ANR Pipeline Company; Notice of Scoping Period Requesting Comments on Environmental Issues for The Proposed Skunk River Replacement Project, 33272-33274 [2021-13295]
Download as PDF
khammond on DSKJM1Z7X2PROD with NOTICES
33272
Federal Register / Vol. 86, No. 119 / Thursday, June 24, 2021 / Notices
Filed Date: 6/14/21.
Accession Number: 20210614–5068.
Comments Due: 5 p.m. ET 7/6/21.
Docket Numbers: ER21–2126–000.
Applicants: American Electric Power
Service Corporation, Ohio Power
Company, PJM Interconnection, L.L.C.
Description: § 205(d) Rate Filing: AEP
submits Two FAs re: ILDSA SA No.
1336 to be effective 8/14/2021.
Filed Date: 6/14/21.
Accession Number: 20210614–5040.
Comments Due: 5 p.m. ET 7/6/21.
Docket Numbers: ER21–2127–000.
Applicants: AEP Texas Inc.
Description: § 205(d) Rate Filing:
AEPTX–AP Solar 4 (Charger Solar) GIA
to be effective 6/5/2021.
Filed Date: 6/14/21.
Accession Number: 20210614–5045.
Comments Due: 5 p.m. ET 7/6/21.
Docket Numbers: ER21–2128–000.
Applicants: 0HAM WHAM8 SOLAR,
LLC.
Description: Baseline eTariff Filing:
Application for Market-Based Rate
Authorization under Section 205 of the
FPA to be effective 8/14/2021.
Filed Date: 6/14/21.
Accession Number: 20210614–5046.
Comments Due: 5 p.m. ET 7/6/21.
Docket Numbers: ER21–2129–000.
Applicants: 276FED WHAM8 SOLAR,
LLC.
Description: Baseline eTariff Filing:
Application for Market-Based Rate
Authorization under Section 205 of the
FPA to be effective 8/14/2021.
Filed Date: 6/14/21.
Accession Number: 20210614–5047.
Comments Due: 5 p.m. ET 7/6/21.
Docket Numbers: ER21–2130–000.
Applicants: Public Service Company
of Oklahoma.
Description: § 205(d) Rate Filing:
PSO–AECI Mazie Delivery Point
Agreement to be effective 6/5/2021.
Filed Date: 6/14/21.
Accession Number: 20210614–5049.
Comments Due: 5 p.m. ET 7/6/21.
Docket Numbers: ER21–2131–000.
Applicants: AEP Texas Inc.
Description: § 205(d) Rate Filing:
AEPTX–BRP Antlia BESS GIA to be
effective 6/5/2021.
Filed Date: 6/14/21.
Accession Number: 20210614–5054.
Comments Due: 5 p.m. ET 7/6/21.
Docket Numbers: ER21–2132–000.
Applicants: Florida Power & Light
Company.
Description: § 205(d) Rate Filing: FPLSeminole Amendments to Exhibit A of
Contract for Interconnected Operations
to be effective 6/1/2021.
Filed Date: 6/14/21.
Accession Number: 20210614–5067.
VerDate Sep<11>2014
19:19 Jun 23, 2021
Jkt 253001
Comments Due: 5 p.m. ET 7/6/21.
Docket Numbers: ER21–2133–000.
Applicants: Midcontinent
Independent System Operator, Inc., AEP
Indiana Michigan Transmission
Company.
Description: Compliance filing: 2021–
06–14_AEP IMTCO Compliance Filing
to be effective 4/15/2021.
Filed Date: 6/14/21.
Accession Number: 20210614–5098.
Comments Due: 5 p.m. ET 7/6/21.
Docket Numbers: ER21–2134–000.
Applicants: Basin Electric Power
Cooperative.
Description: Tariff Cancellation: Basin
Electric Notice of Cancellation for
Service Agreement No. 26 to be effective
3/2/2021.
Filed Date: 6/14/21.
Accession Number: 20210614–5111.
