Mad River Power Associates; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 36742-36743 [2021-14843]
Download as PDF
36742
Federal Register / Vol. 86, No. 131 / Tuesday, July 13, 2021 / Notices
jbell on DSKJLSW7X2PROD with NOTICES
Energy Projects granted an extension of
time until September 28, 2020 to
construct the onshore facilities and
make them available for service.
On June 25, 2020, Delphin requested
an extension of time until September 28,
2021 to continue to construct the
onshore facilities. Delphin explains that
it was continuing to work to develop the
Project, however, a variety of factors
complicated the task of negotiating
offtake agreements with potential
customers. Delfin states that on July 15,
2020, via delegated order, the
Commission granted an extension of
time until September 28, 2021 to
construct the onshore facilities and
make them available for service. (2020
Extension)
Delfin states that since the 2020
Extension, it has continued to work to
develop the Project. Additionally, Delfin
asserts that economic conditions are
recovering from the global coronavirus
pandemic, and the spot and short-term
market for the LNG have significantly
improved. Delfin views these
developments as a precursor for an
improved longer-term market, which it
asserts will support long-term LNG
offtake contract(s). Accordingly,
applicants request an extension of time
until September 28, 2022 to complete
construction of the onshore facilities
and place them into service.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Delfin’s request for an
extension of time may do so. No reply
comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).2
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,3 the Commission will aim to
issue an order acting on the request
2 Only motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC ¶ 61,144, at P 39 (2020).
3 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
VerDate Sep<11>2014
17:47 Jul 12, 2021
Jkt 253001
within 45 days.4 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.5 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.6 At the time
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.7 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, The Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and three copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern
Time on, July 22, 2021.
4 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
5 Id. at P 40.
6 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
7 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
Dated: July 7, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–14845 Filed 7–12–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3253–015]
Mad River Power Associates; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 3253–015.
c. Date Filed: November 3, 2020.
d. Applicant: Mad River Power
Associates (MRPA).
e. Name of Project: Campton
Hydroelectric Project (project).
f. Location: On the Mad River in
Grafton County, New Hampshire. The
project occupies approximately 0.05
acre of federal land administered by the
U.S. Forest Service.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Ian Clark,
Mad River Power Associates, 1 Pepsi
Way, Suite 6n75, Katonah, NY 10536;
Phone at (914) 297–7645, or email at
info@dichotomycapital.com.
i. FERC Contact: Amanda Gill, (202)
502–6773 or amanda.gill@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
E:\FR\FM\13JYN1.SGM
13JYN1
36743
jbell on DSKJLSW7X2PROD with NOTICES
Federal Register / Vol. 86, No. 131 / Tuesday, July 13, 2021 / Notices
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. The first page of any filing
should include docket number P–3253–
015.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is ready for environmental analysis
at this time.
The Council on Environmental
Quality (CEQ) issued a final rule on July
15, 2020, revising the regulations under
40 CFR parts 1500–1518 that federal
agencies use to implement the National
Environmental Policy Act (NEPA) (see
Update to the Regulations Implementing
the Procedural Provisions of the
National Environmental Policy Act, 85
FR 43,304). The Final Rule became
effective on and applies to any NEPA
process begun after September 14, 2020.
Commission staff intends to conduct its
NEPA review in accordance with CEQ’s
new regulations.
l. Project Description: The project
consists of: (1) A 22-foot-wide, 24-foothigh concrete intake structure located
approximately 60 feet upstream of the
U.S. Forest Service’s Campton Dam on
the east shoreline of the U.S. Forest
Service’s Campton Pond, that includes a
25-foot-long,13-foot-high trashrack with
1.75-inch clear bar spacing; (2) a 600foot-long, 78-inch-diameter
underground steel penstock that
trifurcates into three 48-inch-diameter
sections measuring 20 feet, 30 feet, and
43 feet in length, respectively; (3) a 43foot-long, 30-foot-wide powerhouse
located on the east side of the Mad River
that contains a 167-kW Francis turbinegenerator unit; (4) two 236-kW
submersible Flygt turbine-generator
units located outside of the powerhouse;
(5) an approximately 55-foot-long, 40foot-wide tailrace; (6) a 200-foot-long
transmission line and a 33.5-kilovolt
transformer that connects the generators
to the electric grid; (7) an Atlantic
salmon smolt bypass facility consisting
VerDate Sep<11>2014
17:47 Jul 12, 2021
Jkt 253001
of an 85-foot-long, 20-inch diameter cast
iron pipe that empties into an 3.5-footdeep plunge pool approximately 15 feet
downstream of the dam; and (8)
appurtenant facilities. The project
creates an approximately 600-foot-long
bypassed reach of the Mad River.
