Alliance Pipeline, L.P. ; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Three Rivers Interconnection Project, 53044-53046 [2021-20771]
Download as PDF
53044
Federal Register / Vol. 86, No. 183 / Friday, September 24, 2021 / Notices
website at: www.whitehouse.gov/
PCAST.
Public Participation: The meeting is
open to the public. It is the policy of the
PCAST to accept written public
comments no longer than 10 pages and
to accommodate oral public comments,
whenever possible. The PCAST expects
that public statements presented at its
meetings will not be repetitive of
previously submitted oral or written
statements.
The public comment period for this
meeting will take place on Wednesday,
September 29, 2021, at a time specified
in the meeting agenda. This public
comment period is designed only for
substantive commentary on PCAST’s
work, not for business marketing
purposes.
This meeting is being published less
than 15 days prior to the scheduled
meeting to allow the PCAST to convene
swiftly in light of the on-going public
health crisis and associated supply
chain shortages.
Oral Comments: To be considered for
the public speaker list at the meeting,
interested parties should register to
speak at PCAST@ostp.eop.gov, no later
than 5 p.m. Eastern Time on Monday,
September 27, 2021. To accommodate as
many speakers as possible, the time for
public comments will be limited to two
(2) minutes per person, with a total
public comment period of up to 10
minutes. If more speakers register than
there is space available on the agenda,
PCAST will select speakers on a firstcome, first-served basis from those who
registered. Those not able to present oral
comments may file written comments
with the council.
Written Comments: Although written
comments are accepted continuously,
written comments should be submitted
to PCAST@ostp.eop.gov no later than 5
p.m. Eastern Time on Monday,
September 27, 2021, so that the
comments may be made available to the
PCAST members for their consideration
prior to this meeting.
PCAST operates under the provisions
of FACA, all public comments and/or
presentations will be treated as public
documents and will be made available
for public inspection, including being
posted on the PCAST website
www.whitehouse.gov/PCAST.
Minutes: Minutes will be available
within 45 days by emailing PCAST@
ostp.eop.gov.
Signing Authority
This document of the Department of
Energy was signed on September 22,
2021, by Miles Fernandez, Acting
Committee Management Officer, Office
of Management, pursuant to delegated
VerDate Sep<11>2014
16:50 Sep 23, 2021
Jkt 253001
authority from the Secretary of Energy.
That document with the original
signature and date is maintained by
DOE. For administrative purposes only,
and in compliance with requirements of
the Office of the Federal Register, the
undersigned DOE Federal Register
Liaison Officer has been authorized to
sign and submit the document in
electronic format for publication, as an
official document of the Department of
Energy. This administrative process in
no way alters the legal effect of this
document upon publication in the
Federal Register.
Signed in Washington, DC, on September
22, 2021.
Treena V. Garrett,
Federal Register Liaison Officer, U.S.
Department of Energy.
[FR Doc. 2021–20960 Filed 9–23–21; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ID–9265–000]
Broder, Joshua B.; Notice of Filing
Take notice that on September 17,
2021, Joshua B. Broder submitted for
filing, application for authority to hold
interlocking positions, pursuant to
section 305(b) of the Federal Power Act,
16 U.S.C. 825d (b) and Part 45.8 of the
Federal Energy Regulatory
Commission’s (Commission) Rules of
Practice and Procedure, 18 CFR part
45.8.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically may mail similar
pleadings to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand
delivered submissions in docketed
proceedings should be delivered to
Health and Human Services, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Comment Date: 5:00 p.m. Eastern
Time on October 12, 2021.
Dated: September 20, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–20775 Filed 9–23–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–113–000]
Alliance Pipeline, L.P. ; Notice of
Scoping Period Requesting Comments
on Environmental Issues for the
Proposed Three Rivers
Interconnection Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document, that will
discuss the environmental impacts of
the Three Rivers Interconnection Project
involving construction and operation of
facilities by Alliance Pipeline, L.P.
(Alliance) in Grundy County, Illinois.
The Commission will use this
environmental document in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
project. As part of the National
E:\FR\FM\24SEN1.SGM
24SEN1
Federal Register / Vol. 86, No. 183 / Friday, September 24, 2021 / Notices
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. This
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and Environmental Document section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on
October 19, 2021. Comments should be
submitted in written form. Further
details on how to submit comments are
provided in the Public Participation
section of this notice.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
Your input will help the Commission
staff determine what issues they need to
evaluate in the environmental
document. Commission staff will
consider all comments during the
preparation of the environmental
document.
If you submitted comments on this
project to the Commission before the
opening of this docket on April 1, 2021,
you will need to file those comments in
Docket No. CP21–113–000 to ensure
they are considered as part of this
proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, the Natural Gas Act conveys
the right of eminent domain to the
VerDate Sep<11>2014
16:50 Sep 23, 2021
Jkt 253001
company. Therefore, if you and the
company do not reach an easement
agreement, the pipeline company could
initiate condemnation proceedings in
court. In such instances, compensation
would be determined by a judge in
accordance with state law. The
Commission does not subsequently
grant, exercise, or oversee the exercise
of that eminent domain authority. The
courts have exclusive authority to
handle eminent domain cases; the
Commission has no jurisdiction over
these matters.
