Exelon Generation Company, LLC, Dresden Nuclear Power Station, Units 2 and 3, 48446-48450 [2021-18600]
Download as PDF
48446
Federal Register / Vol. 86, No. 165 / Monday, August 30, 2021 / Notices
RCS contains all schedules approved
since 1973.
Engagement and Public Affairs Records
(DAA–0064–2018–0008).
Background
Laurence Brewer,
Chief Records Officer for the U.S.
Government.
Each year, Federal agencies create
billions of records. To control this
accumulation, agency records managers
prepare schedules proposing retention
periods for records and submit these
schedules for NARA’s approval. Once
approved by NARA, records schedules
provide mandatory instructions on what
happens to records when no longer
needed for current Government
business. The records schedules
authorize agencies to preserve records of
continuing value in the National
Archives or to destroy, after a specified
period, records lacking continuing
administrative, legal, research, or other
value. Some schedules are
comprehensive and cover all the records
of an agency or one of its major
subdivisions. Most schedules, however,
cover records of only one office or
program or a few series of records. Many
of these update previously approved
schedules, and some include records
proposed as permanent.
Agencies may not destroy Federal
records without the approval of the
Archivist of the United States. The
Archivist grants this approval only after
thorough consideration of the records’
administrative use by the agency of
origin, the rights of the Government and
of private people directly affected by the
Government’s activities, and whether or
not the records have historical or other
value. Public review and comment on
these records schedules is part of the
Archivist’s consideration process.
khammond on DSKJM1Z7X2PROD with NOTICES
Schedules Pending
1. Department of Defense, Defense
Logistics Agency, Environmental and
Hazardous Materials Management
Records (DAA–0361–2021–0011).
2. Department of Defense, Defense
Logistics Agency, Human Resource
Management Records (DAA–0361–
2021–0022).
3. Department of Health and Human
Services, Administration for Children
and Families, Technical Assistance
Records (DAA–0292–2021–0003).
4. Department of Transportation,
Federal Aviation Administration,
Automatic Dependent SurveillanceBroadcast Service Availability
Prediction Tool (DAA–0237–2020–
0002).
5. Department of Transportation,
Federal Aviation Administration,
Survey Study Records (DAA–0237–
2019–0004).
6. National Archives and Records
Administration, Agency-wide,
VerDate Sep<11>2014
18:40 Aug 27, 2021
Jkt 253001
[FR Doc. 2021–18578 Filed 8–27–21; 8:45 am]
BILLING CODE 7515–01–P
NATIONAL SCIENCE FOUNDATION
Notice of Permit Applications Received
Under the Antarctic Conservation Act
of 1978
National Science Foundation.
Notice of permit applications
received.
AGENCY:
ACTION:
The National Science
Foundation (NSF) is required to publish
a notice of permit applications received
to conduct activities regulated under the
Antarctic Conservation Act of 1978.
NSF has published regulations under
the Antarctic Conservation Act in the
Code of Federal Regulations. This is the
required notice of permit applications
received.
SUMMARY:
Interested parties are invited to
submit written data, comments, or
views with respect to this permit
application by September 29, 2021. This
application may be inspected by
interested parties at the Permit Office,
address below.
ADDRESSES: Comments should be
addressed to Permit Office, Office of
Polar Programs, National Science
Foundation, 2415 Eisenhower Avenue,
Alexandria, Virginia 22314 or
ACApermits@nsf.gov.
FOR FURTHER INFORMATION CONTACT:
Polly Penhale, ACA Permit Officer, at
the above address, 703–292–7420.
SUPPLEMENTARY INFORMATION: The
National Science Foundation, as
directed by the Antarctic Conservation
Act of 1978 (Pub. L. 95–541, 45 CFR
670), as amended by the Antarctic
Science, Tourism and Conservation Act
of 1996, has developed regulations for
the establishment of a permit system for
various activities in Antarctica and
designation of certain animals and
certain geographic areas a requiring
special protection. The regulations
establish such a permit system to
designate Antarctic Specially Protected
Areas.
DATES:
Application Details
Permit Application: 2022–008
1. Applicant: Jonathan Schwartz, 411
Walnut St., #12926, Green Cove
Springs, FL 32043
PO 00000
Frm 00062
Fmt 4703
Sfmt 4703
Activity for Which Permit is
Requested: Waste management. The
applicant seeks an Antarctic
Conservation Act permit for a planned
yacht-based expedition to the Antarctic
Peninsula Region between December
2021 and March 2022. Activities
include shore landings, photography,
and wildlife viewing. Designated
pollutants that would be generated
during the trip include air emissions,
wastewater (urine, grey water) and solid
waste (food waste, human solid waste,
and packaging materials). Human waste
and grey water would be disposed of in
offshore waters, complying with the
provisions of Article 5 of Annex III and
Article 6 of Annex IV of MARPOL
Protocol. Food waste will either be
macerated and discharged at least 12
miles from shore or ice shelves or stored
aboard the vessel for disposal at port.
All other wastes would be kept for
proper disposal at the end of the
expedition. The applicant also plans to
use Unoccupied Arial Systems (UAS)
for navigational purposes and
occasional photography. UAS will be
launched, recovered, and piloted from
the primary vessel and mitigation
measures are in place to minimize
potential loss of the aircraft as well as
to prevent possible disturbances to
wildlife.
Location: Western Antarctic
Peninsula.
Dates of Permitted Activities:
December 26, 2021–April 1, 2022.
Erika N. Davis,
Program Specialist, Office of Polar Programs.
[FR Doc. 2021–18582 Filed 8–27–21; 8:45 am]
BILLING CODE 7555–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–237 and 50–249; NRC–
2021–0155]
Exelon Generation Company, LLC,
Dresden Nuclear Power Station, Units
2 and 3
Nuclear Regulatory
Commission.
ACTION: Exemption; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
exemption in response to a September
28, 2020, request from Exelon
Generation Company, LLC. The
exemption allows either a licensed
senior operator or a certified fuel
handler to approve the emergency
suspension of security measures for
Dresden Nuclear Power Station, Units 2
and 3 during certain emergency
SUMMARY:
E:\FR\FM\30AUN1.SGM
30AUN1
Federal Register / Vol. 86, No. 165 / Monday, August 30, 2021 / Notices
conditions or during severe weather
after both the certification of permanent
cessation of operations and the
certification of permanent fuel removal
have been docketed for the facility.
For the Nuclear Regulatory Commission.
Joel S. Wiebe,
Senior Project Manager, Plant Licensing
Branch III, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
The exemption was issued on
August 23, 2021.