The current license requires: (1)
Inflow to be discharged over the
spillway to the bypassed reach during
periods of non-generation or when
inflow is less than 25 cfs; (2) a
minimum flow of 4.5 cfs through the
Atlantic salmon smolt bypass facility
during periods of generation or when
inflow is greater than 25 cfs; and (3)
operation of the smolt bypass facility
from mid-April to mid-June. The
average annual generation of the project
is currently approximately 1,170
megawatt-hours (MWh).
MRPA proposes to: (1) Continue
operating the project in a run-of-release
mode; (2) replace one of the 236-kW
Flygt turbine-generator units with a new
340-kW Flygt turbine-generator unit, for
a total installed capacity of 743 kW at
the project; (2) release a minimum flow
of 29 cfs or inflow, whichever is less,
over the dam to the bypassed reach; and
(3) close the existing smolt bypass
facility. MRPA estimates that the
average annual generation of the
proposed project will be approximately
1,900 MWh.
m. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
All filings must: (1) Bear in all capital
letters the title ‘‘COMMENTS,’’ ‘‘REPLY
COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and
conditions, or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. Each filing must be
accompanied by proof of service on all
persons listed on the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
You may also register online at
https://www.ferc.gov/ferc-online/
overview to be notified via email of new
filings and issuances related to this or
other pending projects. For assistance,
contact FERC Online Support.
n. The applicant must file no later
than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification. Please note that the
certification request must comply with
40 CFR 121.5(b), including
documentation that a pre-filing meeting
request was submitted to the certifying
authority at least 30 days prior to
submitting the certification request.
Please also note that the certification
request must be sent to the certifying
authority and to the Commission
concurrently.
o. Procedural Schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Milestone
Deadline for filing comments, recommendations, preliminary terms
and conditions, and preliminary fishway prescriptions.
Deadline for filing reply
comments.
Target date
September
2021.
October 2021.
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
Dated: July 7, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–14843 Filed 7–12–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Sunshine Act Meetings
July 15, 2021, 10:00 a.m.
Open to the public via audio
Webcast only. Join FERC online to listen
live at https://ferc.capitolconnection.org/.
STATUS: Open.
MATTERS TO BE CONSIDERED: Agenda.
* Note—Items listed on the agenda
may be deleted without further notice.
This is a list of matters to be
considered by the Commission. It does
TIME AND DATE:
PLACE:
E:\FR\FM\13JYN1.SGM
13JYN1
Agencies
[Federal Register Volume 86, Number 131 (Tuesday, July 13, 2021)]
[Notices]
[Pages 36742-36743]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-14843]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3253-015]
Mad River Power Associates; Notice of Application Ready for
Environmental Analysis and Soliciting Comments, Recommendations, Terms
and Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent Minor License.
b. Project No.: 3253-015.
c. Date Filed: November 3, 2020.
d. Applicant: Mad River Power Associates (MRPA).
e. Name of Project: Campton Hydroelectric Project (project).
f. Location: On the Mad River in Grafton County, New Hampshire. The
project occupies approximately 0.05 acre of federal land administered
by the U.S. Forest Service.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Ian Clark, Mad River Power Associates, 1
Pepsi Way, Suite 6n75, Katonah, NY 10536; Phone at (914) 297-7645, or
email at [email protected].
i. FERC Contact: Amanda Gill, (202) 502-6773 or
[email protected].
