PSEG Nuclear, LLC; Exelon Generation Company, LLC; Salem Nuclear Generating Station, Unit No. 2, 34788-34790 [2021-13896]
Download as PDF
34788
Federal Register / Vol. 86, No. 123 / Wednesday, June 30, 2021 / Notices
NUCLEAR REGULATORY
COMMISSION
I. Obtaining Information and
Submitting Comments
[Docket No. 50–311; NRC–2021–0131]
A. Obtaining Information
Please refer to Docket ID NRC–2021–
0131, facility name, unit number(s),
docket number(s), application date, and
subject, if applicable, when contacting
the NRC about the availability of
information for this action. You may
obtain publicly available information
related to this action by any of the
following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2021–0131.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced (if it is
available in ADAMS) is provided the
first time that it is mentioned in this
document.
Attention: The PDR, where you may
examine and order copies of public
documents, is currently closed. You
may submit your request to the PDR via
email at pdr.resource@nrc.gov or call 1–
800–397–4209 or 301–415–4737,
between 8:00 a.m. and 4:00 p.m. (EST),
Monday through Friday, except Federal
holidays.
PSEG Nuclear, LLC; Exelon Generation
Company, LLC; Salem Nuclear
Generating Station, Unit No. 2
Nuclear Regulatory
Commission.
ACTION: License amendment application;
opportunity to comment, request a
hearing, and petition for leave to
intervene.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is considering
issuance of amendments to Renewed
Facility Operating License No. DPR–75,
issued to PSEG Nuclear, LLC, for
operation of the Salem Nuclear
Generating Station, Unit No. 2. The
proposed amendments would revise
Technical Specification (TS) actions for
rod position indicators. This is a onetime change during the current
operating cycle to support maintenance
on the transformer supplying power to
all of the Unit No. 2 rod position
indicators.
DATES: Submit comments by July 30,
2021. Request for a hearing or petitions
for leave to intervene must be filed by
August 30, 2021.
ADDRESSES: You may submit comments
by any of the following methods;
however, the NRC encourages electronic
comment submission through the
Federal Rulemaking website:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2021–0131. Address
questions about Docket IDs in
Regulations.gov to Stacy Schumann;
telephone: 301–415–0624; email:
Stacy.Schumann@nrc.gov. For technical
questions, contact the individuals listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• Mail comments to: Office of
Administration, Mail Stop: TWFN–7–
A60M, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, ATTN: Program Management,
Announcements and Editing Staff.
For additional direction on obtaining
information and submitting comments,
see ‘‘Obtaining Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION section of
this document.
FOR FURTHER INFORMATION CONTACT:
James S. Kim, Office of Nuclear Reactor
Regulation, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, telephone: 301–415–6606, email:
James.Kim@nrc.gov.
SUPPLEMENTARY INFORMATION:
jbell on DSKJLSW7X2PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:47 Jun 29, 2021
Jkt 253001
B. Submitting Comments
The NRC encourages electronic
comment submission through the
Federal Rulemaking website (https://
www.regulations.gov). Please include
Docket ID NRC–2021–0131 in your
comment submission.
The NRC cautions you not to include
identifying or contact information that
you do not want to be publicly
disclosed in your comment submission.
The NRC will post all comment
submissions at https://
www.regulations.gov as well as enter the
comment submissions into ADAMS.
The NRC does not routinely edit
comment submissions to remove
identifying or contact information.
If you are requesting or aggregating
comments from other persons for
submission to the NRC, then you should
inform those persons not to include
identifying or contact information that
they do not want to be publicly
disclosed in their comment submission.
Your request should state that the NRC
PO 00000
Frm 00076
Fmt 4703
Sfmt 4703
does not routinely edit comment
submissions to remove such information
before making the comment
submissions available to the public or
entering the comment into ADAMS.
II. Introduction
The NRC is considering issuance of
amendments to Renewed Facility
Operating License No. DPR–75, issued
to PSEG Nuclear LLC, for operation of
the Salem Nuclear Generating Station,
Unit No. 2, located in Salem County,
New Jersey.
