Alice Falls Hydro, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 56926-56927 [2021-22185]
Download as PDF
56926
Federal Register / Vol. 86, No. 195 / Wednesday, October 13, 2021 / Notices
Dated: October 5, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–22182 Filed 10–12–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER02–2001–000]
jspears on DSK121TN23PROD with NOTICES1
Southern California Edison Company;
Notice of Filing
Take notice that on September 15,
2021, Southern California Edison
Company (SCE) requested that the
Federal Energy Regulatory Commission
(Commission) review and confirm SCE’s
Electric Quarterly Report submission
practices for transaction information
received from the California
Independent System Operator
Corporation (CAISO). In particular,
given recent changes to the CAISO
market settlement timeline, SCE
requests that the Commission approve
SCE’s longstanding practices of (1)
providing CAISO transaction data for a
given quarter by the filing deadline for
the following quarter; and (2) providing
CAISO transaction data only once using
final settlement data, as opposed to
filing both initial and final settlement
data.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant. On
or before the comment date, it is not
necessary to serve motions to intervene
or protests on persons other than the
Applicant.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
VerDate Sep<11>2014
18:01 Oct 12, 2021
Jkt 256001
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically may mail similar
pleadings to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand
delivered submissions in docketed
proceedings should be delivered to
Health and Human Services, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Comment Date: 5:00 p.m. Eastern
Time on November 5, 2021.
Dated: October 6, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–22229 Filed 10–12–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 5867–054]
Alice Falls Hydro, LLC; Notice of
Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests and
Establishing Procedural Schedule for
Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 5867–054.
c. Date Filed: September 29, 2021.
d. Applicant: Alice Falls Hydro, LLC.
e. Name of Project: Alice Falls
Hydroelectric Project (Alice Falls
Project).
f. Location: On the Ausable River, in
the Town of Chesterfield, Clinton and
Essex Counties, New York. The project
does not occupy federal land.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Jody Smet, Vice
President, Regulatory Affairs, Eagle
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
Creek Renewable Energy, LLC, Two
Bethesda Metro Center, Suite 1330,
Bethesda, MD 20814; (804) 739–0654;
email—Jody.Smet@eaglecreekre.com.
i. FERC Contact: John Stokely at (202)
502–8534; or email at john.stokely@
ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: November 28, 2021.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. All filings must clearly identify
the project name and docket number on
the first page: Alice Falls Project
(P–5867–054).
m. The application is not ready for
environmental analysis at this time.
n. The Alice Falls Project consists of
the following existing facilities: (1) A
stone masonry dam, 88 feet long and 63
feet high; (2) a 110-foot-long section of
E:\FR\FM\13OCN1.SGM
13OCN1
jspears on DSK121TN23PROD with NOTICES1
Federal Register / Vol. 86, No. 195 / Wednesday, October 13, 2021 / Notices
rock ledge adjacent to the dam with 2.5foot-high pipe-supported flashboards;
(3) a reservoir with a surface area of 4.8
acres with a normal water surface
elevation of 350 feet mean sea level; (4)
an intake structure; (5) a divided, 45foot-long, reinforced concrete penstock;
(6) a powerhouse containing two
turbine-generator units of 1.5 megawatts
and 0.6 megawatts; (7) a substation; (8)
a 1,500-foot-long, 46.0-kilovolt buried
transmission line; and (9) appurtenant
facilities.
The Alice Falls Project is operated in
a run-of-river mode with an average
annual generation of 4,021 megawatthours.
o. A copy of the application may be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. At this time, the Commission
has suspended access to the
Commission’s Public Reference Room,
due to the proclamation declaring a
National Emergency concerning the
Novel Coronavirus Disease (COVID–19),
issued by the President on March 13,
2020. For assistance, contact FERC
Online Support.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Issue Deficiency Letter (if necessary)
November 2021
Request Additional Information
November 2021
Issue Acceptance Letter February 2022
Issue Scoping Document 1 for
comments March 2022
Request Additional Information (if
necessary) May 2022
Issue Scoping Document 2 June 2022
Issue Notice of Ready for Environmental
Analysis June 2022
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: October 5, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–22185 Filed 10–12–21; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
18:01 Oct 12, 2021
Jkt 256001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC22–2–000.
Applicants: Stanly Solar, LLC, PGR
2021 Lessee 1, LLC.
Description: Joint Application for
Authorization Under Section 203 of the
Federal Power Act of Stanly Solar, LLC,
et al.
Filed Date: 10/1/21.
Accession Number: 20211001–5377.
Comment Date: 5 p.m. ET 10/22/21.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER21–1280–003.
Applicants: Southern California
Edison Company.
Description: Compliance filing: SCE
Refile Compliance Filing—Morongo
WOD Formula Rate Protocols to be
effective 5/5/2021.
Filed Date: 10/6/21.
Accession Number: 20211006–5076.
Comment Date: 5 p.m. ET 10/20/21.
Docket Numbers: ER21–2819–001.
