Download as PDF 31498 Federal Register / Vol. 86, No. 112 / Monday, June 14, 2021 / Notices MOD–032–1—Continued [Verification of models and data for turbine/governor and load control or active power/frequency control functions] Evidence Retention ................. Total ................................. Number of respondents Annual number of responses per respondent Total number of responses Average burden & cost per response Total annual burden hours & total annual cost Cost per respondent ($) (1) (2) (1) * (2) = (3) (4) (3) * (4) = (5) (5) ÷ (1) 1 1,418 1 hr.; $34.79 18 ....... 1,418 hrs.; $49,332.22. ........................ ........................ ................................ 12,762 hrs.; $998,484.70. 1,418 (BA, GO, PA/PC, RP, TO, TP, and TSP). ........................ 34.79 ........................ MOD–033–2 (FORMERLY MOD–033–1) [Steady-state and dynamics system model validation] Data Submittal ........................ Evidence Retention ................. MOD–033–2 Net Changes in RD20–4 (in the first table above). New Total for MOD–033– 2 Renewal. Number of respondents Annual number of responses per respondent Total number of responses Avg. burden & cost per response Total annual burden hours & total annual cost Cost per respondent ($) (1) (2) (1) * (2) = (3) (4) (3) * (4) = (5) (5) ÷ (1) 178 (RC and TOP). 243 (PA/PC, RC, and TOP). ........................ ........................ lotter on DSK11XQN23PROD with NOTICES1 The total annual estimated burden and cost for the FERC–725L information collection is 38,724 hours and $2,960,375.60 respectively. 12 The estimates reflect a program decrease of 63 de-registered LSEs (and corresponding program decrease of 504 hrs.) related to Docket No. RD20– 4–000, and an adjustment/clarification (decrease) of 498 DPs, TPs, and BAs (and corresponding decrease of 3,984 hrs.), not related to Docket No. RD20–4– 000. The updated number of 381 DPs, TPs and BAs is listed in a new row clarifying their applicability with Requirements R2 and R4. Requirement R2 requires applicable entities to develop and provide data pursuant with Requirement R1. 13 The 113 PCs and BAs were originally estimated in FERC–725A due to Order No. 693. However, the estimates and descriptions were not clearly spelled out, so we are clarifying them. [Some of this burden may still be in FERC–725A (and double counted temporarily).] 14 The estimate is changing to 174 (from 188) due to normal industry fluctuation. 15 The estimate is changing to 188 (from 194) due to normal industry fluctuation. 16 The number of respondents for MOD–025–2/ MOD–026–1/MOD–027–1/MOD–31–3/MOD–032-/ MOD–033–2 are from the NERC compliance registry February 5, 2021. 17 This wage figure uses the average hourly wage (plus benefits) for electrical engineers (Occupation Code: 17–2071, $70.19/hour) and managers (Occupation Code: 11–0000, $97.15/hour) obtained from the Bureau of Labor Statistics (BLS) (from https://www.bls.gov/oes/current/naics2_22.htm). VerDate Sep<11>2014 17:26 Jun 11, 2021 Jkt 253001 1 178 8 hrs.; $669.36 20 ... 1 243 1 hr.; $34.79 18 ....... 1,424 hrs.; $119,146.08. 243 hrs.; $8,453.97 ........................ ¥28 ................................ ¥126 ..................... ........................ ........................ 393 ................................ 1,541 hrs.; $128,935.47. ........................ Comments: Comments are invited on: (1) Whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use The average used the following calculation: [$70.19/hour + $97.15/hour] ÷ 2 = $83.67/hour. 18 The estimate uses the hourly average wage (plus benefits) for file clerks obtained from the Bureau of Labor Statistics: $34.79/hour (BLS Occupation Code: 43–4071). 19 It is estimated that the applicable numbers of generator owner respondents used to calculate the public reporting burden for these standards MOD– 026–1, MOD–027- 1, MOD–032–1 and MOD–033– 1 is half of total numbers of GO (501=1003/2) due to the higher applicability threshold for those Reliability Standards. 