The proposed amendments would
revise TS 3.1.3.2.1, ‘‘Position Indication
Systems—Operating,’’ to modify TS
Action b.4 for more than one inoperable
analog rod position indicator per group
from 24 hours to 30 hours. This is a onetime change during the current
operating cycle to support maintenance
on the transformer supplying power to
all of the Unit No. 2 rod position
indicators.
Before any issuance of the proposed
license amendment, the NRC will need
to make the findings required by the
Atomic Energy Act of 1954, as amended
(the Act), and NRC’s regulations.
The NRC has made a proposed
determination that the license
amendment request involves no
significant hazards consideration. Under
the NRC’s regulations in § 50.92 of title
10 of the Code of Federal Regulations
(10 CFR), this means that operation of
the facility in accordance with the
proposed amendment would not (1)
involve a significant increase in the
probability or consequences of an
accident previously evaluated; or (2)
create the possibility of a new or
different kind of accident from any
accident previously evaluated; or (3)
involve a significant reduction in a
margin of safety. As required by 10 CFR
50.91(a), the licensee has provided its
analysis of the issue of no significant
hazards consideration, which is
presented below:
1. Does the proposed change involve a
significant increase in the probability or
consequences of an accident previously
evaluated?
Response: No.
Rod position indication instrumentation is
not an accident initiator, providing
indication only of the control and shutdown
rods positions. Normal operation, abnormal
occurrences and accident analyses assume
the rods are at certain positions within the
reactor core. The proposed one-time change
modifies the time that rod position indication
may be inoperable. The existing TS Actions
and other plant instrumentation provide
appropriate compensation for that
inoperability. Thus, this change does not
involve a significant increase in the
probability of an accident.
E:\FR\FM\30JNN1.SGM
30JNN1
Federal Register / Vol. 86, No. 123 / Wednesday, June 30, 2021 / Notices
jbell on DSKJLSW7X2PROD with NOTICES
Extending the allowed outage time to
restore inoperable rod position indicators
does not affect the operability of the
shutdown or control rods. With rod position
indicators inoperable, the position of nonindicating rods is required to be verified by
indirect means (i.e., moveable incore
detectors). Thus, inoperable rod position
indication instrumentation does not involve
an increase in the consequences of an
accident. The inoperable rod position
indication does not have any impact on the
ability to trip the reactor in response to
analyzed accidents and transients.
Therefore, the proposed change does not
represent a significant increase in the
probability or consequences of an accident
previously evaluated.
2. Does the proposed change create the
possibility of a new or different kind of
accident from any accident previously
evaluated?
Response: No.
The proposed change does not alter the
design, function, or operation of any plant
component and does not install any new or
different equipment. The proposed change
will not impose any new or different
requirement or introduce a new accident
initiator, accident precursor, or malfunction
mechanism.
Therefore, the proposed one-time change
does not create the possibility of a new or
different kind of accident from any accident
previously evaluated.
3. Does the proposed change involve a
significant reduction in a margin of safety?
Response: No.
Loss of rod position indication does not
cause a rod to be misaligned. With rod
position indicators inoperable, the control
rods are required to be placed in manual
control, and the position of non-indicating
rods is required to be verified using indirect
means. The proposed change will not affect
the ability of the shutdown or control rods
to perform their required function.
The proposed amendment will not result
in a design basis or safety limit being
exceeded or altered. Therefore, since the
proposed change does not impact the
response of the plant to a design basis
accident, the proposed change does not
involve a significant reduction in a margin of
safety.
The NRC staff has reviewed the
licensee’s analysis and, based on this
review, it appears that the 3 standards
of 10 CFR 50.92(c) are satisfied.
Therefore, the NRC staff proposes to
determine that the license amendment
request involves no significant hazards
consideration.
The NRC is seeking public comments
on this proposed determination that the
license amendment request involves no
significant hazards consideration. Any
comments received within 30 days after
the date of publication of this notice
will be considered in making any final
determination.
Normally, the Commission will not
issue the amendment until the
expiration of the 60 day notice period.
