City of North Little Rock; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 51881-51882 [2021-20134]
Download as PDF
Federal Register / Vol. 86, No. 178 / Friday, September 17, 2021 / Notices
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: October 30, 2021.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. All filings
must clearly identify the project name
and docket number on the first page:
Felt Hydroelectric Project (P–5089–027).
m. The application is not ready for
environmental analysis at this time.
n. Project Description: The existing
Felt Project consists of: (1) A 125-footlong, 12-foot-high concrete dam that
includes the following sections: (a) 25foot-wide sluiceway section with a 4foot-wide fish ladder and a 14-foot-wide
corrugated steel radial gate and (b) a 96foot-wide uncontrolled overflow
spillway with a crest elevation of 5,530feet mean sea level (msl); (2) a 7-acre
impoundment with a storage capacity of
28 acre-feet at a normal water surface
elevation of 5,530-feet msl; (3) a 178foot-long, 8.5-foot-deep fish screen
structure equipped with a bar rack with
3/8-inch clear bar spacing and diamond
mesh screen; (4) three intake openings
located behind the fish screen each
equipped with 10-foot-wide intake gates
VerDate Sep<11>2014
16:19 Sep 16, 2021
Jkt 253001
and 10-foot-wide trash racks with 3-inch
clear bar spacing; (5) three, 8-foot-square
unlined rock tunnels connecting the
intakes to penstocks and consisting of:
(a) A 180-foot-long Tunnel No. 1
connecting to a 280-foot-long, 78-inchdiameter steel penstock that bifurcates
into two, 180-foot-long, 60-inchdiameter steel penstocks that connect to
Powerhouse No. 1; and (b) A 180-footlong Tunnel No. 2 and a 200-foot-long
Tunnel No. 3 each connecting to a
1,750-foot-long, 96-inch-diameter steel
penstock that connects to Powerhouse
No. 2; (6) an 83-foot-long, 26-foot-wide,
13-foot-high reinforced concrete
Powerhouse No. 1 containing two
horizontal Francis turbine-generator
units with a combined generating
capacity of 1,950 kilowatts (kW); (7) a
36-foot-long, 36-foot-wide, 25-foot-high
reinforced concrete Powerhouse No. 2
containing two vertical Francis turbinegenerator units with a combined
generating capacity of 5,500 kW; (8) two
tailrace channels discharging to the
Teton River from Powerhouses No. 1
and No. 2; (9) a 1,500-foot-long, 4.16
kilovolt (kV) overhead transmission line
connecting Powerhouse No. 1 to a
transformer located next to Powerhouse
No. 2; (10) a 2,000-foot-long, 24.9 kV
overhead transmission line leading from
the transformer to the interconnection
point; and (11) appurtenant facilities.
The 7.45-megawatt Felt Project is
operated in run-of-river mode and
generates an average of 33,100
megawatt-hours per year. A continuous
minimum flow is released below the
dam according to the following
schedule: 20 cubic feet per second (cfs)
from July 1 to March 14 and 50 cfs from
March 15 to June 30.
o. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–5089).
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19) issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
51881
You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Issue Deficiency Letter (if necessary)—
October 2021
Request Additional Information (if
needed)—October 2021
Issue Notice of Acceptance—January
2021
Issue Scoping Document 1 for
comments—February 2022
Issue Scoping Document 2—May 2022
Issue Notice of Ready for Environmental
Analysis—May 2022
q. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: September 13, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20137 Filed 9–16–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15151–000]
City of North Little Rock; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On June 11, 2021, the City of North
Little Rock filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the David D.
Terry Lock & Dam Hydroelectric Project
No. 15151–000 (David D. Terry Project,
or project), a run-of-river project to be
located in Pulaski County, Arkansas.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any landdisturbing activities or otherwise enter
upon lands or waters owned by others
without the owners’ express permission.
The proposed project would consist of
the following: (1) An existing, 4,710acre reservoir at a maximum water
E:\FR\FM\17SEN1.SGM
17SEN1
51882
Federal Register / Vol. 86, No. 178 / Friday, September 17, 2021 / Notices
surface elevation of 231.3 feet mean sea
level; (2) an existing lock and dam,
including a spillway section; (3) a new
headrace intake channel; (4) a new
concrete powerhouse housing the
turbine-generator unit(s); (5) a new
discharge penstock; (6) a new tailrace
receiving flow from the penstock; (7) a
new, 8-mile-long interconnection line to
an existing, 69 kilo-Volt substation; and
(8) appurtenant facilities. The estimated
annual generation of the project would
be 128 gigawatt-hours.
Applicant Contact: Scott Springer,
1400 W Maryland Ave., North Little
Rock, Arkansas, 72118; phone: (501)
372–0100.
FERC Contact: Navreet Deo; phone:
(202) 502–6304; email: navreet.deo@
ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. In lieu of electronic
filing, you may submit a paper copy.
Submissions sent via the U.S. Postal
Service must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–15151–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s website at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–15151) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: September 13, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–20134 Filed 9–16–21; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
16:19 Sep 16, 2021
Jkt 253001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG21–248–000.
Applicants: IP Radian, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of IP Radian, LLC.
Filed Date: 9/13/21.
Accession Number: 20210913–5183.
Comment Date: 5 p.m. ET 10/4/21.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER21–2043–000.
Applicants: PJM Interconnection,
L.L.C.
Description: PJM Interconnection,
L.L.C. submits informational filing on
posted Effective Load Carrying
Capability methodology documentation,
model, and input data.
