Public Utility District No. 1 of Pend Oreille County, Washington; Notice of Availability of Environmental Assessment, 35082 [2021-14066]
Download as PDF
35082
Federal Register / Vol. 86, No. 124 / Thursday, July 1, 2021 / Notices
For further information, contact Holly
Frank at (202) 502–6833, or by email at
holly.frank@ferc.gov.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Dated: June 25, 2021.
Kimberly D. Bose,
Secretary.
[Project No. 2042–191]
khammond on DSKJM1Z7X2PROD with NOTICES
Public Utility District No. 1 of Pend
Oreille County, Washington; Notice of
Availability of Environmental
Assessment
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380, the Office
of Energy Projects has reviewed an
application submitted by Public Utility
District No. 1 of Pend Oreille County,
Washington to amend the license for the
Box Canyon Project No. 2042, and has
prepared an Environmental Assessment
(EA) for the proposed amendment. The
licensee proposes an amendment of the
project license to be consistent with the
terms of an Amended Settlement
Agreement and to incorporate revised
mandatory conditions submitted by the
U.S. Department of the Interior under
section 4(e) and section 18 of the
Federal Power Act. The project is
located on the Pend Oreille River in
Pend Oreille County, Washington, and
Bonner County, Idaho and occupies
lands within the Kalispel Indian
Reservation and lands within the
Colville National Forest.
The EA contains Commission staff’s
analysis of the potential environmental
effects of the proposed amendment to
the license, and concludes that the
proposed amendment, with appropriate
environmental protective measures,
would not constitute a major federal
action that would significantly affect the
quality of the human environment.
The EA may be viewed on the
Commission’s website at www.ferc.gov
using the ‘‘eLibrary’’ link. Enter the
docket number (P–2042) in the docket
number field to access the document. At
this time, the Commission has
suspended access to the Commission’s
Public Reference Room due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC Online
Support at FERCOnlineSupport@
ferc.gov or toll-free at 1–866–208–3676,
or for TTY, (202) 502–8659. You may
also register online at www.ferc.gov/
docs-filing/esubscription.asp to be
notified via email of new filings and
issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
VerDate Sep<11>2014
16:45 Jun 30, 2021
Jkt 253001
[FR Doc. 2021–14066 Filed 6–30–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP20–527–000]
Columbia Gulf Transmission, LLC;
Notice of Availability of The Draft
Environmental Impact Statement for
The Proposed East Lateral Xpress
Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared a draft
environmental impact statement (EIS)
for the East Lateral XPress Project
(Project), proposed by Columbia Gulf
Transmission, LLC (Columbia Gulf) in
the above-referenced docket. Columbia
Gulf requests authorization to construct
and operate natural gas transmission
facilities in Louisiana. The Project is
designed to provide a total of 725
million standard cubic feet per day of
firm transportation capacity, through a
combination of incremental and existing
capacity on Columbia Gulf’s interstate
natural gas pipeline system, to an
interconnect with Venture Global Gator
Express, LLC, for ultimate delivery as
feed gas for Venture Global Plaquemines
LNG, LLC’s facility in Plaquemines
Parish.
The draft EIS responds to comments
that were received on the Commission’s
March 16, 2021 Environmental
Assessment (EA) 1 and discloses
downstream greenhouse gas emissions
for the Project. With the exception of
climate change impacts, the FERC staff
concludes that approval of the proposed
Project, with the mitigation measures
recommended in this EIS, would not
result in significant environmental
impacts. FERC staff continues to be
unable to determine significance with
regards to climate change impacts.
The draft EIS incorporates the above
referenced EA, which addressed the
potential environmental effects of the
construction and operation of the
following Project facilities:
• 8.1 miles of 30-inch-diameter
pipeline lateral within Barataria Bay in
1 The Project’s Environmental Assessment is
available on eLibrary under accession no.
20210316–3010.
