DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–57–000]
Mountain Valley Pipeline, LLC; Notice
of Supplemental Scoping Period for
the Proposed Amendment to the
Certificate of Public Convenience and
Necessity for the Mountain Valley
Pipeline Project and Request for
Comments on Environmental Issues
On March 16, 2021, Commission staff
issued a ‘‘Notice of Scoping Period and
Requesting Comments on
Environmental Issues for the Proposed
Amendment to the Certificate of Public
Convenience and Necessity for the
Mountain Valley Pipeline Project’’
(Notice of Scoping). The Notice of
Scoping is included as attachment 1.1
The scoping comment period ended on
April 15, 2021.
It has come to our attention that the
entire environmental mailing list may
not have received copies of the Notice
of Scoping; therefore, the Commission is
issuing this Notice of Supplemental
Scoping Period to provide interested
parties that did not receive the previous
notice an opportunity to file comments
on environmental issues. The
supplemental scoping period will close
on August 2, 2021.
The staff of the Commission is
preparing an environmental assessment
(EA) that will discuss the environmental
impacts of the proposed Amendment to
the Certificate of Public Convenience
and Necessity for the Mountain Valley
Pipeline Project (Amendment Project)
involving construction and operation of
facilities by Mountain Valley Pipeline,
LLC (Mountain Valley) in Wetzel,
Lewis, Webster, Nicholas, Greenbrier,
Summers, and Monroe Counties, West
Virginia and Giles, Montgomery,
Roanoke, Franklin, and Pittsylvania
Counties, Virginia.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
Your input will help the Commission
staff determine what issues they need to
evaluate in the EA. Commission staff
will consider all written comments
during the preparation of the EA. If you
submitted comments in Docket No.
CP21–57–000 during the previous
scoping period, those comments will be
considered and do not need to be
resubmitted.
On June 11, 2021, Commission staff
issued a ‘‘Notice of Schedule for the
Preparation of an Environmental
Assessment for the Proposed
Amendment to the Certificate of Public
Convenience and Necessity for the
Mountain Valley Pipeline Project’’
(Notice of Schedule).2 As indicated in
the Notice of Schedule, the EA is
scheduled to be published on August
13, 2021. If a schedule change becomes
necessary, the Commission will issue a
revised schedule.
Additional information on the
Amendment Project including how to
submit comments to the Commission, a
summary of the proposed project, the
NEPA Process, and information on the
environmental mailing list can be found
in the Notice of Scoping included in
attachment 1.
Additional information about the
project is also available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or (866)
208–3676, or for TTY, contact (202)
502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Dated: July 1, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–14626 Filed 7–8–21; 8:45 am]
BILLING CODE 6717–01–P
jbell on DSKJLSW7X2PROD with NOTICES
1 The
appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’. For instructions on
connecting to eLibrary, refer to the last page of this
notice. At this time, the Commission has suspended
access to the Commission’s Public Reference Room
due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus
Disease (COVID–19), issued by the President on
March 13, 2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll free, (886)
208–3676 or TTY (202) 502–8659.
VerDate Sep<11>2014
17:01 Jul 08, 2021
Jkt 253001
PO 00000
2 See
accession number 20210611–3044.
Frm 00027
Fmt 4703
Sfmt 4703
36275
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2322–069]
Brookfield White Pine Hydro LLC;
Notice of Availability of Draft
Environmental Assessment and
Revised Procedural Schedule
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380, the Office
of Energy Projects has reviewed the
application for license for the Shawmut
Hydroelectric Project, located on the
Kennebec River in Kennebec and
Somerset Counties, Maine, and has
prepared a Draft Environmental
Assessment (DEA) for the project. No
federal land is occupied by project
works or located within the project
boundary.
The DEA contains staff’s analysis of
the potential environmental impacts of
the project and concludes that licensing
the project, with appropriate
environmental protective measures,
would not constitute a major federal
action that would significantly affect the
quality of the human environment.
The Commission provides all
interested persons with an opportunity
to view and/or print the EA via the
internet through the Commission’s
Home Page (https://www.ferc.gov/), using
the ‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field, to access the
document. At this time, the Commission
has suspended access to the
Commission’s Public Reference Room,
due to the proclamation declaring a
National Emergency concerning the
Novel Coronavirus Disease (COVID–19),
issued by the President on March 13,
2020. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov, or tollfree at (866) 208–3676, or for TTY, (202)
502–8659.
You may also register online at
https://ferconline.ferc.gov/
eSubscription.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Any comments should be filed within
45 days from the date of this notice.
The Commission strongly encourages
electronic filing. Please file comments
using the Commission’s eFiling system
at https://ferconline.ferc.gov/
eFiling.aspx. Commenters can submit
brief comments up to 6,000 characters,
E:\FR\FM\09JYN1.SGM
09JYN1
36276
Federal Register / Vol. 86, No. 129 / Friday, July 9, 2021 / Notices
without prior registration, using the
eComment system at https://
ferconline.ferc.gov/QuickComment.
aspx. You must include your name and
contact information at the end of your
comments. For assistance, please
contact FERC Online Support. In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. The first page of any filing
should include docket number P–2322–
069.
With this notice, we are waiving
section 5.25(a) of the Commission’s
regulations that require the DEA to be
issued no later than 180 days from the
date responses are due to the notice of
acceptance and ready for environmental
analysis. Instead, the license application
will be processed according to the
following revised procedural schedule.
Revisions to the schedule may be made
as appropriate.
Milestone
Issue Draft EA ...................
Comments on Draft EA
due.
Modified terms and conditions due.
Commission issues Final
EA.
Target date
July 2021.
August 2021.
October 2021.
January 2022.
For further information, contact Matt
Cutlip at (503) 552–2762, or by email at
matt.cutlip@ferc.gov.
