Village of Highland Falls High-Point Utility, LDC; Notice of Existing Licensee's Failure To File a Notice of Intent To File a Subsequent License Application, and Soliciting; Notices of Intent To File a License Application and Pre-Application Documents, 44010 [2021-17136]
Download as PDF
44010
Federal Register / Vol. 86, No. 152 / Wednesday, August 11, 2021 / Notices
Issue Scoping Document 2—March 2022
Issue Notice of Ready for Environmental
Analysis—March 2022
q. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: August 5, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–17137 Filed 8–10–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 7656–000]
jbell on DSKJLSW7X2PROD with NOTICES
Village of Highland Falls High-Point
Utility, LDC; Notice of Existing
Licensee’s Failure To File a Notice of
Intent To File a Subsequent License
Application, and Soliciting; Notices of
Intent To File a License Application
and Pre-Application Documents
The current license for Buttermilk
Falls Hydroelectric Project No. 7656
(Buttermilk Falls Project) was issued to
the original licensee, John A. Dodson,
on June 24, 1986, for a term of 40 years,
ending May 31, 2026.1 The project
became non-operational in 2012 due to
damage caused by Hurricanes Sandy
and Irene, and has remained nonoperational since. The license was
transferred to the current licensee,
Village of Highland Falls High-Point
Utility, LDC (High-Point Utility) on
September 21, 2017.2 The 75-kilowatt
(kW) project is located on Buttermilk
Falls Brook, a tributary of the Hudson
River, in Orange County, New York.
The principal project works consist
of: (1) An 18-inch-high, 15-foot-long
dam; (2) an 18-inch-diameter, 400-footlong PVC penstock; (3) a powerhouse
containing one 55-kW and one 20-kW
generating unit, for a total of installed
generating capacity of 75-kW; (4) two
480-volt generator leads; (5) a 300-footlong, 480-volt transmission line; and (6)
a 0.48/13.6-kilovolt cable connecting the
transformer to the area distribution
system.
At least five years before the
expiration of a license for a minor water
power project in which sections 14 and
15 of the Federal Power Act were
waived, the Commission’s regulations
require the licensee to file with the
Commission a notice of intent (NOI) that
1 See
John A. Dodson, 35 FERC ¶ 62,532 (1986).
John A. Dodson, Village of Highland Falls
High-Point Utility, LDC, 160 FERC ¶ 62,239 (2017).
2 See
VerDate Sep<11>2014
23:05 Aug 10, 2021
Jkt 253001
contains an unequivocal statement of
the licensee’s intention to file or not to
file an application for a subsequent
license, details on the principal project
works and installed plant capacity, and
other information.3
If such a licensee does not inform the
Commission that it intends to file an
application for, in this case, a
subsequent license for the project, the
licensee may not file an application for
a subsequent license, either individually
or in conjunction with an entity or
entities that are not currently licensees
of the project.4
Because the current license expires on
May 31, 2026, the NOI was due to be
filed no later than the close of business
on May 31, 2021.5 High-Point Utility,
the current licensee for the Buttermilk
Falls Project, failed to file an NOI by
this date.6
Any party interested in filing a license
application for the Buttermilk Falls
Project No. 7656 must first file a NOI 7
and pre-application document (PAD) 8
pursuant to Part 5 of the Commission’s
regulations. Although the integrated
licensing process is the default prefiling process, section 5.3(b) of the
Commission’s regulations allows a
potential license applicant to request to
use alternative licensing procedures
when it files its NOI.9
This notice sets a deadline of 120
days from the date of this notice for
interested applicants, other than the
existing licensee, to file NOIs, PADs,
and requests to use an alternative
licensing process.
Applications for a subsequent license
from potential (non-licensee) applicants
must be filed with the Commission at
3 18 CFR 16.19(b) (2020) (citing 18 CFR 16.6(b)).
Section 16.19(b) applies to licenses not subject to
Parts 14 and 15 of the Federal Power Act.
4 18 CFR 16.24(b) (2020).
5 The Commission’s Rules of Practice and
Procedure provide that if a filing deadline falls on
a Saturday, Sunday, holiday, or other day when the
Commission is closed for business, the filing
deadline does not end until the close of business
on the next business day. 18 CFR 2007(a)(2) (2020).
