ECOsponsible, LLC; Notice of Termination of License (Major Project) by Implied Surrender and Soliciting Comments, Protests, and Motions To Intervene, 64197-64198 [2021-25077]

Download as PDF Federal Register / Vol. 86, No. 219 / Wednesday, November 17, 2021 / Notices potentially affected by the proposed project Amendment. If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please complete one of the following steps: (1) Send an email to GasProjectAddressChange@ferc.gov stating your request. You must include the docket number CP14–517–001 in your request. If you are requesting a change to your address, please be sure to include your name and the correct address. If you are requesting to delete your address from the mailing list, please include your name and address as it appeared on this notice. This email address is unable to accept comments. OR (2) Return the attached ‘‘Mailing List Update Form’’ (appendix 2). Additional Information Additional information about the project Amendment is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number in the ‘‘Docket Number’’ field. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Public sessions or site visits will be posted on the Commission’s calendar located at https://www.ferc.gov/newsevents/events along with other related information. Dated: November 10, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–25080 Filed 11–16–21; 8:45 am] khammond on DSKJM1Z7X2PROD with NOTICES BILLING CODE 6717–01–P VerDate Sep<11>2014 17:11 Nov 16, 2021 Jkt 256001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 9709–070] ECOsponsible, LLC; Notice of Termination of License (Major Project) by Implied Surrender and Soliciting Comments, Protests, and Motions To Intervene Take notice that the following hydroelectric proceeding has been initiated by the Commission: a. Application Type: Termination of License by Implied Surrender. b. Project No: 9709–070. c. Date Initiated: November 8, 2021. d. Licensee: ECOsponsible, LLC. e. Name of Project: Herkimer Hydroelectric Project. f. Location: The Herkimer Hydroelectric Project is located on the West Canada Creek, Herkimer County, New York. g. Filed Pursuant to: Standard Article 26. h. Applicant Contact: Mr. Dennis Ryan, ECOsponsible, LLC, 469 Snyder Road, East Aurora, New York 14052– 9710. i. FERC Contact: David Rudisail, (202) 502–6376, david.rudisail@ferc.gov. j. Deadline for filing comments, motions to intervene and protests: December 27, 2021. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket numbers P–9709–070. Comments emailed to Commission staff are not PO 00000 Frm 00021 Fmt 4703 Sfmt 4703 64197 considered part of the Commission record. k. Description of Project Facilities: The project works include: A timber crib dam with a 9-foot-high, 95-foot-long section reaching a crest elevation of 420 feet mean sea level (msl) and 12-foothigh, 145-foot-long section reaching a crest elevation of 419.2 feet msl; a reservoir with a surface area of 19 acres, storage capacity of 163 acre-feet, and normal water surface elevation of 420.5 feet msl; timber flashboards; an intake structure; a reinforced concrete and steel powerhouse containing four generating units with a capacity of 400 kilowatts (kW) each and an 80-kW minimum flow generator at the base of the dam for a total installed capacity of 1,680 kW; a 50-foot-long, 13.2-kilovolt transmission line; and appurtenant facilities. The project has been not operated since 2006. l. Description of Proceeding: License Article 26 states in part: If the licensee shall abandon or discontinue good faith operation of the project or refuse or neglect to comply with the terms of the license and the lawful orders of the Commission mailed to the record address of the licensee or its agent, the Commission will deem it to be the intent of the licensee to surrender the license. The project has fallen into disrepair and has not operated since 2006. The project was transferred to the licensee by order dated March 12, 2015 (2015 Order). The 2015 Order required the licensee to file a plan and schedule to restore project operation within 60 days. Since that time, the Commission’s Division of Dam Safety and Inspections New York Regional Office (NYRO) has issued eight letters requiring the licensee to file a plan and schedule to make the needed repairs and to restore project operation. The licensee has responded over the years with at least five plans, but all have been deficient because they lack sufficient detail for NYRO’s review and approval. The licensee has never filed satisfactory plans and specifications to repair the project. On August 26, 2021, NYRO inspected the project and found it in unsatisfactory condition and largely abandoned. The licensee did not attend the inspection and has failed to respond to phone calls and emails since. In a final letter to the licensee dated October 18, 2021, NYRO again required the licensee to reply to past letters but the licensee has stopped responding to the Commission. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. E:\FR\FM\17NON1.SGM 17NON1 khammond on DSKJM1Z7X2PROD with NOTICES 64198 Federal Register / Vol. 86, No. 219 / Wednesday, November 17, 2021 / Notices n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Agency Comments: Federal, state, and local agencies are invited to file comments on the described proceeding. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. p. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS,’’ ‘‘PROTEST,’’ or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001–385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the implied surrender. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: November 10, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–25077 Filed 11–16–21; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 17:11 Nov 16, 2021 Jkt 256001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: PR22–4–000. Applicants: Rocky Mountain Natural Gas LLC. Description: Submits tariff filing per 284.123(b),(e)/: RMNG 2021 SOC Filing to be effective 11/1/2021. Filed Date: 11/8/21. Accession Number: 20211108–5096. Comments/Protests Due: 5 p.m. ET 11/29/21. Docket Numbers: CP22–14–000. Applicants: Southern Natural Gas Company, L.L.C. Description: Application for Authorization to Abandon Services of Southern Natural Gas Company, L.L.C. Filed Date: 11/09/2021. Accession Number: 20211109–5055. Comment Date: 5 p.m. ET 11/30/21. Docket Numbers: RP22–202–000. Applicants: Tres Palacios Gas Storage LLC. Description: Compliance filing: Tres Palacios Gas Storage LLC Order No. 587–Z Compliance Filing to be effective 6/1/2022. Filed Date: 11/9/21. Accession Number: 20211109–5152. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–203–000. Applicants: ANR Storage Company. Description: Compliance filing: Compliance to RM96–1–042—Order No. 587–Z to be effective 6/1/2022. Filed Date: 11/9/21. Accession Number: 20211109–5196. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–204–000. Applicants: Midwestern Gas Transmission Company. Description: Compliance filing: NAESB 3.2 Compliance Filing to be effective 6/1/2022. Filed Date: 11/9/21. Accession Number: 20211109–5204. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–205–000. Applicants: OkTex Pipeline Company, L.L.C. Description: Compliance filing: NAESB 3.2 Compliance Filing to be effective 6/1/2022. Filed Date: 11/9/21. Accession Number: 20211109–5207. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–206–000. PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 Applicants: Guardian Pipeline, L.L.C. Description: Compliance filing: NAESB 3.2 Compliance Filing to be effective 6/1/2022. Filed Date: 11/9/21. Accession Number: 20211109–5209. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–207–000. Applicants: Viking Gas Transmission Company. Description: Compliance filing: NAESB 3.2 Compliance Filing to be effective 6/1/2022. Filed Date: 11/9/21. Accession Number: 20211109–5210. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–208–000. Applicants: Bison Pipeline LLC. Description: Compliance filing: Compliance to RM96–1–042—Order No. 587–Z to be effective 6/1/2022. Filed Date: 11/10/21. Accession Number: 20211110–5000. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–209–000. Applicants: Maritimes & Northeast Pipeline, L.L.C. Description: Compliance filing: MNUS Order 587–Z (Docket RM96–1– 042) Compliance Filing to be effective 6/ 1/2022. Filed Date: 11/10/21. Accession Number: 20211110–5022. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–210–000. Applicants: NEXUS Gas Transmission, LLC. Description: Compliance filing: NEXUS Order 587–Z (Docket RM96–1– 042) Compliance Filing to be effective 6/ 1/2022. Filed Date: 11/10/21. Accession Number: 20211110–5025. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–211–000. Applicants: Dominion Energy Questar Pipeline, LLC. Description: Compliance filing: Order No. 587–Z—NAESB 3.2 Compliance Filing to be effective 6/1/2022. Filed Date: 11/10/21. Accession Number: 20211110–5035. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–212–000. Applicants: Dominion Energy Overthrust Pipeline, LLC. Description: Compliance filing: Order No. 587–Z—NAESB 3.2 Compliance Filing to be effective 6/1/2022. Filed Date: 11/10/21. Accession Number: 20211110–5036. Comment Date: 5 p.m. ET 11/22/21. Docket Numbers: RP22–213–000. Applicants: White River Hub, LLC. Description: Compliance filing: Order 587–Z—NAESB 3.2 Compliance Filing to be effective 6/1/2022. E:\FR\FM\17NON1.SGM 17NON1

Agencies

[Federal Register Volume 86, Number 219 (Wednesday, November 17, 2021)]
[Notices]
[Pages 64197-64198]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-25077]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 9709-070]