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
The Commission strongly encourages electronic filing. Please file
comments, recommendations, terms and conditions, and prescriptions
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://ferconline.ferc.gov/QuickComment.aspx. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a
[[Page 36743]]
paper copy. Submissions sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. The first page of any filing should
include docket number P-3253-015.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is ready for
environmental analysis at this time.
The Council on Environmental Quality (CEQ) issued a final rule on
July 15, 2020, revising the regulations under 40 CFR parts 1500-1518
that federal agencies use to implement the National Environmental
Policy Act (NEPA) (see Update to the Regulations Implementing the
Procedural Provisions of the National Environmental Policy Act, 85 FR
43,304). The Final Rule became effective on and applies to any NEPA
process begun after September 14, 2020. Commission staff intends to
conduct its NEPA review in accordance with CEQ's new regulations.
l. Project Description: The project consists of: (1) A 22-foot-
wide, 24-foot-high concrete intake structure located approximately 60
feet upstream of the U.S. Forest Service's Campton Dam on the east
shoreline of the U.S. Forest Service's Campton Pond, that includes a
25-foot-long,13-foot-high trashrack with 1.75-inch clear bar spacing;
(2) a 600-foot-long, 78-inch-diameter underground steel penstock that
trifurcates into three 48-inch-diameter sections measuring 20 feet, 30
feet, and 43 feet in length, respectively; (3) a 43-foot-long, 30-foot-
wide powerhouse located on the east side of the Mad River that contains
a 167-kW Francis turbine-generator unit; (4) two 236-kW submersible
Flygt turbine-generator units located outside of the powerhouse; (5) an
approximately 55-foot-long, 40-foot-wide tailrace; (6) a 200-foot-long
transmission line and a 33.5-kilovolt transformer that connects the
generators to the electric grid; (7) an Atlantic salmon smolt bypass
facility consisting of an 85-foot-long, 20-inch diameter cast iron pipe
that empties into an 3.5-foot-deep plunge pool approximately 15 feet
downstream of the dam; and (8) appurtenant facilities. The project
creates an approximately 600-foot-long bypassed reach of the Mad River.
The current license requires: (1) Inflow to be discharged over the
spillway to the bypassed reach during periods of non-generation or when
inflow is less than 25 cfs; (2) a minimum flow of 4.5 cfs through the
Atlantic salmon smolt bypass facility during periods of generation or
when inflow is greater than 25 cfs; and (3) operation of the smolt
bypass facility from mid-April to mid-June. The average annual
generation of the project is currently approximately 1,170 megawatt-
hours (MWh).
MRPA proposes to: (1) Continue operating the project in a run-of-
release mode; (2) replace one of the 236-kW Flygt turbine-generator
units with a new 340-kW Flygt turbine-generator unit, for a total
installed capacity of 743 kW at the project; (2) release a minimum flow
of 29 cfs or inflow, whichever is less, over the dam to the bypassed
reach; and (3) close the existing smolt bypass facility. MRPA estimates
that the average annual generation of the proposed project will be
approximately 1,900 MWh.
m. A copy of the application can be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC Online
Support.
All filings must: (1) Bear in all capital letters the title
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions, or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b) and 385.2010.
You may also register online at https://www.ferc.gov/ferc-online/overview to be notified via email of new filings and issuances related
to this or other pending projects. For assistance, contact FERC Online
Support.
n. The applicant must file no later than 60 days following the date
of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification. Please note
that the certification request must comply with 40 CFR 121.5(b),
including documentation that a pre-filing meeting request was submitted
to the certifying authority at least 30 days prior to submitting the
certification request. Please also note that the certification request
must be sent to the certifying authority and to the Commission
concurrently.
o. Procedural Schedule: The application will be processed according
to the following schedule. Revisions to the schedule will be made as
appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Deadline for filing comments, September 2021.
recommendations, preliminary terms and
conditions, and preliminary fishway
prescriptions.
Deadline for filing reply comments..... October 2021.
------------------------------------------------------------------------
p. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
Dated: July 7, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-14843 Filed 7-12-21; 8:45 am]
BILLING CODE 6717-01-P