VerDate Sep<11>2014
17:47 Jun 29, 2021
Jkt 253001
However, if circumstances change
during the notice period, such that
failure to act in a timely way would
result, for example, in derating or
shutdown of the facility, the
Commission may issue the license
amendment before the expiration of the
notice period, provided that its final
determination is that the amendment
involves no significant hazards
consideration. The final determination
will consider all public and State
comments received. If the Commission
takes action prior to the expiration of
either the comment period or the notice
period, it will publish in the Federal
Register a notice of issuance. The
Commission expects that the need to
take this action will occur very
infrequently.
III. Opportunity To Request a Hearing
and Petition for Leave To Intervene
Within 60 days after the date of
publication of this notice, any person
(petitioner) whose interest may be
affected by this action may file a request
for a hearing and petition for leave to
intervene (petition) with respect to the
action. Petitions shall be filed in
accordance with the Commission’s
‘‘Agency Rules of Practice and
Procedure’’ in 10 CFR part 2. Interested
persons should consult 10 CFR 2.309. If
a petition is filed, the presiding officer
will rule on the petition and, if
appropriate, a notice of a hearing will be
issued.
Petitions must be filed no later than
60 days from the date of publication of
this notice in accordance with the filing
instructions in the ‘‘Electronic
Submissions (E-Filing’’) section of this
document. Petitions and motions for
leave to file new or amended
contentions that are filed after the
deadline will not be entertained absent
a determination by the presiding officer
that the filing demonstrates good cause
by satisfying the three factors in 10 CFR
2.309(c)(1)(i) through (iii).
If a hearing is requested and the
Commission has not made a final
determination on the issue of no
significant hazards consideration, the
Commission will make a final
determination on the issue of no
significant hazards consideration, which
will serve to establish when the hearing
is held. If the final determination is that
the amendment request involves no
significant hazards consideration, the
Commission may issue the amendment
and make it immediately effective,
notwithstanding the request for a
hearing. Any hearing would take place
after issuance of the amendment. If the
final determination is that the
amendment request involves a
PO 00000
Frm 00077
Fmt 4703
Sfmt 4703
34789
significant hazards consideration, then
any hearing held would take place
before the issuance of the amendment
unless the Commission finds an
imminent danger to the health or safety
of the public, in which case it will issue
an appropriate order or rule under 10
CFR part 2.
A State, local governmental body,
Federally recognized Indian Tribe, or
designated agency thereof, may submit
a petition to the Commission to
participate as a party under 10 CFR
2.309(h) no later than 60 days from the
date of publication of this notice.
Alternatively, a State, local
governmental body, Federally
recognized Indian Tribe, or agency
thereof may participate as a non-party
under 10 CFR 2.315(c).
For information about filing a petition
and about participation by a person not
a party under 10 CFR 2.315, see ADAMS
Accession No. ML20340A053 and on
the NRC website at https://www.nrc.gov/
about-nrc/regulatory/adjudicatory/
hearing.html#participate.
IV. Electronic Submissions (E-Filing)
All documents filed in NRC
adjudicatory proceedings including
documents filed by an interested State,
local governmental body, Federally
recognized Indian Tribe, or designated
agency thereof that requests to
participate under 10 CFR 2.315(c), must
be filed in accordance with 10 CFR
2.302. The E-Filing process requires
participants to submit and serve all
adjudicatory documents over the
internet, or in some cases, to mail copies
on electronic storage media, unless an
exemption permitting an alternative
filing method, as discussed below, is
granted. Detailed guidance on electronic
submissions is located in the Guidance
for Electronic Submissions to the NRC
(ADAMS Accession No. ML13031A056)
and on the NRC website at https://
www.nrc.gov/site-help/esubmittals.html.