20 The estimate uses the average hourly wage (plus benefits) of $70.19/hour for electrical engineers (Occupation Code: 17–2071) from the Bureau of Labor Statistics. PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 $669.36 34.79 of automated collection techniques or other forms of information technology. Dated: June 8, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–12376 Filed 6–11–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. IC21–12–000] Commission Information Collection Activities (Ferc-725x); Comment Request; Extension Federal Energy Regulatory Commission. ACTION: Notice of information collection and request for comments. AGENCY: In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting public comment on a renewal of SUMMARY: E:\FR\FM\14JNN1.SGM 14JNN1 Federal Register / Vol. 86, No. 112 / Monday, June 14, 2021 / Notices currently approved information collection FERC 725X (Mandatory Reliability Standards: Voltage and Reactive (VAR) Standards), which will be submitted to the Office of Management and Budget (OMB) for review. Comments on the collection of information are due July 14, 2021. ADDRESSES: Send written comments on FERC–725X to OMB through www.reginfo.gov/public/do/PRAMain. Attention: Federal Energy Regulatory Commission Desk Officer. Please identify the OMB Control Number (1902–0278) in the subject line of your comments. Comments should be sent within 30 days of publication of this notice to www.reginfo.gov/public/do/ PRAMain. Please submit copies of your comments to the Commission. You may submit copies of your comments (identified by Docket No. IC21–12–000) by one of the following methods: Electronic filing through https:// www.ferc.gov, is preferred. • Electronic Filing: Documents must be filed in acceptable native applications and print-to-PDF, but not in scanned or picture format. • For those unable to file electronically, comments may be filed by USPS mail or by hand (including courier) delivery. Æ Mail via U.S. Postal Service Only: Addressed to: Federal Energy Regulatory Commission, Secretary of the Commission, 888 First Street NE, Washington, DC 20426. Æ Hand (including courier) delivery: Deliver to: Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. Instructions: OMB submissions must be formatted and filed in accordance with submission guidelines at www.reginfo.gov/public/do/PRAMain. Using the search function under the ‘‘Currently Under Review’’ field, select Federal Energy Regulatory Commission; click ‘‘submit,’’ and select ‘‘comment’’ to the right of the subject collection. FERC submissions must be formatted and filed in accordance with submission guidelines at: https://www.ferc.gov. For user assistance, contact FERC Online Support by email at ferconlinesupport@ ferc.gov, or by phone at: (866) 208–3676 (toll-free). Docket: Users interested in receiving automatic notification of activity in this docket or in viewing/downloading comments and issuances in this docket may do so at https://www.ferc.gov/ferconline/overview. FOR FURTHER INFORMATION CONTACT: Ellen Brown may be reached by email lotter on DSK11XQN23PROD with NOTICES1 DATES: VerDate Sep<11>2014 17:26 Jun 11, 2021 Jkt 253001 at DataClearance@FERC.gov, telephone at (202) 502–8663. SUPPLEMENTARY INFORMATION: Title: FERC 725X (Mandatory Reliability Standards: Voltage and Reactive (VAR) Standards). OMB Control No.: 1902–0278. Type of Request: Three-year extension of the FERC–725X information collection requirements with no changes to the current reporting requirements. Abstract: Pursuant to Section 215 of the Federal Power Act (FPA),1 North American Electric Reliability Corporation (NERC) established the Voltage and Reactive (‘‘VAR’’) group of Reliability Standards, which consists of two continent-wide Reliability Standards, VAR–001–5 and VAR–002– 4.1. NERC conducts periodic reviews of Reliability Standards in accordance with Section 317 of the NERC Rules of Procedure and Section 13 of the NERC Standard Processes Manual. In accordance with these authorities and the NERC Reliability Standards Development Plan: 2017–2019, NERC recently completed Project 2016–EPR– 02 Enhanced Periodic Review of Voltage and Reactive Reliability Standards. This project conducted a periodic review of mandatory and enforceable Reliability Standards VAR–001–4.1 (Voltage and Reactive Control) 2 and VAR–002–4 (Generator Operation for Maintaining Network Schedules).3 These two standards were designed to maintain voltage stability on the Bulk-Power System, protect transmission, generation, distribution, and customer equipment, and support the reliable operation of the Bulk-Power System. Voltage stability is the ability of a power system to maintain acceptable voltage levels throughout the system under normal