Combined Notice of Filings #1, 52143-52144 [2021-20252]
Download as PDF
Federal Register / Vol. 86, No. 179 / Monday, September 20, 2021 / Notices
i. FERC Contact: Monir Chowdhury at
(202) 502–6736 or email at
monir.chowdhury@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The Little Falls
Project consists of: (1) Two state-owned
dams (i.e., North State Dam and South
State Dam) joined by an island, and
equipped with 1-foot-high flashboards
and flow control gates, with a total
length of 594 feet and a height of about
6.25 feet; (2) a reservoir with a storage
capacity of 800 acre-feet at a normal
surface elevation of 363.8 feet; 1 (3) a 45foot-wide, 300-foot-long navigation lock
(Lock 17); (4) a 55-foot-wide, 73-footlong concrete intake structure with two
roller head gates to control flow through
the intake; (5) two 14-foot-diameter, 90foot-long steel penstocks; (6) a 65-footwide by 99-foot-long concrete
powerhouse containing two-turbinegenerator units each with a capacity of
6.8 megawatts; (7) two sets of 4.16kilovolt (kV), 60-foot-long generator
leads that run from the powerhouse to
a switchyard containing a 4.16/46-kV
transformer; (8) a 46-kV, 50-foot-long
transmission line from the switchyard to
a nearby interconnection point that
connects the project with the National
Grid; and (9) appurtenant facilities.
There are several structures inside the
project boundary that are not considered
part of the project: A flood gate structure
owned by the New York State Canal
Corporation to protect the canal during
periods of high headwater; the Middle
Dam, with sixty percent of the dam
currently breached, located in the
bypassed reach of the Mohawk River,
and built as part of a hydropower plant
that was decommissioned in 1962; and
the Gilbert Dam located also in the
bypassed reach approximately 700 feet
upstream of the powerhouse to measure
flow through the Mohawk River and to
assure minimum flow conditions are
met in the river.
l. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested individuals an opportunity to
view and/or print the contents of this
document and the full license
application via the internet through the
Commission’s Home Page
(www.ferc.gov) using the ‘‘eLibrary’’
link. At this time, the Commission has
suspended access to the Commission’s
Public Access Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
1 All elevations refer to Barge Canal Datum which
is 0.8 foot higher than elevations in National
Geodetic Vertical Datum of 1929.
VerDate Sep<11>2014
16:49 Sep 17, 2021
Jkt 253001
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target date
Issue Deficiency Letter (if
necessary).
Request Additional Information.
Notice of Acceptance/Notice of Ready for Environmental Analysis.
September
2021.
October 2021.
February 2022.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20271 Filed 9–17–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC21–133–000.
Applicants: Maverick Solar 6, LLC,
Maverick Solar 7, LLC.
Description: Joint Application for
Authorization Under Section 203 of the
Federal Power Act of Maverick Solar 6,
LLC, et al.
Filed Date: 9/13/21.
Accession Number: 20210913–5247.
Comment Date: 5 pm ET 10/4/21.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER21–2424–001.
Applicants: Generation Bridge M&M
Holdings, LLC.
Description: Tariff Amendment:
Amendment to Market-Based Rate
Application and Response to Deficiency
Letter to be effective 7/15/2021.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
52143
Filed Date: 9/14/21.
Accession Number: 20210914–5161.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21–2884–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2021–09–14_SA 3438 Entergy ArkansasLong Lake Solar 1st Rev GIA (J663 J834)
to be effective 9/8/2021.
Filed Date: 9/14/21.
Accession Number: 20210914–5116.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21–2885–000.
Applicants: Arizona Public Service
Company.
Description: § 205(d) Rate Filing:
Service Agreement No. 300 to be
effective 11/14/2021.
Filed Date: 9/14/21.
Accession Number: 20210914–5118.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21–2886–000.
Applicants: Old Middleboro Road
Solar, LLC.
Description: Baseline eTariff Filing:
Old Middleboro Road Solar, LLC MBR
Application Filing to be effective 10/1/
2021.
Filed Date: 9/14/21.
Accession Number: 20210914–5140.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21–2887–000.
Applicants: Leicester Street Solar,
LLC.
Description: Baseline eTariff Filing:
Leicester Street Solar LLC MBR
Application Filing to be effective 10/1/
2021.
Filed Date: 9/14/21.
Accession Number: 20210914–5141.
Comment Date: 5 pm ET 10/5/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
E:\FR\FM\20SEN1.SGM
20SEN1
52144
Federal Register / Vol. 86, No. 179 / Monday, September 20, 2021 / Notices
Dated: September 14, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Comment Date: 5:00 p.m. Eastern
Time on October 12, 2021.
