Combined Notice of Filings #1, 66293-66294 [2021-25402]
Download as PDF
Federal Register / Vol. 86, No. 222 / Monday, November 22, 2021 / Notices
Additional Coronavirus Response and
Relief Consolidated Appropriations Act,
2021 Public Law 116–260.
Signing Authority
This document of the Department of
Energy was signed on November 16,
2021, by Kelly Speakes-Backman,
Principal Deputy Assistant Secretary
and Acting Assistant Secretary for
Energy Efficiency and Renewable
Energy, pursuant to delegated authority
from the Secretary of Energy. That
document with the original signature
and date is maintained by DOE. For
administrative purposes only, and in
compliance with requirements of the
Office of the Federal Register, the
undersigned DOE Federal Register
Liaison Officer has been authorized to
sign and submit the document in
electronic format for publication, as an
official document of the Department of
Energy. This administrative process in
no way alters the legal effect of this
document upon publication in the
Federal Register.
Signed in Washington, DC, on November
17, 2021.
Treena V. Garrett,
Federal Register Liaison Officer, U.S.
Department of Energy.
[FR Doc. 2021–25429 Filed 11–19–21; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PL21–3–000]
jspears on DSK121TN23PROD with NOTICES1
Technical Conference on Greenhouse
Gas Mitigation: Natural Gas Act
Sections 3 and 7 Authorizations;
Notice Inviting Technical Conference
Comments
On November 19, 2021, the Federal
Energy Regulatory Commission
(Commission) will convene a
Commission staff-led technical
conference to discuss methods natural
gas companies may use to mitigate the
effects of direct and indirect greenhouse
gas emissions resulting from Natural
Gas Act sections 3 and 7 authorizations.
All interested persons are invited to
file post-technical conference comments
to address issues raised during the
technical conference and identified in
the Supplemental Notices of Technical
Conference issued on October 1, 2021,
and November 9, 2021. For reference,
the questions included in the
Supplemental Notices are included
below. Commenters need not answer all
of the questions but are encouraged to
organize responses using the numbering
VerDate Sep<11>2014
18:30 Nov 19, 2021
Jkt 256001
66293
and order in the questions below.
Commenters are also invited to
reference material previously filed in
this docket but are encouraged to avoid
repetition or replication of previous
material. Comments are due on
Tuesday, December 14, 2021.
Comments may be filed electronically
via the internet.1 Instructions are
available on the Commission’s website
https://www.ferc.gov/docs-filing/
efiling.asp. For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659.
For more information about this
notice, please contact GHGTechConf@
ferc.gov.
GHG emissions project sponsors are
currently available to project sponsors?
c. Are market-based mitigation
measures effective and verifiable
methods of mitigation over the life of a
project? What effects would this type of
mitigation from Commissionjurisdictional projects have on offset,
REC, and GHG compliance markets?
d. Should project applicants submit
mitigation proposals with their project
application? How soon might current
project applicants be able to supplement
the record or respond to a Commission
data request with their mitigation
proposal?
e. What factors should the
Commission consider in evaluating the
sufficiency of a mitigation proposal?
Dated: November 16, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
3. Compliance and Cost Recovery of
Mitigation
Post-Technical Conference Questions
for Comment
1. The Level of Mitigation for a Proposed
Project’s Reasonably Foreseeable
Greenhouse Gas Emissions
a. When determining the amount of
reasonably foreseeable GHG emissions
associated with a proposed project, how
could the Commission consider: Project
utilization projections; State or regional
natural gas usage projections from
Public Utility Commissions or other
entities; individual emissions data for
industrial or electric generation
customers; known netting effects from
displacement of higher or lower
emitting sources, including
displacement that may occur over the
life of the project; or other factors?
b. What is the appropriate level of
mitigation associated with GHG
emissions for a proposed project?
Should the Commission determine the
amount of mitigation required on a caseby-case basis or should the mitigation
levels be set at zero, less than
significant, or some other level?
2. Types of Mitigation
a. What types of physical mitigation
associated with GHG emissions are
project sponsors currently using at their
facilities? What types of physical
mitigation associated with GHG
emissions project sponsors are currently
available to project sponsors? Are there
limitations to physical mitigation
measures?
b. What types of market-based
mitigation associated with GHG
emissions are project sponsors currently
using? What types of alternative or
market-based mitigation associated with
1 See
PO 00000
18 CFR 385.2001(a)(1)(iii) (2020).
Frm 00025
Fmt 4703
Sfmt 4703
a. How could the Commission ensure
continued verification and accounting
of GHG mitigation measures since the
Commission would need to monitor and
assess mitigation during the life of the
project?
b. Are there federal or state agencies
which currently monitor compliance of
GHG mitigation measures? Should the
Commission explore potential
interagency agreements or
memorandums of understanding with
other federal agencies to monitor
compliance of GHG mitigation
measures?
c. How could the Commission allow
project sponsors to recover the costs of
market-based mitigation measures, such
as the purchase of offsets? Would
allowing recovery of such costs through
an annual tracker or surcharge be
appropriate?
