Southern California Edison Company; Notice of Intent To File License Application, Filing of Pre Application Document (Pad), Commencement of Pre Filing Process, and Scoping; Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests, 67704-67706 [2021-25940]

Download as PDF khammond on DSKJM1Z7X2PROD with NOTICES 67704 Federal Register / Vol. 86, No. 226 / Monday, November 29, 2021 / Notices Filed Date: 11/22/21. Accession Number: 20211122–5115. Comment Date: 5 p.m. ET 12/13/21. Docket Numbers: ER22–457–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2021–11–15_SA 3393 Ameren ILSapphire Sky Wind 2nd Rev GIA (J826 J1022) to be effective 11/15/2021. Filed Date: 11/22/21. Accession Number: 20211122–5137. Comment Date: 5 p.m. ET 12/13/21. Docket Numbers: ER22–458–000. Applicants: Southern California Edison Company. Description: § 205(d) Rate Filing: LGIA Cyclone Solar TOT806 SA No 274 to be effective 11/23/2021. Filed Date: 11/22/21. Accession Number: 20211122–5140. Comment Date: 5 p.m. ET 12/13/21. Docket Numbers: ER22–459–000. Applicants: PPL Electric Utilities Corporation, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: PPL Electric Utilities Corporation submits tariff filing per 35.13(a)(2)(iii: PPL Electric submits SA No 6222 Construction Agreement with Borough of Weatherly to be effective 11/23/2021. Filed Date: 11/22/21. Accession Number: 20211122–5149. Comment Date: 5 p.m. ET 12/13/21. Docket Numbers: ER22–460–000. Applicants: PPL Electric Utilities Corporation, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: PPL Electric Utilities Corporation submits tariff filing per 35.13(a)(2)(iii: PPL Electric submits SA No 6223 Construction Agreement with Schuylkill Haven to be effective 11/23/2021. Filed Date: 11/22/21. Accession Number: 20211122–5152. Comment Date: 5 p.m. ET 12/13/21. Docket Numbers: ER22–461–000. Applicants: Midcontinent Independent System Operator, Inc. Description: Compliance filing: 2021– 11–22_Waiver Request on SER–II Ineligibility to Provide Offline STR to be effective N/A. Filed Date: 11/22/21. Accession Number: 20211122–5168. Comment Date: 5 p.m. ET 12/13/21. Docket Numbers: ER22–462–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2021–11–22_SER–II Ineligibility to Provide Offline STR to be effective 12/ 7/2021. Filed Date: 11/22/21. Accession Number: 20211122–5169. VerDate Sep<11>2014 16:55 Nov 26, 2021 Jkt 256001 Comment Date: 5 p.m. ET 12/13/21. DEPARTMENT OF ENERGY Docket Numbers: ER22–463–000. Applicants: Wisconsin Public Service Corporation. Description: § 205(d) Rate Filing: Agent Services Agreement Filing to be effective 1/22/2022. Filed Date: 11/22/21. Accession Number: 20211122–5187. Comment Date: 5 p.m. ET 12/13/21. Federal Energy Regulatory Commission Docket Numbers: ER22–464–000. Applicants: Indra Power Business MD LLC. Description: Baseline eTariff Filing: Tariffs and Agreements to be effective 1/ 22/2022. Filed Date: 11/22/21. Accession Number: 20211122–5209. Comment Date: 5 p.m. ET 12/13/21. Docket Numbers: ER22–465–000. Applicants: Tri-State Generation and Transmission Association, Inc. Description: § 205(d) Rate Filing: Amendment to Rate Schedule No. 812 to be effective 2/25/2020. Filed Date: 11/22/21. Accession Number: 20211122–5221. Comment Date: 5 p.m. ET 12/13/21. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: November 22, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–25942 Filed 11–26–21; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 [Project No. 2290–122] Southern California Edison Company; Notice of Intent To File License Application, Filing of Pre Application Document (Pad), Commencement of Pre Filing Process, and Scoping; Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests a. Type of Filing: Notice of Intent to File License Application for a New License and Commencing Pre-filing Process. b. Project No.: 2290–122. c. Dated Filed: September 22, 2021. d. Submitted By: Southern California Edison Company (SCE). e. Name of Project: Kern River