Comments Due: 5 p.m. ET 7/6/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/fercgen
search.asp) by querying the docket
number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: June 14, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–13422 Filed 6–23–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–446–000]
ANR Pipeline Company; Notice of
Scoping Period Requesting Comments
on Environmental Issues for The
Proposed Skunk River Replacement
Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document, that will
PO 00000
Frm 00067
Fmt 4703
Sfmt 4703
discuss the environmental impacts of
the Skunk River Replacement Project
involving the abandonment and
construction of facilities by ANR
Pipeline Company (ANR) in Henry
County, Iowa. The Commission will use
this environmental document in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
project. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
issuing a Certificate of Public
Convenience and Necessity. This
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and Environmental Document section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 pm Eastern Time on July 17,
2021. Comments may be submitted in
written form. Further details on how to
submit comments are provided in the
Public Participation section of this
notice.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
Your input will help the Commission
staff determine what issues they need to
evaluate in the environmental
document. Commission staff will
consider all written comments during
the preparation of the environmental
document.
If you submitted comments on this
project to the Commission before the
opening of this docket on May 20, 2021,
you will need to file those comments in
Docket No. CP21–446–000 to ensure
they are considered as part of this
proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
E:\FR\FM\24JNN1.SGM
24JNN1
Federal Register / Vol. 86, No. 119 / Thursday, June 24, 2021 / Notices
khammond on DSKJM1Z7X2PROD with NOTICES
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, the Natural Gas Act conveys
the right of eminent domain to the
company. Therefore, if you and the
company do not reach an easement
agreement, the pipeline company could
initiate condemnation proceedings in
court. In such instances, compensation
would be determined by a judge in
accordance with state law. The
Commission does not subsequently
grant, exercise, or oversee the exercise
of that eminent domain authority. The
courts have exclusive authority to
handle eminent domain cases; the
Commission has no jurisdiction over
these matters.
ANR provided landowners with a fact
sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
which addresses typically asked
questions, including the use of eminent
domain and how to participate in the
Commission’s proceedings. This fact
sheet along with other landowner topics
of interest are available for viewing on
the FERC website (www.ferc.gov) under
the Natural Gas Questions or
Landowner Topics link.
Public Participation
There are three methods you can use
to submit your comments to the
Commission.
Please carefully follow these
instructions so that your comments are
properly recorded. The Commission
encourages electronic filing of
comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
VerDate Sep<11>2014
19:19 Jun 23, 2021
Jkt 253001
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP21–446–000)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Additionally, the Commission offers a
free service called eSubscription which
makes it easy to stay informed of all
issuances and submittals regarding the
dockets/projects to which you
subscribe. These instant email
notifications are the fastest way to
receive notification and provide a link
to the document files which can reduce
the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
Summary of the Proposed Project
Specifically, ANR seeks authority to
abandon, remove, and construct
pipeline facilities in Henry County,
Iowa, as follows:
• Construction of approximately
1,880 feet of 24-inch-diameter pipeline
using horizontal directional drill
method;
• abandonment in-place of
approximately 1,500 feet of 24-inchdiameter pipeline; and
• removal of approximately 380 feet
of 24-inch-diameter pipeline.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Land requirements for the proposed
Project total approximately 22 acres,
with operation of the pipeline requiring
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’. For instructions on
connecting to eLibrary, refer to the last page of this
notice. At this time, the Commission has suspended
access to the Commission’s Public Reference Room
due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus
Disease (COVID–19), issued by the President on
March 13, 2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll free, (886)
208–3676 or TTY (202) 502–8659.
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
33273
5.1 acres. The land requirements for the
Project include the existing permanent
right-of-way, additional temporary
workspace areas, a contractor staging
area, and temporary access roads.
NEPA Process and the Environmental
Document
Any environmental document issued
by the Commission will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under the relevant
general resource areas:
• Geology and soils;
• water resources and wetlands;
• vegetation and wildlife;
• threatened and endangered species;
• cultural resources;
• land use;
• air quality and noise; and
• reliability and safety.
Commission staff will also evaluate
reasonable alternatives to the proposed
project or portions of the project and
make recommendations on how to
lessen or avoid impacts on the various
resource areas. Your comments will
help Commission staff identify and
focus on the issues that might have an
effect on the human environment and
potentially eliminate others from further
study and discussion in the
environmental document.
Following this scoping period,
Commission staff will determine
whether to prepare an Environmental
Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the
EIS will present Commission staff’s
independent analysis of the issues. If
Commission staff prepares an EA, a
Notice of Schedule for the Preparation
of an Environmental Assessment will be
issued. The EA may be issued for an
allotted public comment period. The
Commission would consider timely
comments on the EA before making its
decision regarding the proposed project.