[FR Doc. 2021–25403 Filed 11–19–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC22–16–000.
Applicants: Energy Center Paxton
LLC, KKR Thor Bidco, LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act of Energy Center
Paxton LLC.
Filed Date: 11/15/21.
Accession Number: 20211115–5233.
Comment Date: 5 p.m. ET 12/6/21.
E:\FR\FM\22NON1.SGM
22NON1
jspears on DSK121TN23PROD with NOTICES1
66294
Federal Register / Vol. 86, No. 222 / Monday, November 22, 2021 / Notices
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG22–23–000.
Applicants: Arlington Energy Center
III, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Arlington Energy
Center III, LLC.
Filed Date: 11/16/21.
Accession Number: 20211116–5108.
Comment Date: 5 p.m. ET 12/7/21.
Take notice that the Commission
received the following Complaints and
Compliance filings in EL Dockets:
Docket Numbers: EL22–9–000.
Applicants: ITC Midwest LLC.
Description: Petition for Declaratory
Order of ITC Midwest LLC.
Filed Date: 11/2/21.
Accession Number: 20211102–5230.
Comment Date: 5 p.m. ET 12/2/21.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER20–1906–001.
Applicants: Story County Wind, LLC.
Description: Midcontinent
Independent System Operator, Inc.
submits tariff filing per 35.19a(b):
Refund Report__Story County Wind,
LLC to be effective N/A.
Filed Date: 11/16/21.
Accession Number: 20211116–5167.
Comment Date: 5 p.m. ET 12/7/21.
Docket Numbers: ER22–1–001.
Applicants: Alliant Energy Corporate
Services, Inc.
Description: Tariff Amendment:
Amendment to Schedule 2 Submission
to be effective 11/30/2021.
Filed Date: 11/16/21.
Accession Number: 20211116–5101.
Comment Date: 5 p.m. ET 12/7/21.
Docket Numbers: ER22–244–000;
TS22–1–000.
Applicants: Caddo Wind, LLC, Caddo
Wind, LLC.
Description: Amended Request for
Temporary Tariff Waiver, et al. of Caddo
Wind, LLC.
Filed Date: 11/10/21.
Accession Number: 20211110–5270.
Comment Date: 5 p.m. ET 11/22/21.
Docket Numbers: ER22–355–000.
Applicants: ISO New England Inc.
Description: ISO New England Inc.
Resource Termination—Killingly Energy
Center.
Filed Date: 11/4/21.
Accession Number: 20211104–5202.
Comment Date: 5 p.m. ET 11/26/21.
Docket Numbers: ER22–408–000.
Applicants: Persimmon Creek Wind
Farm 1, LLC.
Description: Request for Waiver and
Expedited Consideration of Persimmon
Creek Wind Farm 1, LLC.
VerDate Sep<11>2014
18:30 Nov 19, 2021
Jkt 256001
Filed Date: 11/12/21.
Accession Number: 20211112–5386.
Comment Date: 5 p.m. ET 12/3/21.
Docket Numbers: ER22–413–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Amendment to WMPA SA No. 5588;
Queue No. AE2–114 to be effective 1/8/
2020.
Filed Date: 11/16/21.
Accession Number: 20211116–5086.
Comment Date: 5 p.m. ET 12/7/21.
Docket Numbers: ER22–414–000.
Applicants: AES Marketing and
Trading, LLC.
Description: Baseline eTariff Filing:
AES Marketing and Trading, LLC MBR
Tariff to be effective 11/17/2021.
Filed Date: 11/16/21.
Accession Number: 20211116–5140.
Comment Date: 5 p.m. ET 12/7/21.
Docket Numbers: ER22–415–000.
Applicants: Arlington Energy Center
III, LLC.
Description: Baseline eTariff Filing:
Arlington Energy Center III, LLC
Application for Market-Based Rate
Authorization to be effective 1/16/2022.
Filed Date: 11/16/21.
Accession Number: 20211116–5172.
Comment Date: 5 p.m. ET 12/7/21.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES22–23–000.
Applicants: Basin Electric Power
Cooperative.
Description: Application Under
Section 204 of the Federal Power Act for
Authorization to Issue Securities of
Basin Electric Power Cooperative.
Filed Date: 11/16/21.
Accession Number: 20211116–5183.
