Little Falls Hydroelectric Associates, LP; Notice of Application Tendered for Filing With The Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 52142-52143 [2021-20271]
Download as PDF
52142
Federal Register / Vol. 86, No. 179 / Monday, September 20, 2021 / Notices
switchyard; (6) a 1,150-foot-long 4.16 kV
transmission line connecting the lower
powerhouse to the switchyard; and (7)
appurtenant facilities.
The Pyrites Project is operated in a
run-of-river mode with an average
annual generation of 27,865 megawatthours.
o. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–6115).
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19) issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Milestone
Issue Deficiency Letter (if
necessary).
Request Additional Information.
Issue Acceptance Letter ..
Issue Scoping Document
1 for comments.
Issue Scoping Document
2.
Issue Notice of Ready for
Environmental Analysis.
Target date
October 2021.
October 2021.
January 2022.
February 2022.
May 2022.
May 2022.
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20272 Filed 9–17–21; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
16:49 Sep 17, 2021
Jkt 253001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3102–000]
Jason and Carol Victoria Presley;
Notice of Authorization for Continued
Project Operation
On September 12, 2017, Jason and
Carol Victoria Presley, licensees for the
High Shoals Hydroelectric Project No.
3102, filed a Notice of Intent to File
Subsequent License Application for the
project, and on November 1, 2017, they
filed a Preliminary Application
Document. On August 27, 2019, they
filed a Notice of Intent to Surrender the
project followed by an application for
Surrender of License on November 7,
2019. The High Shoals Hydroelectric
Project is located on the Apalachee
River in Walton, Morgan, and Oconee
Counties, Georgia.
The license for Project No. 3102 was
issued for a period ending August 31,
2021. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee(s)
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 3102
is issued to Jason and Carol Victoria
Presley for a period effective September
1, 2021 through August 31, 2022 or until
the issuance of a new license for the
project or other disposition under the
FPA, whichever comes first. If issuance
of a new license (or other disposition)
does not take place on or before August
31, 2022, notice is hereby given that,
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
pursuant to 18 CFR 16.18(c), an annual
license under section 15(a)(1) of the
FPA is renewed automatically without
further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Jason and Carol Victoria Presley are
authorized to continue operation of the
High Shoals Hydroelectric Project, until
such time as the Commission takes final
action on the application for Surrender
of License.
Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20275 Filed 9–17–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3509–042]
Little Falls Hydroelectric Associates,
LP; Notice of Application Tendered for
Filing With The Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 3509–042.
c. Date Filed: August 31, 2021.
d. Applicant: Little Falls
Hydroelectric Associates, LP.
e. Name of Project: Little Falls
Hydroelectric Project (Little Falls
Project).
f. Location: The existing project is
located on the Mohawk River, in the
City of Little Falls, Herkimer County,
New York. The project does not occupy
federal land.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825 (r).
h. Applicant Contact: David H. Fox,
Director, Licensing and Compliance,
Little Falls Hydroelectric Associates, LP,
Eagle Creek Renewable Energy, 7315
Wisconsin Avenue, Suite 1100W,
Bethesda, MD 20814, email—david.fox@
eaglecreekre.com; Jody J. Smet, Vice
President, Regulatory Affairs, Little
Falls Hydroelectric Associates, LP, Eagle
Creek Renewable Energy, 7315
Wisconsin Avenue, Suite 1100W,
Bethesda, MD 20814, email—
jody.smet@eaglecreekre.com.
