Jason and Carol Victoria Presley; Notice of Authorization for Continued Project Operation, 52142 [2021-20275]
Download as PDF
52142
Federal Register / Vol. 86, No. 179 / Monday, September 20, 2021 / Notices
switchyard; (6) a 1,150-foot-long 4.16 kV
transmission line connecting the lower
powerhouse to the switchyard; and (7)
appurtenant facilities.
The Pyrites Project is operated in a
run-of-river mode with an average
annual generation of 27,865 megawatthours.
o. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–6115).
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19) issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Milestone
Issue Deficiency Letter (if
necessary).
Request Additional Information.
Issue Acceptance Letter ..
Issue Scoping Document
1 for comments.
Issue Scoping Document
2.
Issue Notice of Ready for
Environmental Analysis.
Target date
October 2021.
October 2021.
January 2022.
February 2022.
May 2022.
May 2022.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20272 Filed 9–17–21; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
16:49 Sep 17, 2021
Jkt 253001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3102–000]
Jason and Carol Victoria Presley;
Notice of Authorization for Continued
Project Operation
On September 12, 2017, Jason and
Carol Victoria Presley, licensees for the
High Shoals Hydroelectric Project No.
3102, filed a Notice of Intent to File
Subsequent License Application for the
project, and on November 1, 2017, they
filed a Preliminary Application
Document. On August 27, 2019, they
filed a Notice of Intent to Surrender the
project followed by an application for
Surrender of License on November 7,
2019. The High Shoals Hydroelectric
Project is located on the Apalachee
River in Walton, Morgan, and Oconee
Counties, Georgia.
The license for Project No. 3102 was
issued for a period ending August 31,
2021. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee(s)
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 3102
is issued to Jason and Carol Victoria
Presley for a period effective September
1, 2021 through August 31, 2022 or until
the issuance of a new license for the
project or other disposition under the
FPA, whichever comes first. If issuance
of a new license (or other disposition)
does not take place on or before August
31, 2022, notice is hereby given that,
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
pursuant to 18 CFR 16.18(c), an annual
license under section 15(a)(1) of the
FPA is renewed automatically without
further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Jason and Carol Victoria Presley are
authorized to continue operation of the
High Shoals Hydroelectric Project, until
such time as the Commission takes final
action on the application for Surrender
of License.
Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20275 Filed 9–17–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3509–042]
Little Falls Hydroelectric Associates,
LP; Notice of Application Tendered for
Filing With The Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 3509–042.
c. Date Filed: August 31, 2021.
d. Applicant: Little Falls
Hydroelectric Associates, LP.
e. Name of Project: Little Falls
Hydroelectric Project (Little Falls
Project).
f. Location: The existing project is
located on the Mohawk River, in the
City of Little Falls, Herkimer County,
New York. The project does not occupy
federal land.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825 (r).
h. Applicant Contact: David H. Fox,
Director, Licensing and Compliance,
Little Falls Hydroelectric Associates, LP,
Eagle Creek Renewable Energy, 7315
Wisconsin Avenue, Suite 1100W,
Bethesda, MD 20814, email—david.fox@
eaglecreekre.com; Jody J. Smet, Vice
President, Regulatory Affairs, Little
Falls Hydroelectric Associates, LP, Eagle
Creek Renewable Energy, 7315
Wisconsin Avenue, Suite 1100W,
Bethesda, MD 20814, email—
jody.smet@eaglecreekre.com.
E:\FR\FM\20SEN1.SGM
20SEN1
Agencies
[Federal Register Volume 86, Number 179 (Monday, September 20, 2021)]
[Notices]
[Page 52142]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-20275]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3102-000]
Jason and Carol Victoria Presley; Notice of Authorization for
Continued Project Operation
On September 12, 2017, Jason and Carol Victoria Presley, licensees
for the High Shoals Hydroelectric Project No. 3102, filed a Notice of
Intent to File Subsequent License Application for the project, and on
November 1, 2017, they filed a Preliminary Application Document. On
August 27, 2019, they filed a Notice of Intent to Surrender the project
followed by an application for Surrender of License on November 7,
2019. The High Shoals Hydroelectric Project is located on the Apalachee
River in Walton, Morgan, and Oconee Counties, Georgia.
The license for Project No. 3102 was issued for a period ending
August 31, 2021. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee(s) under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 3102 is issued to
Jason and Carol Victoria Presley for a period effective September 1,
2021 through August 31, 2022 or until the issuance of a new license for
the project or other disposition under the FPA, whichever comes first.
If issuance of a new license (or other disposition) does not take place
on or before August 31, 2022, notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that Jason and Carol Victoria Presley are authorized to
continue operation of the High Shoals Hydroelectric Project, until such
time as the Commission takes final action on the application for
Surrender of License.
Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-20275 Filed 9-17-21; 8:45 am]