Alliance provided landowners with a
fact sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
which addresses typically asked
questions, including the use of eminent
domain and how to participate in the
Commission’s proceedings. This fact
sheet along with other landowner topics
of interest are available for viewing on
the FERC website (www.ferc.gov) under
the Natural Gas Questions or
Landowner Topics link.
Public Participation
There are three methods you can use
to submit your comments to the
Commission. Please carefully follow
these instructions so that your
comments are properly recorded. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP21–113–000)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
53045
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Additionally, the Commission offers a
free service called eSubscription which
makes it easy to stay informed of all
issuances and submittals regarding the
dockets/projects to which you
subscribe. These instant email
notifications are the fastest way to
receive notification and provide a link
to the document files which can reduce
the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
Summary of the Proposed Project
Alliance proposes to construct and
operate about 2.9 miles of 20-inchdiameter natural gas transmission
pipeline and associated facilities. This
pipeline would connect Alliance’s
existing interstate natural gas
transmission system with the CPV Three
Rivers Energy Center; and would be
capable of transporting up to 0.21
billion cubic feet per day. According to
Alliance, the project is necessary to
provide the CPV Three Rivers Energy
Center with access to an additional
natural gas supply source. The general
location of the project is shown in
appendix 1.1
Land Requirements for Construction
Constructing the project would
require the temporary use of about 42.8
acres of land. Following construction,
Alliance would restore about 25.1 acres
of land and would permanently
maintain about 17.7 acres of land to
operate the project.
NEPA Process and the Environmental
Document
Any environmental document issued
by the Commission will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under the relevant
general resource areas:
• Geology and soils;
• water resources and wetlands;
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’. For instructions on
connecting to eLibrary, refer to the last page of this
notice. At this time, the Commission has suspended
access to the Commission’s Public Reference Room
due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus
Disease (COVID–19), issued by the President on
March 13, 2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll free, (886)
208–3676 or TTY (202) 502–8659.
E:\FR\FM\24SEN1.SGM
24SEN1
53046
Federal Register / Vol. 86, No. 183 / Friday, September 24, 2021 / Notices
• vegetation and wildlife;
• protected species;
• cultural resources;
• land use;
• air quality and noise; and
• reliability and safety.
Commission staff will also evaluate
reasonable alternatives to the proposed
project or portions of the project and
make recommendations on how to
lessen or avoid impacts on the various
resource areas. Your comments will
help Commission staff identify and
focus on the issues that might have an
effect on the human environment and
potentially eliminate others from further
study and discussion in the
environmental document.
Following this scoping period,
Commission staff will determine
whether to prepare an Environmental
Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the
EIS will present Commission staff’s
independent analysis of the issues. If
Commission staff prepares an EA, a
Notice of Schedule for the Preparation
of an Environmental Assessment will be
issued. The EA may be issued for an
allotted public comment period. The
Commission would consider timely
comments on the EA before making its
decision regarding the proposed project.
If Commission staff prepares an EIS, a
Notice of Intent to Prepare an EIS/
Notice of Schedule will be issued,
which will open up an additional
comment period. Staff will then prepare
a draft EIS which will be issued for
public comment. Commission staff will
consider all timely comments received
during the comment period on the draft
EIS and revise the document, as
necessary, before issuing a final EIS.
Any EA or draft and final EIS will be
available in electronic format in the
public record through eLibrary 2 and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the
environmental document is issued.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this project
to formally cooperate in the preparation
of the environmental document.3
Agencies that would like to request
cooperating agency status should follow
2 For
instructions on connecting to eLibrary, refer
to the last page of this notice.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Section 1501.8.
VerDate Sep<11>2014
16:50 Sep 23, 2021
Jkt 253001
the instructions for filing comments
provided under the Public Participation
section of this notice.
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
potential effects on historic properties.4
The environmental document for this
project will document findings on the
impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project and includes a
mailing address with their comments.
Commission staff will update the
environmental mailing list as the
analysis proceeds to ensure that
Commission notices related to this
environmental review are sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
If you need to make changes to your
name/address, or if you would like to
remove your name from the mailing list,
please complete one of the following
steps:
(1) Send an email to
GasProjectAddressChange@ferc.gov
stating your request. You must include
the docket number CP21–113–000 in
your request. If you are requesting a
change to your address, please be sure
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
to include your name and the correct
address. If you are requesting to delete
your address from the mailing list,
please include your name and address
as it appeared on this notice. This email
address is unable to accept comments.
OR
(2) Return the attached ‘‘Mailing List
Update Form’’ (appendix 2).