E:\FR\FM\20SEN1.SGM
20SEN1
Federal Register / Vol. 86, No. 179 / Monday, September 20, 2021 / Notices
i. FERC Contact: Monir Chowdhury at
(202) 502–6736 or email at
monir.chowdhury@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The Little Falls
Project consists of: (1) Two state-owned
dams (i.e., North State Dam and South
State Dam) joined by an island, and
equipped with 1-foot-high flashboards
and flow control gates, with a total
length of 594 feet and a height of about
6.25 feet; (2) a reservoir with a storage
capacity of 800 acre-feet at a normal
surface elevation of 363.8 feet; 1 (3) a 45foot-wide, 300-foot-long navigation lock
(Lock 17); (4) a 55-foot-wide, 73-footlong concrete intake structure with two
roller head gates to control flow through
the intake; (5) two 14-foot-diameter, 90foot-long steel penstocks; (6) a 65-footwide by 99-foot-long concrete
powerhouse containing two-turbinegenerator units each with a capacity of
6.8 megawatts; (7) two sets of 4.16kilovolt (kV), 60-foot-long generator
leads that run from the powerhouse to
a switchyard containing a 4.16/46-kV
transformer; (8) a 46-kV, 50-foot-long
transmission line from the switchyard to
a nearby interconnection point that
connects the project with the National
Grid; and (9) appurtenant facilities.
There are several structures inside the
project boundary that are not considered
part of the project: A flood gate structure
owned by the New York State Canal
Corporation to protect the canal during
periods of high headwater; the Middle
Dam, with sixty percent of the dam
currently breached, located in the
bypassed reach of the Mohawk River,
and built as part of a hydropower plant
that was decommissioned in 1962; and
the Gilbert Dam located also in the
bypassed reach approximately 700 feet
upstream of the powerhouse to measure
flow through the Mohawk River and to
assure minimum flow conditions are
met in the river.
l. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested individuals an opportunity to
view and/or print the contents of this
document and the full license
application via the internet through the
Commission’s Home Page
(www.ferc.gov) using the ‘‘eLibrary’’
link. At this time, the Commission has
suspended access to the Commission’s
Public Access Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
1 All elevations refer to Barge Canal Datum which
is 0.8 foot higher than elevations in National
Geodetic Vertical Datum of 1929.
VerDate Sep<11>2014
16:49 Sep 17, 2021
Jkt 253001
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target date
Issue Deficiency Letter (if
necessary).
Request Additional Information.
Notice of Acceptance/Notice of Ready for Environmental Analysis.
September
2021.
October 2021.
February 2022.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20271 Filed 9–17–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC21–133–000.
Applicants: Maverick Solar 6, LLC,
Maverick Solar 7, LLC.
Description: Joint Application for
Authorization Under Section 203 of the
Federal Power Act of Maverick Solar 6,
LLC, et al.
Filed Date: 9/13/21.
Accession Number: 20210913–5247.
Comment Date: 5 pm ET 10/4/21.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER21–2424–001.
Applicants: Generation Bridge M&M
Holdings, LLC.
Description: Tariff Amendment:
Amendment to Market-Based Rate
Application and Response to Deficiency
Letter to be effective 7/15/2021.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
52143
Filed Date: 9/14/21.
Accession Number: 20210914–5161.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21–2884–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2021–09–14_SA 3438 Entergy ArkansasLong Lake Solar 1st Rev GIA (J663 J834)
to be effective 9/8/2021.
Filed Date: 9/14/21.
Accession Number: 20210914–5116.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21–2885–000.
Applicants: Arizona Public Service
Company.
Description: § 205(d) Rate Filing:
Service Agreement No. 300 to be
effective 11/14/2021.
Filed Date: 9/14/21.
Accession Number: 20210914–5118.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21–2886–000.
Applicants: Old Middleboro Road
Solar, LLC.
Description: Baseline eTariff Filing:
Old Middleboro Road Solar, LLC MBR
Application Filing to be effective 10/1/
2021.
Filed Date: 9/14/21.
Accession Number: 20210914–5140.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21–2887–000.
Applicants: Leicester Street Solar,
LLC.
Description: Baseline eTariff Filing:
Leicester Street Solar LLC MBR
Application Filing to be effective 10/1/
2021.
Filed Date: 9/14/21.
Accession Number: 20210914–5141.
