Cocheco Falls Associates Notice of Intent To Prepare an Environmental Assessment, 60230 [2021-23736]

Download as PDF 60230 Federal Register / Vol. 86, No. 208 / Monday, November 1, 2021 / Notices to the merits of a contested proceeding, to deliver to the Secretary of the Commission, a copy of the communication, if written, or a summary of the substance of any oral communication. Prohibited communications are included in a public, non-decisional file associated with, but not a part of, the decisional record of the proceeding. Unless the Commission determines that the prohibited communication and any responses thereto should become a part of the decisional record, the prohibited off-the-record communication will not be considered by the Commission in reaching its decision. Parties to a proceeding may seek the opportunity to respond to any facts or contentions made in a prohibited off-the-record communication and may request that the Commission place the prohibited communication and responses thereto in the decisional record. The Commission will grant such a request only when it determines that fairness so requires. Any person identified below as having made a prohibited off-the-record communication shall serve the document on all parties listed on the official service list for the applicable proceeding in accordance with Rule 2010, 18 CFR 385.2010. Exempt off-the-record communications are included in the decisional record of the proceeding, unless the communication was with a cooperating agency as described by 40 CFR 1501.6, made under 18 CFR 385.2201(e)(1)(v). Docket Nos. The following is a list of off-therecord communications recently received by the Secretary of the Commission. The communications listed are grouped by docket numbers in ascending order. These filings are available for electronic review at the Commission in the Public Reference Room or may be viewed on the Commission’s website at https:// www.ferc.gov using the eLibrary link. Enter the docket number, excluding the last three digits, in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202)502–8659. File date Prohibited: 1. P–1494–438 ...................................................................................................... 2. P–1494–438 ...................................................................................................... 3. P–1494–438 ...................................................................................................... Exempt: 1. EL21–6–000, EL21–94–000 ............................................................................. 2. CP17–40–000 ................................................................................................... Presenter or requester 10–18–2021 10–19–2021 10–20–2021 FERC Staff.1 FERC Staff.2 FERC Staff.3 10–18–2021 Massachusetts Office of the Attorney General.4 U.S. Senator Roy Blunt. 10–21–2021 1 Emailed comments dated 10/17/2021 from Richard Spotts. comments dated 10/18/2021 from Ashlyn Roten. comments dated 10/19/2021 from Regina Milione. 4 Rebecca Tepper, Chief and Christina H. Belew Assistant Attorney General. 2 Emailed 3 Emailed Dated: October 26, 2021. Debbie-Anne A. Reese, Deputy Secretary. does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to license the project. The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission’s final licensing decision. The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate. [FR Doc. 2021–23706 Filed 10–29–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 4718–039] lotter on DSK11XQN23PROD with NOTICES1 Cocheco Falls Associates Notice of Intent To Prepare an Environmental Assessment On December 29, 2020, Cocheco Falls Associates filed an application for a subsequent license to continue operating the existing 714-kilowatt Cocheco Falls Dam Project No. 4718 (project). The project is located on the Cocheco River in the city of Dover, Strafford County, New Hampshire. The project does not occupy federal land. In accordance with the Commission’s regulations, on August 12, 2021, Commission staff issued a notice that the project was ready for environmental analysis (REA notice). Based on the information in the record, including comments filed on the REA notice, staff VerDate Sep<11>2014 18:03 Oct 29, 2021 Jkt 256001 Milestone Target date Commission issues EA ...... Comments on EA .............. April 2022. 1 May 2022. Any questions regarding this notice may be directed to Amy Chang at (202) 502–8250 or amy.chang@ferc.gov. 1 The Council on Environmental Quality’s (CEQ) regulations under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 year of the federal action agency’s decision to prepare an EA. This notice establishes the Commission’s intent to prepare an EA for the Cocheco Falls Dam Project. Therefore, in accordance with CEQ’s regulations, the EA must be issued within 1 year of the issuance date of this notice. PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 Dated: October 26, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–23736 Filed 10–29–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14985–000] Cherokee Rivers Company, LLC; Notice of Meeting a. Project Name and Number: Lower Coosawattee Hydroelectric Project P– 14985–000. b. Date and Time of Meeting: November 8, 2021; 4:00 p.m.–5:00 p.m. Eastern Time. c. FERC Contact: Dustin Wilson, 202– 502–6528, dustin.wilson@ferc.gov. d. Purpose of Meeting: To discuss the proposed Lower Coosawattee Hydroelectric Project. e. All local, state, and federal agencies, Indian tribes, and other interested parties are invited to attend. Discussion will be limited to the Lower Coosawattee Hydroelectric Project, P– 14985. Please email the FERC contact E:\FR\FM\01NON1.SGM 01NON1

Agencies

[Federal Register Volume 86, Number 208 (Monday, November 1, 2021)]
[Notices]
[Page 60230]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-23736]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 4718-039]


Cocheco Falls Associates Notice of Intent To Prepare an 
Environmental Assessment

    On December 29, 2020, Cocheco Falls Associates filed an application 
for a subsequent license to continue operating the existing 714-
kilowatt Cocheco Falls Dam Project No. 4718 (project). The project is 
located on the Cocheco River in the city of Dover, Strafford County, 
New Hampshire. The project does not occupy federal land.
    In accordance with the Commission's regulations, on August 12, 
2021, Commission staff issued a notice that the project was ready for 
environmental analysis (REA notice). Based on the information in the 
record, including comments filed on the REA notice, staff does not 
anticipate that licensing the project would constitute a major federal 
action significantly affecting the quality of the human environment. 
Therefore, staff intends to prepare an Environmental Assessment (EA) on 
the application to license the project.
    The EA will be issued and circulated for review by all interested 
parties. All comments filed on the EA will be analyzed by staff and 
considered in the Commission's final licensing decision.
    The application will be processed according to the following 
schedule. Revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Commission issues EA...................  April 2022. \1\
Comments on EA.........................  May 2022.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Amy Chang at 
(202) 502-8250 or [email protected].
---------------------------------------------------------------------------

    \1\ The Council on Environmental Quality's (CEQ) regulations 
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 
year of the federal action agency's decision to prepare an EA. This 
notice establishes the Commission's intent to prepare an EA for the 
Cocheco Falls Dam Project. Therefore, in accordance with CEQ's 
regulations, the EA must be issued within 1 year of the issuance 
date of this notice.

    Dated: October 26, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-23736 Filed 10-29-21; 8:45 am]
BILLING CODE 6717-01-P