operating conditions and following a disturbance. Failure to maintain acceptable voltage levels (i.e., voltage levels become too high or too low) may cause violations of System Operating Limits (‘‘SOLs’’) and Interconnection Reliability Operating Limits (‘‘IROLs’’), result in damage to Bulk-Power System equipment, and 16 U.S.C. 824o (2012). The Commission approved Reliability Standard VAR–001–4 (Voltage and Reactive Control) on August 1, 2014. See North American Electric Reliability Corp., Docket No. RD14–11–000 (Aug. 1, 2014) (delegated letter order). The Commission approved errata version VAR–001–4.1 on November 13, 2015. See North American Electric Reliability Corp., Docket No. RD15–6–000 (Nov. 13, 2015) (delegated letter order). 3 The Commission approved Reliability Standard VAR–002–4, which clarified the applicability of the VAR–002 standard to dispersed generation resources, on May 29, 2015. See North American Electric Reliability Corp, 151 FERC ¶ 61,186 (May 29, 2015). 1 2 PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 31499 thereby threaten the reliable operation of the Bulk-Power System. Reliability Standard VAR–001–5 This Reliability Standard requires Transmission Operators to: • Specify a system-wide voltage schedule (which is either a range or a target value with an associated tolerance band) as part of its plan to operate within SOLs and IROLs, and to provide the voltage schedule to its Reliability Coordinator and adjacent Transmission Operators upon request (Requirement R1); • Schedule sufficient reactive resources to regulate voltage levels (Requirement R2); • Operate or direct the operation of devices to regulate transmission voltage and reactive flows (Requirement R3); • Develop a set of criteria to exempt generators from certain requirements under Reliability Standard VAR–002– 4.1 related to voltage or Reactive Power schedules, automatic voltage regulations, and notification (Requirement R4); • Specify a voltage or Reactive Power schedule (which is either a range or a target value with an associated tolerance band) for generators at either the high or low voltage side of the generator stepup transformer, provide the schedule to the associated Generator Operator, direct the Generator Operator to comply with that schedule in automatic voltage control mode, provide the Generator Operator the notification requirements for deviating from the schedule, and, if requested, provide the Generator Operator the criteria used to develop the schedule (Requirement R5); and • Communicate step-up transformer tap changes, the time frame for completion, and the justification for these changes to Generator Owners (Requirement R6). Reliability Standard VAR–002–4.1 This Reliability Standard includes an information collection activity for ‘‘Requirement R1’’ and a separate information collection activity for ‘‘Requirements R2 through R6.’’ This Reliability Standard requires Generator Operators to: • Operate each of its generators connected to the interconnected transmission system in automatic voltage control mode or in a different control mode as instructed by the Transmission Operator, unless the Generator Operator (1) is exempted pursuant to the criteria developed under VAR–001–5, Requirement R4, or (2) makes certain notifications to the Transmission Operator specifying the E:\FR\FM\14JNN1.SGM 14JNN1 31500 Federal Register / Vol. 86, No. 112 / Monday, June 14, 2021 / Notices reasons it cannot so operate (Requirement R1); • Maintain the Transmission Operator’s generator voltage or Reactive Power schedule, unless the Generator Operator (1) is exempted pursuant to the criteria developed under VAR–001–5, Requirement R4, or (2) complies with the notification requirements for deviations as established by the Transmission Owner pursuant to VAR– 001–5, Requirement R5 (Requirement R2); • Notify the Transmission Operator of a change in status of its voltage controlling device within 30 minutes, unless the status is restored within that time period (Requirement R3); and • Notify the Transmission Operator of a change in reactive capability due to factors other than those described in VAR–002–4.1, Requirement R3 within 30 minutes unless the capability has been restored during that time period (Requirement R4). • Provide information on its step-up transformers and auxiliary transformers within 30 days of a request from the