To comply with the procedural
requirements of E-Filing, at least 10
days prior to the filing deadline, the
participant should contact the Office of
the Secretary by email at
hearing.docket@nrc.gov, or by telephone
at 301–415–1677, to (1) request a digital
identification (ID) certificate, which
allows the participant (or its counsel or
representative) to digitally sign
submissions and access the E-Filing
system for any proceeding in which it
is participating; and (2) advise the
Secretary that the participant will be
submitting a petition or other
adjudicatory document (even in
instances in which the participant, or its
counsel or representative, already holds
E:\FR\FM\30JNN1.SGM
30JNN1
jbell on DSKJLSW7X2PROD with NOTICES
34790
Federal Register / Vol. 86, No. 123 / Wednesday, June 30, 2021 / Notices
an NRC-issued digital ID certificate).
Based upon this information, the
Secretary will establish an electronic
docket for the proceeding if the
Secretary has not already established an
electronic docket.
Information about applying for a
digital ID certificate is available on the
NRC’s public website at https://
www.nrc.gov/site-help/e-submittals/
getting-started.html. After a digital ID
certificate is obtained and a docket
created, the participant must submit
adjudicatory documents in Portable
Document Format. Guidance on
submissions is available on the NRC’s
public website at https://www.nrc.gov/
site-help/electronic-sub-ref-mat.html. A
filing is considered complete at the time
the document is submitted through the
NRC’s E-Filing system. To be timely, an
electronic filing must be submitted to
the E-Filing system no later than 11:59
p.m. Eastern Time on the due date.
Upon receipt of a transmission, the EFiling system timestamps the document
and sends the submitter an email
confirming receipt of the document. The
E-Filing system also distributes an email
that provides access to the document to
the NRC’s Office of the General Counsel
and any others who have advised the
Office of the Secretary that they wish to
participate in the proceeding, so that the
filer need not serve the document on
those participants separately. Therefore,
applicants and other participants (or
their counsel or representative) must
apply for and receive a digital ID
certificate before adjudicatory
documents are filed to obtain access to
the documents via the E-Filing system.
A person filing electronically using
the NRC’s adjudicatory E-Filing system
may seek assistance by contacting the
NRC’s Electronic Filing Help Desk
through the ‘‘Contact Us’’ link located
on the NRC’s public website at https://
www.nrc.gov/site-help/esubmittals.html, by email to
MSHD.Resource@nrc.gov, or by a tollfree call at 1–866–672–7640. The NRC
Electronic Filing Help Desk is available
between 9 a.m. and 6 p.m., Eastern
Time, Monday through Friday,
excluding government holidays.
Participants who believe that they
have good cause for not submitting
documents electronically must file an
exemption request, in accordance with
10 CFR 2.302(g), with their initial paper
filing stating why there is good cause for
not filing electronically and requesting
authorization to continue to submit
documents in paper format. Such filings
must be submitted in accordance with
10 CFR 2.302(b)–(d). Participants filing
adjudicatory documents in this manner
are responsible for serving their
VerDate Sep<11>2014
17:47 Jun 29, 2021
Jkt 253001
documents on all other participants.
Participants granted an exemption
under 10 CFR 2.302(g)(2) must still meet
the electronic formatting requirement in
10 CFR 2.302(g)(1), unless the
participant also seeks and is granted an
exemption from 10 CFR 2.302(g)(1).
Documents submitted in adjudicatory
proceedings will appear in the NRC’s
electronic hearing docket, which is
publicly available at https://
adams.nrc.gov/ehd, unless excluded
pursuant to an order of the presiding
officer. If you do not have an NRCissued digital ID certificate as described
above, click ‘‘cancel’’ when the link
requests certificates and you will be
automatically directed to the NRC’s
electronic hearing dockets where you
will be able to access any publicly
available documents in a particular
hearing docket. Participants are
requested not to include personal
privacy information such as social
security numbers, home addresses, or
personal phone numbers in their filings
unless an NRC regulation or other law
requires submission of such
information. With respect to
copyrighted works, except for limited
excerpts that serve the purpose of the
adjudicatory filings and would
constitute a Fair Use application,
participants should not include
copyrighted materials in their
submission.
For further details with respect to this
action, see the application for license
amendment dated June 18, 2021
(ADAMS Accession No. ML21169A004).