Because the deadline to file the NOI fell on a federal
holiday (i.e., Memorial Day), the filing deadline was
extended until the close of business on Tuesday,
June 1, 2021.
6 On June 23, 2021, High-Point Utility filed a
letter indicating that it intended to proceed with
relicensing for the Buttermilk Falls Hydroelectric
Project No. 7656, however, the filing was not in
conformance with the noticing requirements of
section 5.5 of the Commission’s regulations,
because among other things, it did not identify the
principle project works and it did not include the
names and mailing addresses of nearby
municipalities, counties, political subdivisions, or
affected Indian tribes. It also did not include a preapplication document as required by section 5.6 of
the regulations.
7 18 CFR 5.5 (2020).
8 18 CFR 5.6 (2020).
9 18 CFR 5.3(b) (2020).
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
least 24 months prior to the expiration
of the current license.10 Because the
current license expires on May 31, 2026,
applications for license for this project
must be filed by May 31, 2024.11
Questions concerning this notice
should be directed to Samantha Pollak
at (202) 502–6419 or samantha.pollak@
ferc.gov.
Dated: August 5, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–17136 Filed 8–10–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. IC21–36–000]
Commission Information Collection
Activities (FERC–725G1 and FERC–
725G4); Consolidated Comment
Request; Extension
Federal Energy Regulatory
Commission, DOE.
ACTION: Notice of information
collections and request for comments.
AGENCY:
In compliance with the
requirements of the Paperwork
Reduction Act of 1995, the Federal
Energy Regulatory Commission
(Commission or FERC) is soliciting
public comment on the currently
approved information collections,
FERC–725G1 (Mandatory Reliability
Standards for the Bulk-Power System:
Reliability Standard PRC–004–6) and
FERC–725G4 (Mandatory Reliability
Standards: Reliability Standard PRC–
010–2 (Undervoltage Load Shedding)).
DATES: Comments on the collections of
information are due October 12, 2021.
ADDRESSES: You may submit your
comments (identified by Docket No.
IC21–36–000) on FERC–725G1 and/or
FERC–725G4 by one of the following
methods:
Electronic filing through https://
www.ferc.gov is preferred.
• Electronic Filing: Documents must
be filed in acceptable native
applications and print-to-PDF, but not
in scanned or picture format.
• For those unable to file
electronically, comments may be filed
by USPS mail or by hand (including
courier) delivery:
SUMMARY:
10 18
CFR 16.20 (2020).
the extent an interested applicant files an
NOI and PAD and elects or is required to use the
Commission’s ILP, a process plan will be issued
within 180 days of this notice, which accelerates
the steps of the ILP to allow for filing a subsequent
license application by the May 31, 2024 deadline.
11 To
E:\FR\FM\11AUN1.SGM
11AUN1
Agencies
[Federal Register Volume 86, Number 152 (Wednesday, August 11, 2021)]
[Notices]
[Page 44010]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-17136]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 7656-000]
Village of Highland Falls High-Point Utility, LDC; Notice of
Existing Licensee's Failure To File a Notice of Intent To File a
Subsequent License Application, and Soliciting; Notices of Intent To
File a License Application and Pre-Application Documents
The current license for Buttermilk Falls Hydroelectric Project No.
7656 (Buttermilk Falls Project) was issued to the original licensee,
John A. Dodson, on June 24, 1986, for a term of 40 years, ending May
31, 2026.\1\ The project became non-operational in 2012 due to damage
caused by Hurricanes Sandy and Irene, and has remained non-operational
since. The license was transferred to the current licensee, Village of
Highland Falls High-Point Utility, LDC (High-Point Utility) on
September 21, 2017.\2\ The 75-kilowatt (kW) project is located on
Buttermilk Falls Brook, a tributary of the Hudson River, in Orange
County, New York.
---------------------------------------------------------------------------
\1\ See John A. Dodson, 35 FERC ] 62,532 (1986).
\2\ See John A. Dodson, Village of Highland Falls High-Point
Utility, LDC, 160 FERC ] 62,239 (2017).