ECOsponsible, LLC; Notice of Termination of License (Major 
Project) by Implied Surrender and Soliciting Comments, Protests, and 
Motions To Intervene

    Take notice that the following hydroelectric proceeding has been 
initiated by the Commission:
    a. Application Type: Termination of License by Implied Surrender.
    b. Project No: 9709-070.
    c. Date Initiated: November 8, 2021.
    d. Licensee: ECOsponsible, LLC.
    e. Name of Project: Herkimer Hydroelectric Project.
    f. Location: The Herkimer Hydroelectric Project is located on the 
West Canada Creek, Herkimer County, New York.
    g. Filed Pursuant to: Standard Article 26.
    h. Applicant Contact: Mr. Dennis Ryan, ECOsponsible, LLC, 469 
Snyder Road, East Aurora, New York 14052-9710.
    i. FERC Contact: David Rudisail, (202) 502-6376, 
[email protected].
    j. Deadline for filing comments, motions to intervene and protests: 
December 27, 2021.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, and protests using the Commission's 
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. 
Commenters can submit brief comments up to 6,000 characters, without 
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at [email protected], (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may 
submit a paper copy. Submissions sent via the U.S. Postal Service must 
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852. The first page of any filing should 
include docket numbers P-9709-070. Comments emailed to Commission staff 
are not considered part of the Commission record.
    k. Description of Project Facilities: The project works include: A 
timber crib dam with a 9-foot-high, 95-foot-long section reaching a 
crest elevation of 420 feet mean sea level (msl) and 12-foot-high, 145-
foot-long section reaching a crest elevation of 419.2 feet msl; a 
reservoir with a surface area of 19 acres, storage capacity of 163 
acre-feet, and normal water surface elevation of 420.5 feet msl; timber 
flashboards; an intake structure; a reinforced concrete and steel 
powerhouse containing four generating units with a capacity of 400 
kilowatts (kW) each and an 80-kW minimum flow generator at the base of 
the dam for a total installed capacity of 1,680 kW; a 50-foot-long, 
13.2-kilovolt transmission line; and appurtenant facilities. The 
project has been not operated since 2006.
    l. Description of Proceeding: License Article 26 states in part: If 
the licensee shall abandon or discontinue good faith operation of the 
project or refuse or neglect to comply with the terms of the license 
and the lawful orders of the Commission mailed to the record address of 
the licensee or its agent, the Commission will deem it to be the intent 
of the licensee to surrender the license.
    The project has fallen into disrepair and has not operated since 
2006. The project was transferred to the licensee by order dated March 
12, 2015 (2015 Order). The 2015 Order required the licensee to file a 
plan and schedule to restore project operation within 60 days. Since 
that time, the Commission's Division of Dam Safety and Inspections New 
York Regional Office (NYRO) has issued eight letters requiring the 
licensee to file a plan and schedule to make the needed repairs and to 
restore project operation. The licensee has responded over the years 
with at least five plans, but all have been deficient because they lack 
sufficient detail for NYRO's review and approval. The licensee has 
never filed satisfactory plans and specifications to repair the 
project. On August 26, 2021, NYRO inspected the project and found it in 
unsatisfactory condition and largely abandoned. The licensee did not 
attend the inspection and has failed to respond to phone calls and 
emails since. In a final letter to the licensee dated October 18, 2021, 
NYRO again required the licensee to reply to past letters but the 
licensee has stopped responding to the Commission.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.

[[Page 64198]]

    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214, respectively. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Agency Comments: Federal, state, and local agencies are invited 
to file comments on the described proceeding. If an agency does not 
file comments within the time specified for filing comments, it will be 
presumed to have no comments.
    p. Filing and Service of Responsive Documents: Any filing must (1) 
bear in all capital letters the title ``COMMENTS,'' ``PROTEST,'' or 
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001-385.2005. All comments, 
motions to intervene, or protests must set forth their evidentiary 
basis and otherwise comply with the requirements of 18 CFR 4.34(b). All 
comments, motions to intervene, or protests should relate to project 
works which are the subject of the implied surrender. A copy of any 
protest or motion to intervene must be served upon each representative 
of the applicant specified in the particular application. If an 
intervener files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency. A copy of all other filings in reference to 
this application must be accompanied by proof of service on all persons 
listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.

    Dated: November 10, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-25077 Filed 11-16-21; 8:45 am]