If Commission staff prepares an EIS, a
Notice of Intent to Prepare an EIS/
Notice of Schedule will be issued,
which will open up an additional
comment period. Staff will then prepare
a draft EIS which will be issued for
public comment. Commission staff will
consider all timely comments received
during the comment period on the draft
EIS and revise the document, as
necessary, before issuing a final EIS.
Any EA or draft and final EIS will be
available in electronic format in the
public record through eLibrary 2 and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
2 For instructions on connecting to eLibrary, refer
to the last page of this notice.
E:\FR\FM\24JNN1.SGM
24JNN1
33274
Federal Register / Vol. 86, No. 119 / Thursday, June 24, 2021 / Notices
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the
environmental document is issued.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this project
to formally cooperate in the preparation
of the environmental document.3
Agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this notice.
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
potential effects on historic properties.4
The environmental document for this
project will document findings on the
impacts on historic properties and
summarize the status of consultations
under section 106.
khammond on DSKJM1Z7X2PROD with NOTICES
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project and includes a
mailing address with their comments.
Commission staff will update the
environmental mailing list as the
analysis proceeds to ensure that
Commission notices related to this
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Section 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
19:19 Jun 23, 2021
Jkt 253001
environmental review are sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
If you need to make changes to your
name/address, or if you would like to
remove your name from the mailing list,
please complete one of the following
steps:
(1) Send an email to
GasProjectAddressChange@ferc.gov
stating your request. You must include
the docket number CP21–446–000 in
your request. If you are requesting a
change to your address, please be sure
to include your name and the correct
address. If you are requesting to delete
your address from the mailing list,
please include your name and address
as it appeared on this notice. This email
address is unable to accept comments.
OR
(2) Return the attached ‘‘Mailing List
Update Form’’ (appendix 2).
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or (866)
208–3676, or for TTY, contact (202)
502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Dated: June 17, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–13295 Filed 6–23–21; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–457–000]
Dominion Energy Questar Pipeline,
LLC; Notice of Request Under Blanket
Authorization and Establishing
Intervention and Protest Deadline
Take notice that on June 3, 2021,
Dominion Energy Questar Pipeline,
LLC, (DEQP), 333 South State Street,
Salt Lake City, Utah 84111 filed in the
above referenced docket a prior notice
pursuant to its blanket certificate
authority granted in Docket No. CP82–
491–000 1 and sections 157.205, 157.208
and 157.210 of the Federal Energy
Regulatory Commission’s regulations
under the Natural Gas Act, requesting
authorization to construct facilities and
make automation and communication
updates at the Skull Creek Compressor
Station (Skull Creek CS). The Skull
Creek Expansion Project (Project)
proposes to remove a capacity
constraint at Skull Creek CS and thereby
restore the operationally available
capacity on Main Line (ML) 86 by
17,750 Dth/d, while remaining within
the currently certificated capacity of the
existing facilities. DEQP owns and
operates Skull Creek CS, located on ML
86, near the border of Colorado in
Sweetwater County, WY. ML 86 extends
perpendicularly from DEQP’s ML 22/23
Junction located in Moffat County, CO,
approximately 26 miles north to the
Southern Star Central Gas Pipeline, Inc
(Southern Star) interconnect located in
the southeast section of Sweetwater
County, WY. The project will cause no
adverse impacts or reduction of service
to any existing customers on DEQP. The
estimated cost for the Project is
approximately $1,322,000, all as more
fully set forth in the request which is on
file with the Commission and open to
public inspection.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
1 Mountain Fuel Resources, Inc., 20 FERC
¶ 62,580 (1982).