No. 3 Hydroelectric Project (Kern 3 Project). f. Location: The project is located on the North Fork Kern River and on Salmon and Corral Creeks in Kern and Tulare Counties, California. The existing FERC project boundary encompasses a total of 234.6 acres of land, consisting of 9.4 acres of land owned by SCE and 225.2 acres of federal land in Sequoia National Forest administered by the U.S. Forest Service. g. Filed Pursuant to: 18 CFR part 5 of the Commission’s Regulations. h. Potential Applicant Contact: Martin Ostendorf, Senior Manager, Southern California Edison Company, 1515 Walnut Grove Avenue, Rosemead, CA 91770; (559) 893–2033; martin.ostendorf@sce.com. i. FERC Contact: Quinn Emmering at (202) 502–6382 or email at quinn.emmering@ferc.gov. j. Cooperating Agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item o below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See 94 FERC ¶ 61,076 (2001). k. With this notice, we are initiating informal consultation with: (a) The U.S. Fish and Wildlife Service and/or the National Oceanic and Atmospheric Administration Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR part 402 and (b) the State E:\FR\FM\29NON1.SGM 29NON1 khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 86, No. 226 / Monday, November 29, 2021 / Notices Historic Preservation Office, as required by section 106, National Historic Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating SCE as the Commission’s non-federal representative for carrying out informal consultation, pursuant to section 7 of the Endangered Species Act and section 106 of the National Historic Preservation Act. m. SCE filed with the Commission a Pre-Application Document (PAD), including a proposed process plan and schedule, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents via the internet through the Commission’s Home Page (https://www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCONlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TYY, (202) 502–8659. Register online at https:// ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. o. With this notice, we are soliciting comments on the PAD and Commission staff’s Scoping Document 1 (SD1), as well as study requests. All comments on the PAD and SD1, and study requests should be sent to the address above in paragraph h. In addition, all comments on the PAD and SD1, study requests, requests for cooperating agency status, and all communications to and from staff related to the merits of the potential application must be filed with the Commission. The Commission strongly encourages electronic filing. Please file all documents using the Commission’s eFiling system at https:// ferconline.ferc.gov/FERC.aspx. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.gov/ QuickComment.aspx. You must include your name and contact information at the end of your comments. For VerDate Sep<11>2014 16:55 Nov 26, 2021 Jkt 256001 assistance, please contact FERC Support at FERCOnlineSupport@ferc.gov. In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–2290– 122. All filings with the Commission must bear the appropriate heading: ‘‘Comments on Pre-Application Document,’’ ‘‘Study Requests,’’ ‘‘Comments on Scoping Document 1,’’ ‘‘Request for Cooperating Agency Status,’’ or ‘‘Communications to and from Commission Staff.’’ Any individual or entity interested in submitting study requests, commenting on the PAD or SD1, and any agency requesting cooperating status must do so by January 20, 2022. p. The Commission’s scoping process will help determine the required level of analysis and satisfy the National Environmental Policy Act (NEPA) scoping requirements, irrespective of whether the Commission prepares an environmental assessment or environmental impact statement. Scoping Meetings Due to on-going concerns with large gatherings related to COVID–19, we do not intend to hold in-person public scoping meetings or an in-person environmental site review. Rather, Commission staff will hold two public