Attachment: Exemption
DATES:
Please refer to Docket ID
NRC–2021–0155 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly available
information related to this document
using any of the following methods:
• Federal Rulemaking website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2021–0155. Address
questions about Docket IDs in
Regulations.gov to Stacy Schumann;
telephone: 301–415–0624; email:
Stacy.Schumann@nrc.gov. For technical
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, contact the
NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced (if it is
available in ADAMS) is provided the
first time that it is mentioned in this
document.
• Attention: The PDR, where you may
examine and order copies of public
documents, is currently closed. You
may submit your request to the PDR via
email at pdr.resource@nrc.gov or call 1–
800–397–4209 or 301–415–4737,
between 8:00 a.m. and 4:00 p.m. (ET),
Monday through Friday, except Federal
holidays.
ADDRESSES:
Joel
S. Wiebe, Office of Nuclear Reactor
Regulation, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001; telephone: 301–415–6606; email:
Joel.Wiebe@nrc.gov.
khammond on DSKJM1Z7X2PROD with NOTICES
FOR FURTHER INFORMATION CONTACT:
SUPPLEMENTARY INFORMATION:
The text of
the exemption is attached.
Dated: August 25, 2021.
VerDate Sep<11>2014
18:40 Aug 27, 2021
Jkt 253001
NUCLEAR REGULATORY
COMMISSION
Docket Nos. 50–237 and 50–249
Exelon Generation Company, LLC;
Dresden Nuclear Power Station, Units 2
and 3
Exemption Related to the Approval
Authority for Suspension of Security
Measures in an Emergency or During
Severe Weather
I. Background
Exelon Generation Company, LLC
(Exelon) is the holder of Renewed
Facility Operating License Nos. DPR–19
and DPR–25 for the Dresden Nuclear
Power Station, Units 2 and 3 (Dresden).
The licenses provide, among other
things, that the facility is subject to all
applicable rules, regulations, and orders
of the U.S. Nuclear Regulatory
Commission (NRC, the Commission),
now or hereafter in effect. The Dresden
facility consists of two boiling-water
reactors located in Grundy County,
Illinois.
By letter dated September 2, 2020
(Agencywide Documents Access and
Management System (ADAMS)
Accession No. ML20246G627), Exelon
provided formal notification to the NRC
pursuant to Title 10 of the Code of
Federal Regulations (10 CFR) Sections
50.82(a)(1)(i) and 50.4(b)(8) of the
intention to permanently cease power
operations at Dresden on or before
November 30, 2021.
In accordance with 10 CFR
50.82(a)(1)(i)–(ii) and 50.82(a)(2), the 10
CFR part 50 licenses for the facility will
no longer authorize reactor operation or
emplacement or retention of fuel in the
reactor vessel after certifications of
permanent cessation of operations and
permanent removal of fuel from the
reactor vessel are docketed for Dresden.
As a result, licensed senior operators
(i.e., individuals licensed under 10 CFR
part 55 to manipulate the controls of a
facility and to direct the licensed
activities of licensed operators) will no
longer be required to support plant
operating activities. Instead, certified
fuel handlers (CFHs) (i.e., non-licensed
operators who have qualified in
accordance with a fuel handler training
program approved by the Commission)
will perform activities associated with
decommissioning, irradiated fuel
handling, and management.
PO 00000
Frm 00063
Fmt 4703
Sfmt 4703
48447
Commission approval of a fuel handler
training program is needed to facilitate
these activities.
By letter dated September 24, 2020
(ADAMS Accession No. ML20269A233),
Exelon submitted a request for
Commission approval of the CFH
Training and Retraining Program for
Dresden and by letter dated August 17,
2021 (ADAMS Accession No.
ML21076A371), the Commission
approved the CFH Training and
Retraining Program. The CFH Training
and Retraining Program is to be used to
satisfy training requirements for the
plant personnel responsible for
supervising and directing the
monitoring, storage, handling, and
cooling of irradiated fuel in a manner
consistent with ensuring the health and
safety of the public. As stated in 10 CFR
50.2, ‘‘Definitions,’’ CFHs are qualified
in accordance with a Commissionapproved training program.
II. Request/Action
The Commission’s regulation at 10
CFR 73.55(p)(1) addresses the
suspension of security measures in an
emergency (10 CFR 73.55(p)(1)(i)) or
during severe weather (10 CFR
73.55(p)(1)(ii)) by stating:
The licensee may suspend implementation
of affected requirements of this section under
the following conditions:
(i) In accordance with §§ 50.54(x) and
50.54(y) of this chapter, the licensee may
suspend any security measures under this
section in an emergency when this action is
immediately needed to protect the public
health and safety and no action consistent
with license conditions and technical
specifications that can provide adequate or
equivalent protection is immediately
apparent. This suspension of security
measures must be approved as a minimum by
a licensed senior operator before taking this
action.
(ii) During severe weather when the
suspension of affected security measures is
immediately needed to protect the personal
health and safety of security force personnel
and no other immediately apparent action
consistent with the license conditions and
technical specifications can provide adequate
or equivalent protection. This suspension of
security measures must be approved, as a
minimum, by a licensed senior operator, with
input from the security supervisor or
manager, before taking this action.
By letter dated September 28, 2020
(ADAMS Accession No. ML20272A212),
Exelon requested an exemption from 10
CFR 73.55(p)(1)(i) and (ii), pursuant to
10 CFR 73.5, ‘‘Specific exemptions.’’
Consistent with 10 CFR 50.54(y), the
proposed exemption would authorize a
CFH, in addition to a licensed senior
operator, to approve the suspension of
security measures in an emergency or
during severe weather at Dresden.
E:\FR\FM\30AUN1.SGM
30AUN1
48448
Federal Register / Vol. 86, No. 165 / Monday, August 30, 2021 / Notices
III. Discussion
The NRC’s security rules have long
recognized the potential need to
suspend security or safeguards measures
under certain conditions. Accordingly,
10 CFR 50.54(x) and (y), first published
in 1983, allow a licensee to take
reasonable actions in an emergency that
depart from license conditions or
technical specifications when those
actions are immediately ‘‘needed to
protect the public health and safety’’
and no actions consistent with license
conditions and technical specifications
that can provide adequate or equivalent
protection are immediately apparent (48
FR 13970; April 1, 1983). This departure
from license conditions or technical
specifications must be approved, as a
minimum, by a licensed senior operator.