Comment Date: 5 pm ET 10/5/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
E:\FR\FM\20SEN1.SGM
20SEN1
Agencies
[Federal Register Volume 86, Number 179 (Monday, September 20, 2021)]
[Notices]
[Pages 52142-52143]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-20271]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3509-042]
Little Falls Hydroelectric Associates, LP; Notice of Application
Tendered for Filing With The Commission and Establishing Procedural
Schedule for Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 3509-042.
c. Date Filed: August 31, 2021.
d. Applicant: Little Falls Hydroelectric Associates, LP.
e. Name of Project: Little Falls Hydroelectric Project (Little
Falls Project).
f. Location: The existing project is located on the Mohawk River,
in the City of Little Falls, Herkimer County, New York. The project
does not occupy federal land.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825 (r).
h. Applicant Contact: David H. Fox, Director, Licensing and
Compliance, Little Falls Hydroelectric Associates, LP, Eagle Creek
Renewable Energy, 7315 Wisconsin Avenue, Suite 1100W, Bethesda, MD
20814, [email protected]; Jody J. Smet, Vice President,
Regulatory Affairs, Little Falls Hydroelectric Associates, LP, Eagle
Creek Renewable Energy, 7315 Wisconsin Avenue, Suite 1100W, Bethesda,
MD 20814, [email protected]
[[Page 52143]]
i. FERC Contact: Monir Chowdhury at (202) 502-6736 or email at
[email protected].
j. This application is not ready for environmental analysis at this
time.
k. Project Description: The Little Falls Project consists of: (1)
Two state-owned dams (i.e., North State Dam and South State Dam) joined
by an island, and equipped with 1-foot-high flashboards and flow
control gates, with a total length of 594 feet and a height of about
6.25 feet; (2) a reservoir with a storage capacity of 800 acre-feet at
a normal surface elevation of 363.8 feet; \1\ (3) a 45-foot-wide, 300-
foot-long navigation lock (Lock 17); (4) a 55-foot-wide, 73-foot-long
concrete intake structure with two roller head gates to control flow
through the intake; (5) two 14-foot-diameter, 90-foot-long steel
penstocks; (6) a 65-foot-wide by 99-foot-long concrete powerhouse
containing two-turbine-generator units each with a capacity of 6.8
megawatts; (7) two sets of 4.16-kilovolt (kV), 60-foot-long generator
leads that run from the powerhouse to a switchyard containing a 4.16/
46-kV transformer; (8) a 46-kV, 50-foot-long transmission line from the
switchyard to a nearby interconnection point that connects the project
with the National Grid; and (9) appurtenant facilities.
---------------------------------------------------------------------------
\1\ All elevations refer to Barge Canal Datum which is 0.8 foot
higher than elevations in National Geodetic Vertical Datum of 1929.
---------------------------------------------------------------------------
There are several structures inside the project boundary that are
not considered part of the project: A flood gate structure owned by the
New York State Canal Corporation to protect the canal during periods of
high headwater; the Middle Dam, with sixty percent of the dam currently
breached, located in the bypassed reach of the Mohawk River, and built
as part of a hydropower plant that was decommissioned in 1962; and the
Gilbert Dam located also in the bypassed reach approximately 700 feet
upstream of the powerhouse to measure flow through the Mohawk River and
to assure minimum flow conditions are met in the river.
l. In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested individuals an
opportunity to view and/or print the contents of this document and the
full license application via the internet through the Commission's Home
Page (www.ferc.gov) using the ``eLibrary'' link. At this time, the
Commission has suspended access to the Commission's Public Access Room
due to the proclamation declaring a National Emergency concerning the
Novel Coronavirus Disease (COVID-19), issued by the President on March
13, 2020. For assistance, contact FERC at [email protected] or
call toll-free, (886) 208-3676 or TTY, (202) 502-8659.
m. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue Deficiency Letter (if necessary). September 2021.
Request Additional Information......... October 2021.
Notice of Acceptance/Notice of Ready February 2022.
for Environmental Analysis.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-20271 Filed 9-17-21; 8:45 am]
BILLING CODE 6717-01-P