scoping meetings using a telephone conference line. The daytime scoping meeting will focus on resource agency, Indian tribes, and non-governmental organization (NGO) concerns, while the evening scoping meeting will focus on receiving input from the public. We invite all interested agencies, Native American tribes, NGOs, and individuals to attend one of these meetings to assist us in identifying the scope of environmental issues that should be analyzed in the NEPA document. Additionally, a virtual site tour of the Kern 3 Project is available on SCE’s website. The dates and times of the meetings as well as how to access the virtual site tour are listed below. Virtual site tour of the project: Access online at: www.sce.com/regulatory/ hydro-licensing/kr3. Meeting for resource agencies, Tribes, and NGOs: Tuesday, December 14, 2021, 9:00 a.m.–12:00 p.m. PST. Call PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 67705 in number: (415) 527–5035. Access code: 2762 739 2357. When prompted for attendee ID: Press #. Meeting for the general public: Tuesday, December 14, 2021, 6:00 p.m.–8:00 p.m. PST. Call in number: (415) 527– 5035. Access code: 2762 506 0330. When prompted for attendee ID: Press #. SD1, which outlines the subject areas to be addressed in the environmental document, was mailed to the individuals and entities on the Commission’s mailing list and SCE’s distribution list. Copies of SD1 may be viewed on the web at https:// www.ferc.gov, using the ‘‘eLibrary’’ link. Follow the directions for accessing information in paragraph n. Based on all oral and written comments, a Scoping Document 2 (SD2) may be issued. SD2 may include a revised process plan and schedule, as well as a list of issues, identified through the scoping process. Meeting Objectives At the scoping meetings, Commission staff will: (1) Initiate scoping of the issues; (2) review and discuss existing conditions; (3) review and discuss existing information and identify preliminary information and study needs; (4) review and discuss the process plan and schedule for pre-filing activity that incorporates the time frames provided for in Part 5 of the Commission’s regulations and, to the extent possible, maximizes coordination of federal, state, and tribal permitting and certification processes; and (5) discuss the potential of any federal or state agency or Indian tribe to act as a cooperating agency for development of an environmental document. Meeting participants should come prepared to discuss their issues and/or concerns. Please review the PAD in preparation for the scoping meetings. Directions on how to obtain a copy of the PAD and SD1 are included in item n of this document. Meeting Procedures Commission staff will be moderating the scoping meetings. The meetings will begin promptly at their respective start times listed above. After calling the phone number listed above, enter the correct access code and when prompted to enter the attendee ID press the ‘#’ button (no ID number is required). All participants will be automatically muted upon joining the meeting. At the start of the meeting, staff will provide further instructions regarding the meeting setup, agenda, and time period for comments and questions. We ask for your patience as staff present information and field participant E:\FR\FM\29NON1.SGM 29NON1 67706 Federal Register / Vol. 86, No. 226 / Monday, November 29, 2021 / Notices comments in orderly manner. To indicate you have a question or comment, press * and 3 to virtually ‘‘raise your hand’’. Oral comments will be limited to 5 minutes in duration for each participant. The meetings will be recorded by a stenographer and will be filed to the public record of the project. Please note, that if no participants join the meetings within 15 minutes after the start time, staff will end the meeting and conference call. The meetings will end after participants have presented their oral comments or at the specified end time, whichever occurs first. Dated: November 22, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–25940 Filed 11–26–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Filings in Existing Proceedings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Docket Numbers: RP20–614–006. Applicants: Transcontinental Gas Pipe Line Company, LLC. Description: Refund Report: Cash Out Refund Report Supplement Docket Nos. RP20–614 & RP20–618 to be effective N/ A. Filed Date: 11/19/21. Accession Number: 20211119–5022. Comment Date: 5 p.m. ET 12/1/21. Any person desiring to protest in any the above proceedings must file in accordance with Rule 211 of the Commission’s Regulations (18 CFR 385.211) on or before 5:00 p.m. Eastern time on the specified comment date. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Filings Instituting Proceedings khammond on DSKJM1Z7X2PROD with NOTICES Applicants: Texas Eastern Transmission, LP. Description: § 4(d) Rate Filing: TEAM 2014 Project Historical Capacity Releases to be effective 12/1/2021. Filed Date: 11/19/21. Accession Number: 20211119–5257. Comment Date: 5 p.m. ET 12/1/21. Docket Numbers: RP22–338–000. Applicants: Iroquois Gas Transmission System, L.P. Description: § 4(d) Rate Filing: 11.22.21 Negotiated Rates—Equinor Natural Gas LLC R–7120–14 to be effective 12/1/2021. Filed Date: 11/22/21. Accession Number: 20211122–5064. Comment Date: 5 p.m. ET 12/6/21. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. Docket Numbers: RP22–334–000. Applicants: Rockies Express Pipeline LLC. Description: § 4(d) Rate Filing: REX 2021–11–19 GT&C Section 11.3 Revisions to be effective 12/19/2021. Filed Date: 11/19/21. Accession Number: 20211119–5201. Comment Date: 5 p.m. ET 12/1/21. Docket Numbers: RP22–335–000. Applicants: Cheyenne Connector, LLC. Description: § 4(d) Rate Filing: CC 2021–11–19 GT&C Section 11.3 Revisions to be effective 12/19/2021. Filed Date: 11/19/21. Accession Number: 20211119–5203. Comment Date: 5 p.m. ET 12/1/21. Docket Numbers: RP22–336–000. Applicants: Texas Eastern Transmission, LP. Description: § 4(d) Rate Filing: Negotiated Rates Filing—Noble to Direct Energy to be effective 12/1/2021. Filed Date: 11/19/21. Accession Number: 20211119–5222. Comment Date: 5 p.m. ET 12/1/21. Docket Numbers: RP22–337–000. VerDate Sep<11>2014 16:55 Nov 26, 2021 Jkt 256001 Dated: November 22, 2021. Kimberly D. Bose, Secretary. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AD21–15–000] Joint Federal-State Task Force on Electric Transmission; Notice Inviting Post-Meeting Comments On November 10, 2021, the Joint Federal-State Task Force on Electric Transmission convened for its first public meeting. All interested persons are invited to file post-meeting comments to address issues raised during the meeting and identified in the Agenda issued October 27, 2021. Comments must be submitted on or before 30 days from the date of this Notice. Comments may be filed electronically via the internet.1 Instructions are available on the Commission’s website https://www.ferc.gov/docs-filing/ efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, submissions sent via the U.S. Postal Service must be addressed to: Federal Energy Regulatory Commission, Office of the Secretary, 888 First Street NE, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Federal Energy Regulatory Commission, Office of the Secretary, 12225 Wilkins Avenue, Rockville, Maryland 20852. For more information about this Notice, please contact: Michael Cackoski (Technical Information), Office of Energy Policy and Innovation, (202) 502–6169, Michael.Cackoski@ferc.gov Gretchen Kershaw (Legal Information), Office of the General Counsel, (202) 502–8213, Gretchen.Kershaw@ ferc.gov Dated: November 22, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–25939 Filed 11–26–21; 8:45 am] BILLING CODE 6717–01–P [FR Doc. 2021–25941 Filed 11–26–21; 8:45 am] 1 See BILLING CODE 6717–01–P PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 E:\FR\FM\29NON1.SGM 18 CFR 385.2001(a)(1)(iii) (2020). 29NON1