In 1986, in its final rule, ‘‘Miscellaneous
Amendments Concerning the Physical
Protection of Nuclear Power Plants’’ (51
FR 27817; August 4, 1986), the
Commission issued 10 CFR 73.55(a),
stating, in part:
In accordance with § 50.54 (x) and (y) of
Part 50, the licensee may suspend any
safeguards measures pursuant to § 73.55 in
an emergency when this action is
immediately needed to protect the public
health and safety and no action consistent
with license conditions and technical
specification that can provide adequate or
equivalent protection is immediately
apparent. This suspension must be approved
as a minimum by a licensed senior operator
prior to taking the action.
khammond on DSKJM1Z7X2PROD with NOTICES
In 1996, the NRC made a number of
regulatory changes to address
decommissioning. One of the changes
was to amend 10 CFR 50.54(x) and (y)
to authorize a non-licensed operator
called a ‘‘certified fuel handler,’’ in
addition to a licensed senior operator, to
approve such protective actions in an
emergency situation at a permanently
shutdown facility. Specifically, in
addressing the role of the CFH during
emergencies, the Commission stated in
the proposed rule, ‘‘Decommissioning of
Nuclear Power Reactors’’ (60 FR 37379;
July 20, 1995):
The Commission is proposing to amend 10
CFR 50.54(y) to permit a certified fuel
handler at nuclear power reactors that have
permanently ceased operations and
permanently removed fuel from the reactor
vessel, subject to the requirements of
§ 50.82(a) and consistent with the proposed
definition of ‘‘Certified Fuel Handler’’
specified in § 50.2, to make these evaluations
and judgments. A nuclear power reactor that
has permanently ceased operations and no
longer has fuel in the reactor vessel does not
require a licensed individual to monitor core
conditions. A certified fuel handler at a
permanently shutdown and defueled nuclear
power reactor undergoing decommissioning
is an individual who has the requisite
VerDate Sep<11>2014
18:40 Aug 27, 2021
Jkt 253001
knowledge and experience to evaluate plant
conditions and make these judgments.
In the final rule (61 FR 39298; July 29,
1996), the NRC added the following
definition to 10 CFR 50.2: ‘‘Certified
fuel handler means, for a nuclear power
reactor facility, a non-licensed operator
who has qualified in accordance with a
fuel handler training program approved
by the Commission.’’ However, the
decommissioning rule did not propose
or make parallel changes to 10 CFR
73.55(a), and did not discuss the role of
a non-licensed CFH at a permanently
shutdown facility.
In the final rule, ‘‘Power Reactor
Security Requirements’’ (74 FR 13926;
March 27, 2009), the NRC relocated the
security suspension requirements from
10 CFR 73.55(a) to 10 CFR 73.55(p)(1)(i)
and (ii). The role of a CFH was not
discussed in the rulemaking; therefore,
the suspension of security measures in
accordance with 10 CFR 73.55(p)
continues to require approval, as a
minimum, by a licensed senior operator,
even for a permanently shutdown
facility.
Under 10 CFR 73.5, the Commission
may, upon application of any interested
person or upon its own initiative, grant
exemptions from the requirements of 10
CFR part 73, as it determines are
authorized by law, will not endanger
life or property or the common defense
and security, and are otherwise in the
public interest. As explained below, the
proposed exemption is authorized by
law, will not endanger life or property
or the common defense and security,
and is otherwise in the public interest.
A. The Exemption Is Authorized by Law
The proposed exemption from 10 CFR
73.55(p)(1)(i) and (ii) would permit, as
a minimum, a CFH, in addition to a
licensed senior operator, to approve the
suspension of security measures in an
emergency or during severe weather at
Dresden when it is permanently
shutdown. Although the exemption is
effective upon receipt, the actions
permitted by the proposed exemption
may not be implemented at Dresden
until the 10 CFR part 50 licenses no
longer authorize operation of the
reactors or emplacement or retention of
fuel in the reactor vessels in accordance
with 10 CFR 50.82(a)(2). The intent of
the proposed exemption is to align these
regulations with 10 CFR 50.54(y) by
using the authority of either a licensed
senior operator or a CFH to approve the
suspension of security measures during
an emergency or during severe weather.
Per 10 CFR 73.5, the NRC is
authorized to grant specific exemptions
from the regulations in 10 CFR part 73,
as are authorized by law. The NRC staff
PO 00000
Frm 00064
Fmt 4703
Sfmt 4703
has determined that granting the
proposed exemption is consistent with
the Atomic Energy Act of 1954, as
amended, and not otherwise
inconsistent with NRC regulations or
other applicable laws. Therefore, the
exemption is authorized by law.
B. The Exemption Will Not Endanger
Life or Property or the Common Defense
and Security
Permitting, as a minimum, a CFH, in
addition to a licensed senior operator, to
approve the suspension of security
measures in an emergency or during
severe weather at Dresden when it is
permanently shutdown will not
endanger life or property or the common
defense and security for the reasons
discussed below.
First, 10 CFR 73.55(p)(2) will
continue to require that ‘‘[s]uspended
security measures must be reinstated as
soon as conditions permit.’’
Second, the suspension of security
measures for non-weather emergencies
under 10 CFR 73.55(p)(1)(i) will
continue to be invoked only ‘‘when this
action is immediately needed to protect
the public health and safety and no
action consistent with license
conditions and technical specifications
that can provide adequate or equivalent
protection is immediately apparent.’’
Thus, the exemption would not prevent
the licensee from meeting the
underlying purpose of 10 CFR
73.55(p)(1)(i) to protect the public
health and safety.
Third, the suspension of security
measures for severe weather under 10
CFR 73.55(p)(1)(ii) will continue to be
used only when ‘‘the suspension of
affected security measures is
immediately needed to protect the
personal health and safety of security
force personnel and no other
immediately apparent action consistent
with the license conditions and
technical specifications can provide
adequate or equivalent protection.’’ The
requirement in 10 CFR 73.55(p)(1)(ii) to
receive input from the security
supervisor or manager will remain.
Therefore, the exemption would not
prevent the licensee from meeting the
underlying purpose of 10 CFR
73.55(p)(1)(ii) to protect the health and
safety of the security force.
Additionally, by letter dated August
17, 2021, the NRC approved the Dresden
CFH Training and Retraining Program.
The NRC staff found that, among other
things, the program addresses the safe
conduct of decommissioning activities,
the safe handling and storage of spent
fuel, and the appropriate response to
plant emergencies. Because a CFH at
Dresden will be sufficiently trained and
E:\FR\FM\30AUN1.SGM
30AUN1
Federal Register / Vol. 86, No. 165 / Monday, August 30, 2021 / Notices
qualified under an NRC-approved
program, the NRC staff considers the
CFH to have sufficient knowledge of
operational and safety concerns, such
that allowing the CFH to suspend
security measures in an emergency or
during severe weather will not result in
undue risk to the public health and
safety.
