Alabama Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 42820 [2021-16730]

Download as PDF 42820 Federal Register / Vol. 86, No. 148 / Thursday, August 5, 2021 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2146–260] khammond on DSKJM1Z7X2PROD with NOTICES Alabama Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Non-Capacity Amendment of License. b. Project No: P–2146–260. c. Date Filed: July 2, 2021. d. Applicant: Alabama Power Company (Alabama Power). e. Name of Project: Coosa River Project. f. Location: The project is located on the Coosa River, in Coosa, Chilton, Talladega and Shelby counties, Alabama. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Alan L. Peeples, Alabama Power Company, 600 North 18th Street, P.O. Box 2641, Birmingham, AL 35291–8180, (205) 257–1401. i. FERC Contact: Zeena Aljibury, (202) 502–6065, zeena.aljibury@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests is 30 days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, or recommendations using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include the docket number P–2146–260. Comments VerDate Sep<11>2014 17:07 Aug 04, 2021 Jkt 253001 emailed to Commission staff are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency k. Description of Request: Alabama Power requests approval to modify Unit 6 at the Lay Development to address significant maintenance needs and to improve power and efficiency. The proposed scope of work for Unit 6 includes complete turbine replacement, wicket gate replacement, wicket gate stem bushings installation, turbine, and generator bearing upgrades, and related component replacement. Alabama Power states the turbine replacement is not expected to result in an increase to the total rated capacity or the maximum discharge of the unit at rated conditions. Alabama Power notes that project operations will not change, and refurbishment will not include any structural changes to the project facilities. l. Locations of the Application: The Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s website at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. Agencies may obtain copies of the application directly from the applicant. At this time, the Commission has suspended access to the Commission’s Public Reference Room due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll free, (866) 208–3676 or TTY, (202) 502–8659. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: July 30, 2021. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2021–16730 Filed 8–4–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–467–000] Texas Gas Transmission, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Henderson County Expansion Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental document that will discuss the environmental impacts of the Henderson County Expansion Project involving construction and operation of facilities by Texas Gas Transmission, LLC (Texas Gas) in Henderson and Webster Counties, E:\FR\FM\05AUN1.SGM 05AUN1

Agencies

[Federal Register Volume 86, Number 148 (Thursday, August 5, 2021)]
[Notices]
[Page 42820]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-16730]



[[Page 42820]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2146-260]


Alabama Power Company; Notice of Application Accepted for Filing 
and Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Non-Capacity Amendment of License.
    b. Project No: P-2146-260.
    c. Date Filed: July 2, 2021.
    d. Applicant: Alabama Power Company (Alabama Power).
    e. Name of Project: Coosa River Project.
    f. Location: The project is located on the Coosa River, in Coosa, 
Chilton, Talladega and Shelby counties, Alabama.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Alan L. Peeples, Alabama Power Company, 600 
North 18th Street, P.O. Box 2641, Birmingham, AL 35291-8180, (205) 257-
1401.
    i. FERC Contact: Zeena Aljibury, (202) 502-6065, 
[email protected].
    j. Deadline for filing comments, motions to intervene, and protests 
is 30 days from the issuance date of this notice by the Commission.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene, protests, comments, or recommendations using the 
Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852. The first page of any filing should include the docket 
number P-2146-260. Comments emailed to Commission staff are not 
considered part of the Commission record.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person whose name appears on the official service 
list for the project. Further, if an intervenor files comments or 
documents with the Commission relating to the merits of an issue that 
may affect the responsibilities of a particular resource agency, they 
must also serve a copy of the document on that resource agency
    k. Description of Request: Alabama Power requests approval to 
modify Unit 6 at the Lay Development to address significant maintenance 
needs and to improve power and efficiency. The proposed scope of work 
for Unit 6 includes complete turbine replacement, wicket gate 
replacement, wicket gate stem bushings installation, turbine, and 
generator bearing upgrades, and related component replacement. Alabama 
Power states the turbine replacement is not expected to result in an 
increase to the total rated capacity or the maximum discharge of the 
unit at rated conditions. Alabama Power notes that project operations 
will not change, and refurbishment will not include any structural 
changes to the project facilities.
    l. Locations of the Application: The Commission provides all 
interested persons an opportunity to view and/or print the contents of 
this document via the internet through the Commission's website at 
https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number 
excluding the last three digits in the docket number field to access 
the document. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and 
issuances related to this or other pending projects. Agencies may 
obtain copies of the application directly from the applicant. At this 
time, the Commission has suspended access to the Commission's Public 
Reference Room due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact the Federal Energy 
Regulatory Commission at [email protected] or call toll free, 
(866) 208-3676 or TTY, (202) 502-8659.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214, respectively. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Filing and Service of Documents: Any filing must (1) bear in all 
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO 
INTERVENE'' as applicable; (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person commenting, protesting or intervening; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis. Any filing made by an intervenor must be accompanied 
by proof of service on all persons listed in the service list prepared 
by the Commission in this proceeding, in accordance with 18 CFR 
385.2010.

    Dated: July 30, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021-16730 Filed 8-4-21; 8:45 am]