Transmission Operator or Transmission Planner (Requirement R5); and • Comply with the Transmission Operator’s step-up transformer tap change directives unless compliance would violate safety, an equipment rating, or applicable laws, rules or regulations (Requirement R6). The 60-day notice was published to the Federal Register on March 31, 2021 and received no comments. Type of Respondents: Generator operators and Transmission Operators. Estimate of Annual Burden: 4 The Commission estimates the annual public reporting burden for the information collection as: FERC–725X—MANDATORY RELIABILITY STANDARDS: VOLTAGE AND REACTIVE (VAR) STANDARDS Number of respondents 5 Annual number of responses per respondent Total number of responses Average burden & cost per response 6 Total annual burden hours & total annual cost Cost per respondent ($) (1) (2) (1) * (2) = (3) (4) (3) * (4) = (5) (5) ÷ (1) VAR–001–5 (Require- 167 (TOP) ......... ments R1–R6). VAR–002–4.1 (Re937 (GOP) ........ quirement R1). VAR–002–4.1 (Re937 (GOP) ........ quirements R2–R6). lotter on DSK11XQN23PROD with NOTICES1 Total ................... ........................... 1 167 160 hrs.; $11,230.40 1 937 80 hrs.; $5,615.20 .... 1 937 120 hrs.; $8,422.80 .. ........................ 2,041 ................................... 26,720 hrs.; $1,875,476.80. 74,960 hrs.; $5,261,442.4. 112,440 hrs.; $7,892,163.6. 214,120 hrs.; $15,029,082.80. $11,230.40 5,615.20 8,422.80 ........................ The burden for the FERC–725X information collection includes estimates related to both of the previously approved Reliability Standards (VAR–001–4.2 and VAR– 002–4.1). The total annual burden and cost of the FERC–725X information collection is 214,120 hours and $15,029,083 (rounded). Comments: Comments are invited on: (1) Whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology. Dated: June 8, 2021. Kimberly D. Bose, Secretary. The Administrator, Southwestern Power Administration (Southwestern), is proposing a two-year extension to the currently approved rate schedules for the Integrated System, the Sam Rayburn Dam, and the Robert Douglas Willis Hydropower Project (Robert D. Willis) for the period of October 1, 2021 to September 30, 2023. Southwestern’s current Integrated System rate schedules (P–13A, NFTS– 13A, and EE–13), the Sam Rayburn Dam rate schedule (SRD–15), and the Robert D. Willis rate schedule (RDW–15), expire September 30, 2021. DATES: The consultation and comment period will begin on June 14, 2021 and will end on July 14, 2021. Written comments are due on or before July 14, 2021. ADDRESSES: Comments should be submitted to Ms. Fritha Ohlson, Senior Vice President and Chief Operating Officer, Southwestern Power Administration, U.S. Department of Energy, One West Third Street, Tulsa, Oklahoma 74103. FOR FURTHER INFORMATION CONTACT: Ms. Fritha Ohlson, Senior Vice President, Chief Operating Officer, Office of Corporate Operations, (918) 595–6684, fritha.ohlson@swpa.gov, or facsimile transmission (918) 595–6684. SUPPLEMENTARY INFORMATION: Originally established by Order 1865, Secretary of the Interior, dated August 31, 1943 and effective September 1, 1943 (8 FR 12142 (Sept. 3, 1943)), Southwestern is 4 The Commission defines burden as the total time, effort, or financial resources expended by persons to generate, maintain, retain, or disclose or provide information to or for a Federal agency. For further explanation of what is included in the information collection burden, reference 5 Code of Federal Regulations 1320.3. 5 TOP = transmission operator; GOP = generator operators. Respondent counts based of the NERC Compliance Registry numbers February 5, 2021. 6 The estimate for hourly cost is $70.19/hour. This figure is the average salary plus benefits for an electrical engineer (Occupation Code: 17–2071) from the Bureau of Labor Statistics (May 2020) at https://www.bls.gov/oes/current/naics2_22.htm. VerDate Sep<11>2014 17:26 Jun 11, 2021 Jkt 253001 [FR Doc. 2021–12377 Filed 6–11–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Southwestern Power Administration Integrated System, Sam Rayburn Dam, and Robert D. Willis Rate Schedules Southwestern Power Administration, DOE. ACTION: Notice of proposed rate schedules extension and opportunity for public review and comment. AGENCY: SUMMARY: PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 E:\FR\FM\14JNN1.SGM 14JNN1