In addition, since the exemption
allows a CFH the same authority
currently given to the licensed senior
operator under 10 CFR 73.55(p)(1)(i)
and (ii), no change is required to
physical security. Since no change is
required to physical security, the
exemption would not reduce the overall
effectiveness of the Dresden physical
security plan and would not adversely
impact the licensee’s ability to
physically secure the site or protect
special nuclear material at Dresden and,
thus, would not have an effect on the
common defense and security. The NRC
staff has determined that the exemption
would not reduce security measures
currently in place to protect against
radiological sabotage. Instead, the
exemption would align the
requirements of 10 CFR 73.55(p)(1)(i)
and (ii) with the existing requirements
of 10 CFR 50.54(y).
For these reasons, granting the
exemption from the requirements in 10
CFR 73.55(p)(1)(i) and (ii) to permit, as
a minimum, a CFH, in addition to a
licensed senior operator, to approve the
suspension of security measures in an
emergency or during severe weather at
Dresden when it is permanently
shutdown will not endanger life or
property or the common defense and
security.
khammond on DSKJM1Z7X2PROD with NOTICES
C. The Exemption Is Otherwise in the
Public Interest
The proposed exemption would allow
a CFH, in addition to a licensed senior
operator, to approve the suspension of
security measures in an emergency
when ‘‘immediately needed to protect
the public health and safety’’ or during
severe weather when ‘‘immediately
needed to protect the personal health
and safety of security force personnel’’
at Dresden when it is permanently
shutdown. If the exemption is not
granted, Dresden will be required to
have a licensed senior operator available
to approve the suspension of security
measures in an emergency or during
severe weather for a permanently
shutdown plant, even though there
would no longer be an NRC requirement
for Exelon to maintain a licensed senior
operator at Dresden after the
certifications required by 10 CFR
50.82(a)(1)(i) and (ii) are submitted.
VerDate Sep<11>2014
18:40 Aug 27, 2021
Jkt 253001
This proposed exemption is in the
public interest for the following reasons.
Without the exemption there would be
uncertainty regarding how the licensee
would invoke the temporary suspension
of security measures that may be needed
for protecting the public health and
safety or the personal health and safety
of the security force personnel in
emergencies or during severe weather,
given the differences between the
requirements in 10 CFR 73.55(p)(1)(i)
and (ii) and 10 CFR 50.54(y). The
exemption would allow the licensee to
make decisions pursuant to 10 CFR
73.55(p)(1)(i) and (ii) without having to
maintain a staff of licensed senior
operators at a nuclear power reactor that
has permanently ceased operations and
permanently removed fuel from the
reactor vessel. The exemption would
also allow the licensee to have an
established procedure in place to allow
either a licensed senior operator or a
CFH to suspend security measures in an
emergency or during severe weather
after the certifications required by 10
CFR 50.82(a)(1)(i) and (ii) have been
submitted. Finally, the consistent and
efficient regulation of nuclear power
plants serves the public interest and this
exemption would assure consistency
between the regulations in 10 CFR part
73 and 10 CFR 50.54(y) and the
requirements concerning licensed
operators in 10 CFR part 55.
The NRC staff has determined that
granting the proposed exemption would
allow the licensee to designate a CFH
with qualifications appropriate for a
permanently shutdown and defueled
reactor to approve the suspension of
security measures in an emergency to
protect the public health and safety and
during severe weather to protect the
personal health and safety of the
security force personnel. The actions
permitted by the exemption may be
implemented at Dresden when both the
certification of permanent cessation of
operations and the certification of
permanent fuel removal are submitted
in accordance with 10 CFR 50.82(a)(1)(i)
and (ii), which is consistent with the
similar authority provided by 10 CFR
50.54(y). Therefore, the exemption is in
the public interest.
D. Environmental Consideration
The NRC’s approval of the proposed
exemption belongs to a category of
actions that the Commission, by rule or
regulation, has declared to be a
categorical exclusion, after first finding
that the category of actions does not
individually or cumulatively have a
significant effect on the human
environment. Specifically, the NRC’s
approval of the exemption is
PO 00000
Frm 00065
Fmt 4703
Sfmt 4703
48449
categorically excluded from further
environmental analysis under 10 CFR
51.22(c)(25).
Under 10 CFR 51.22(c)(25), the
granting of an exemption from the
requirements of any regulation of
Chapter I to 10 CFR is a categorical
exclusion provided that: (i) There is no
significant hazards consideration; (ii)
there is no significant change in the
types or significant increase in the
amounts of any effluents that may be
released offsite; (iii) there is no
significant increase in individual or
cumulative public or occupational
radiation exposure; (iv) there is no
significant construction impact; (v)
there is no significant increase in the
potential for or consequences from
radiological accidents; and (vi) the
requirements from which the exemption
is sought involve, among others:
Safeguard plans, and materials control
and accounting inventory scheduling
requirements or other requirements of
an administrative, managerial, or
organizational nature. The basis for the
NRC’s determination is provided in the
following evaluation of the
requirements in 10 CFR 51.22(c)(25)(i)–
(vi).
Requirements in 10 CFR 51.22(c)(25)(i)
To qualify for a categorical exclusion
under 10 CFR 51.22(c)(25)(i), the
exemption must involve a no significant
hazards consideration. The criteria for
making a no significant hazards
consideration determination are found
in 10 CFR 50.92(c). The NRC staff has
determined that granting the proposed
exemption involves no significant
hazards consideration because allowing
a CFH, in addition to a licensed senior
operator, to approve the security
suspension at a permanently shutdown
and defueled power plant does not (1)
involve a significant increase in the
probability or consequences of an
accident previously evaluated; or (2)
create the possibility of a new or
different kind of accident from any
accident previously evaluated; or (3)
involve a significant reduction in a
margin of safety. The proposed
exemption is unrelated to any
operational restriction. Therefore, the
requirements of 10 CFR 51.22(c)(25)(i)
are met.
Requirements in 10 CFR 51.22(c)(25)(ii)
and (iii)
The proposed exemption would not
change radioactive effluents or
emissions that affect radiation
exposures to plant workers and
members of the public. Accordingly,
there is no significant change in the
types or significant increase in the
E:\FR\FM\30AUN1.SGM
30AUN1
48450
Federal Register / Vol. 86, No. 165 / Monday, August 30, 2021 / Notices
amounts of any effluents that may be
released offsite and no significant
increase in individual or cumulative
public or occupational radiation
exposure. Therefore, the requirements of
10 CFR 51.22(c)(25)(ii) and (iii) are met.
Requirements in 10 CFR 51.22(c)(25)(iv)
The proposed exemption is not
associated with construction or major
renovations of any buildings or
structures. Therefore, the requirements
of 10 CFR 51.22(c)(25)(iv) are met
because there is no significant
construction impact.
