Lakeport Hydroelectric One, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 51883-51884 [2021-20135]
Download as PDF
Federal Register / Vol. 86, No. 178 / Friday, September 17, 2021 / Notices
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at:https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: September 13, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–20129 Filed 9–16–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 6440–010]
Lakeport Hydroelectric One, LLC;
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
and Establishing Procedural Schedule
for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 6440–010.
c. Date filed: August 30, 2021.
d. Applicant: Lakeport Hydroelectric
One, LLC (Lakeport).
e. Name of Project: Lakeport
Hydroelectric Project (project).
f. Location: On the Winnipesaukee
River in Belknap County, New
Hampshire. The project does not occupy
any federal land.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Ms. Jody Smet,
Lakeport Hydroelectric One, LLC c/o
Eagle Creek Renewable Energy, LLC,
7315 Wisconsin Avenue, Suite 1100W,
Bethesda, MD 20814; Phone at (240)
482–2700, or email at jody.smet@
eaglecreekre.com.
VerDate Sep<11>2014
16:19 Sep 16, 2021
Jkt 253001
i. FERC Contact: Erin Kimsey at (202)
502–8621, or erin.kimsey@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: October 29, 2021.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, MD 20852. All filings must
clearly identify the project name and
docket number on the first page:
Lakeport Hydroelectric Project (P–6440–
010).
m. The application is not ready for
environmental analysis at this time.
n. Project Description: The existing
Lakeport Project consists of: (1) A 220foot-long, 10-foot-high concrete gravity
dam that includes three 10-foot-high,
18-foot-wide gates, a spillway, and a
stoplog gate; (2) an impoundment with
a surface area of approximately 70
square miles at an elevation of 504 feet
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
51883
NGVD 29; (3) a 40-foot-wide, 12-footlong concrete and granite intake
structure that is equipped with three
headgates and a trashrack with 2-inch
clear bar spacing with a 0.75-inch
overlay; (4) a concrete and lumber
powerhouse containing three 200kilowatt (kW) vertical submersible Flygt
turbine-generator units located on
concrete pilings outside for a total
installed capacity of 600 kW; (5) a 200foot-long, 50-foot-wide tailrace that
discharges into the Winnipesaukee
River; (6) three 0.48-kilovolt (kV)
generator leads, three 0.48/12.4-kV stepup transformers, and a 250-foot-long,
12.4 kV transmission line that connect
the project to the local utility
distribution system; and (7) appurtenant
facilities.
The project is operated as a run ofriver facility. The average annual
generation of the project is
approximately 2,250 megawatt-hours.
o. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–6440).
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Issue Deficiency Letter (if necessary)—
October 2021
Request Additional Information—
October 2021
Issue Scoping Document 1 for
comments—January 2022
Request Additional Information (if
necessary)—February 2022
Issue Acceptance Letter—February 2022
Issue Scoping Document 2—March 2022
Issue Notice of Ready for Environmental
Analysis—March 2022
q. Final amendments to the
application must be filed with the
Commission no later than 30 days from
E:\FR\FM\17SEN1.SGM
17SEN1
51884
Federal Register / Vol. 86, No. 178 / Friday, September 17, 2021 / Notices
the issuance date of the notice of ready
for environmental analysis.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20135 Filed 9–16–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3409–034]
Boyne USA, Inc.; Notice of Petition for
Declaratory Order
Take notice that on August 30, 2021,
pursuant to Rule 207 of the Federal
Energy Regulatory Commission’s Rules
of Practice and Procedure, 18 CFR
385.207 (2020), Boyne USA, Inc., filed
a petition for declaratory order (Petition)
requesting that the Commission declare
that the Michigan Department of
Environment, Great Lakes, and Energy
has waived its authority to issue a
certification for the Boyne River
Hydroelectric Project No. 3409 under
Section 401 of the Clean Water Act, 33
U.S.C. 1341(a)(1), as more fully
explained in the Petition.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Petitioner.
Any person wishing to comment on
Boyne’s Petition may do so.1 The
deadline for filing comments is 30 days
from the issuance of this notice. The
Commission encourages electronic
submission of comments in lieu of
paper using the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should send comments to
the following address: Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. Hand
delivered submissions in docketed
proceedings should be delivered to
Health and Human Services, 12225
Wilkins Avenue, Rockville, Maryland
20852. Be sure to reference the project
docket number (P–3409–032) with your
submission.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons the opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the document number excluding
the last three digits in the docket
number field to access the document. At
this time, the Commission has
suspended access to the Commission’s
Public Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance with any FERC Online
service, please email
FERCOnlineSupport@ferc.gov or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on October 13, 2021.
Dated: September 13, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–20128 Filed 9–16–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD21–10–000]
Modernizing Electricity Market Design;
Supplemental Notice of Technical
Conference on Energy and Ancillary
Services in the Evolving Electricity
Sector
As first announced in the Notice of
Technical Conference issued in this
proceeding on July 14, 2021, the Federal
Energy Regulatory Commission
(Commission) will convene a staff-led
technical conference in the abovereferenced proceeding on September 14,
2021, from approximately 9:00 a.m. to
5:00 p.m. Eastern time. The conference
will be held remotely. This
Supplemental Notice includes an
updated pending proceedings list and
attached is an agenda for the technical
conference, which includes the final
conference program and updated
speaker list. Commissioners may attend
and participate in the technical
conference.