Agencies

[Federal Register Volume 86, Number 112 (Monday, June 14, 2021)]
[Notices]
[Pages 31498-31500]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-12377]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. IC21-12-000]


Commission Information Collection Activities (Ferc-725x); Comment 
Request; Extension

AGENCY: Federal Energy Regulatory Commission.

ACTION: Notice of information collection and request for comments.

-----------------------------------------------------------------------

SUMMARY: In compliance with the requirements of the Paperwork Reduction 
Act of 1995, the Federal Energy Regulatory Commission (Commission or 
FERC) is soliciting public comment on a renewal of

[[Page 31499]]

currently approved information collection FERC 725X (Mandatory 
Reliability Standards: Voltage and Reactive (VAR) Standards), which 
will be submitted to the Office of Management and Budget (OMB) for 
review.

DATES: Comments on the collection of information are due July 14, 2021.

ADDRESSES: Send written comments on FERC-725X to OMB through 
www.reginfo.gov/public/do/PRAMain. Attention: Federal Energy Regulatory 
Commission Desk Officer. Please identify the OMB Control Number (1902-
0278) in the subject line of your comments. Comments should be sent 
within 30 days of publication of this notice to www.reginfo.gov/public/do/PRAMain.
    Please submit copies of your comments to the Commission. You may 
submit copies of your comments (identified by Docket No. IC21-12-000) 
by one of the following methods:
    Electronic filing through https://www.ferc.gov, is preferred.
     Electronic Filing: Documents must be filed in acceptable 
native applications and print-to-PDF, but not in scanned or picture 
format.
     For those unable to file electronically, comments may be 
filed by USPS mail or by hand (including courier) delivery.
    [cir] Mail via U.S. Postal Service Only: Addressed to: Federal 
Energy Regulatory Commission, Secretary of the Commission, 888 First 
Street NE, Washington, DC 20426.
    [cir] Hand (including courier) delivery: Deliver to: Federal Energy 
Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852.
    Instructions: OMB submissions must be formatted and filed in 
accordance with submission guidelines at www.reginfo.gov/public/do/PRAMain. Using the search function under the ``Currently Under Review'' 
field, select Federal Energy Regulatory Commission; click ``submit,'' 
and select ``comment'' to the right of the subject collection.
    FERC submissions must be formatted and filed in accordance with 
submission guidelines at: https://www.ferc.gov. For user assistance, 
contact FERC Online Support by email at [email protected], or 
by phone at: (866) 208-3676 (toll-free).
    Docket: Users interested in receiving automatic notification of 
activity in this docket or in viewing/downloading comments and 
issuances in this docket may do so at https://www.ferc.gov/ferc-online/overview.

FOR FURTHER INFORMATION CONTACT: Ellen Brown may be reached by email at 
[email protected], telephone at (202) 502-8663.

SUPPLEMENTARY INFORMATION:
    Title: FERC 725X (Mandatory Reliability Standards: Voltage and 
Reactive (VAR) Standards).
    OMB Control No.: 1902-0278.
    Type of Request: Three-year extension of the FERC-725X information 
collection requirements with no changes to the current reporting 
requirements.
    Abstract: Pursuant to Section 215 of the Federal Power Act 
(FPA),\1\ North American Electric Reliability Corporation (NERC) 
established the Voltage and Reactive (``VAR'') group of Reliability 
Standards, which consists of two continent-wide Reliability Standards, 
VAR-001-5 and VAR-002-4.1. NERC conducts periodic reviews of 
Reliability Standards in accordance with Section 317 of the NERC Rules 
of Procedure and Section 13 of the NERC Standard Processes Manual. In 
accordance with these authorities and the NERC Reliability Standards 
Development Plan: 2017-2019, NERC recently completed Project 2016-EPR-
02 Enhanced Periodic Review of Voltage and Reactive Reliability 
Standards. This project conducted a periodic review of mandatory and 
enforceable Reliability Standards VAR-001-4.1 (Voltage and Reactive 
Control) \2\ and VAR-002-4 (Generator Operation for Maintaining Network 
Schedules).\3\ These two standards were designed to maintain voltage 
stability on the Bulk-Power System, protect transmission, generation, 
distribution, and customer equipment, and support the reliable 
operation of the Bulk-Power System. Voltage stability is the ability of 
a power system to maintain acceptable voltage levels throughout the 
system under normal operating conditions and following a disturbance. 
Failure to maintain acceptable voltage levels (i.e., voltage levels 
become too high or too low) may cause violations of System Operating 
Limits (``SOLs'') and Interconnection Reliability Operating Limits 
(``IROLs''), result in damage to Bulk-Power System equipment, and 
thereby threaten the reliable operation of the Bulk-Power System.
---------------------------------------------------------------------------

    \1\ 16 U.S.C. 824o (2012).
    \2\ The Commission approved Reliability Standard VAR-001-4 
(Voltage and Reactive Control) on August 1, 2014. See North American 
Electric Reliability Corp., Docket No. RD14-11-000 (Aug. 1, 2014) 
(delegated letter order). The Commission approved errata version 
VAR-001-4.1 on November 13, 2015. See North American Electric 
Reliability Corp., Docket No. RD15-6-000 (Nov. 13, 2015) (delegated 
letter order).
    \3\ The Commission approved Reliability Standard VAR-002-4, 
which clarified the applicability of the VAR-002 standard to 
dispersed generation resources, on May 29, 2015. See North American 
Electric Reliability Corp, 151 FERC ] 61,186 (May 29, 2015).
---------------------------------------------------------------------------