Requirements in 10 CFR 51.22(c)(25)(v)
The proposed exemption does not
concern the source term (i.e., potential
amount of radiation in an accident) or
mitigation. Thus, there is no significant
increase in the potential for or
consequences from radiological
accidents. Therefore, the requirements
of 10 CFR 51.22(c)(25)(v) are met.
Requirements in 10 CFR 51.22(c)(25)(vi)
The proposed exemption is from the
requirement to have a licensed senior
operator approve suspensions of
security measures in an emergency or
during severe weather. Therefore, the
requirement from which the exemption
is sought involves safeguard plans,
materials control, and managerial and
organizational matters and, thus, the
requirements of 10 CFR 51.22(c)(25)(vi)
are met.
khammond on DSKJM1Z7X2PROD with NOTICES
Determination Regarding 10 CFR
51.22(c)(25) Requirements
Based on the above, the NRC staff
determines that the proposed exemption
meets the eligibility criteria for a
categorical exclusion set forth in 10 CFR
51.22(c)(25). Therefore, pursuant to 10
CFR 51.22(b), no environmental impact
statement or environmental assessment
need be prepared in connection with the
approval of the proposed exemption.
IV. Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
73.5, the proposed exemption is
authorized by law, will not endanger
life or property or the common defense
and security, and is otherwise in the
public interest. Therefore, the
Commission hereby grants the licensee’s
request for an exemption from the
requirements of 10 CFR 73.55(p)(1)(i)
and (ii) to allow either a licensed senior
operator or a CFH to approve the
suspension of security measures in an
emergency or during severe weather at
Dresden once the certifications required
under 10 CFR 50.82(a)(1) have been
submitted.
VerDate Sep<11>2014
18:40 Aug 27, 2021
Jkt 253001
The exemption is effective upon
receipt.
Dated: August 23, 2021.
For the Nuclear Regulatory Commission.
Caroline L. Carusone,
Deputy Director, Division of Operating
Reactor Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2021–18600 Filed 8–27–21; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2021–0001]
Sunshine Act Meetings
Weeks of August 30,
September 6, 13, 20, 27, October 4,
2021.
PLACE: Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland and via Teleconference.
STATUS: Public and closed.
MATTERS TO BE CONSIDERED:
TIME AND DATE:
Week of August 30, 2021
Tuesday, August 31, 2021
11:30 a.m. Affirmation Session (Public
Meeting) (Tentative), FirstEnergy
Companies and TMI–2 Solutions, LLC
(Three Mile Island Nuclear Station,
Unit 2), Petition for Reconsideration
of CLI–21–8 (Tentative). (Contact:
Wesley Held: 301–287–3591)
Additional Information: Due to
COVID–19, there will be no physical
public attendance. The public is invited
to attend the Commission’s meeting
live; via teleconference. Details for
joining the teleconference in listen only
mode at https://www.nrc.gov/pmns/mtg.
Week of September 6, 2021—Tentative
There are no meetings scheduled for
the week of September 6, 2021.
Week of September 13, 2021—Tentative
Tuesday, September 14, 2021
10:00 a.m. Briefing on NRC
International Activities (Closed—Ex. 1
& 9)
Week of September 20, 2021—Tentative
There are no meetings scheduled for
the week of September 20, 2021.
Week of September 27, 2021—Tentative
Thursday, September 30, 2021
9:00 a.m. Strategic Programmatic
Overview of the Operating Reactors
and New Reactors Business Lines
(Public Meeting). (Contact: Caty
Nolan: 301–415–1535)
Additional Information: Due to
COVID–19, there will be no physical
PO 00000
Frm 00066
Fmt 4703
Sfmt 4703
public attendance. The public is invited
to attend the Commission’s meeting live
by webcast at the Web address—https://
video.nrc.gov/.
Week of October 4, 2021—Tentative
Tuesday, October 5, 2021
10:00 a.m. Meeting with the Advisory
Committee on the Medical Uses of
Isotopes (Public Meeting). (Contact:
Suzanne Dennis: 301–415–0760)
Additional Information: Due to
COVID–19, there will be no physical
public attendance. The public is invited
to attend the Commission’s meeting live
by webcast at the Web address—https://
video.nrc.gov/.
Friday, October 8, 2021
10:00 a.m. Meeting with the Advisory
Committee on Reactor Safeguards
(Public Meeting). (Contact: Larry
Burkhart: 301–287–3775)
Additional Information: Due to
COVID–19, there will be no physical
public attendance. The public is invited
to attend the Commission’s meeting live
by webcast at the Web address—https://
video.nrc.gov/.
CONTACT PERSON FOR MORE INFORMATION:
For more information or to verify the
status of meetings, contact Wesley Held
at 301–287–3591 or via email at
Wesley.Held@nrc.gov. The schedule for
Commission meetings is subject to
change on short notice.
The NRC Commission Meeting
Schedule can be found on the internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.,
braille, large print), please notify Anne
Silk, NRC Disability Program Specialist,
at 301–287–0745, by videophone at
240–428–3217, or by email at
Anne.Silk@nrc.gov. Determinations on
requests for reasonable accommodation
will be made on a case-by-case basis.
Members of the public may request to
receive this information electronically.
If you would like to be added to the
distribution, please contact the Nuclear
Regulatory Commission, Office of the
Secretary, Washington, DC 20555, at
301–415–1969, or by email at
Wendy.Moore@nrc.gov or
Betty.Thweatt@nrc.gov.
The NRC is holding the meetings
under the authority of the Government
in the Sunshine Act, 5 U.S.C. 552b.
Dated: August 25, 2021.
E:\FR\FM\30AUN1.SGM
30AUN1
Agencies
[Federal Register Volume 86, Number 165 (Monday, August 30, 2021)]
[Notices]
[Pages 48446-48450]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-18600]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-237 and 50-249; NRC-2021-0155]
Exelon Generation Company, LLC, Dresden Nuclear Power Station,
Units 2 and 3
AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an
exemption in response to a September 28, 2020, request from Exelon
Generation Company, LLC. The exemption allows either a licensed senior
operator or a certified fuel handler to approve the emergency
suspension of security measures for Dresden Nuclear Power Station,
Units 2 and 3 during certain emergency
[[Page 48447]]
conditions or during severe weather after both the certification of
permanent cessation of operations and the certification of permanent
fuel removal have been docketed for the facility.
DATES: The exemption was issued on August 23, 2021.
ADDRESSES: Please refer to Docket ID NRC-2021-0155 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0155. Address
questions about Docket IDs in Regulations.gov to Stacy Schumann;
telephone: 301-415-0624; email: [email protected]. For technical
questions, contact the individual listed in the FOR FURTHER INFORMATION
CONTACT section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, contact the NRC's Public Document
Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email
to [email protected]. The ADAMS accession number for each document
referenced (if it is available in ADAMS) is provided the first time
that it is mentioned in this document.