Discussions at the conference may
involve issues raised in proceedings that
are currently pending before the
Commission. These proceedings
include, but are not limited to:
Docket No.
California Independent System Operator Corporation ...............................................................................
California Independent System Operator Corporation ...............................................................................
New York Independent System Operator, Inc ...........................................................................................
PJM Interconnection, L.L.C ........................................................................................................................
PJM Interconnection, L.L.C ........................................................................................................................
PJM Interconnection, L.L.C ........................................................................................................................
PJM Interconnection, L.L.C ........................................................................................................................
Midcontinent Independent System Operator, Inc .......................................................................................
Midcontinent Independent System Operator, Inc .......................................................................................
Midcontinent Independent System Operator, Inc .......................................................................................
Midcontinent Independent System Operator, Inc .......................................................................................
Midcontinent Independent System Operator, Inc .......................................................................................
1 Boyne’s request is part of its relicensing
proceeding in Project No. 3409–032. Thus, any
person that intervened in the relicensing
proceeding is already a party. Generally, the filing
of a petition for a declaratory order involving an
issue arising from the licensing proceeding does not
VerDate Sep<11>2014
17:37 Sep 16, 2021
Jkt 253001
trigger a new opportunity to intervene. Accordingly,
at this point in this proceeding, any person seeking
to become a party to the proceeding must file a
motion to intervene out-of-time pursuant to Rule
214(b)(3) and (d) of the Commission’s Rules of
Practice and Procedure that provides justification
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
ER21–2455–000.
ER21–2779–000.
ER21–2460–000.
ER21–1919–000.
EL21–78–000, et al.
EL19–58, et al.; ER19–1486, et al.
ER21–2582–000.
ER21–2620–000.
ER21–2486–000; ER21–2487–000.
ER21–2720–000.
ER21–2801–000.
ER21–2797–000.
by reference to the factors set forth in Rule 214(d).
The Commission may limit a late intervenor’s
participation to the issues raised in the petition for
declaratory order. 18 CFR 385.214(d)(3)(i).
E:\FR\FM\17SEN1.SGM
17SEN1
Agencies
[Federal Register Volume 86, Number 178 (Friday, September 17, 2021)]
[Notices]
[Pages 51883-51884]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-20135]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 6440-010]
Lakeport Hydroelectric One, LLC; Notice of Application Tendered
for Filing With the Commission and Soliciting Additional Study Requests
and Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent Minor License.
b. Project No.: 6440-010.
c. Date filed: August 30, 2021.
d. Applicant: Lakeport Hydroelectric One, LLC (Lakeport).
e. Name of Project: Lakeport Hydroelectric Project (project).
f. Location: On the Winnipesaukee River in Belknap County, New
Hampshire. The project does not occupy any federal land.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Ms. Jody Smet, Lakeport Hydroelectric One,
LLC c/o Eagle Creek Renewable Energy, LLC, 7315 Wisconsin Avenue, Suite
1100W, Bethesda, MD 20814; Phone at (240) 482-2700, or email at
[email protected].
i. FERC Contact: Erin Kimsey at (202) 502-8621, or
[email protected].
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: October 29, 2021.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. For assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
MD 20852. All filings must clearly identify the project name and docket
number on the first page: Lakeport Hydroelectric Project (P-6440-010).
m. The application is not ready for environmental analysis at this
time.
n. Project Description: The existing Lakeport Project consists of:
(1) A 220-foot-long, 10-foot-high concrete gravity dam that includes
three 10-foot-high, 18-foot-wide gates, a spillway, and a stoplog gate;
(2) an impoundment with a surface area of approximately 70 square miles
at an elevation of 504 feet NGVD 29; (3) a 40-foot-wide, 12-foot-long
concrete and granite intake structure that is equipped with three
headgates and a trashrack with 2-inch clear bar spacing with a 0.75-
inch overlay; (4) a concrete and lumber powerhouse containing three
200-kilowatt (kW) vertical submersible Flygt turbine-generator units
located on concrete pilings outside for a total installed capacity of
600 kW; (5) a 200-foot-long, 50-foot-wide tailrace that discharges into
the Winnipesaukee River; (6) three 0.48-kilovolt (kV) generator leads,
three 0.48/12.4-kV step-up transformers, and a 250-foot-long, 12.4 kV
transmission line that connect the project to the local utility
distribution system; and (7) appurtenant facilities.
The project is operated as a run of-river facility. The average
annual generation of the project is approximately 2,250 megawatt-hours.
o. In addition to publishing the full text of this notice in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this notice, as well
as other documents in the proceeding (e.g., license application) via
the internet through the Commission's Home Page (https://www.ferc.gov)
using the ``eLibrary'' link. Enter the docket number excluding the last
three digits in the docket number field to access the document (P-
6440). For assistance, contact FERC at [email protected] or
call toll-free, (866) 208-3676 or (202) 502-8659 (TTY).
You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate.
Issue Deficiency Letter (if necessary)--October 2021
Request Additional Information--October 2021
Issue Scoping Document 1 for comments--January 2022
Request Additional Information (if necessary)--February 2022
Issue Acceptance Letter--February 2022
Issue Scoping Document 2--March 2022
Issue Notice of Ready for Environmental Analysis--March 2022
q. Final amendments to the application must be filed with the
Commission no later than 30 days from
[[Page 51884]]
the issuance date of the notice of ready for environmental analysis.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-20135 Filed 9-16-21; 8:45 am]