Comment Date: 5 p.m. ET 12/7/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
Dated: November 16, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–25402 Filed 11–19–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14634–003]
New England Hydropower Company,
LLC; Notice of Application Tendered
for Filing With the Commission and
Soliciting Additional Study Requests
and Establishing Procedural Schedule
for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Minor
License.
b. Project No.: 14634–003.
c. Date filed: November 2, 2021.
d. Applicant: New England
Hydropower Company, LLC (NEHC).
e. Name of Project: Ashton Dam
Hydroelectric Project (project).
f. Location: On the Blackstone River
in Providence County, Rhode Island. No
federal or tribal lands would be
occupied by project works or located
within the project boundary.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Michael
Kerr, New England Hydropower
Company, LLC, 100 Cummings Center,
Suite 451C, Beverly, MA 01915; Phone
at (978) 360–2547, or email at michael@
nehydropower.com.
i. FERC Contact: John Baummer at
(202) 502–6837, or john.baummer@
ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
E:\FR\FM\22NON1.SGM
22NON1
Agencies
[Federal Register Volume 86, Number 222 (Monday, November 22, 2021)]
[Notices]
[Pages 66293-66294]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-25402]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
corporate filings:
Docket Numbers: EC22-16-000.
Applicants: Energy Center Paxton LLC, KKR Thor Bidco, LLC.
Description: Application for Authorization Under Section 203 of the
Federal Power Act of Energy Center Paxton LLC.
Filed Date: 11/15/21.
Accession Number: 20211115-5233.
Comment Date: 5 p.m. ET 12/6/21.
[[Page 66294]]
Take notice that the Commission received the following exempt
wholesale generator filings:
Docket Numbers: EG22-23-000.
Applicants: Arlington Energy Center III, LLC.
Description: Notice of Self-Certification of Exempt Wholesale
Generator Status of Arlington Energy Center III, LLC.
Filed Date: 11/16/21.
Accession Number: 20211116-5108.
Comment Date: 5 p.m. ET 12/7/21.
Take notice that the Commission received the following Complaints
and Compliance filings in EL Dockets:
Docket Numbers: EL22-9-000.
Applicants: ITC Midwest LLC.
Description: Petition for Declaratory Order of ITC Midwest LLC.
Filed Date: 11/2/21.
Accession Number: 20211102-5230.
Comment Date: 5 p.m. ET 12/2/21.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER20-1906-001.
Applicants: Story County Wind, LLC.
Description: Midcontinent Independent System Operator, Inc. submits
tariff filing per 35.19a(b): Refund Report__Story County Wind, LLC to
be effective N/A.
Filed Date: 11/16/21.
Accession Number: 20211116-5167.
Comment Date: 5 p.m. ET 12/7/21.
Docket Numbers: ER22-1-001.
Applicants: Alliant Energy Corporate Services, Inc.
Description: Tariff Amendment: Amendment to Schedule 2 Submission
to be effective 11/30/2021.
Filed Date: 11/16/21.
Accession Number: 20211116-5101.
Comment Date: 5 p.m. ET 12/7/21.
Docket Numbers: ER22-244-000; TS22-1-000.
Applicants: Caddo Wind, LLC, Caddo Wind, LLC.
Description: Amended Request for Temporary Tariff Waiver, et al. of
Caddo Wind, LLC.
Filed Date: 11/10/21.
Accession Number: 20211110-5270.
Comment Date: 5 p.m. ET 11/22/21.
Docket Numbers: ER22-355-000.
Applicants: ISO New England Inc.
Description: ISO New England Inc. Resource Termination--Killingly
Energy Center.
Filed Date: 11/4/21.
Accession Number: 20211104-5202.
Comment Date: 5 p.m. ET 11/26/21.
Docket Numbers: ER22-408-000.
Applicants: Persimmon Creek Wind Farm 1, LLC.
Description: Request for Waiver and Expedited Consideration of
Persimmon Creek Wind Farm 1, LLC.
Filed Date: 11/12/21.
Accession Number: 20211112-5386.
Comment Date: 5 p.m. ET 12/3/21.
Docket Numbers: ER22-413-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Amendment to WMPA SA No.
5588; Queue No. AE2-114 to be effective 1/8/2020.
Filed Date: 11/16/21.
Accession Number: 20211116-5086.
Comment Date: 5 p.m. ET 12/7/21.
Docket Numbers: ER22-414-000.
Applicants: AES Marketing and Trading, LLC.
Description: Baseline eTariff Filing: AES Marketing and Trading,
LLC MBR Tariff to be effective 11/17/2021.
Filed Date: 11/16/21.
Accession Number: 20211116-5140.
Comment Date: 5 p.m. ET 12/7/21.
Docket Numbers: ER22-415-000.
Applicants: Arlington Energy Center III, LLC.
Description: Baseline eTariff Filing: Arlington Energy Center III,
LLC Application for Market-Based Rate Authorization to be effective 1/
16/2022.
Filed Date: 11/16/21.
Accession Number: 20211116-5172.
Comment Date: 5 p.m. ET 12/7/21.
Take notice that the Commission received the following electric
securities filings:
Docket Numbers: ES22-23-000.
Applicants: Basin Electric Power Cooperative.
Description: Application Under Section 204 of the Federal Power Act
for Authorization to Issue Securities of Basin Electric Power
Cooperative.
Filed Date: 11/16/21.
Accession Number: 20211116-5183.
Comment Date: 5 p.m. ET 12/7/21.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: November 16, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021-25402 Filed 11-19-21; 8:45 am]