Filed Date: 9/13/21.
Accession Number: 20210913–5088.
Comment Date: 5 p.m. ET 10/4/21.
Docket Numbers: ER21–2183–001.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment: 3825
Prairie Hills Wind GIA—Deficiency
Response to be effective 6/14/2021.
Filed Date: 9/13/21.
Accession Number: 20210913–5164.
Comment Date: 5 p.m. ET 10/4/21.
Docket Numbers: ER21–2261–001.
Applicants: Exelon Generation
Company, LLC.
Description: Tariff Amendment:
Request for Seven Day Deferral of
Commission Action to be effective 9/14/
2021.
Filed Date: 9/13/21.
Accession Number: 20210913–5074.
Comment Date: 5 p.m. ET 9/20/21.
Docket Numbers: ER21–2878–000.
Applicants: Salt Creek Solar, LLC.
Description: Request for Temporary
Tariff Waiver, et al. of Salt Creek Solar,
LLC.
Filed Date: 9/10/21.
Accession Number: 20210910–5178.
Comment Date: 5 p.m. ET 10/1/21.
Docket Numbers: ER21–2879–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original WMPA, Service Agreement No.
6187; Queue No. AF2–314 to be
effective 8/12/2021.
Filed Date: 9/13/21.
Accession Number: 20210913–5036.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
Comment Date: 5 p.m. ET 10/4/21.
Docket Numbers: ER21–2880–000.
Applicants: The Connecticut Light
and Power Company.
Description: § 205(d) Rate Filing:
Engineering Design and Procurement
Agreement with EIP Investments–Black
Rock Sub to be effective 9/14/2021.
Filed Date: 9/13/21.
Accession Number: 20210913–5077.
Comment Date: 5 p.m. ET 10/4/21.
Docket Numbers: ER21–2881–000.
Applicants: Power Authority of the
State of New York, New York
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
Power Authority of the State of New
York submits tariff filing per
35.13(a)(2)(iii: 205 SGIA between
NYISO and NYPA for North Country SA
No. 2648—CEII to be effective 8/27/
2021.
Filed Date: 9/13/21.
Accession Number: 20210913–5089.
Comment Date: 5 p.m. ET 10/4/21.
Docket Numbers: ER21–2882–000.
Applicants: Pacific Gas and Electric
Company.
Description: Application to Recover
50 Percent of Abandoned Plant Costs of
Pacific Gas and Electric Company.
Filed Date: 9/10/21.
Accession Number: 20210910–5184.
Comment Date: 5 p.m. ET 10/1/21.
Docket Numbers: ER21–2883–000.
Applicants: New York Independent
System Operator, Inc.
Description: § 205(d) Rate Filing:
NYISO 205: Metering Services for
Demand Side Resources to be effective
11/13/2021.
Filed Date: 9/13/21.
Accession Number: 20210913–5149.
Comment Date: 5 p.m. ET 10/4/21.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES21–67–000.
Applicants: Mississippi Power
Company.
Description: Application Under
Section 204 of the Federal Power Act for
Authorization to Issue Securities of
Mississippi power Company.
Filed Date: 9/10/21.
Accession Number: 20210910–5185.
Comment Date: 5 p.m. ET 10/1/21.
Docket Numbers: ES21–68–000.
Applicants: Old Dominion Electric
Cooperative.
Description: Application Under
Section 204 of the Federal Power Act for
Authorization to Issue Securities of Old
Dominion Electric Cooperative8.
Filed Date: 9/13/21.
Accession Number: 20210913–5159.
Comment Date: 5 p.m. ET 10/4/21.
E:\FR\FM\17SEN1.SGM
17SEN1
Agencies
[Federal Register Volume 86, Number 178 (Friday, September 17, 2021)]
[Notices]
[Pages 51881-51882]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-20134]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 15151-000]
City of North Little Rock; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
On June 11, 2021, the City of North Little Rock filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act, proposing to study the feasibility of the David D.
Terry Lock & Dam Hydroelectric Project No. 15151-000 (David D. Terry
Project, or project), a run-of-river project to be located in Pulaski
County, Arkansas. The sole purpose of a preliminary permit, if issued,
is to grant the permit holder priority to file a license application
during the permit term. A preliminary permit does not authorize the
permit holder to perform any land-disturbing activities or otherwise
enter upon lands or waters owned by others without the owners' express
permission.
The proposed project would consist of the following: (1) An
existing, 4,710-acre reservoir at a maximum water
[[Page 51882]]
surface elevation of 231.3 feet mean sea level; (2) an existing lock
and dam, including a spillway section; (3) a new headrace intake
channel; (4) a new concrete powerhouse housing the turbine-generator
unit(s); (5) a new discharge penstock; (6) a new tailrace receiving
flow from the penstock; (7) a new, 8-mile-long interconnection line to
an existing, 69 kilo-Volt substation; and (8) appurtenant facilities.
The estimated annual generation of the project would be 128 gigawatt-
hours.
Applicant Contact: Scott Springer, 1400 W Maryland Ave., North
Little Rock, Arkansas, 72118; phone: (501) 372-0100.
FERC Contact: Navreet Deo; phone: (202) 502-6304; email:
[email protected].
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852. The first page of any filing should include docket
number P-15151-000.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-15151) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: September 13, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-20134 Filed 9-16-21; 8:45 am]
BILLING CODE 6717-01-P