Frm 00069
Fmt 4703
Sfmt 4703
E:\FR\FM\24JNN1.SGM
24JNN1
Agencies
[Federal Register Volume 86, Number 119 (Thursday, June 24, 2021)]
[Notices]
[Pages 33272-33274]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-13295]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP21-446-000]
ANR Pipeline Company; Notice of Scoping Period Requesting
Comments on Environmental Issues for The Proposed Skunk River
Replacement Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document, that will discuss
the environmental impacts of the Skunk River Replacement Project
involving the abandonment and construction of facilities by ANR
Pipeline Company (ANR) in Henry County, Iowa. The Commission will use
this environmental document in its decision-making process to determine
whether the project is in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers issuing
a Certificate of Public Convenience and Necessity. This gathering of
public input is referred to as ``scoping.'' The main goal of the
scoping process is to focus the analysis in the environmental document
on the important environmental issues. Additional information about the
Commission's NEPA process is described below in the NEPA Process and
Environmental Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 pm Eastern Time on July 17, 2021. Comments may be submitted
in written form. Further details on how to submit comments are provided
in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues they need to evaluate in the environmental document. Commission
staff will consider all written comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on May 20, 2021, you will need to file those
comments in Docket No. CP21-446-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should
[[Page 33273]]
notify their constituents of this proposed project and encourage them
to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, the Natural Gas Act conveys the right of eminent
domain to the company. Therefore, if you and the company do not reach
an easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law. The Commission does
not subsequently grant, exercise, or oversee the exercise of that
eminent domain authority. The courts have exclusive authority to handle
eminent domain cases; the Commission has no jurisdiction over these
matters.
ANR provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' which addresses typically asked questions, including
the use of eminent domain and how to participate in the Commission's
proceedings. This fact sheet along with other landowner topics of
interest are available for viewing on the FERC website (www.ferc.gov)
under the Natural Gas Questions or Landowner Topics link.
Public Participation
There are three methods you can use to submit your comments to the
Commission.
Please carefully follow these instructions so that your comments
are properly recorded. The Commission encourages electronic filing of
comments and has staff available to assist you at (866) 208-3676 or
[email protected].
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP21-
446-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
Summary of the Proposed Project
Specifically, ANR seeks authority to abandon, remove, and construct
pipeline facilities in Henry County, Iowa, as follows:
Construction of approximately 1,880 feet of 24-inch-
diameter pipeline using horizontal directional drill method;
abandonment in-place of approximately 1,500 feet of 24-
inch-diameter pipeline; and
removal of approximately 380 feet of 24-inch-diameter
pipeline.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary''. For instructions on
connecting to eLibrary, refer to the last page of this notice. At
this time, the Commission has suspended access to the Commission's
Public Reference Room due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus Disease (COVID-19),
issued by the President on March 13, 2020. For assistance, contact
FERC at [email protected] or call toll free, (886) 208-3676
or TTY (202) 502-8659.
---------------------------------------------------------------------------
Land Requirements for Construction
Land requirements for the proposed Project total approximately 22
acres, with operation of the pipeline requiring 5.1 acres. The land
requirements for the Project include the existing permanent right-of-
way, additional temporary workspace areas, a contractor staging area,
and temporary access roads.
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the construction and operation
of the proposed project under the relevant general resource areas:
Geology and soils;
water resources and wetlands;
vegetation and wildlife;
threatened and endangered species;
cultural resources;
land use;
air quality and noise; and
reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Following this scoping period, Commission staff will determine
whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission
staff's independent analysis of the issues. If Commission staff
prepares an EA, a Notice of Schedule for the Preparation of an
Environmental Assessment will be issued. The EA may be issued for an
allotted public comment period. The Commission would consider timely
comments on the EA before making its decision regarding the proposed
project. If Commission staff prepares an EIS, a Notice of Intent to
Prepare an EIS/Notice of Schedule will be issued, which will open up an
additional comment period. Staff will then prepare a draft EIS which
will be issued for public comment. Commission staff will consider all
timely comments received during the comment period on the draft EIS and
revise the document, as necessary, before issuing a final EIS. Any EA
or draft and final EIS will be available in electronic format in the
public record through eLibrary \2\ and the Commission's natural gas
environmental documents web page (https://www.ferc.gov/industries-data/
[[Page 33274]]
natural-gas/environment/environmental-documents). If eSubscribed, you
will receive instant email notification when the environmental document
is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Section 1501.6.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The environmental document for this
project will document findings on the impacts on historic properties
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to [email protected] stating your
request. You must include the docket number CP21-446-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments.
OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field. Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at [email protected] or (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: June 17, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-13295 Filed 6-23-21; 8:45 am]
BILLING CODE 6717-01-P