---------------------------------------------------------------------------
The principal project works consist of: (1) An 18-inch-high, 15-
foot-long dam; (2) an 18-inch-diameter, 400-foot-long PVC penstock; (3)
a powerhouse containing one 55-kW and one 20-kW generating unit, for a
total of installed generating capacity of 75-kW; (4) two 480-volt
generator leads; (5) a 300-foot-long, 480-volt transmission line; and
(6) a 0.48/13.6-kilovolt cable connecting the transformer to the area
distribution system.
At least five years before the expiration of a license for a minor
water power project in which sections 14 and 15 of the Federal Power
Act were waived, the Commission's regulations require the licensee to
file with the Commission a notice of intent (NOI) that contains an
unequivocal statement of the licensee's intention to file or not to
file an application for a subsequent license, details on the principal
project works and installed plant capacity, and other information.\3\
---------------------------------------------------------------------------
\3\ 18 CFR 16.19(b) (2020) (citing 18 CFR 16.6(b)). Section
16.19(b) applies to licenses not subject to Parts 14 and 15 of the
Federal Power Act.
---------------------------------------------------------------------------
If such a licensee does not inform the Commission that it intends
to file an application for, in this case, a subsequent license for the
project, the licensee may not file an application for a subsequent
license, either individually or in conjunction with an entity or
entities that are not currently licensees of the project.\4\
---------------------------------------------------------------------------
\4\ 18 CFR 16.24(b) (2020).
---------------------------------------------------------------------------
Because the current license expires on May 31, 2026, the NOI was
due to be filed no later than the close of business on May 31, 2021.\5\
High-Point Utility, the current licensee for the Buttermilk Falls
Project, failed to file an NOI by this date.\6\
---------------------------------------------------------------------------
\5\ The Commission's Rules of Practice and Procedure provide
that if a filing deadline falls on a Saturday, Sunday, holiday, or
other day when the Commission is closed for business, the filing
deadline does not end until the close of business on the next
business day. 18 CFR 2007(a)(2) (2020). Because the deadline to file
the NOI fell on a federal holiday (i.e., Memorial Day), the filing
deadline was extended until the close of business on Tuesday, June
1, 2021.
\6\ On June 23, 2021, High-Point Utility filed a letter
indicating that it intended to proceed with relicensing for the
Buttermilk Falls Hydroelectric Project No. 7656, however, the filing
was not in conformance with the noticing requirements of section 5.5
of the Commission's regulations, because among other things, it did
not identify the principle project works and it did not include the
names and mailing addresses of nearby municipalities, counties,
political subdivisions, or affected Indian tribes. It also did not
include a pre-application document as required by section 5.6 of the
regulations.
---------------------------------------------------------------------------
Any party interested in filing a license application for the
Buttermilk Falls Project No. 7656 must first file a NOI \7\ and pre-
application document (PAD) \8\ pursuant to Part 5 of the Commission's
regulations. Although the integrated licensing process is the default
pre-filing process, section 5.3(b) of the Commission's regulations
allows a potential license applicant to request to use alternative
licensing procedures when it files its NOI.\9\
---------------------------------------------------------------------------
\7\ 18 CFR 5.5 (2020).
\8\ 18 CFR 5.6 (2020).
\9\ 18 CFR 5.3(b) (2020).
---------------------------------------------------------------------------
This notice sets a deadline of 120 days from the date of this
notice for interested applicants, other than the existing licensee, to
file NOIs, PADs, and requests to use an alternative licensing process.
Applications for a subsequent license from potential (non-licensee)
applicants must be filed with the Commission at least 24 months prior
to the expiration of the current license.\10\ Because the current
license expires on May 31, 2026, applications for license for this
project must be filed by May 31, 2024.\11\
---------------------------------------------------------------------------
\10\ 18 CFR 16.20 (2020).
\11\ To the extent an interested applicant files an NOI and PAD
and elects or is required to use the Commission's ILP, a process
plan will be issued within 180 days of this notice, which
accelerates the steps of the ILP to allow for filing a subsequent
license application by the May 31, 2024 deadline.
---------------------------------------------------------------------------
Questions concerning this notice should be directed to Samantha
Pollak at (202) 502-6419 or [email protected].
Dated: August 5, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-17136 Filed 8-10-21; 8:45 am]
BILLING CODE 6717-01-P