Texas Gas Transmission, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Henderson County Expansion Project, 42820-42823 [2021-16687]

Download as PDF 42820 Federal Register / Vol. 86, No. 148 / Thursday, August 5, 2021 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2146–260] khammond on DSKJM1Z7X2PROD with NOTICES Alabama Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Non-Capacity Amendment of License. b. Project No: P–2146–260. c. Date Filed: July 2, 2021. d. Applicant: Alabama Power Company (Alabama Power). e. Name of Project: Coosa River Project. f. Location: The project is located on the Coosa River, in Coosa, Chilton, Talladega and Shelby counties, Alabama. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Alan L. Peeples, Alabama Power Company, 600 North 18th Street, P.O. Box 2641, Birmingham, AL 35291–8180, (205) 257–1401. i. FERC Contact: Zeena Aljibury, (202) 502–6065, zeena.aljibury@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests is 30 days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, or recommendations using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include the docket number P–2146–260. Comments VerDate Sep<11>2014 17:07 Aug 04, 2021 Jkt 253001 emailed to Commission staff are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency k. Description of Request: Alabama Power requests approval to modify Unit 6 at the Lay Development to address significant maintenance needs and to improve power and efficiency. The proposed scope of work for Unit 6 includes complete turbine replacement, wicket gate replacement, wicket gate stem bushings installation, turbine, and generator bearing upgrades, and related component replacement. Alabama Power states the turbine replacement is not expected to result in an increase to the total rated capacity or the maximum discharge of the unit at rated conditions. Alabama Power notes that project operations will not change, and refurbishment will not include any structural changes to the project facilities. l. Locations of the Application: The Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s website at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. Agencies may obtain copies of the application directly from the applicant. At this time, the Commission has suspended access to the Commission’s Public Reference Room due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll free, (866) 208–3676 or TTY, (202) 502–8659. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: July 30, 2021. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2021–16730 Filed 8–4–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–467–000] Texas Gas Transmission, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Henderson County Expansion Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental document that will discuss the environmental impacts of the Henderson County Expansion Project involving construction and operation of facilities by Texas Gas Transmission, LLC (Texas Gas) in Henderson and Webster Counties, E:\FR\FM\05AUN1.SGM 05AUN1 khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 86, No. 148 / Thursday, August 5, 2021 / Notices Kentucky and Posey and Johnson Counties, Indiana. The Commission will use this environmental document in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies regarding the project. As part of the National Environmental Policy Act (NEPA) review process, the Commission takes into account concerns the public may have about proposals and the environmental impacts that could result from its action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. This gathering of public input is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the environmental document on the important environmental issues. Additional information about the Commission’s NEPA process is described below in the NEPA Process and Environmental Document section of this notice. By this notice, the Commission requests public comments on the scope of issues to address in the environmental document. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC on or before 5:00 p.m. Eastern Time on August 30, 2021. Comments may be submitted in written form. Further details on how to submit comments are provided in the Public Participation section of this notice. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the environmental document. Commission staff will consider all written comments during the preparation of the environmental document. If you submitted comments on this project to the Commission before the opening of this docket on June 25, 2021, you will need to file those comments in Docket No. CP21–467–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. VerDate Sep<11>2014 17:07 Aug 04, 2021 Jkt 253001 If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable easement agreement. You are not required to enter into an agreement. However, if the Commission approves the project, the Natural Gas Act conveys the right of eminent domain to the company. Therefore, if you and the company do not reach an easement agreement, the pipeline company could initiate condemnation proceedings in court. In such instances, compensation would be determined by a judge in accordance with state law. The Commission does not subsequently grant, exercise, or oversee the exercise of that eminent domain authority. The courts have exclusive authority to handle eminent domain cases; the Commission has no jurisdiction over these matters. Texas Gas provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ which addresses typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. This fact sheet along with other landowner topics of interest are available for viewing on the FERC website (www.ferc.gov) under the Natural Gas Questions or Landowner Topics link. Public Participation There are three methods you can use to submit your comments to the Commission. Please carefully follow these instructions so that your comments are properly recorded. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208–3676 or FercOnlineSupport@ferc.gov. (1) You can file your comments electronically using the eComment feature, which is located on the Commission’s website (www.ferc.gov) under the link to FERC Online. Using eComment is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to FERC Online. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 42821 you are making; a comment on a particular project is considered a ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the Commission. Be sure to reference the project docket number (CP21–467–000) on your letter. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. Additionally, the Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances and submittals regarding the dockets/projects to which you subscribe. These instant email notifications are the fastest way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. Go to https:// www.ferc.gov/ferc-online/overview to register for eSubscription. Summary of the Proposed Project Texas Gas proposes to construct and operate a new lateral and meter and regulator (M&R) station, upgrade an existing M&R station, and add additional compression to and modify Texas Gas’ existing Slaughters Compressor Station. The Henderson County Expansion Project would provide up to 220 million standard cubic feet of natural gas per day to Southern Indiana Gas and Electric Company d/b/a CenterPoint Energy Indiana South (CenterPoint) at its AB Brown Generating Station in Posey County, Indiana. According to Texas Gas, its project would support CenterPoint’s retirement of four existing coal-fired units and implementation of new intermittent renewable resources (i.e., solar and wind) by providing the reliability of intermittent natural gas service during natural fluctuations in wind and solar availability. The Henderson County Expansion Project would consist of the following facilities: • Henderson County Lateral— Construction of an approximately 24mile-long, 20-inch-diameter natural gas transmission pipeline extending from a new tie-in facility in Henderson County, Kentucky to the new AB Brown M&R Station in Posey County, Indiana. • AB Brown M&R Station and Point of Demarcation Site (Posey County, Indiana)—Construction of a delivery M&R station, receiver facility, and a E:\FR\FM\05AUN1.SGM 05AUN1 42822 Federal Register / Vol. 86, No. 148 / Thursday, August 5, 2021 / Notices 0.08-mile-long, 16-inch-diameter interconnecting pipeline terminating at the new Point of Demarcation Site which would serve as CenterPoint’s tiein for project facilities for its AB Brown Plant. • Slaughters Compressor Station (Webster County, Kentucky)— Installation of a new 4,863-horsepower Solar Centaur 50 turbine compressor unit with piping modifications and other appurtenant facilities, abandonment in place of the existing Compressor Unit 5, and placement on standby of existing Compressor Units 6 and 7. • New ancillary facilities including a main line valve and tie-in facility in Henderson County, Kentucky and upgrades to an existing M&R station in Johnson County, Indiana. The general location of the project facilities is shown in appendix 1.1 Land Requirements for Construction Construction of the proposed facilities would disturb about 402 acres of land for the aboveground facilities and the pipeline. Following construction, Texas Gas would maintain about 152 acres for permanent operation of the project’s facilities; the remaining acreage would be restored and revert to former uses. About 47.5 percent of the proposed pipeline route parallels existing pipeline, utility, or road rights-of-way. NEPA Process and the Environmental Document khammond on DSKJM1Z7X2PROD with NOTICES Any environmental document issued by the Commission will discuss impacts that could occur as a result of the construction and operation of the proposed project under the relevant general resource areas: • Geology and soils; • water resources and wetlands; • vegetation and wildlife; • threatened and endangered species; • cultural resources; • land use; • air quality and noise; and • reliability and safety. Commission staff will also evaluate reasonable alternatives to the proposed project or portions of the project and 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of the appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary.’’ For instructions on connecting to eLibrary, refer to the last page of this notice. At this time, the Commission has suspended access to the Commission’s Public Reference Room due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll free, (886) 208–3676 or TTY (202) 502–8659. VerDate Sep<11>2014 17:07 Aug 04, 2021 Jkt 253001 make recommendations on how to lessen or avoid impacts on the various resource areas. Your comments will help Commission staff identify and focus on the issues that might have an effect on the human environment and potentially eliminate other issues from further study and discussion in the environmental document. Following this scoping period, Commission staff will determine whether to prepare an Environmental Assessment (EA) or an Environmental Impact Statement (EIS). The EA or the EIS will present Commission staff’s independent analysis of the issues. If Commission staff prepares an EA, a Notice of Schedule for the Preparation of an Environmental Assessment will be issued. The EA may be issued for an allotted public comment