Attention: The PDR, where you may examine and order copies
of public documents, is currently closed. You may submit your request
to the PDR via email at [email protected] or call 1-800-397-4209 or
301-415-4737, between 8:00 a.m. and 4:00 p.m. (ET), Monday through
Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: Joel S. Wiebe, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-6606; email: [email protected].
SUPPLEMENTARY INFORMATION: The text of the exemption is attached.
Dated: August 25, 2021.
For the Nuclear Regulatory Commission.
Joel S. Wiebe,
Senior Project Manager, Plant Licensing Branch III, Division of
Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
Attachment: Exemption
NUCLEAR REGULATORY COMMISSION
Docket Nos. 50-237 and 50-249
Exelon Generation Company, LLC; Dresden Nuclear Power Station, Units 2
and 3
Exemption Related to the Approval Authority for Suspension of Security
Measures in an Emergency or During Severe Weather
I. Background
Exelon Generation Company, LLC (Exelon) is the holder of Renewed
Facility Operating License Nos. DPR-19 and DPR-25 for the Dresden
Nuclear Power Station, Units 2 and 3 (Dresden). The licenses provide,
among other things, that the facility is subject to all applicable
rules, regulations, and orders of the U.S. Nuclear Regulatory
Commission (NRC, the Commission), now or hereafter in effect. The
Dresden facility consists of two boiling-water reactors located in
Grundy County, Illinois.
By letter dated September 2, 2020 (Agencywide Documents Access and
Management System (ADAMS) Accession No. ML20246G627), Exelon provided
formal notification to the NRC pursuant to Title 10 of the Code of
Federal Regulations (10 CFR) Sections 50.82(a)(1)(i) and 50.4(b)(8) of
the intention to permanently cease power operations at Dresden on or
before November 30, 2021.
In accordance with 10 CFR 50.82(a)(1)(i)-(ii) and 50.82(a)(2), the
10 CFR part 50 licenses for the facility will no longer authorize
reactor operation or emplacement or retention of fuel in the reactor
vessel after certifications of permanent cessation of operations and
permanent removal of fuel from the reactor vessel are docketed for
Dresden. As a result, licensed senior operators (i.e., individuals
licensed under 10 CFR part 55 to manipulate the controls of a facility
and to direct the licensed activities of licensed operators) will no
longer be required to support plant operating activities. Instead,
certified fuel handlers (CFHs) (i.e., non-licensed operators who have
qualified in accordance with a fuel handler training program approved
by the Commission) will perform activities associated with
decommissioning, irradiated fuel handling, and management. Commission
approval of a fuel handler training program is needed to facilitate
these activities.
By letter dated September 24, 2020 (ADAMS Accession No.
ML20269A233), Exelon submitted a request for Commission approval of the
CFH Training and Retraining Program for Dresden and by letter dated
August 17, 2021 (ADAMS Accession No. ML21076A371), the Commission
approved the CFH Training and Retraining Program. The CFH Training and
Retraining Program is to be used to satisfy training requirements for
the plant personnel responsible for supervising and directing the
monitoring, storage, handling, and cooling of irradiated fuel in a
manner consistent with ensuring the health and safety of the public. As
stated in 10 CFR 50.2, ``Definitions,'' CFHs are qualified in
accordance with a Commission-approved training program.
II. Request/Action
The Commission's regulation at 10 CFR 73.55(p)(1) addresses the
suspension of security measures in an emergency (10 CFR 73.55(p)(1)(i))
or during severe weather (10 CFR 73.55(p)(1)(ii)) by stating:
The licensee may suspend implementation of affected requirements
of this section under the following conditions:
(i) In accordance with Sec. Sec. 50.54(x) and 50.54(y) of this
chapter, the licensee may suspend any security measures under this
section in an emergency when this action is immediately needed to
protect the public health and safety and no action consistent with
license conditions and technical specifications that can provide
adequate or equivalent protection is immediately apparent. This
suspension of security measures must be approved as a minimum by a
licensed senior operator before taking this action.
(ii) During severe weather when the suspension of affected
security measures is immediately needed to protect the personal
health and safety of security force personnel and no other
immediately apparent action consistent with the license conditions
and technical specifications can provide adequate or equivalent
protection. This suspension of security measures must be approved,
as a minimum, by a licensed senior operator, with input from the
security supervisor or manager, before taking this action.
By letter dated September 28, 2020 (ADAMS Accession No.
ML20272A212), Exelon requested an exemption from 10 CFR 73.55(p)(1)(i)
and (ii), pursuant to 10 CFR 73.5, ``Specific exemptions.'' Consistent
with 10 CFR 50.54(y), the proposed exemption would authorize a CFH, in
addition to a licensed senior operator, to approve the suspension of
security measures in an emergency or during severe weather at Dresden.
[[Page 48448]]
III. Discussion
The NRC's security rules have long recognized the potential need to
suspend security or safeguards measures under certain conditions.
Accordingly, 10 CFR 50.54(x) and (y), first published in 1983, allow a
licensee to take reasonable actions in an emergency that depart from
license conditions or technical specifications when those actions are
immediately ``needed to protect the public health and safety'' and no
actions consistent with license conditions and technical specifications
that can provide adequate or equivalent protection are immediately
apparent (48 FR 13970; April 1, 1983). This departure from license
conditions or technical specifications must be approved, as a minimum,
by a licensed senior operator. In 1986, in its final rule,
``Miscellaneous Amendments Concerning the Physical Protection of
Nuclear Power Plants'' (51 FR 27817; August 4, 1986), the Commission
issued 10 CFR 73.55(a), stating, in part:
In accordance with Sec. 50.54 (x) and (y) of Part 50, the
licensee may suspend any safeguards measures pursuant to Sec. 73.55
in an emergency when this action is immediately needed to protect
the public health and safety and no action consistent with license
conditions and technical specification that can provide adequate or
equivalent protection is immediately apparent. This suspension must
be approved as a minimum by a licensed senior operator prior to
taking the action.
