separate document. In Order No. 659,4
the Commission modified the reporting
requirements in 18 CFR 294.101(e) to
provide that public utilities must
comply with the requirements to report
shortages and anticipated shortages by
submitting this information
electronically using the Office of
Electric Reliability’s alert system at
emergency@ferc.gov in lieu of
submitting an original and two copies to
the Secretary of the Commission. The
Commission uses the information to
evaluate and formulate an appropriate
option for action in the event an
unanticipated shortage is reported and/
or materializes. Without this
information, the Commission and State
agencies would be unable to:
• Examine and approve or modify
utility actions;
• prepare a response to anticipated
disruptions in electric energy; and/or
• ensure equitable treatment of all
public utility customers under the
shortage situation.
38705
The Commission implements these
filing requirements in the Code of
Federal Regulations (CFR) under 18 CFR
part 294.101.
The 60-day notice 5 published on 5/
06/2021 with no comments received.
Type of Respondents: Public Utilities.
Estimate of Annual Burden: 6 The
Commission estimates the annual public
reporting burden for the information
collection as:
FERC–585 (REPORTING OF ELECTRIC SHORTAGES AND CONTINGENCY PLANS UNDER PURPA SECTION 206)
Number of
respondents
Annual
number of
responses per
respondent
Total number
of responses
Average burden & cost
per response 7
Total annual burden
hours & total annual
cost
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
Contingency plan ......
Capacity Shortage ....
1
1
1
1
1
1
1 hrs.; $83.00 ................
1 hrs.; $83.00 ................
1 hrs.; $83.00 ................
1 hrs.; $83.00 ................
$83.00
83.00
Total ...................
........................
........................
........................
.......................................
2 hrs.; $166.00 ..............
........................
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–15591 Filed 7–21–21; 8:45 am]
BILLING CODE 6717–01–P
lotter on DSK11XQN23PROD with NOTICES1
Cost per
respondent
($)
(5)÷(1)
4 Final Rule in Docket RM05–19–000, issued on
5/27/2005
5 86 FR 20684
6 ‘‘Burden’’ is defined as the total time, effort, or
financial resources expended by persons to
generate, maintain, retain, or disclose or provide
VerDate Sep<11>2014
17:10 Jul 21, 2021
Jkt 253001
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Temporary
variance of license requirement.
b. Project No.: 2310–242.
c. Date Filed: July 2, 2021 and
supplemented on July 14, 2021.
d. Applicant: Pacific Gas and Electric
Company (licensee).
e. Name of Project: Drum-Spaulding
Project.
f. Location: South Yuba River and
Bear River in Placer and Nevada
counties, California.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Michelle
Ocken, License Coordinator, Pacific Gas
and Electric Company, (530) 863–3439.
i. FERC Contact: Robert Ballantine,
(202) 502–6289, robert.ballantine@
ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests is 20
days from the issuance of this notice by
the Commission (August 4, 2021).
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, MD 20852. The first page of
any filing should include docket
number P–2310–242. Comments
emailed to Commission staff are not
information to or for a Federal agency. For further
explanation of what is included in the information
collection burden, refer to 5 Code of Federal
Regulations 1320.3.
7 The estimates for cost per response are derived
using the following formula: Average Burden Hours
per Response * 83.00 per Hour = Average Cost per
Response. This is Based upon FERC’s 2020 FTE
average salary plus benefits. Commission staff
believes that any industry effort applied to FERC–
585 would be compensated similarly to FERC’s
average salary.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2310–242]
Pacific Gas and Electric Company;
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
E:\FR\FM\22JYN1.SGM
22JYN1
lotter on DSK11XQN23PROD with NOTICES1
38706
Federal Register / Vol. 86, No. 138 / Thursday, July 22, 2021 / Notices
considered part of the Commission
record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: Due to
persistent drought conditions, the
licensee requests Commission approval
of a temporary variance of the minimum
flow requirement at streamflow gages
YB–316 (Upper Peak Lower Peak and/or
Kidd Lake), YB–207 (Lake Creek below
Feeley Lake), YB–208 (Carr Lake), and
YB–209 (Rucker Creek below Blue
Lake). The licensee is requesting to
reduce flow at YB–316, to 3 cubic feet
per second (cfs) and that flows at YB–
207, YB–208 and YB–209 be reduced
from license required flows of 0.50 cfs
(target), 0.20 cfs (allowable) to proposed
flows of 0.50 cfs (target), 0.10 cfs
(allowable), measured as a 48-hour
average. As requested, the reduced flow
releases would prevent dewatering of
these reaches. If granted, the variance
would last through October 1, 2021, or
until adequate precipitation occurs to
ensure that inflow equals outflow at the
referenced reservoirs for at least seven
consecutive days, whichever comes
later.
l. Locations of the Application: The
Commission provides all interested
persons an opportunity to view and/or
print the contents of this document via
the internet through the Commission’s
website at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
Agencies may obtain copies of the
application directly from the applicant.
At this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll free, (866) 208–3676 or TTY, (202)
502–8659.
VerDate Sep<11>2014
17:10 Jul 21, 2021
Jkt 253001
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: All filings must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene, or
protests must set forth their evidentiary
basis. A copy of all other filings in
reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with
385.2010.