period. The Commission would consider timely comments on the EA before making its decision regarding the proposed project. If Commission staff prepares an EIS, a Notice of Intent to Prepare an EIS/ Notice of Schedule will be issued, which will open up an additional comment period. Staff would then prepare a draft EIS which would be issued for public comment. Commission staff will consider all timely comments received during the comment period on the draft EIS and revise the document, as necessary, before issuing a final EIS. Any EA or draft and final EIS will be available in electronic format in the public record through eLibrary 2 and the Commission’s natural gas environmental documents web page (https://www.ferc.gov/industries-data/ natural-gas/environment/ environmental-documents). If eSubscribed, you will receive instant email notification when the environmental document is issued. With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the environmental document.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultation Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 2 For instructions on connecting to eLibrary, refer to the last page of this notice. 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Section 1501.8. PO 00000 Frm 00047 Fmt 4703 Sfmt 4703 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office(s), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 The environmental document for this project will document findings on the impacts on historic properties and summarize the status of consultations under section 106. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project and includes a mailing address with their comments. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please complete one of the following steps: (1) Send an email to GasProjectAddressChange@ferc.gov stating your request. You must include the docket number CP21–467–000 in your request. If you are requesting a change to your address, please be sure to include your name and the correct address. If you are requesting to delete your address from the mailing list, please include your name and address as it appeared on this notice. This email address is unable to accept comments. OR (2) Return the attached ‘‘Mailing List Update Form’’ (appendix 2). 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. E:\FR\FM\05AUN1.SGM 05AUN1 Federal Register / Vol. 86, No. 148 / Thursday, August 5, 2021 / Notices Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number in the ‘‘Docket Number’’ field. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Public sessions or site visits will be posted on the Commission’s calendar located at https://www.ferc.gov/newsevents/events along with other related information. Dated: July 29, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–16687 Filed 8–4–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–477–000] khammond on DSKJM1Z7X2PROD with NOTICES Enable Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that on July 22, 2021, Enable Gas Transmission, LLC (Enable), 910 Louisiana Street, Ste. 48040, Houston, Texas 77002, filed in the above referenced docket a prior notice pursuant to sections 157.205, 157.208, and 157.211 of the Federal Energy Regulatory Commission’s regulations under the Natural Gas Act (NGA), and Enable’s blanket certificate issued in Docket Nos. CP82–384–000 and CP82– 384–001, for authorization to construct: (i) The 2.6-mile-long, 8-inch-diameter JM–44 pipeline from Enable’s existing Line J to a new meter station; (ii) the Nucor Meter Station; (iii) the 0.6-milelong, 8-inch-diameter JM–44A pipeline; and (iv) aboveground auxiliary facilities at the tie-in locations on Enable’s existing Line J and Line JM–40 all located in Mississippi County, Arkansas (Nucor Pipeline Project). The project will allow Enable to transport 5,000 dekatherms per day of firm transportation capacity to Nucor Corporation’s Cold Steel Mill (Nucor). VerDate Sep<11>2014 17:07 Aug 04, 2021 Jkt 253001 Enable states that the project is being proposed because they claim that the local distribution company that currently delivers Nucor’s natural gas cannot meet Nucor’s additional volumes requirements. The estimated cost for the project is $3,798,095, all as more fully set forth in the request which is on file with the Commission and open to public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions concerning this application should be directed to Lisa Yoho, Sr. Director Regulatory and FERC Compliance, Enable Gas Transmission, LLC, 910 Louisiana Street, 48th floor, Houston, Texas 77002, by phone: (346) 701–2539, by facsimile: (346) 701–2905, or by email: lisa.yoho@ enablemidstream.com. Public Participation There are three ways to become involved in the Commission’s review of this project: You can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on September 28, 2021. How to file protests, motions to intervene, and comments is explained below. Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,1 any person 2 or the Commission’s staff may file a protest to the request. If CFR 157.205. include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,3 and must be submitted by the protest deadline, which is September 28, 2021. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 4 and the regulations under the NGA 5 by the intervention deadline for the project, which is September 28, 2021. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https:// www.ferc.gov/resources/guides/how-to/ intervene.asp. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A 1 18 2 Persons PO 00000 Frm 00048 Fmt 4703 Sfmt 4703 42823 3 18 CFR 157.205(e). CFR 385.214. 5 18 CFR 157.10. 4 18 E:\FR\FM\05AUN1.SGM 05AUN1