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
Jefferson and Plaquemines Parish,
Louisiana;
• Centerville Compressor Station—a
new 23,470-horsepower (hp)
compressor station at an abandoned
Columbia Gulf compressor station site
in St. Mary Parish, Louisiana;
• Golden Meadow Compressor
Station—a new 23,470-hp compressor
station adjacent to an existing tie-in
facility in Lafourche Parish, Louisiana;
• a point of delivery meter station in
Plaquemines Parish, Louisiana; and
• a tie-in facility with two mainline
valves and other appurtenances on a
new platform in Barataria Bay, Jefferson
Parish, Louisiana.
The Commission mailed a copy of the
Notice of Availability of the Draft
Environmental Impact Statement for the
Proposed East Lateral Xpress Project to
federal, state, and local government
representatives and agencies; elected
officials; environmental and public
interest groups; Native American tribes;
potentially affected landowners and
other interested individuals and groups;
and newspapers and libraries in the
Project area. The draft EIS is only
available in electronic format. It may be
viewed and downloaded from the
FERC’s website (www.ferc.gov), on the
natural gas environmental documents
page (https://www.ferc.gov/industriesdata/natural-gas/environment/
environmental-documents). In addition,
the draft EIS may be accessed by using
the eLibrary link on the FERC’s website.
Click on the eLibrary link (https://
elibrary.ferc.gov/eLibrary/search) select
‘‘General Search’’ and enter the docket
number in the ‘‘Docket Number’’ field
(i.e., CP20–527). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659.
The draft EIS is not a decision
document. It presents Commission
staff’s independent analysis of the
environmental issues for the
Commission to consider when
addressing the merits of all issues in
this proceeding. Any person wishing to
comment on the draft EIS may do so.
Your comments should focus on the
draft EIS’s disclosure and discussion of
potential environmental effects,
including climate impacts, measures to
avoid or lessen environmental impacts,
and completeness of the submitted
alternatives, information and analyses.
To ensure consideration of your
comments on the proposal in the final
EIS, it is important that the Commission
receive your comments on or before 5:00
p.m. Eastern Time on August 16, 2021.
E:\FR\FM\01JYN1.SGM
01JYN1
Agencies
[Federal Register Volume 86, Number 124 (Thursday, July 1, 2021)]
[Notices]
[Page 35082]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-14066]
[[Page 35082]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2042-191]
Public Utility District No. 1 of Pend Oreille County, Washington;
Notice of Availability of Environmental Assessment
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's (Commission)
regulations, 18 CFR part 380, the Office of Energy Projects has
reviewed an application submitted by Public Utility District No. 1 of
Pend Oreille County, Washington to amend the license for the Box Canyon
Project No. 2042, and has prepared an Environmental Assessment (EA) for
the proposed amendment. The licensee proposes an amendment of the
project license to be consistent with the terms of an Amended
Settlement Agreement and to incorporate revised mandatory conditions
submitted by the U.S. Department of the Interior under section 4(e) and
section 18 of the Federal Power Act. The project is located on the Pend
Oreille River in Pend Oreille County, Washington, and Bonner County,
Idaho and occupies lands within the Kalispel Indian Reservation and
lands within the Colville National Forest.
The EA contains Commission staff's analysis of the potential
environmental effects of the proposed amendment to the license, and
concludes that the proposed amendment, with appropriate environmental
protective measures, would not constitute a major federal action that
would significantly affect the quality of the human environment.
The EA may be viewed on the Commission's website at www.ferc.gov
using the ``eLibrary'' link. Enter the docket number (P-2042) in the
docket number field to access the document. At this time, the
Commission has suspended access to the Commission's Public Reference
Room due to the proclamation declaring a National Emergency concerning
the Novel Coronavirus Disease (COVID-19), issued by the President on
March 13, 2020. For assistance, contact FERC Online Support at
[email protected] or toll-free at 1-866-208-3676, or for TTY,
(202) 502-8659. You may also register online at www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
For further information, contact Holly Frank at (202) 502-6833, or
by email at [email protected].
Dated: June 25, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-14066 Filed 6-30-21; 8:45 am]