Agencies

[Federal Register Volume 86, Number 226 (Monday, November 29, 2021)]
[Notices]
[Pages 67704-67706]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-25940]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2290-122]


Southern California Edison Company; Notice of Intent To File 
License Application, Filing of Pre Application Document (Pad), 
Commencement of Pre Filing Process, and Scoping; Request for Comments 
on the Pad and Scoping Document, and Identification of Issues and 
Associated Study Requests

    a. Type of Filing: Notice of Intent to File License Application for 
a New License and Commencing Pre-filing Process.
    b. Project No.: 2290-122.
    c. Dated Filed: September 22, 2021.
    d. Submitted By: Southern California Edison Company (SCE).
    e. Name of Project: Kern River No. 3 Hydroelectric Project (Kern 3 
Project).
    f. Location: The project is located on the North Fork Kern River 
and on Salmon and Corral Creeks in Kern and Tulare Counties, 
California. The existing FERC project boundary encompasses a total of 
234.6 acres of land, consisting of 9.4 acres of land owned by SCE and 
225.2 acres of federal land in Sequoia National Forest administered by 
the U.S. Forest Service.
    g. Filed Pursuant to: 18 CFR part 5 of the Commission's 
Regulations.
    h. Potential Applicant Contact: Martin Ostendorf, Senior Manager, 
Southern California Edison Company, 1515 Walnut Grove Avenue, Rosemead, 
CA 91770; (559) 893-2033; [email protected].
    i. FERC Contact: Quinn Emmering at (202) 502-6382 or email at 
[email protected].
    j. Cooperating Agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item o below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See 94 FERC ] 
61,076 (2001).
    k. With this notice, we are initiating informal consultation with: 
(a) The U.S. Fish and Wildlife Service and/or the National Oceanic and 
Atmospheric Administration Fisheries under section 7 of the Endangered 
Species Act and the joint agency regulations thereunder at 50 CFR part 
402 and (b) the State

[[Page 67705]]

Historic Preservation Office, as required by section 106, National 
Historic Preservation Act, and the implementing regulations of the 
Advisory Council on Historic Preservation at 36 CFR 800.2.
    l. With this notice, we are designating SCE as the Commission's 
non-federal representative for carrying out informal consultation, 
pursuant to section 7 of the Endangered Species Act and section 106 of 
the National Historic Preservation Act.
    m. SCE filed with the Commission a Pre-Application Document (PAD), 
including a proposed process plan and schedule, pursuant to 18 CFR 5.6 
of the Commission's regulations.
    n. In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents via the internet through 
the Commission's Home Page (https://www.ferc.gov) using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. At this time, the 
Commission has suspended access to the Commission's Public Reference 
Room, due to the proclamation declaring a National Emergency concerning 
the Novel Coronavirus Disease (COVID-19), issued by the President on 
March 13, 2020. For assistance, contact FERC at 
[email protected] or call toll-free, (866) 208-3676 or TYY, 
(202) 502-8659.
    Register online at https://ferconline.ferc.gov/FERCOnline.aspx to 
be notified via email of new filing and issuances related to this or 
other pending projects. For assistance, contact FERC Online Support.
    o. With this notice, we are soliciting comments on the PAD and 
Commission staff's Scoping Document 1 (SD1), as well as study requests. 
All comments on the PAD and SD1, and study requests should be sent to 
the address above in paragraph h. In addition, all comments on the PAD 
and SD1, study requests, requests for cooperating agency status, and 
all communications to and from staff related to the merits of the 
potential application must be filed with the Commission.
    The Commission strongly encourages electronic filing. Please file 
all documents using the Commission's eFiling system at https://ferconline.ferc.gov/FERC.aspx. Commenters can submit brief comments up 
to 6,000 characters, without prior registration, using the eComment 
system at https://ferconline.gov/QuickComment.aspx. You must include 
your name and contact information at the end of your comments. For 
assistance, please contact FERC Support at [email protected] 
In lieu of electronic filing, you may submit a paper copy. Submissions 
sent via the U.S. Postal Service must be addressed to: Kimberly D. 
Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE, Room 1A, Washington, DC 20426. Submissions sent via any other 
carrier must be addressed to: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852. The first page of any filing should include docket number P-
2290-122.
    All filings with the Commission must bear the appropriate heading: 
``Comments on Pre-Application Document,'' ``Study Requests,'' 
``Comments on Scoping Document 1,'' ``Request for Cooperating Agency 
Status,'' or ``Communications to and from Commission Staff.'' Any 
individual or entity interested in submitting study requests, 
commenting on the PAD or SD1, and any agency requesting cooperating 
status must do so by January 20, 2022.
    p. The Commission's scoping process will help determine the 
required level of analysis and satisfy the National Environmental 
Policy Act (NEPA) scoping requirements, irrespective of whether the 
Commission prepares an environmental assessment or environmental impact 
statement.