Attorney for licensee: Steven
Fleischer, PSEG Services Corporation,
80 Park Plaza, T–5, Newark, NJ 07102.
NRC Branch Chief: James G. Danna.
Dated: June 24, 2021.
For the Nuclear Regulatory Commission.
James S. Kim, Project Manager,
Plant Licensing Branch I, Division of
Operating Reactor Licensing, Office of
Nuclear Reactor Regulation.
[FR Doc. 2021–13896 Filed 6–29–21; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 72–01; NRC–2021–0122]
GE-Hitachi Nuclear Energy Americas,
LLC; Morris Operation
Nuclear Regulatory
Commission.
ACTION: License renewal application;
opportunity to request a hearing and to
petition for leave to intervene; order
imposing procedures.
AGENCY:
PO 00000
Frm 00078
Fmt 4703
Sfmt 4703
The U.S. Nuclear Regulatory
Commission (NRC) staff received and is
considering an application for the
renewal of special nuclear materials
(SNM) License No. SNM–2500, which
currently authorizes GE-Hitachi Nuclear
Energy Americas, LLC (GEH), to
possess, transfer, and store radioactive
material at the Morris Operation. The
renewed license would authorize GEH
to continue to store radioactive material
for an additional 20 years from May 31,
2022, the expiration date of the current
license. Because this license renewal
application contains Sensitive
Unclassified Non-Safeguards
Information (SUNSI), an order imposes
procedures to obtain access to SUNSI
for contention preparation.
DATES: A request for a hearing or
petition for leave to intervene must be
filed by August 30, 2021. Any potential
party as defined in section 2.4 of title 10
of the Code of Federal Regulations (10
CFR) who believes access to SUNSI is
necessary to respond to this notice must
request document access by July 12,
2021.
ADDRESSES: Please refer to Docket ID
NRC–2021–0122 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2021–0122. Address
questions about Docket IDs in
Regulations.gov to Stacy Schumann;
telephone: 301–415–0624; email:
Stacy.Schumann@nrc.gov. For technical
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced (if it is
available in ADAMS) is provided the
first time that it is mentioned in this
document.
• Attention: The PDR, where you may
examine and order copies of public
documents, is currently closed. You
may submit your request to the PDR via
email at pdr.resource@nrc.gov or call 1–
800–397–4209 or 301–415–4737,
SUMMARY:
E:\FR\FM\30JNN1.SGM
30JNN1
Agencies
[Federal Register Volume 86, Number 123 (Wednesday, June 30, 2021)]
[Notices]
[Pages 34788-34790]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-13896]
[[Page 34788]]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-311; NRC-2021-0131]
PSEG Nuclear, LLC; Exelon Generation Company, LLC; Salem Nuclear
Generating Station, Unit No. 2
AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment application; opportunity to comment, request
a hearing, and petition for leave to intervene.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of amendments to Renewed Facility Operating License No. DPR-
75, issued to PSEG Nuclear, LLC, for operation of the Salem Nuclear
Generating Station, Unit No. 2. The proposed amendments would revise
Technical Specification (TS) actions for rod position indicators. This
is a one-time change during the current operating cycle to support
maintenance on the transformer supplying power to all of the Unit No. 2
rod position indicators.
DATES: Submit comments by July 30, 2021. Request for a hearing or
petitions for leave to intervene must be filed by August 30, 2021.
ADDRESSES: You may submit comments by any of the following methods;
however, the NRC encourages electronic comment submission through the
Federal Rulemaking website:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0131. Address
questions about Docket IDs in Regulations.gov to Stacy Schumann;
telephone: 301-415-0624; email: [email protected]. For technical
questions, contact the individuals listed in the FOR FURTHER
INFORMATION CONTACT section of this document.
Mail comments to: Office of Administration, Mail Stop:
TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001, ATTN: Program Management, Announcements and Editing Staff.