Agencies

[Federal Register Volume 86, Number 148 (Thursday, August 5, 2021)]
[Notices]
[Pages 42820-42823]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-16687]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP21-467-000]


Texas Gas Transmission, LLC; Notice of Scoping Period Requesting 
Comments on Environmental Issues for the Proposed Henderson County 
Expansion Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental document that will discuss 
the environmental impacts of the Henderson County Expansion Project 
involving construction and operation of facilities by Texas Gas 
Transmission, LLC (Texas Gas) in Henderson and Webster Counties,

[[Page 42821]]

Kentucky and Posey and Johnson Counties, Indiana. The Commission will 
use this environmental document in its decision-making process to 
determine whether the project is in the public convenience and 
necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies regarding the project. As part of the National Environmental 
Policy Act (NEPA) review process, the Commission takes into account 
concerns the public may have about proposals and the environmental 
impacts that could result from its action whenever it considers the 
issuance of a Certificate of Public Convenience and Necessity. This 
gathering of public input is referred to as ``scoping.'' The main goal 
of the scoping process is to focus the analysis in the environmental 
document on the important environmental issues. Additional information 
about the Commission's NEPA process is described below in the NEPA 
Process and Environmental Document section of this notice.
    By this notice, the Commission requests public comments on the 
scope of issues to address in the environmental document. To ensure 
that your comments are timely and properly recorded, please submit your 
comments so that the Commission receives them in Washington, DC on or 
before 5:00 p.m. Eastern Time on August 30, 2021. Comments may be 
submitted in written form. Further details on how to submit comments 
are provided in the Public Participation section of this notice.
    Your comments should focus on the potential environmental effects, 
reasonable alternatives, and measures to avoid or lessen environmental 
impacts. Your input will help the Commission staff determine what 
issues they need to evaluate in the environmental document. Commission 
staff will consider all written comments during the preparation of the 
environmental document.
    If you submitted comments on this project to the Commission before 
the opening of this docket on June 25, 2021, you will need to file 
those comments in Docket No. CP21-467-000 to ensure they are considered 
as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable easement agreement. You 
are not required to enter into an agreement. However, if the Commission 
approves the project, the Natural Gas Act conveys the right of eminent 
domain to the company. Therefore, if you and the company do not reach 
an easement agreement, the pipeline company could initiate condemnation 
proceedings in court. In such instances, compensation would be 
determined by a judge in accordance with state law. The Commission does 
not subsequently grant, exercise, or oversee the exercise of that 
eminent domain authority. The courts have exclusive authority to handle 
eminent domain cases; the Commission has no jurisdiction over these 
matters.
    Texas Gas provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?'' which addresses typically asked questions, including 
the use of eminent domain and how to participate in the Commission's 
proceedings. This fact sheet along with other landowner topics of 
interest are available for viewing on the FERC website (www.ferc.gov) 
under the Natural Gas Questions or Landowner Topics link.

Public Participation

    There are three methods you can use to submit your comments to the 
Commission. Please carefully follow these instructions so that your 
comments are properly recorded. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to FERC Online. Using eComment is an easy method for 
submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to FERC Online. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; a comment on a particular project is considered a ``Comment 
on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the Commission. Be sure to reference the project docket number (CP21-
467-000) on your letter. Submissions sent via the U.S. Postal Service 
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, MD 20852.
    Additionally, the Commission offers a free service called 
eSubscription which makes it easy to stay informed of all issuances and 
submittals regarding the dockets/projects to which you subscribe. These 
instant email notifications are the fastest way to receive notification 
and provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.

Summary of the Proposed Project

    Texas Gas proposes to construct and operate a new lateral and meter 
and regulator (M&R) station, upgrade an existing M&R station, and add 
additional compression to and modify Texas Gas' existing Slaughters 
Compressor Station. The Henderson County Expansion Project would 
provide up to 220 million standard cubic feet of natural gas per day to 
Southern Indiana Gas and Electric Company d/b/a CenterPoint Energy 
Indiana South (CenterPoint) at its AB Brown Generating Station in Posey 
County, Indiana. According to Texas Gas, its project would support 
CenterPoint's retirement of four existing coal-fired units and 
implementation of new intermittent renewable resources (i.e., solar and 
wind) by providing the reliability of intermittent natural gas service 
during natural fluctuations in wind and solar availability.
    The Henderson County Expansion Project would consist of the 
following facilities:
     Henderson County Lateral--Construction of an approximately 
24-mile-long, 20-inch-diameter natural gas transmission pipeline 
extending from a new tie-in facility in Henderson County, Kentucky to 
the new AB Brown M&R Station in Posey County, Indiana.
     AB Brown M&R Station and Point of Demarcation Site (Posey 
County, Indiana)--Construction of a delivery M&R station, receiver 
facility, and a

[[Page 42822]]