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or (866)
208–3676, or for TTY, contact (202)
502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Dated: September 20, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–20771 Filed 9–23–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14775–004]
Marine Renewable Energy
Collaborative of New England; Notice
of Intent To File License Application,
Filing of Draft Application, Request for
Waivers of Integrated Licensing
Process Regulations Necessary for
Expedited Processing of a
Hydrokinetic Pilot Project License
Application, and Soliciting Comments
a. Type of Filing: Notice of Intent to
File a License Application for an
Original License for a Hydrokinetic Pilot
Project.
b. Project No.: 14775–004.
c. Date Filed: September 7, 2021.
d. Submitted By: Marine Renewable
Energy Collaborative of New England
(MRECo).
e. Name of Project: Bourne Tidal Test
Site Project.
E:\FR\FM\24SEN1.SGM
24SEN1
Agencies
[Federal Register Volume 86, Number 183 (Friday, September 24, 2021)]
[Notices]
[Pages 53044-53046]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-20771]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP21-113-000]
Alliance Pipeline, L.P. ; Notice of Scoping Period Requesting
Comments on Environmental Issues for the Proposed Three Rivers
Interconnection Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document, that will discuss
the environmental impacts of the Three Rivers Interconnection Project
involving construction and operation of facilities by Alliance
Pipeline, L.P. (Alliance) in Grundy County, Illinois. The Commission
will use this environmental document in its decision-making process to
determine whether the project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National
[[Page 53045]]
Environmental Policy Act (NEPA) review process, the Commission takes
into account concerns the public may have about proposals and the
environmental impacts that could result from its action whenever it
considers the issuance of a Certificate of Public Convenience and
Necessity. This gathering of public input is referred to as
``scoping.'' The main goal of the scoping process is to focus the
analysis in the environmental document on the important environmental
issues. Additional information about the Commission's NEPA process is
described below in the NEPA Process and Environmental Document section
of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on October 19, 2021. Comments should be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues they need to evaluate in the environmental document. Commission
staff will consider all comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on April 1, 2021, you will need to file
those comments in Docket No. CP21-113-000 to ensure they are considered
as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, the Natural Gas Act conveys the right of eminent
domain to the company. Therefore, if you and the company do not reach
an easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law. The Commission does
not subsequently grant, exercise, or oversee the exercise of that
eminent domain authority. The courts have exclusive authority to handle
eminent domain cases; the Commission has no jurisdiction over these
matters.
Alliance provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' which addresses typically asked questions, including
the use of eminent domain and how to participate in the Commission's
proceedings. This fact sheet along with other landowner topics of
interest are available for viewing on the FERC website (www.ferc.gov)
under the Natural Gas Questions or Landowner Topics link.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP21-
113-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
Summary of the Proposed Project
Alliance proposes to construct and operate about 2.9 miles of 20-
inch-diameter natural gas transmission pipeline and associated
facilities. This pipeline would connect Alliance's existing interstate
natural gas transmission system with the CPV Three Rivers Energy
Center; and would be capable of transporting up to 0.21 billion cubic
feet per day. According to Alliance, the project is necessary to
provide the CPV Three Rivers Energy Center with access to an additional
natural gas supply source. The general location of the project is shown
in appendix 1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary''. For instructions on
connecting to eLibrary, refer to the last page of this notice. At
this time, the Commission has suspended access to the Commission's
Public Reference Room due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus Disease (COVID-19),
issued by the President on March 13, 2020. For assistance, contact
FERC at [email protected] or call toll free, (886) 208-3676
or TTY (202) 502-8659.
---------------------------------------------------------------------------
Land Requirements for Construction
Constructing the project would require the temporary use of about
42.8 acres of land. Following construction, Alliance would restore
about 25.1 acres of land and would permanently maintain about 17.7
acres of land to operate the project.
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the construction and operation
of the proposed project under the relevant general resource areas:
Geology and soils;
water resources and wetlands;
[[Page 53046]]
vegetation and wildlife;
protected species;
cultural resources;
land use;
air quality and noise; and
reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Following this scoping period, Commission staff will determine
whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission
staff's independent analysis of the issues. If Commission staff
prepares an EA, a Notice of Schedule for the Preparation of an
Environmental Assessment will be issued. The EA may be issued for an
allotted public comment period. The Commission would consider timely
comments on the EA before making its decision regarding the proposed
project. If Commission staff prepares an EIS, a Notice of Intent to
Prepare an EIS/Notice of Schedule will be issued, which will open up an
additional comment period. Staff will then prepare a draft EIS which
will be issued for public comment. Commission staff will consider all
timely comments received during the comment period on the draft EIS and
revise the document, as necessary, before issuing a final EIS. Any EA
or draft and final EIS will be available in electronic format in the
public record through eLibrary \2\ and the Commission's natural gas
environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you
will receive instant email notification when the environmental document
is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Section 1501.8.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The environmental document for this
project will document findings on the impacts on historic properties
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to [email protected] stating your
request. You must include the docket number CP21-113-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments.
OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field. Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at [email protected] or (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: September 20, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021-20771 Filed 9-23-21; 8:45 am]