[FR Doc. 2021–20252 Filed 9–17–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Dated: September 14, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[Docket No. EF21–10–000]
[FR Doc. 2021–20253 Filed 9–17–21; 8:45 am]
Western Area Power Administration;
Notice of Filing
BILLING CODE 6717–01–P
Take notice that on September 9,
2021, Western Area Power
Administration submitted tariff filing:
RMR–WAPA–196–Errata Filing, to be
effective 10/1/2021.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically may mail similar
pleadings to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand
delivered submissions in docketed
proceedings should be delivered to
Health and Human Services, 12225
Wilkins Avenue, Rockville, Maryland
20852.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
VerDate Sep<11>2014
16:49 Sep 17, 2021
Jkt 253001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3777–000]
Town of Rollinsford, New Hampshire;
Notice of Authorization for Continued
Project Operation
On August 29, 2019, the Town of
Rollinsford, New Hampshire, licensee
for the Rollinsford Hydroelectric Project
No. 3777, filed an Application for a
Subsequent License pursuant to the
Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Rollinsford Hydroelectric Project is
located on the Salmon Falls River in
Strafford County, New Hampshire and
York County, Maine.
The license for Project No. 3777 was
issued for a period ending August 31,
2021. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee(s)
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 3777
is issued to the Town of Rollinsford,
New Hampshire for a period effective
September 1, 2021 through August 31,
2022 or until the issuance of a new
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before August 31, 2022,
notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
unless the Commission orders
otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the Town of Rollinsford, New
Hampshire is authorized to continue
operation of the Rollinsford
Hydroelectric Project, until such time as
the Commission acts on its application
for a subsequent license.
Dated: September 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20274 Filed 9–17–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3820–000]
Aclara Meters, LLC; Notice of
Authorization for Continued Project
Operation
On March 29, 2019, Aclara Meters,
LLC, licensee for the Somersworth
Hydroelectric Project No. 3820, filed an
application for Surrender of License.
The Somersworth Hydroelectric Project
is located on the Salmon Falls River in
Strafford County, New Hampshire, and
York County, Maine.
The license for Project No. 3820 was
issued for a period ending August 31,
2021. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee(s)
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
E:\FR\FM\20SEN1.SGM
20SEN1
Agencies
[Federal Register Volume 86, Number 179 (Monday, September 20, 2021)]
[Notices]
[Pages 52143-52144]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-20252]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
corporate filings:
Docket Numbers: EC21-133-000.
Applicants: Maverick Solar 6, LLC, Maverick Solar 7, LLC.
Description: Joint Application for Authorization Under Section 203
of the Federal Power Act of Maverick Solar 6, LLC, et al.
Filed Date: 9/13/21.
Accession Number: 20210913-5247.
Comment Date: 5 pm ET 10/4/21.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER21-2424-001.
Applicants: Generation Bridge M&M Holdings, LLC.
Description: Tariff Amendment: Amendment to Market-Based Rate
Application and Response to Deficiency Letter to be effective 7/15/
2021.
Filed Date: 9/14/21.
Accession Number: 20210914-5161.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21-2884-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Sec. 205(d) Rate Filing: 2021-09-14_SA 3438 Entergy
Arkansas-Long Lake Solar 1st Rev GIA (J663 J834) to be effective 9/8/
2021.
Filed Date: 9/14/21.
Accession Number: 20210914-5116.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21-2885-000.
Applicants: Arizona Public Service Company.
Description: Sec. 205(d) Rate Filing: Service Agreement No. 300 to
be effective 11/14/2021.
Filed Date: 9/14/21.
Accession Number: 20210914-5118.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21-2886-000.
Applicants: Old Middleboro Road Solar, LLC.
Description: Baseline eTariff Filing: Old Middleboro Road Solar,
LLC MBR Application Filing to be effective 10/1/2021.
Filed Date: 9/14/21.
Accession Number: 20210914-5140.
Comment Date: 5 pm ET 10/5/21.
Docket Numbers: ER21-2887-000.
Applicants: Leicester Street Solar, LLC.
Description: Baseline eTariff Filing: Leicester Street Solar LLC
MBR Application Filing to be effective 10/1/2021.
Filed Date: 9/14/21.
Accession Number: 20210914-5141.
Comment Date: 5 pm ET 10/5/21.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
[[Page 52144]]
Dated: September 14, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021-20252 Filed 9-17-21; 8:45 am]
BILLING CODE 6717-01-P