0.08-mile-long, 16-inch-diameter interconnecting pipeline terminating 
at the new Point of Demarcation Site which would serve as CenterPoint's 
tie-in for project facilities for its AB Brown Plant.
     Slaughters Compressor Station (Webster County, Kentucky)--
Installation of a new 4,863-horsepower Solar Centaur 50 turbine 
compressor unit with piping modifications and other appurtenant 
facilities, abandonment in place of the existing Compressor Unit 5, and 
placement on standby of existing Compressor Units 6 and 7.
     New ancillary facilities including a main line valve and 
tie-in facility in Henderson County, Kentucky and upgrades to an 
existing M&R station in Johnson County, Indiana.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary.'' For instructions on 
connecting to eLibrary, refer to the last page of this notice. At 
this time, the Commission has suspended access to the Commission's 
Public Reference Room due to the proclamation declaring a National 
Emergency concerning the Novel Coronavirus Disease (COVID-19), 
issued by the President on March 13, 2020. For assistance, contact 
FERC at [email protected] or call toll free, (886) 208-3676 
or TTY (202) 502-8659.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 402 
acres of land for the aboveground facilities and the pipeline. 
Following construction, Texas Gas would maintain about 152 acres for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and revert to former uses. About 47.5 percent of the 
proposed pipeline route parallels existing pipeline, utility, or road 
rights-of-way.

NEPA Process and the Environmental Document

    Any environmental document issued by the Commission will discuss 
impacts that could occur as a result of the construction and operation 
of the proposed project under the relevant general resource areas:

 Geology and soils;
 water resources and wetlands;
 vegetation and wildlife;
 threatened and endangered species;
 cultural resources;
 land use;
 air quality and noise; and
 reliability and safety.

    Commission staff will also evaluate reasonable alternatives to the 
proposed project or portions of the project and make recommendations on 
how to lessen or avoid impacts on the various resource areas. Your 
comments will help Commission staff identify and focus on the issues 
that might have an effect on the human environment and potentially 
eliminate other issues from further study and discussion in the 
environmental document.
    Following this scoping period, Commission staff will determine 
whether to prepare an Environmental Assessment (EA) or an Environmental 
Impact Statement (EIS). The EA or the EIS will present Commission 
staff's independent analysis of the issues. If Commission staff 
prepares an EA, a Notice of Schedule for the Preparation of an 
Environmental Assessment will be issued. The EA may be issued for an 
allotted public comment period. The Commission would consider timely 
comments on the EA before making its decision regarding the proposed 
project. If Commission staff prepares an EIS, a Notice of Intent to 
Prepare an EIS/Notice of Schedule will be issued, which will open up an 
additional comment period. Staff would then prepare a draft EIS which 
would be issued for public comment. Commission staff will consider all 
timely comments received during the comment period on the draft EIS and 
revise the document, as necessary, before issuing a final EIS. Any EA 
or draft and final EIS will be available in electronic format in the 
public record through eLibrary \2\ and the Commission's natural gas 
environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you 
will receive instant email notification when the environmental document 
is issued.
---------------------------------------------------------------------------

    \2\ For instructions on connecting to eLibrary, refer to the 
last page of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues of this project to formally cooperate in the 
preparation of the environmental document.\3\ Agencies that would like 
to request cooperating agency status should follow the instructions for 
filing comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Section 1501.8.
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office(s), 
and to solicit their views and those of other government agencies, 
interested Indian tribes, and the public on the project's potential 
effects on historic properties.\4\ The environmental document for this 
project will document findings on the impacts on historic properties 
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project and includes a mailing address with their 
comments. Commission staff will update the environmental mailing list 
as the analysis proceeds to ensure that Commission notices related to 
this environmental review are sent to all individuals, organizations, 
and government entities interested in and/or potentially affected by 
the proposed project.
    If you need to make changes to your name/address, or if you would 
like to remove your name from the mailing list, please complete one of 
the following steps:
    (1) Send an email to [email protected] stating your 
request. You must include the docket number CP21-467-000 in your 
request. If you are requesting a change to your address, please be sure 
to include your name and the correct address. If you are requesting to 
delete your address from the mailing list, please include your name and 
address as it appeared on this notice. This email address is unable to 
accept comments.

OR

    (2) Return the attached ``Mailing List Update Form'' (appendix 2).

[[Page 42823]]

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at www.ferc.gov using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number 
in the ``Docket Number'' field. Be sure you have selected an 
appropriate date range. For assistance, please contact FERC Online 
Support at [email protected] or (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of all formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at https://www.ferc.gov/news-events/events along with 
other related information.

    Dated: July 29, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-16687 Filed 8-4-21; 8:45 am]