For additional direction on obtaining information and submitting
comments, see ``Obtaining Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: James S. Kim, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001, telephone: 301-415-6606, email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC-2021-0131, facility name, unit
number(s), docket number(s), application date, and subject, if
applicable, when contacting the NRC about the availability of
information for this action. You may obtain publicly available
information related to this action by any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0131.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room reference staff at 1-800-397-4209, 301-415-4737, or by
email to [email protected]. The ADAMS accession number for each
document referenced (if it is available in ADAMS) is provided the first
time that it is mentioned in this document.
Attention: The PDR, where you may examine and order copies of
public documents, is currently closed. You may submit your request to
the PDR via email at [email protected] or call 1-800-397-4209 or
301-415-4737, between 8:00 a.m. and 4:00 p.m. (EST), Monday through
Friday, except Federal holidays.
B. Submitting Comments
The NRC encourages electronic comment submission through the
Federal Rulemaking website (https://www.regulations.gov). Please
include Docket ID NRC-2021-0131 in your comment submission.
The NRC cautions you not to include identifying or contact
information that you do not want to be publicly disclosed in your
comment submission. The NRC will post all comment submissions at
https://www.regulations.gov as well as enter the comment submissions
into ADAMS. The NRC does not routinely edit comment submissions to
remove identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publicly disclosed in their comment submission. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment into ADAMS.
II. Introduction
The NRC is considering issuance of amendments to Renewed Facility
Operating License No. DPR-75, issued to PSEG Nuclear LLC, for operation
of the Salem Nuclear Generating Station, Unit No. 2, located in Salem
County, New Jersey.
The proposed amendments would revise TS 3.1.3.2.1, ``Position
Indication Systems--Operating,'' to modify TS Action b.4 for more than
one inoperable analog rod position indicator per group from 24 hours to
30 hours. This is a one-time change during the current operating cycle
to support maintenance on the transformer supplying power to all of the
Unit No. 2 rod position indicators.
Before any issuance of the proposed license amendment, the NRC will
need to make the findings required by the Atomic Energy Act of 1954, as
amended (the Act), and NRC's regulations.
The NRC has made a proposed determination that the license
amendment request involves no significant hazards consideration. Under
the NRC's regulations in Sec. 50.92 of title 10 of the Code of Federal
Regulations (10 CFR), this means that operation of the facility in
accordance with the proposed amendment would not (1) involve a
significant increase in the probability or consequences of an accident
previously evaluated; or (2) create the possibility of a new or
different kind of accident from any accident previously evaluated; or
(3) involve a significant reduction in a margin of safety. As required
by 10 CFR 50.91(a), the licensee has provided its analysis of the issue
of no significant hazards consideration, which is presented below:
1. Does the proposed change involve a significant increase in
the probability or consequences of an accident previously evaluated?
Response: No.
Rod position indication instrumentation is not an accident
initiator, providing indication only of the control and shutdown
rods positions. Normal operation, abnormal occurrences and accident
analyses assume the rods are at certain positions within the reactor
core. The proposed one-time change modifies the time that rod
position indication may be inoperable. The existing TS Actions and
other plant instrumentation provide appropriate compensation for
that inoperability. Thus, this change does not involve a significant
increase in the probability of an accident.
[[Page 34789]]
Extending the allowed outage time to restore inoperable rod
position indicators does not affect the operability of the shutdown
or control rods. With rod position indicators inoperable, the
position of non-indicating rods is required to be verified by
indirect means (i.e., moveable incore detectors). Thus, inoperable
rod position indication instrumentation does not involve an increase
in the consequences of an accident. The inoperable rod position
indication does not have any impact on the ability to trip the
reactor in response to analyzed accidents and transients.
Therefore, the proposed change does not represent a significant
increase in the probability or consequences of an accident
previously evaluated.
2. Does the proposed change create the possibility of a new or
different kind of accident from any accident previously evaluated?
Response: No.
The proposed change does not alter the design, function, or
operation of any plant component and does not install any new or
different equipment. The proposed change will not impose any new or
different requirement or introduce a new accident initiator,
accident precursor, or malfunction mechanism.
Therefore, the proposed one-time change does not create the
possibility of a new or different kind of accident from any accident
previously evaluated.
