee requests a temporary variance
from the reservoir elevation
requirements for the Hebgen
Development required by item (4) of
Article 403 of the licensee. Specifically,
the Hebgen reservoir dropped below the
minimum required elevation of 6,530.26
feet beginning July 22 through October
1, 2021. The reservoir elevation fell
below the requirements due to low
winter snowpack, minimal inflow, and
hot and dry conditions in 2021 reducing
availability of water in the Madison
River drainage and Hebgen reservoir. In
addition, maintaining the required
minimum and pulse flows contributed
to accelerated drafting of Hebgen
VerDate Sep<11>2014
16:50 Dec 10, 2021
Jkt 256001
reservoir in 2021. The variance has
concluded, and the licensee’s filing
requesting a temporary variance is afterthe-fact, as required by Commission
staff’s September 10, 2021 letter.
l. Locations of the Application: This
filing may be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. Agencies may
obtain copies of the application directly
from the applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
Dated: December 7, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–26895 Filed 12–10–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2628–065]
Alabama Power Company; Notice of
Application Tendered for Filing With
the Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2628–065.
c. Date Filed: November 23, 2021.
d. Applicant: Alabama Power
Company (Alabama Power).
e. Name of Project: R.L. Harris
Hydroelectric Project (Harris Project).
f. Location: The Harris Project is
located on the Tallapoosa River near the
City of Lineville in Randolph, Clay, and
Cleburne Counties, Alabama. The Harris
Project also includes land within the
James D. Martin-Skyline Wildlife
Management Area located
approximately 110 miles north of Harris
Reservoir in Jackson County, Alabama.
The project occupies 4.90 acres of
federal land administered by the Bureau
of Land Management.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Angie
Anderegg, Harris Relicensing Project
Manager, Alabama Power Company; 600
North 18th Street, P.O. Box 2641,
Birmingham, AL 35203–8180; (205)
257–2251, or email at arsegars@
southernco.com.
i. FERC Contact: Sarah Salazar at
(202) 502–6863, or email at
sarah.salazar@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. The Harris Project consists of: (1)
The 29-mile-long, 9,870-acre Harris
Lake at a normal full pool elevation of
793 feet mean sea level (msl); (2) a
151.5-foot-high concrete dam; (3) a 310foot-long gated spillway with five 40.5feet-high by 40-feet-wide radial gates for
passing flood flows, and one radial trash
gate; (4) a variable level powerhouse
intake, integral with the dam, which can
draw water from lake elevations
E:\FR\FM\13DEN1.SGM
13DEN1
Agencies
[Federal Register Volume 86, Number 236 (Monday, December 13, 2021)]
[Notices]
[Pages 70835-70836]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-26895]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2188-259]
Northwestern Corporation; Notice of Application Accepted for
Filing and Soliciting Comments, Motions To Intervene, and Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Temporary Variance of Article 403.
b. Project No: 2188-259.
c. Date Filed: November 9, 2021, and supplemented on November 12,
2021.
d. Applicant: Northwestern Corporation (licensee).
e. Name of Project: Missouri-Madison Hydroelectric Project.
f. Location: The project consists of nine hydroelectric
developments located on the Madison and Missouri Rivers in Gallatin,
Madison, Lewis and Clark, and Cascade counties, in southwestern
Montana.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Mary Gail Sullivan, Director, Environmental
and Lands, Northwestern Corporation, 11 East Park Street, Butte,
Montana 59701, (406) 497-3382, [email protected].
[[Page 70836]]
i. FERC Contact: Jeremy Jessup, (202) 502-6779,
[email protected].
j. Deadline for filing comments, motions to intervene, and
protests: January 6, 2022.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, and protests using the Commission's
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may
submit a paper copy. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. The first page of any filing should
include the docket number P-2188-259. Comments emailed to Commission
staff are not considered part of the Commission record.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervenor files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency.
k. Description of Request: The licensee requests a temporary
variance from the reservoir elevation requirements for the Hebgen
Development required by item (4) of Article 403 of the licensee.
Specifically, the Hebgen reservoir dropped below the minimum required
elevation of 6,530.26 feet beginning July 22 through October 1, 2021.
The reservoir elevation fell below the requirements due to low winter
snowpack, minimal inflow, and hot and dry conditions in 2021 reducing
availability of water in the Madison River drainage and Hebgen
reservoir. In addition, maintaining the required minimum and pulse
flows contributed to accelerated drafting of Hebgen reservoir in 2021.
The variance has concluded, and the licensee's filing requesting a
temporary variance is after-the-fact, as required by Commission staff's
September 10, 2021 letter.
l. Locations of the Application: This filing may be viewed on the
Commission's website at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. You may also register
online at https://www.ferc.gov/docs-filing/esubscription.asp to be
notified via email of new filings and issuances related to this or
other pending projects. For assistance, call 1-866-208-3676 or email
[email protected], for TTY, call (202) 502-8659. Agencies may
obtain copies of the application directly from the applicant.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214, respectively. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a party to the proceeding. Any comments,
protests, or motions to intervene must be received on or before the
specified comment date for the particular application.
o. Filing and Service of Documents: Any filing must (1) bear in all
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO
INTERVENE'' as applicable; (2) set forth in the heading the name of the
applicant and the project number of the application to which the filing
responds; (3) furnish the name, address, and telephone number of the
person commenting, protesting or intervening; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis. Any filing made by an intervenor must be accompanied
by proof of service on all persons listed in the service list prepared
by the Commission in this proceeding, in accordance with 18 CFR
385.2010.
Dated: December 7, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-26895 Filed 12-10-21; 8:45 am]