Dated: July 1, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–14629 Filed 7–8–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
jbell on DSKJLSW7X2PROD with NOTICES
[Docket No. ER21–2331–000]
Duran Mesa LLC; Supplemental Notice
That Initial Market-Based Rate Filing
Includes Request for Blanket Section
204 Authorization
This is a supplemental notice in the
above-referenced proceeding of Duran
Mesa LLC’s application for marketbased rate authority, with an
accompanying rate tariff, noting that
VerDate Sep<11>2014
17:51 Jul 08, 2021
Jkt 253001
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is July 22,
2021.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
may mail similar pleadings to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426. Hand delivered submissions in
docketed proceedings should be
delivered to Health and Human
Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
Dated: July 2, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–14667 Filed 7–8–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #2
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2136–017.
Applicants: Invenergy Cannon Falls
LLC.
Description: Triennial Market Power
Analysis for Central Region of Invenergy
Cannon Falls LLC.
Filed Date: 6/30/21.
Accession Number: 20210630–5347.
Comments Due: 5 p.m. ET 8/30/21.
Docket Numbers: ER10–2417–004;
ER13–122–004.
Applicants: ExxonMobil Baton Rouge
Complex, ExxonMobil Beaumont
Complex.
Description: Triennial Market Power
Analysis for Central Region of
ExxonMobil Baton Rouge Complex, et
al.
Filed Date: 6/30/21.
Accession Number: 20210630–5352.
Comments Due: 5 p.m. ET 8/30/21.
Docket Numbers: ER10–2421–007;
ER10–2616–021; ER10–3247–014;
ER11–2457–007; ER11–4398–009;
ER11–4400–017; ER12–2250–008;
ER12–2251–008; ER12–2252–009;
ER12–2253–008; ER14–1569–014;
ER14–2245–008; ER14–883–015; ER14–
922–007; ER14–924–007; ER15–1161–
001; ER15–1596–014; ER15–1599–014;
ER15–2535–004; ER19–102–007; ER19–
158–009; ER19–2608–001; ER19–2803–
006; ER19–2806–006; ER19–2807–006;
ER19–2809–006; ER19–2810–006;
ER19–2811–006.
Applicants: Energy Services
Providers, Inc., Ambit Northeast, LLC,
Cincinnati Bell Energy LLC, Connecticut
Gas & Electric, Inc., Dynegy Energy
Services, LLC, Dynegy Energy Services
(East), LLC, Dynegy Marketing and
Trade, LLC, Dynegy Midwest
Generation, LLC, Dynegy Power
Marketing, LLC, Electric Energy, Inc.,
Energy Rewards, LLC, Everyday Energy
NJ, LLC, Everyday Energy, LLC, Illinois
Power Generating Company, Illinois
Power Marketing Company, Illinois
Power Resources Generating, LLC,
Luminant Commercial Asset
Management LLC, Luminant Energy
Company LLC, Massachusetts Gas &
E:\FR\FM\09JYN1.SGM
09JYN1
Agencies
[Federal Register Volume 86, Number 129 (Friday, July 9, 2021)]
[Notices]
[Pages 36275-36276]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-14629]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2322-069]
Brookfield White Pine Hydro LLC; Notice of Availability of Draft
Environmental Assessment and Revised Procedural Schedule
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's (Commission)
regulations, 18 CFR part 380, the Office of Energy Projects has
reviewed the application for license for the Shawmut Hydroelectric
Project, located on the Kennebec River in Kennebec and Somerset
Counties, Maine, and has prepared a Draft Environmental Assessment
(DEA) for the project. No federal land is occupied by project works or
located within the project boundary.
The DEA contains staff's analysis of the potential environmental
impacts of the project and concludes that licensing the project, with
appropriate environmental protective measures, would not constitute a
major federal action that would significantly affect the quality of the
human environment.
The Commission provides all interested persons with an opportunity
to view and/or print the EA via the internet through the Commission's
Home Page (https://www.ferc.gov/), using the ``eLibrary'' link. Enter
the docket number, excluding the last three digits in the docket number
field, to access the document. At this time, the Commission has
suspended access to the Commission's Public Reference Room, due to the
proclamation declaring a National Emergency concerning the Novel
Coronavirus Disease (COVID-19), issued by the President on March 13,
2020. For assistance, contact FERC Online Support at
[email protected], or toll-free at (866) 208-3676, or for TTY,
(202) 502-8659.
You may also register online at https://ferconline.ferc.gov/eSubscription.aspx to be notified via email of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
Any comments should be filed within 45 days from the date of this
notice.
The Commission strongly encourages electronic filing. Please file
comments using the Commission's eFiling system at https://ferconline.ferc.gov/eFiling.aspx. Commenters can submit brief comments
up to 6,000 characters,
[[Page 36276]]
without prior registration, using the eComment system at https://ferconline.ferc.gov/QuickComment.aspx. You must include your name and
contact information at the end of your comments. For assistance, please
contact FERC Online Support. In lieu of electronic filing, you may
submit a paper copy. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. The first page of any filing should
include docket number P-2322-069.
With this notice, we are waiving section 5.25(a) of the
Commission's regulations that require the DEA to be issued no later
than 180 days from the date responses are due to the notice of
acceptance and ready for environmental analysis. Instead, the license
application will be processed according to the following revised
procedural schedule. Revisions to the schedule may be made as
appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Issue Draft EA......................... July 2021.
Comments on Draft EA due............... August 2021.
Modified terms and conditions due...... October 2021.
Commission issues Final EA............. January 2022.
------------------------------------------------------------------------
For further information, contact Matt Cutlip at (503) 552-2762, or
by email at [email protected].
Dated: July 1, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-14629 Filed 7-8-21; 8:45 am]
BILLING CODE 6717-01-P