3. Does the proposed change involve a significant reduction in a
margin of safety?
Response: No.
Loss of rod position indication does not cause a rod to be
misaligned. With rod position indicators inoperable, the control
rods are required to be placed in manual control, and the position
of non-indicating rods is required to be verified using indirect
means. The proposed change will not affect the ability of the
shutdown or control rods to perform their required function.
The proposed amendment will not result in a design basis or
safety limit being exceeded or altered. Therefore, since the
proposed change does not impact the response of the plant to a
design basis accident, the proposed change does not involve a
significant reduction in a margin of safety.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the 3 standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
license amendment request involves no significant hazards
consideration.
The NRC is seeking public comments on this proposed determination
that the license amendment request involves no significant hazards
consideration. Any comments received within 30 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of the 60 day notice period. However, if circumstances
change during the notice period, such that failure to act in a timely
way would result, for example, in derating or shutdown of the facility,
the Commission may issue the license amendment before the expiration of
the notice period, provided that its final determination is that the
amendment involves no significant hazards consideration. The final
determination will consider all public and State comments received. If
the Commission takes action prior to the expiration of either the
comment period or the notice period, it will publish in the Federal
Register a notice of issuance. The Commission expects that the need to
take this action will occur very infrequently.
III. Opportunity To Request a Hearing and Petition for Leave To
Intervene
Within 60 days after the date of publication of this notice, any
person (petitioner) whose interest may be affected by this action may
file a request for a hearing and petition for leave to intervene
(petition) with respect to the action. Petitions shall be filed in
accordance with the Commission's ``Agency Rules of Practice and
Procedure'' in 10 CFR part 2. Interested persons should consult 10 CFR
2.309. If a petition is filed, the presiding officer will rule on the
petition and, if appropriate, a notice of a hearing will be issued.
Petitions must be filed no later than 60 days from the date of
publication of this notice in accordance with the filing instructions
in the ``Electronic Submissions (E-Filing'') section of this document.
Petitions and motions for leave to file new or amended contentions that
are filed after the deadline will not be entertained absent a
determination by the presiding officer that the filing demonstrates
good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i)
through (iii).
If a hearing is requested and the Commission has not made a final
determination on the issue of no significant hazards consideration, the
Commission will make a final determination on the issue of no
significant hazards consideration, which will serve to establish when
the hearing is held. If the final determination is that the amendment
request involves no significant hazards consideration, the Commission
may issue the amendment and make it immediately effective,
notwithstanding the request for a hearing. Any hearing would take place
after issuance of the amendment. If the final determination is that the
amendment request involves a significant hazards consideration, then
any hearing held would take place before the issuance of the amendment
unless the Commission finds an imminent danger to the health or safety
of the public, in which case it will issue an appropriate order or rule
under 10 CFR part 2.
A State, local governmental body, Federally recognized Indian
Tribe, or designated agency thereof, may submit a petition to the
Commission to participate as a party under 10 CFR 2.309(h) no later
than 60 days from the date of publication of this notice.
Alternatively, a State, local governmental body, Federally recognized
Indian Tribe, or agency thereof may participate as a non-party under 10
CFR 2.315(c).
For information about filing a petition and about participation by
a person not a party under 10 CFR 2.315, see ADAMS Accession No.
ML20340A053 and on the NRC website at https://www.nrc.gov/about-nrc/regulatory/adjudicatory/hearing.html#participate.
IV. Electronic Submissions (E-Filing)
All documents filed in NRC adjudicatory proceedings including
documents filed by an interested State, local governmental body,
Federally recognized Indian Tribe, or designated agency thereof that
requests to participate under 10 CFR 2.315(c), must be filed in
accordance with 10 CFR 2.302. The E-Filing process requires
participants to submit and serve all adjudicatory documents over the
internet, or in some cases, to mail copies on electronic storage media,
unless an exemption permitting an alternative filing method, as
discussed below, is granted. Detailed guidance on electronic
submissions is located in the Guidance for Electronic Submissions to
the NRC (ADAMS Accession No. ML13031A056) and on the NRC website at
https://www.nrc.gov/site-help/e-submittals.html.