In 1996, the NRC made a number of regulatory changes to address
decommissioning. One of the changes was to amend 10 CFR 50.54(x) and
(y) to authorize a non-licensed operator called a ``certified fuel
handler,'' in addition to a licensed senior operator, to approve such
protective actions in an emergency situation at a permanently shutdown
facility. Specifically, in addressing the role of the CFH during
emergencies, the Commission stated in the proposed rule,
``Decommissioning of Nuclear Power Reactors'' (60 FR 37379; July 20,
1995):
The Commission is proposing to amend 10 CFR 50.54(y) to permit a
certified fuel handler at nuclear power reactors that have
permanently ceased operations and permanently removed fuel from the
reactor vessel, subject to the requirements of Sec. 50.82(a) and
consistent with the proposed definition of ``Certified Fuel
Handler'' specified in Sec. 50.2, to make these evaluations and
judgments. A nuclear power reactor that has permanently ceased
operations and no longer has fuel in the reactor vessel does not
require a licensed individual to monitor core conditions. A
certified fuel handler at a permanently shutdown and defueled
nuclear power reactor undergoing decommissioning is an individual
who has the requisite knowledge and experience to evaluate plant
conditions and make these judgments.
In the final rule (61 FR 39298; July 29, 1996), the NRC added the
following definition to 10 CFR 50.2: ``Certified fuel handler means,
for a nuclear power reactor facility, a non-licensed operator who has
qualified in accordance with a fuel handler training program approved
by the Commission.'' However, the decommissioning rule did not propose
or make parallel changes to 10 CFR 73.55(a), and did not discuss the
role of a non-licensed CFH at a permanently shutdown facility.
In the final rule, ``Power Reactor Security Requirements'' (74 FR
13926; March 27, 2009), the NRC relocated the security suspension
requirements from 10 CFR 73.55(a) to 10 CFR 73.55(p)(1)(i) and (ii).
The role of a CFH was not discussed in the rulemaking; therefore, the
suspension of security measures in accordance with 10 CFR 73.55(p)
continues to require approval, as a minimum, by a licensed senior
operator, even for a permanently shutdown facility.
Under 10 CFR 73.5, the Commission may, upon application of any
interested person or upon its own initiative, grant exemptions from the
requirements of 10 CFR part 73, as it determines are authorized by law,
will not endanger life or property or the common defense and security,
and are otherwise in the public interest. As explained below, the
proposed exemption is authorized by law, will not endanger life or
property or the common defense and security, and is otherwise in the
public interest.
A. The Exemption Is Authorized by Law
The proposed exemption from 10 CFR 73.55(p)(1)(i) and (ii) would
permit, as a minimum, a CFH, in addition to a licensed senior operator,
to approve the suspension of security measures in an emergency or
during severe weather at Dresden when it is permanently shutdown.
Although the exemption is effective upon receipt, the actions permitted
by the proposed exemption may not be implemented at Dresden until the
10 CFR part 50 licenses no longer authorize operation of the reactors
or emplacement or retention of fuel in the reactor vessels in
accordance with 10 CFR 50.82(a)(2). The intent of the proposed
exemption is to align these regulations with 10 CFR 50.54(y) by using
the authority of either a licensed senior operator or a CFH to approve
the suspension of security measures during an emergency or during
severe weather.
Per 10 CFR 73.5, the NRC is authorized to grant specific exemptions
from the regulations in 10 CFR part 73, as are authorized by law. The
NRC staff has determined that granting the proposed exemption is
consistent with the Atomic Energy Act of 1954, as amended, and not
otherwise inconsistent with NRC regulations or other applicable laws.
Therefore, the exemption is authorized by law.
B. The Exemption Will Not Endanger Life or Property or the Common
Defense and Security
Permitting, as a minimum, a CFH, in addition to a licensed senior
operator, to approve the suspension of security measures in an
emergency or during severe weather at Dresden when it is permanently
shutdown will not endanger life or property or the common defense and
security for the reasons discussed below.
First, 10 CFR 73.55(p)(2) will continue to require that
``[s]uspended security measures must be reinstated as soon as
conditions permit.''
Second, the suspension of security measures for non-weather
emergencies under 10 CFR 73.55(p)(1)(i) will continue to be invoked
only ``when this action is immediately needed to protect the public
health and safety and no action consistent with license conditions and
technical specifications that can provide adequate or equivalent
protection is immediately apparent.'' Thus, the exemption would not
prevent the licensee from meeting the underlying purpose of 10 CFR
73.55(p)(1)(i) to protect the public health and safety.
Third, the suspension of security measures for severe weather under
10 CFR 73.55(p)(1)(ii) will continue to be used only when ``the
suspension of affected security measures is immediately needed to
protect the personal health and safety of security force personnel and
no other immediately apparent action consistent with the license
conditions and technical specifications can provide adequate or
equivalent protection.'' The requirement in 10 CFR 73.55(p)(1)(ii) to
receive input from the security supervisor or manager will remain.
Therefore, the exemption would not prevent the licensee from meeting
the underlying purpose of 10 CFR 73.55(p)(1)(ii) to protect the health
and safety of the security force.
Additionally, by letter dated August 17, 2021, the NRC approved the
Dresden CFH Training and Retraining Program. The NRC staff found that,
among other things, the program addresses the safe conduct of
decommissioning activities, the safe handling and storage of spent
fuel, and the appropriate response to plant emergencies. Because a CFH
at Dresden will be sufficiently trained and
[[Page 48449]]
qualified under an NRC-approved program, the NRC staff considers the
CFH to have sufficient knowledge of operational and safety concerns,
such that allowing the CFH to suspend security measures in an emergency
or during severe weather will not result in undue risk to the public
health and safety.
In addition, since the exemption allows a CFH the same authority
currently given to the licensed senior operator under 10 CFR
73.55(p)(1)(i) and (ii), no change is required to physical security.
Since no change is required to physical security, the exemption would
not reduce the overall effectiveness of the Dresden physical security
plan and would not adversely impact the licensee's ability to
physically secure the site or protect special nuclear material at
Dresden and, thus, would not have an effect on the common defense and
security. The NRC staff has determined that the exemption would not
reduce security measures currently in place to protect against
radiological sabotage. Instead, the exemption would align the
requirements of 10 CFR 73.55(p)(1)(i) and (ii) with the existing
requirements of 10 CFR 50.54(y).
For these reasons, granting the exemption from the requirements in
10 CFR 73.55(p)(1)(i) and (ii) to permit, as a minimum, a CFH, in
addition to a licensed senior operator, to approve the suspension of
security measures in an emergency or during severe weather at Dresden
when it is permanently shutdown will not endanger life or property or
the common defense and security.
C. The Exemption Is Otherwise in the Public Interest
The proposed exemption would allow a CFH, in addition to a licensed
senior operator, to approve the suspension of security measures in an
emergency when ``immediately needed to protect the public health and
safety'' or during severe weather when ``immediately needed to protect
the personal health and safety of security force personnel'' at Dresden
when it is permanently shutdown. If the exemption is not granted,
Dresden will be required to have a licensed senior operator available
to approve the suspension of security measures in an emergency or
during severe weather for a permanently shutdown plant, even though
there would no longer be an NRC requirement for Exelon to maintain a
licensed senior operator at Dresden after the certifications required
by 10 CFR 50.82(a)(1)(i) and (ii) are submitted.
