Mad River Power Associates; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 36742-36743 [2021-14843]

Download as PDF 36742 Federal Register / Vol. 86, No. 131 / Tuesday, July 13, 2021 / Notices jbell on DSKJLSW7X2PROD with NOTICES Energy Projects granted an extension of time until September 28, 2020 to construct the onshore facilities and make them available for service. On June 25, 2020, Delphin requested an extension of time until September 28, 2021 to continue to construct the onshore facilities. Delphin explains that it was continuing to work to develop the Project, however, a variety of factors complicated the task of negotiating offtake agreements with potential customers. Delfin states that on July 15, 2020, via delegated order, the Commission granted an extension of time until September 28, 2021 to construct the onshore facilities and make them available for service. (2020 Extension) Delfin states that since the 2020 Extension, it has continued to work to develop the Project. Additionally, Delfin asserts that economic conditions are recovering from the global coronavirus pandemic, and the spot and short-term market for the LNG have significantly improved. Delfin views these developments as a precursor for an improved longer-term market, which it asserts will support long-term LNG offtake contract(s). Accordingly, applicants request an extension of time until September 28, 2022 to complete construction of the onshore facilities and place them into service. This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on Delfin’s request for an extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10).2 As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for Natural Gas Act facilities when such requests are contested before order issuance. For those extension requests that are contested,3 the Commission will aim to issue an order acting on the request 2 Only motions to intervene from entities that were party to the underlying proceeding will be accepted. Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 39 (2020). 3 Contested proceedings are those where an intervenor disputes any material issue of the filing. 18 CFR 385.2201(c)(1) (2019). VerDate Sep<11>2014 17:47 Jul 12, 2021 Jkt 253001 within 45 days.4 The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.5 The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission’s environmental analysis for the certificate complied with the National Environmental Policy Act.6 At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.7 The OEP Director, or his or her designee, will act on all of those extension requests that are uncontested. In addition to publishing the full text of this document in the Federal Register, The Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and three copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Comment Date: 5:00 p.m. Eastern Time on, July 22, 2021. 4 Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020). 5 Id. at P 40. 6 Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether the Commission’s environmental analysis for the permit order complied with NEPA. 7 Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020). PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 Dated: July 7, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–14845 Filed 7–12–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3253–015] Mad River Power Associates; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent Minor License. b. Project No.: 3253–015. c. Date Filed: November 3, 2020. d. Applicant: Mad River Power Associates (MRPA). e. Name of Project: Campton Hydroelectric Project (project). f. Location: On the Mad River in Grafton County, New Hampshire. The project occupies approximately 0.05 acre of federal land administered by the U.S. Forest Service. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Ian Clark, Mad River Power Associates, 1 Pepsi Way, Suite 6n75, Katonah, NY 10536; Phone at (914) 297–7645, or email at info@dichotomycapital.com. i. FERC Contact: Amanda Gill, (202) 502–6773 or amanda.gill@ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the Commission’s eFiling system at https:// ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/ QuickComment.aspx. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a E:\FR\FM\13JYN1.SGM 13JYN1 36743 jbell on DSKJLSW7X2PROD with NOTICES Federal Register / Vol. 86, No. 131 / Tuesday, July 13, 2021 / Notices paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–3253– 015. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted and is ready for environmental analysis at this time. The Council on Environmental Quality (CEQ) issued a final rule on July 15, 2020, revising the regulations under 40 CFR parts 1500–1518 that federal agencies use to implement the National Environmental Policy Act (NEPA) (see Update to the Regulations Implementing the Procedural Provisions of the National Environmental Policy Act, 85 FR 43,304). The Final Rule became effective on and applies to any NEPA process begun after September 14, 2020. Commission staff intends to conduct its NEPA review in accordance with CEQ’s new regulations. l. Project Description: The project consists of: (1) A 22-foot-wide, 24-foothigh concrete intake structure located approximately 60 feet upstream of the U.S. Forest Service’s Campton Dam on the east shoreline of the U.S. Forest Service’s Campton Pond, that includes a 25-foot-long,13-foot-high trashrack with 1.75-inch clear bar spacing; (2) a 600foot-long, 78-inch-diameter underground steel penstock that trifurcates into three 48-inch-diameter sections measuring 20 feet, 30 feet, and 43 feet in length, respectively; (3) a 43foot-long, 30-foot-wide powerhouse located on the east side of the Mad River that contains a 167-kW Francis turbinegenerator unit; (4) two 236-kW submersible Flygt turbine-generator units located outside of the powerhouse; (5) an approximately 55-foot-long, 40foot-wide tailrace; (6) a 200-foot-long transmission line and a 33.5-kilovolt transformer that connects the generators to the electric grid; (7) an Atlantic salmon smolt bypass facility consisting VerDate Sep<11>2014 17:47 Jul 12, 2021 Jkt 253001 of an 85-foot-long, 20-inch diameter cast iron pipe that empties into an 3.5-footdeep plunge pool approximately 15 feet downstream of the dam; and (8) appurtenant facilities. The project creates an approximately 600-foot-long bypassed reach of the Mad River. The current license requires: (1) Inflow to be discharged over the spillway to the bypassed reach during periods of non-generation or when inflow is less than 25 cfs; (2) a minimum flow of 4.5 cfs through the Atlantic salmon smolt bypass facility during periods of generation or when inflow is greater than 25 cfs; and (3) operation of the smolt bypass facility from mid-April to mid-June. The average annual generation of the project is currently approximately 1,170 megawatt-hours (MWh). MRPA proposes to: (1) Continue operating the project in a run-of-release mode; (2) replace one of the 236-kW Flygt turbine-generator units with a new 340-kW Flygt turbine-generator unit, for a total installed capacity of 743 kW at the project; (2) release a minimum flow of 29 cfs or inflow, whichever is less, over the dam to the bypassed reach; and (3) close the existing smolt bypass facility. MRPA estimates that the average annual generation of the proposed project will be approximately 1,900 MWh. m. A copy of the application can be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. All filings must: (1) Bear in all capital letters the title ‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’ ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions, or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 You may also register online at https://www.ferc.gov/ferc-online/ overview to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. The applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. Please note that the certification request must comply with 40 CFR 121.5(b), including documentation that a pre-filing meeting request was submitted to the certifying authority at least 30 days prior to submitting the certification request. Please also note that the certification request must be sent to the certifying authority and to the Commission concurrently. o. Procedural Schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Milestone Deadline for filing comments, recommendations, preliminary terms and conditions, and preliminary fishway prescriptions. Deadline for filing reply comments. Target date September 2021. October 2021. p. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of this notice. Dated: July 7, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–14843 Filed 7–12–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Sunshine Act Meetings July 15, 2021, 10:00 a.m. Open to the public via audio Webcast only. Join FERC online to listen live at https://ferc.capitolconnection.org/. STATUS: Open. MATTERS TO BE CONSIDERED: Agenda. * Note—Items listed on the agenda may be deleted without further notice. This is a list of matters to be considered by the Commission. It does TIME AND DATE: PLACE: E:\FR\FM\13JYN1.SGM 13JYN1