To comply with the procedural requirements of E-Filing, at least 10
days prior to the filing deadline, the participant should contact the
Office of the Secretary by email at [email protected], or by
telephone at 301-415-1677, to (1) request a digital identification (ID)
certificate, which allows the participant (or its counsel or
representative) to digitally sign submissions and access the E-Filing
system for any proceeding in which it is participating; and (2) advise
the Secretary that the participant will be submitting a petition or
other adjudicatory document (even in instances in which the
participant, or its counsel or representative, already holds
[[Page 34790]]
an NRC-issued digital ID certificate). Based upon this information, the
Secretary will establish an electronic docket for the proceeding if the
Secretary has not already established an electronic docket.
Information about applying for a digital ID certificate is
available on the NRC's public website at https://www.nrc.gov/site-help/e-submittals/getting-started.html. After a digital ID certificate is
obtained and a docket created, the participant must submit adjudicatory
documents in Portable Document Format. Guidance on submissions is
available on the NRC's public website at https://www.nrc.gov/site-help/electronic-sub-ref-mat.html. A filing is considered complete at the
time the document is submitted through the NRC's E-Filing system. To be
timely, an electronic filing must be submitted to the E-Filing system
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of
a transmission, the E-Filing system timestamps the document and sends
the submitter an email confirming receipt of the document. The E-Filing
system also distributes an email that provides access to the document
to the NRC's Office of the General Counsel and any others who have
advised the Office of the Secretary that they wish to participate in
the proceeding, so that the filer need not serve the document on those
participants separately. Therefore, applicants and other participants
(or their counsel or representative) must apply for and receive a
digital ID certificate before adjudicatory documents are filed to
obtain access to the documents via the E-Filing system.
A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC's Electronic
Filing Help Desk through the ``Contact Us'' link located on the NRC's
public website at https://www.nrc.gov/site-help/e-submittals.html, by
email to [email protected], or by a toll-free call at 1-866-672-
7640. The NRC Electronic Filing Help Desk is available between 9 a.m.
and 6 p.m., Eastern Time, Monday through Friday, excluding government
holidays.
Participants who believe that they have good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial paper filing
stating why there is good cause for not filing electronically and
requesting authorization to continue to submit documents in paper
format. Such filings must be submitted in accordance with 10 CFR
2.302(b)-(d). Participants filing adjudicatory documents in this manner
are responsible for serving their documents on all other participants.
Participants granted an exemption under 10 CFR 2.302(g)(2) must still
meet the electronic formatting requirement in 10 CFR 2.302(g)(1),
unless the participant also seeks and is granted an exemption from 10
CFR 2.302(g)(1).
Documents submitted in adjudicatory proceedings will appear in the
NRC's electronic hearing docket, which is publicly available at https://adams.nrc.gov/ehd, unless excluded pursuant to an order of the
presiding officer. If you do not have an NRC-issued digital ID
certificate as described above, click ``cancel'' when the link requests
certificates and you will be automatically directed to the NRC's
electronic hearing dockets where you will be able to access any
publicly available documents in a particular hearing docket.
Participants are requested not to include personal privacy information
such as social security numbers, home addresses, or personal phone
numbers in their filings unless an NRC regulation or other law requires
submission of such information. With respect to copyrighted works,
except for limited excerpts that serve the purpose of the adjudicatory
filings and would constitute a Fair Use application, participants
should not include copyrighted materials in their submission.
For further details with respect to this action, see the
application for license amendment dated June 18, 2021 (ADAMS Accession
No. ML21169A004).
Attorney for licensee: Steven Fleischer, PSEG Services Corporation,
80 Park Plaza, T-5, Newark, NJ 07102.
NRC Branch Chief: James G. Danna.
Dated: June 24, 2021.
For the Nuclear Regulatory Commission.
James S. Kim, Project Manager,
Plant Licensing Branch I, Division of Operating Reactor Licensing,
Office of Nuclear Reactor Regulation.