Download as PDF 52142 Federal Register / Vol. 86, No. 179 / Monday, September 20, 2021 / Notices switchyard; (6) a 1,150-foot-long 4.16 kV transmission line connecting the lower powerhouse to the switchyard; and (7) appurtenant facilities. The Pyrites Project is operated in a run-of-river mode with an average annual generation of 27,865 megawatthours. o. In addition to publishing the full text of this notice in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this notice, as well as other documents in the proceeding (e.g., license application) via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document (P–6115). At this time, the Commission has suspended access to the Commission’s Public Reference Room due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19) issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or (202) 502– 8659 (TTY). You may also register online at https://ferconline.ferc.gov/ FERCOnline.aspx to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Milestone Issue Deficiency Letter (if necessary). Request Additional Information. Issue Acceptance Letter .. Issue Scoping Document 1 for comments. Issue Scoping Document 2. Issue Notice of Ready for Environmental Analysis. Target date October 2021. October 2021. January 2022. February 2022. May 2022. May 2022. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: September 14, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–20272 Filed 9–17–21; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 16:49 Sep 17, 2021 Jkt 253001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3102–000] Jason and Carol Victoria Presley; Notice of Authorization for Continued Project Operation On September 12, 2017, Jason and Carol Victoria Presley, licensees for the High Shoals Hydroelectric Project No. 3102, filed a Notice of Intent to File Subsequent License Application for the project, and on November 1, 2017, they filed a Preliminary Application Document. On August 27, 2019, they filed a Notice of Intent to Surrender the project followed by an application for Surrender of License on November 7, 2019. The High Shoals Hydroelectric Project is located on the Apalachee River in Walton, Morgan, and Oconee Counties, Georgia. The license for Project No. 3102 was issued for a period ending August 31, 2021. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 3102 is issued to Jason and Carol Victoria Presley for a period effective September 1, 2021 through August 31, 2022 or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before August 31, 2022, notice is hereby given that, PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that Jason and Carol Victoria Presley are authorized to continue operation of the High Shoals Hydroelectric Project, until such time as the Commission takes final action on the application for Surrender of License. Dated: September 14, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–20275 Filed 9–17–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3509–042] Little Falls Hydroelectric Associates, LP; Notice of Application Tendered for Filing With The Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Major License. b. Project No.: 3509–042. c. Date Filed: August 31, 2021. d. Applicant: Little Falls Hydroelectric Associates, LP. e. Name of Project: Little Falls Hydroelectric Project (Little Falls Project). f. Location: The existing project is located on the Mohawk River, in the City of Little Falls, Herkimer County, New York. The project does not occupy federal land. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825 (r). h. Applicant Contact: David H. Fox, Director, Licensing and Compliance, Little Falls Hydroelectric Associates, LP, Eagle Creek Renewable Energy, 7315 Wisconsin Avenue, Suite 1100W, Bethesda, MD 20814, email—david.fox@ eaglecreekre.com; Jody J. Smet, Vice President, Regulatory Affairs, Little Falls Hydroelectric Associates, LP, Eagle Creek Renewable Energy, 7315 Wisconsin Avenue, Suite 1100W, Bethesda, MD 20814, email— jody.smet@eaglecreekre.com. E:\FR\FM\20SEN1.SGM 20SEN1

Agencies

[Federal Register Volume 86, Number 179 (Monday, September 20, 2021)]
[Notices]
[Page 52142]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-20275]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3102-000]


Jason and Carol Victoria Presley; Notice of Authorization for 
Continued Project Operation

    On September 12, 2017, Jason and Carol Victoria Presley, licensees 
for the High Shoals Hydroelectric Project No. 3102, filed a Notice of 
Intent to File Subsequent License Application for the project, and on 
November 1, 2017, they filed a Preliminary Application Document. On 
August 27, 2019, they filed a Notice of Intent to Surrender the project 
followed by an application for Surrender of License on November 7, 
2019. The High Shoals Hydroelectric Project is located on the Apalachee 
River in Walton, Morgan, and Oconee Counties, Georgia.
    The license for Project No. 3102 was issued for a period ending 
August 31, 2021. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year-to-year an annual license to the then licensee(s) under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA. If the project's prior 
license waived the applicability of section 15 of the FPA, then, based 
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), 
and as set forth at 18 CFR 16.21(a), if the licensee of such project 
has filed an application for a subsequent license, the licensee may 
continue to operate the project in accordance with the terms and 
conditions of the license after the minor or minor part license 
expires, until the Commission acts on its application. If the licensee 
of such a project has not filed an application for a subsequent 
license, then it may be required, pursuant to 18 CFR 16.21(b), to 
continue project operations until the Commission issues someone else a 
license for the project or otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 3102 is issued to 
Jason and Carol Victoria Presley for a period effective September 1, 
2021 through August 31, 2022 or until the issuance of a new license for 
the project or other disposition under the FPA, whichever comes first. 
If issuance of a new license (or other disposition) does not take place 
on or before August 31, 2022, notice is hereby given that, pursuant to 
18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is 
renewed automatically without further order or notice by the 
Commission, unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that Jason and Carol Victoria Presley are authorized to 
continue operation of the High Shoals Hydroelectric Project, until such 
time as the Commission takes final action on the application for 
Surrender of License.

    Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.