Dated: July 15, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–15542 Filed 7–21–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD21–4–000]
Billing Procedures for Annual Charges
for the Costs of Other Federal
Agencies for Administering Part I of
the Federal Power Act; Notice
Reporting Costs for Other Federal
Agencies’ Administrative Annual
Charges for Fiscal Year 2020
1. The Federal Energy Regulatory
Commission (Commission) is required
to determine the reasonableness of costs
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
incurred by other Federal agencies
(OFAs) 1 in connection with their
participation in the Commission’s
proceedings under the Federal Power
Act (FPA) Part I 2 when those agencies
seek to include such costs in the
administrative charges licensees must
pay to reimburse the United States for
the cost of administering Part I.3 The
Commission’s Order on Remand and
Acting on Appeals of Annual Charge
Bills 4 determined which costs are
eligible to be included in the
administrative annual charges. This
order also established a process
whereby the Commission would
annually request each OFA to submit
cost data, using a form 5 specifically
designed for this purpose. In addition,
the order established requirements for
detailed cost accounting reports and
other documented analyses to explain
the cost assumptions contained in the
OFAs’ submissions.
2. The Commission has completed its
review of the forms and supporting
documentation submitted by the U.S.
Department of the Interior (Interior), the
U.S. Department of Agriculture
(Agriculture), and the U.S. Department
of Commerce (Commerce) for fiscal year
(FY) 2020. This notice reports the costs
the Commission included in its
administrative annual charges for FY
2021.
Scope of Eligible Costs
3. The basis for eligible costs that
should be included in the OFAs’
administrative annual charges is
prescribed by the Office of Management
and Budget’s (OMB) Circular A–25—
User Charges and the Federal
Accounting Standards Advisory Board’s
Statement of Federal Financial
Accounting Standards (SFFAS) Number
4—Managerial Cost Accounting
Concepts and Standards for the Federal
Government. Circular A–25 establishes
Federal policy regarding fees assessed
for government services and provides
specific information on the scope and
type of activities subject to user charges.
1 The OFAs include: The U.S. Department of the
Interior (Bureau of Indian Affairs, Bureau of Land
Management, Bureau of Reclamation, National Park
Service, U.S. Fish and Wildlife Service, Office of
the Solicitor, Office of Environmental Policy &
Compliance, Office of Hearings and Appeals, and
Office of Policy Analysis); the U.S. Department of
Agriculture (U.S. Forest Service); the U.S.
Department of Commerce (National Marine
Fisheries Service); and the U.S. Army Corps of
Engineers.
2 16 U.S.C. 791a–823d (2018).
3 See id. § 803(e)(1) and 42 U.S.C. 7178 (2018).
4 107 FERC ¶ 61,277, order on reh’g, 109 FERC
¶ 61,040 (2004).
5 Other Federal Agency Cost Submission Form,
available at https://www.ferc.gov/docs-filing/
forms.asp#ofa.
E:\FR\FM\22JYN1.SGM
22JYN1
Agencies
[Federal Register Volume 86, Number 138 (Thursday, July 22, 2021)]
[Notices]
[Pages 38705-38706]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-15542]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2310-242]
Pacific Gas and Electric Company; Notice of Application Accepted
for Filing and Soliciting Comments, Motions To Intervene, and Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Temporary variance of license requirement.
b. Project No.: 2310-242.
c. Date Filed: July 2, 2021 and supplemented on July 14, 2021.
d. Applicant: Pacific Gas and Electric Company (licensee).
e. Name of Project: Drum-Spaulding Project.
f. Location: South Yuba River and Bear River in Placer and Nevada
counties, California.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Michelle Ocken, License Coordinator, Pacific
Gas and Electric Company, (530) 863-3439.
i. FERC Contact: Robert Ballantine, (202) 502-6289,
[email protected].
j. Deadline for filing comments, motions to intervene, and protests
is 20 days from the issuance of this notice by the Commission (August
4, 2021).
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, and protests using the Commission's
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may
submit a paper copy. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, MD 20852. The first page of any filing should
include docket number P-2310-242. Comments emailed to Commission staff
are not
[[Page 38706]]
considered part of the Commission record.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervenor files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency.
k. Description of Request: Due to persistent drought conditions,
the licensee requests Commission approval of a temporary variance of
the minimum flow requirement at streamflow gages YB-316 (Upper Peak
Lower Peak and/or Kidd Lake), YB-207 (Lake Creek below Feeley Lake),
YB-208 (Carr Lake), and YB-209 (Rucker Creek below Blue Lake). The
licensee is requesting to reduce flow at YB-316, to 3 cubic feet per
second (cfs) and that flows at YB-207, YB-208 and YB-209 be reduced
from license required flows of 0.50 cfs (target), 0.20 cfs (allowable)
to proposed flows of 0.50 cfs (target), 0.10 cfs (allowable), measured
as a 48-hour average. As requested, the reduced flow releases would
prevent dewatering of these reaches. If granted, the variance would
last through October 1, 2021, or until adequate precipitation occurs to
ensure that inflow equals outflow at the referenced reservoirs for at
least seven consecutive days, whichever comes later.
l. Locations of the Application: The Commission provides all
interested persons an opportunity to view and/or print the contents of
this document via the internet through the Commission's website at
https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number
excluding the last three digits in the docket number field to access
the document. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and
issuances related to this or other pending projects. Agencies may
obtain copies of the application directly from the applicant. At this
time, the Commission has suspended access to the Commission's Public
Reference Room due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact the Federal Energy
Regulatory Commission at [email protected] or call toll free,
(866) 208-3676 or TTY, (202) 502-8659.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
o. Filing and Service of Responsive Documents: All filings must (1)
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis. A copy of all other filings in reference to this
application must be accompanied by proof of service on all persons
listed in the service list prepared by the Commission in this
proceeding, in accordance with 385.2010.
Dated: July 15, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021-15542 Filed 7-21-21; 8:45 am]