Scoping Meetings

    Due to on-going concerns with large gatherings related to COVID-19, 
we do not intend to hold in-person public scoping meetings or an in-
person environmental site review. Rather, Commission staff will hold 
two public scoping meetings using a telephone conference line. The 
daytime scoping meeting will focus on resource agency, Indian tribes, 
and non-governmental organization (NGO) concerns, while the evening 
scoping meeting will focus on receiving input from the public. We 
invite all interested agencies, Native American tribes, NGOs, and 
individuals to attend one of these meetings to assist us in identifying 
the scope of environmental issues that should be analyzed in the NEPA 
document. Additionally, a virtual site tour of the Kern 3 Project is 
available on SCE's website. The dates and times of the meetings as well 
as how to access the virtual site tour are listed below.

Virtual site tour of the project: Access online at: www.sce.com/regulatory/hydro-licensing/kr3.
Meeting for resource agencies, Tribes, and NGOs: Tuesday, December 14, 
2021, 9:00 a.m.-12:00 p.m. PST. Call in number: (415) 527-5035. Access 
code: 2762 739 2357. When prompted for attendee ID: Press #.
Meeting for the general public: Tuesday, December 14, 2021, 6:00 p.m.-
8:00 p.m. PST. Call in number: (415) 527-5035. Access code: 2762 506 
0330. When prompted for attendee ID: Press #.

    SD1, which outlines the subject areas to be addressed in the 
environmental document, was mailed to the individuals and entities on 
the Commission's mailing list and SCE's distribution list. Copies of 
SD1 may be viewed on the web at https://www.ferc.gov, using the 
``eLibrary'' link. Follow the directions for accessing information in 
paragraph n. Based on all oral and written comments, a Scoping Document 
2 (SD2) may be issued. SD2 may include a revised process plan and 
schedule, as well as a list of issues, identified through the scoping 
process.

Meeting Objectives

    At the scoping meetings, Commission staff will: (1) Initiate 
scoping of the issues; (2) review and discuss existing conditions; (3) 
review and discuss existing information and identify preliminary 
information and study needs; (4) review and discuss the process plan 
and schedule for pre-filing activity that incorporates the time frames 
provided for in Part 5 of the Commission's regulations and, to the 
extent possible, maximizes coordination of federal, state, and tribal 
permitting and certification processes; and (5) discuss the potential 
of any federal or state agency or Indian tribe to act as a cooperating 
agency for development of an environmental document. Meeting 
participants should come prepared to discuss their issues and/or 
concerns. Please review the PAD in preparation for the scoping 
meetings. Directions on how to obtain a copy of the PAD and SD1 are 
included in item n of this document.

Meeting Procedures

    Commission staff will be moderating the scoping meetings. The 
meetings will begin promptly at their respective start times listed 
above. After calling the phone number listed above, enter the correct 
access code and when prompted to enter the attendee ID press the `#' 
button (no ID number is required). All participants will be 
automatically muted upon joining the meeting.
    At the start of the meeting, staff will provide further 
instructions regarding the meeting setup, agenda, and time period for 
comments and questions. We ask for your patience as staff present 
information and field participant

[[Page 67706]]

comments in orderly manner. To indicate you have a question or comment, 
press * and 3 to virtually ``raise your hand''. Oral comments will be 
limited to 5 minutes in duration for each participant. The meetings 
will be recorded by a stenographer and will be filed to the public 
record of the project.
    Please note, that if no participants join the meetings within 15 
minutes after the start time, staff will end the meeting and conference 
call. The meetings will end after participants have presented their 
oral comments or at the specified end time, whichever occurs first.

    Dated: November 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-25940 Filed 11-26-21; 8:45 am]