Pacific Gas and Electric Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 50341-50342 [2021-19358]

Download as PDF jbell on DSKJLSW7X2PROD with NOTICES Federal Register / Vol. 86, No. 171 / Wednesday, September 8, 2021 / Notices Take notice that the Commission received the following Complaints and Compliance filings in EL Dockets: Docket Numbers: EL21–100–000. Applicants: Nebraska Public Power District v. Tri-State Generation and Transmission Association, Inc., and Southwest Power Pool, Inc. Description: Complaint of Nebraska Public Power District. Filed Date: 9/1/21. Accession Number: 20210901–5220. Comment Date: 5 p.m. ET 9/21/21. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER20–676–005. Applicants: Tri-State Generation and Transmission Association, Inc. Description: Compliance filing: Settlement Compliance Filing to be effective 3/1/2021. Filed Date: 9/1/21. Accession Number: 20210901–5169. Comment Date: 5 p.m. ET 9/22/21. Docket Numbers: ER21–2438–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 3630SR1 Maverick Wind Project GIA to be effective 6/29/2021. Filed Date: 9/2/21. Accession Number: 20210902–5083. Comment Date: 5 p.m. ET 9/23/21. Docket Numbers: ER21–2490–001. Applicants: PJM Interconnection, L.L.C. Description: Tariff Amendment: Errata to Amendment to ISA No.2967, in Docket No. ER21–2490–000 to be effective 6/17/2011. Filed Date: 9/2/21. Accession Number: 20210902–5090. Comment Date: 5 p.m. ET 9/23/21. Docket Numbers: ER21–2818–000. Applicants: Tri-State Generation and Transmission Association, Inc. Description: § 205(d) Rate Filing: Revisions to Rate Schedule FERC No. 281 (Modified CTP Methodology) to be effective 11/1/2021. Filed Date: 9/1/21. Accession Number: 20210901–5171. Comment Date: 5 p.m. ET 9/22/21. Docket Numbers: ER21–2819–000. Applicants: South Field Energy LLC. Description: § 205(d) Rate Filing: Reactive Power Rate Schedule and Request for Waiver and Expedited Action to be effective 10/1/2021. Filed Date: 9/2/21. Accession Number: 20210902–5000. Comment Date: 5 p.m. ET 9/23/21. Docket Numbers: ER21–2820–000. Applicants: York Generation Company LLC. Description: Tariff Amendment: Notice of Cancellation to be effective 9/ 20/2021. VerDate Sep<11>2014 17:21 Sep 07, 2021 Jkt 253001 Filed Date: 9/2/21. Accession Number: 20210902–5033. Comment Date: 5 p.m. ET 9/23/21. Docket Numbers: ER21–2821–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 3558R1 WAPA, MDU & MISO Interconnection Agreement to be effective 12/31/9998. Filed Date: 9/2/21. Accession Number: 20210902–5046. Comment Date: 5 p.m. ET 9/23/21. Docket Numbers: ER21–2822–000. Applicants: Commonwealth Edison Company, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Commonwealth Edison Company submits tariff filing per 35.13(a)(2)(iii): ComEd submits revisions to Att. H–13 re: Sterling Rail, L.L.C. to be effective 9/ 3/2021. Filed Date: 9/2/21. Accession Number: 20210902–5078. Comment Date: 5 p.m. ET 9/23/21. Docket Numbers: ER21–2823–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2021–09–02_SA 3313 WAPA–MDU 1st Revised Interconnection Agreement to be effective 12/31/9998. Filed Date: 9/2/21. Accession Number: 20210902–5113. Comment Date: 5 p.m. ET 9/23/21. Docket Numbers: ER21–2824–000. Applicants: Duke Energy Carolinas, LLC. Description: Tariff Amendment: DECBroad River Energy, LLC SA No. 240— Notice of Cancellation to be effective 11/ 2/2021. Filed Date: 9/2/21. Accession Number: 20210902–5117. Comment Date: 5 p.m. ET 9/23/21. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. PO 00000 Frm 00019 Fmt 4703 Sfmt 4703 50341 Dated: September 2, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–19458 Filed 9–7–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 1121–132] Pacific Gas and Electric Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Application for Temporary Variance of Flow Requirements. b. Project No: 1121–132. c. Date Filed: August 25, 2021. d. Applicant: Pacific Gas and Electric Company (licensee). e. Name of Project: Battle Creek Hydroelectric Project. f. Location: The project is located on Battle Creek and its tributaries in Shasta and Tehama counties, California. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Ms. Megan Young, License Coordinator, Pacific Gas and Electric Company, Mail Code: N11D, P.O. Box 770000, San Francisco, CA 94177, Phone: (530) 364–6009. i. FERC Contact: John Aedo, (415) 369–3335, john.aedo@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: September 21, 2021. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. E:\FR\FM\08SEN1.SGM 08SEN1 jbell on DSKJLSW7X2PROD with NOTICES 50342 Federal Register / Vol. 86, No. 171 / Wednesday, September 8, 2021 / Notices Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include the docket number P–1121–132. Comments emailed to Commission staff are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: The licensee requests a temporary variance of the minimum flow requirements at three project locations, including North Fork Battle Creek below North Battle Creek Dam, North Fork Battle Creek below Macumber Reservoir, and Battle Creek below Coleman Powerhouse. Specifically, the licensee requests Commission approval to reduce flows below North Battle Creek Reservoir and Macumber Reservoir from a 0.3 cubic feet per second (cfs) instantaneous requirement to a 24-hour average flow. Similarly, the licensee proposes to reduce flows in Battle Creek from a 150 cfs instantaneous minimum flow to a 24-hour average flow. The licensee states that the flow modification would conserve limited water resources during the current drought conditions and to maintain reservoir elevation and water quality in project reservoirs. The licensee requests the variance through October 31, 2021. l. Locations of the Application: This filing may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. VerDate Sep<11>2014 17:21 Sep 07, 2021 Jkt 253001 n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: September 1, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–19358 Filed 9–7–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP21–1086–000. Applicants: Alliance Pipeline L.P. Description: § 4(d) Rate Filing: Negotiated Rates—Various September 1 Capacity Releases to be effective 9/1/ 2021. Filed Date: 9/1/21. Accession Number: 20210901–5072. Comment Date: 5 p.m. ET 9/13/21. Docket Numbers: RP21–1087–000. Applicants: Equitrans, L.P. PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 Description: § 4(d) Rate Filing: Negotiated Rate Capacity Release Agreements—9/1/2021 to be effective 9/ 1/2021. Filed Date: 9/1/21. Accession Number: 20210901–5075. Comment Date: 5 p.m. ET 9/13/21. Docket Numbers: RP21–1088–000. Applicants: Gulf South Pipeline Company, LLC. Description: § 4(d) Rate Filing: Cap Rel Neg Rate Agmts (Marathon releasese effective 9–1–2021) to be effective 9/1/ 2021. Filed Date: 9/1/21. Accession Number: 20210901–5090. Comment Date: 5 p.m. ET 9/13/21. Docket Numbers: RP21–1089–000. Applicants: Texas Eastern Transmission, LP. Description: § 4(d) Rate Filing: Negotiated Rate—UGI Energy 8967380 eff 09–01–2021 to be effective 9/1/2021. Filed Date: 9/1/21. Accession Number: 20210901–5092. Comment Date: 5 p.m. ET 9/13/21. Docket Numbers: RP21–1090–000. Applicants: NEXUS Gas Transmission, LLC. Description: § 4(d) Rate Filing: Negotiated Rates—Releases eff 09–01– 2021 to be effective 9/1/2021. Filed Date: 9/1/21. Accession Number: 20210901–5094. Comment Date: 5 p.m. ET 9/13/21. Docket Numbers: RP21–1091–000. Applicants: NEXUS Gas Transmission, LLC. Description: § 4(d) Rate Filing: Negotiated Rate—Amended DTE Gas 860003 eff 9–1–2021 to be effective 9/ 1/2021. Filed Date: 9/1/21. Accession Number: 20210901–5097. Comment Date: 5 p.m. ET 9/13/21. Docket Numbers: RP21–1092–000. Applicants: Gulf South Pipeline Company, LLC. Description: § 4(d) Rate Filing: Amendment to Neg Rate Agmt and Cap Rel Agmt (Calyx 51762) to be effective 9/1/2021. Filed Date: 9/1/21. Accession Number: 20210901–5102. Comment Date: 5 p.m. ET 9/13/21. Docket Numbers: RP21–1093–000. Applicants: Enable Gas Transmission, LLC. Description: § 4(d) Rate Filing: Adding Firm PALS Option Under Rate Schedule PHS to be effective 10/1/2021. Filed Date: 9/1/21. Accession Number: 20210901–5153. Comment Date: 5 p.m. ET 9/13/21. Docket Numbers: RP21–1094–000. Applicants: NEXUS Gas Transmission, LLC. E:\FR\FM\08SEN1.SGM 08SEN1