Applicants: South Field Energy LLC.
Description: Tariff Amendment:
Supplemental Filing of South Field
Energy LLC and Request for Waiver to
be effective 10/1/2021.
Filed Date: 10/6/21.
Accession Number: 20211006–5113.
Comment Date: 5 p.m. ET 10/27/21.
Docket Numbers: ER21–2944–000.
Applicants: Pacific Gas and Electric
Company.
Description: Notice of Termination of
Service Agreement for Gilroy Energy
Center, LLC, Service Agreement (No. 25)
of Pacific Gas and Electric Company.
Filed Date: 9/24/21.
Accession Number: 20210924–5182.
Comment Date: 5 p.m. ET 10/15/21.
Docket Numbers: ER22–48–000.
Applicants: Gridflex Generation, LLC.
Description: Baseline eTariff Filing:
Application for Market-Based Rate to be
effective 12/6/2021.
Filed Date: 10/5/21.
Accession Number: 20211005–5107.
Comment Date: 5 p.m. ET 10/26/21.
Docket Numbers: ER22–49–000.
Applicants: Tri-State Generation and
Transmission Association, Inc.
Description: § 205(d) Rate Filing:
Initial Filing of Rate Schedule No. 335
to be effective 12/6/2021.
Filed Date: 10/6/21.
Accession Number: 20211006–5018.
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
56927
Comment Date: 5 p.m. ET 10/27/21.
Docket Numbers: ER22–50–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Annual Calculation of
the Cost of New Entry value (‘‘Cone’’)
for each Local Resource Zone (‘‘LRZ’’)
in the MISO Region of Midcontinent
Independent System Operator, Inc.
Filed Date: 10/4/21.
Accession Number: 20211004–5267.
Comment Date: 5 p.m. ET 10/25/21.
Docket Numbers: ER22–51–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original NSA, SA No. 6191; Queue No.
P11 to be effective 9/9/2021.
Filed Date: 10/6/21.
Accession Number: 20211006–5086.
Comment Date: 5 p.m. ET 10/27/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: October 6, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–22219 Filed 10–12–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 4639–033]
Ampersand Christine Falls Hydro, LLC;
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
and Establishing Procedural Schedule
for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
E:\FR\FM\13OCN1.SGM
13OCN1
Agencies
[Federal Register Volume 86, Number 195 (Wednesday, October 13, 2021)]
[Notices]
[Pages 56926-56927]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-22185]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 5867-054]
Alice Falls Hydro, LLC; Notice of Application Tendered for Filing
With the Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 5867-054.
c. Date Filed: September 29, 2021.
d. Applicant: Alice Falls Hydro, LLC.
e. Name of Project: Alice Falls Hydroelectric Project (Alice Falls
Project).
f. Location: On the Ausable River, in the Town of Chesterfield,
Clinton and Essex Counties, New York. The project does not occupy
federal land.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Jody Smet, Vice President, Regulatory
Affairs, Eagle Creek Renewable Energy, LLC, Two Bethesda Metro Center,
Suite 1330, Bethesda, MD 20814; (804) 739-0654; email_
[email protected]
i. FERC Contact: John Stokely at (202) 502-8534; or email at
[email protected].
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: November 28, 2021.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at [email protected], (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, you may submit a paper
copy. Submissions sent via the U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent
via any other carrier must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. All filings must clearly identify the
project name and docket number on the first page: Alice Falls Project
(P-5867-054).
m. The application is not ready for environmental analysis at this
time.
n. The Alice Falls Project consists of the following existing
facilities: (1) A stone masonry dam, 88 feet long and 63 feet high; (2)
a 110-foot-long section of
[[Page 56927]]
rock ledge adjacent to the dam with 2.5-foot-high pipe-supported
flashboards; (3) a reservoir with a surface area of 4.8 acres with a
normal water surface elevation of 350 feet mean sea level; (4) an
intake structure; (5) a divided, 45-foot-long, reinforced concrete
penstock; (6) a powerhouse containing two turbine-generator units of
1.5 megawatts and 0.6 megawatts; (7) a substation; (8) a 1,500-foot-
long, 46.0-kilovolt buried transmission line; and (9) appurtenant
facilities.
The Alice Falls Project is operated in a run-of-river mode with an
average annual generation of 4,021 megawatt-hours.
o. A copy of the application may be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. At this time, the Commission has
suspended access to the Commission's Public Reference Room, due to the
proclamation declaring a National Emergency concerning the Novel
Coronavirus Disease (COVID-19), issued by the President on March 13,
2020. For assistance, contact FERC Online Support.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
Issue Deficiency Letter (if necessary) November 2021
Request Additional Information November 2021
Issue Acceptance Letter February 2022
Issue Scoping Document 1 for comments March 2022
Request Additional Information (if necessary) May 2022
Issue Scoping Document 2 June 2022
Issue Notice of Ready for Environmental Analysis June 2022
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: October 5, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-22185 Filed 10-12-21; 8:45 am]
BILLING CODE 6717-01-P