Agencies

[Federal Register Volume 86, Number 131 (Tuesday, July 13, 2021)]
[Notices]
[Pages 36742-36743]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-14843]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3253-015]


Mad River Power Associates; Notice of Application Ready for 
Environmental Analysis and Soliciting Comments, Recommendations, Terms 
and Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.

    a. Type of Application: Subsequent Minor License.
    b. Project No.: 3253-015.
    c. Date Filed: November 3, 2020.
    d. Applicant: Mad River Power Associates (MRPA).
    e. Name of Project: Campton Hydroelectric Project (project).
    f. Location: On the Mad River in Grafton County, New Hampshire. The 
project occupies approximately 0.05 acre of federal land administered 
by the U.S. Forest Service.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Mr. Ian Clark, Mad River Power Associates, 1 
Pepsi Way, Suite 6n75, Katonah, NY 10536; Phone at (914) 297-7645, or 
email at [email protected].
    i. FERC Contact: Amanda Gill, (202) 502-6773 or 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://ferconline.ferc.gov/QuickComment.aspx. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a

[[Page 36743]]

paper copy. Submissions sent via the U.S. Postal Service must be 
addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852. The first page of any filing should 
include docket number P-3253-015.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is ready for 
environmental analysis at this time.
    The Council on Environmental Quality (CEQ) issued a final rule on 
July 15, 2020, revising the regulations under 40 CFR parts 1500-1518 
that federal agencies use to implement the National Environmental 
Policy Act (NEPA) (see Update to the Regulations Implementing the 
Procedural Provisions of the National Environmental Policy Act, 85 FR 
43,304). The Final Rule became effective on and applies to any NEPA 
process begun after September 14, 2020. Commission staff intends to 
conduct its NEPA review in accordance with CEQ's new regulations.
    l. Project Description: The project consists of: (1) A 22-foot-
wide, 24-foot-high concrete intake structure located approximately 60 
feet upstream of the U.S. Forest Service's Campton Dam on the east 
shoreline of the U.S. Forest Service's Campton Pond, that includes a 
25-foot-long,13-foot-high trashrack with 1.75-inch clear bar spacing; 
(2) a 600-foot-long, 78-inch-diameter underground steel penstock that 
trifurcates into three 48-inch-diameter sections measuring 20 feet, 30 
feet, and 43 feet in length, respectively; (3) a 43-foot-long, 30-foot-
wide powerhouse located on the east side of the Mad River that contains 
a 167-kW Francis turbine-generator unit; (4) two 236-kW submersible 
Flygt turbine-generator units located outside of the powerhouse; (5) an 
approximately 55-foot-long, 40-foot-wide tailrace; (6) a 200-foot-long 
transmission line and a 33.5-kilovolt transformer that connects the 
generators to the electric grid; (7) an Atlantic salmon smolt bypass 
facility consisting of an 85-foot-long, 20-inch diameter cast iron pipe 
that empties into an 3.5-foot-deep plunge pool approximately 15 feet 
downstream of the dam; and (8) appurtenant facilities. The project 
creates an approximately 600-foot-long bypassed reach of the Mad River.
    The current license requires: (1) Inflow to be discharged over the 
spillway to the bypassed reach during periods of non-generation or when 
inflow is less than 25 cfs; (2) a minimum flow of 4.5 cfs through the 
Atlantic salmon smolt bypass facility during periods of generation or 
when inflow is greater than 25 cfs; and (3) operation of the smolt 
bypass facility from mid-April to mid-June. The average annual 
generation of the project is currently approximately 1,170 megawatt-
hours (MWh).
    MRPA proposes to: (1) Continue operating the project in a run-of-
release mode; (2) replace one of the 236-kW Flygt turbine-generator 
units with a new 340-kW Flygt turbine-generator unit, for a total 
installed capacity of 743 kW at the project; (2) release a minimum flow 
of 29 cfs or inflow, whichever is less, over the dam to the bypassed 
reach; and (3) close the existing smolt bypass facility. MRPA estimates 
that the average annual generation of the proposed project will be 
approximately 1,900 MWh.
    m. A copy of the application can be viewed on the Commission's 
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document. For assistance, contact FERC Online 
Support.
    All filings must: (1) Bear in all capital letters the title 
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person submitting the filing; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions, or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicant. Each filing must be 
accompanied by proof of service on all persons listed on the service 
list prepared by the Commission in this proceeding, in accordance with 
18 CFR 4.34(b) and 385.2010.
    You may also register online at https://www.ferc.gov/ferc-online/overview to be notified via email of new filings and issuances related 
to this or other pending projects. For assistance, contact FERC Online 
Support.
    n. The applicant must file no later than 60 days following the date 
of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification. Please note 
that the certification request must comply with 40 CFR 121.5(b), 
including documentation that a pre-filing meeting request was submitted 
to the certifying authority at least 30 days prior to submitting the 
certification request. Please also note that the certification request 
must be sent to the certifying authority and to the Commission 
concurrently.
    o. Procedural Schedule: The application will be processed according 
to the following schedule. Revisions to the schedule will be made as 
appropriate.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Deadline for filing comments,            September 2021.
 recommendations, preliminary terms and
 conditions, and preliminary fishway
 prescriptions.
Deadline for filing reply comments.....  October 2021.
------------------------------------------------------------------------

    p. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of this notice.

    Dated: July 7, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-14843 Filed 7-12-21; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.