Agencies

[Federal Register Volume 86, Number 171 (Wednesday, September 8, 2021)]
[Notices]
[Pages 50341-50342]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-19358]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 1121-132]


Pacific Gas and Electric Company; Notice of Application Accepted 
for Filing and Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Application for Temporary Variance of Flow 
Requirements.
    b. Project No: 1121-132.
    c. Date Filed: August 25, 2021.
    d. Applicant: Pacific Gas and Electric Company (licensee).
    e. Name of Project: Battle Creek Hydroelectric Project.
    f. Location: The project is located on Battle Creek and its 
tributaries in Shasta and Tehama counties, California.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Ms. Megan Young, License Coordinator, Pacific 
Gas and Electric Company, Mail Code: N11D, P.O. Box 770000, San 
Francisco, CA 94177, Phone: (530) 364-6009.
    i. FERC Contact: John Aedo, (415) 369-3335, [email protected].
    j. Deadline for filing comments, motions to intervene, and 
protests: September 21, 2021.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, and protests using the Commission's 
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. 
Commenters can submit brief comments up to 6,000 characters, without 
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at [email protected], (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may 
submit a paper copy. Submissions sent via the U.S. Postal Service must 
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.

[[Page 50342]]

Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852. The first page of any filing should 
include the docket number P-1121-132. Comments emailed to Commission 
staff are not considered part of the Commission record.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person whose name appears on the official service 
list for the project. Further, if an intervenor files comments or 
documents with the Commission relating to the merits of an issue that 
may affect the responsibilities of a particular resource agency, they 
must also serve a copy of the document on that resource agency.
    k. Description of Request: The licensee requests a temporary 
variance of the minimum flow requirements at three project locations, 
including North Fork Battle Creek below North Battle Creek Dam, North 
Fork Battle Creek below Macumber Reservoir, and Battle Creek below 
Coleman Powerhouse. Specifically, the licensee requests Commission 
approval to reduce flows below North Battle Creek Reservoir and 
Macumber Reservoir from a 0.3 cubic feet per second (cfs) instantaneous 
requirement to a 24-hour average flow. Similarly, the licensee proposes 
to reduce flows in Battle Creek from a 150 cfs instantaneous minimum 
flow to a 24-hour average flow. The licensee states that the flow 
modification would conserve limited water resources during the current 
drought conditions and to maintain reservoir elevation and water 
quality in project reservoirs. The licensee requests the variance 
through October 31, 2021.
    l. Locations of the Application: This filing may be viewed on the 
Commission's website at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. You may also register 
online at https://www.ferc.gov/docs-filing/esubscription.asp to be 
notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or email 
[email protected], for TTY, call (202) 502-8659. Agencies may 
obtain copies of the application directly from the applicant.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214, respectively. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Filing and Service of Documents: Any filing must (1) bear in all 
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO 
INTERVENE'' as applicable; (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person commenting, protesting or intervening; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis. Any filing made by an intervenor must be accompanied 
by proof of service on all persons listed in the service list prepared 
by the Commission in this proceeding, in accordance with 18 CFR 
385.2010.

    Dated: September 1, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-19358 Filed 9-7-21; 8:45 am]
BILLING CODE 6717-01-P