This proposed exemption is in the public interest for the following
reasons. Without the exemption there would be uncertainty regarding how
the licensee would invoke the temporary suspension of security measures
that may be needed for protecting the public health and safety or the
personal health and safety of the security force personnel in
emergencies or during severe weather, given the differences between the
requirements in 10 CFR 73.55(p)(1)(i) and (ii) and 10 CFR 50.54(y). The
exemption would allow the licensee to make decisions pursuant to 10 CFR
73.55(p)(1)(i) and (ii) without having to maintain a staff of licensed
senior operators at a nuclear power reactor that has permanently ceased
operations and permanently removed fuel from the reactor vessel. The
exemption would also allow the licensee to have an established
procedure in place to allow either a licensed senior operator or a CFH
to suspend security measures in an emergency or during severe weather
after the certifications required by 10 CFR 50.82(a)(1)(i) and (ii)
have been submitted. Finally, the consistent and efficient regulation
of nuclear power plants serves the public interest and this exemption
would assure consistency between the regulations in 10 CFR part 73 and
10 CFR 50.54(y) and the requirements concerning licensed operators in
10 CFR part 55.
The NRC staff has determined that granting the proposed exemption
would allow the licensee to designate a CFH with qualifications
appropriate for a permanently shutdown and defueled reactor to approve
the suspension of security measures in an emergency to protect the
public health and safety and during severe weather to protect the
personal health and safety of the security force personnel. The actions
permitted by the exemption may be implemented at Dresden when both the
certification of permanent cessation of operations and the
certification of permanent fuel removal are submitted in accordance
with 10 CFR 50.82(a)(1)(i) and (ii), which is consistent with the
similar authority provided by 10 CFR 50.54(y). Therefore, the exemption
is in the public interest.
D. Environmental Consideration
The NRC's approval of the proposed exemption belongs to a category
of actions that the Commission, by rule or regulation, has declared to
be a categorical exclusion, after first finding that the category of
actions does not individually or cumulatively have a significant effect
on the human environment. Specifically, the NRC's approval of the
exemption is categorically excluded from further environmental analysis
under 10 CFR 51.22(c)(25).
Under 10 CFR 51.22(c)(25), the granting of an exemption from the
requirements of any regulation of Chapter I to 10 CFR is a categorical
exclusion provided that: (i) There is no significant hazards
consideration; (ii) there is no significant change in the types or
significant increase in the amounts of any effluents that may be
released offsite; (iii) there is no significant increase in individual
or cumulative public or occupational radiation exposure; (iv) there is
no significant construction impact; (v) there is no significant
increase in the potential for or consequences from radiological
accidents; and (vi) the requirements from which the exemption is sought
involve, among others: Safeguard plans, and materials control and
accounting inventory scheduling requirements or other requirements of
an administrative, managerial, or organizational nature. The basis for
the NRC's determination is provided in the following evaluation of the
requirements in 10 CFR 51.22(c)(25)(i)-(vi).
Requirements in 10 CFR 51.22(c)(25)(i)
To qualify for a categorical exclusion under 10 CFR
51.22(c)(25)(i), the exemption must involve a no significant hazards
consideration. The criteria for making a no significant hazards
consideration determination are found in 10 CFR 50.92(c). The NRC staff
has determined that granting the proposed exemption involves no
significant hazards consideration because allowing a CFH, in addition
to a licensed senior operator, to approve the security suspension at a
permanently shutdown and defueled power plant does not (1) involve a
significant increase in the probability or consequences of an accident
previously evaluated; or (2) create the possibility of a new or
different kind of accident from any accident previously evaluated; or
(3) involve a significant reduction in a margin of safety. The proposed
exemption is unrelated to any operational restriction. Therefore, the
requirements of 10 CFR 51.22(c)(25)(i) are met.
Requirements in 10 CFR 51.22(c)(25)(ii) and (iii)
The proposed exemption would not change radioactive effluents or
emissions that affect radiation exposures to plant workers and members
of the public. Accordingly, there is no significant change in the types
or significant increase in the
[[Page 48450]]
amounts of any effluents that may be released offsite and no
significant increase in individual or cumulative public or occupational
radiation exposure. Therefore, the requirements of 10 CFR
51.22(c)(25)(ii) and (iii) are met.
Requirements in 10 CFR 51.22(c)(25)(iv)
The proposed exemption is not associated with construction or major
renovations of any buildings or structures. Therefore, the requirements
of 10 CFR 51.22(c)(25)(iv) are met because there is no significant
construction impact.
Requirements in 10 CFR 51.22(c)(25)(v)
The proposed exemption does not concern the source term (i.e.,
potential amount of radiation in an accident) or mitigation. Thus,
there is no significant increase in the potential for or consequences
from radiological accidents. Therefore, the requirements of 10 CFR
51.22(c)(25)(v) are met.
Requirements in 10 CFR 51.22(c)(25)(vi)
The proposed exemption is from the requirement to have a licensed
senior operator approve suspensions of security measures in an
emergency or during severe weather. Therefore, the requirement from
which the exemption is sought involves safeguard plans, materials
control, and managerial and organizational matters and, thus, the
requirements of 10 CFR 51.22(c)(25)(vi) are met.
Determination Regarding 10 CFR 51.22(c)(25) Requirements
Based on the above, the NRC staff determines that the proposed
exemption meets the eligibility criteria for a categorical exclusion
set forth in 10 CFR 51.22(c)(25). Therefore, pursuant to 10 CFR
51.22(b), no environmental impact statement or environmental assessment
need be prepared in connection with the approval of the proposed
exemption.
IV. Conclusion
Accordingly, the Commission has determined that, pursuant to 10 CFR
73.5, the proposed exemption is authorized by law, will not endanger
life or property or the common defense and security, and is otherwise
in the public interest. Therefore, the Commission hereby grants the
licensee's request for an exemption from the requirements of 10 CFR
73.55(p)(1)(i) and (ii) to allow either a licensed senior operator or a
CFH to approve the suspension of security measures in an emergency or
during severe weather at Dresden once the certifications required under
10 CFR 50.82(a)(1) have been submitted.
The exemption is effective upon receipt.
Dated: August 23, 2021.
For the Nuclear Regulatory Commission.
Caroline L. Carusone,
Deputy Director, Division of Operating Reactor Licensing, Office of
Nuclear Reactor Regulation.
[FR Doc. 2021-18600 Filed 8-27-21; 8:45 am]