Reliability Standard VAR-001-5

    This Reliability Standard requires Transmission Operators to:
     Specify a system-wide voltage schedule (which is either a 
range or a target value with an associated tolerance band) as part of 
its plan to operate within SOLs and IROLs, and to provide the voltage 
schedule to its Reliability Coordinator and adjacent Transmission 
Operators upon request (Requirement R1);
     Schedule sufficient reactive resources to regulate voltage 
levels (Requirement R2);
     Operate or direct the operation of devices to regulate 
transmission voltage and reactive flows (Requirement R3);
     Develop a set of criteria to exempt generators from 
certain requirements under Reliability Standard VAR-002-4.1 related to 
voltage or Reactive Power schedules, automatic voltage regulations, and 
notification (Requirement R4);
     Specify a voltage or Reactive Power schedule (which is 
either a range or a target value with an associated tolerance band) for 
generators at either the high or low voltage side of the generator 
step-up transformer, provide the schedule to the associated Generator 
Operator, direct the Generator Operator to comply with that schedule in 
automatic voltage control mode, provide the Generator Operator the 
notification requirements for deviating from the schedule, and, if 
requested, provide the Generator Operator the criteria used to develop 
the schedule (Requirement R5); and
     Communicate step-up transformer tap changes, the time 
frame for completion, and the justification for these changes to 
Generator Owners (Requirement R6).

Reliability Standard VAR-002-4.1

    This Reliability Standard includes an information collection 
activity for ``Requirement R1'' and a separate information collection 
activity for ``Requirements R2 through R6.''
    This Reliability Standard requires Generator Operators to:
     Operate each of its generators connected to the 
interconnected transmission system in automatic voltage control mode or 
in a different control mode as instructed by the Transmission Operator, 
unless the Generator Operator (1) is exempted pursuant to the criteria 
developed under VAR-001-5, Requirement R4, or (2) makes certain 
notifications to the Transmission Operator specifying the

[[Page 31500]]

reasons it cannot so operate (Requirement R1);
     Maintain the Transmission Operator's generator voltage or 
Reactive Power schedule, unless the Generator Operator (1) is exempted 
pursuant to the criteria developed under VAR-001-5, Requirement R4, or 
(2) complies with the notification requirements for deviations as 
established by the Transmission Owner pursuant to VAR-001-5, 
Requirement R5 (Requirement R2);
     Notify the Transmission Operator of a change in status of 
its voltage controlling device within 30 minutes, unless the status is 
restored within that time period (Requirement R3); and
     Notify the Transmission Operator of a change in reactive 
capability due to factors other than those described in VAR-002-4.1, 
Requirement R3 within 30 minutes unless the capability has been 
restored during that time period (Requirement R4).
     Provide information on its step-up transformers and 
auxiliary transformers within 30 days of a request from the 
Transmission Operator or Transmission Planner (Requirement R5); and
     Comply with the Transmission Operator's step-up 
transformer tap change directives unless compliance would violate 
safety, an equipment rating, or applicable laws, rules or regulations 
(Requirement R6).
    The 60-day notice was published to the Federal Register on March 
31, 2021 and received no comments.
    Type of Respondents: Generator operators and Transmission 
Operators.
    Estimate of Annual Burden: 4
---------------------------------------------------------------------------

    \4\ The Commission defines burden as the total time, effort, or 
financial resources expended by persons to generate, maintain, 
retain, or disclose or provide information to or for a Federal 
agency. For further explanation of what is included in the 
information collection burden, reference 5 Code of Federal 
Regulations 1320.3.
    \5\ TOP = transmission operator; GOP = generator operators. 
Respondent counts based of the NERC Compliance Registry numbers 
February 5, 2021.
    \6\ The estimate for hourly cost is $70.19/hour. This figure is 
the average salary plus benefits for an electrical engineer 
(Occupation Code: 17-2071) from the Bureau of Labor Statistics (May 
2020) at https://www.bls.gov/oes/current/naics2_22.htm.
---------------------------------------------------------------------------

    The Commission estimates the annual public reporting burden for the 
information collection as:

                                    FERC-725X--Mandatory Reliability Standards: Voltage and Reactive (VAR) Standards
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                              Annual number                       Average burden &   Total annual burden
                                     Number of respondents    of responses    Total number of    cost per response      hours & total        Cost per
                                              \5\            per respondent      responses              \6\              annual cost      respondent ($)
                                   (1).....................             (2)    (1) * (2) = (3)  (4)................  (3) * (4) = (5)....       (5) / (1)
--------------------------------------------------------------------------------------------------------------------------------------------------------
VAR-001-5 (Requirements R1-R6)...  167 (TOP)...............               1                167  160 hrs.;            26,720 hrs.;             $11,230.40
                                                                                                 $11,230.40.          $1,875,476.80.
VAR-002-4.1 (Requirement R1).....  937 (GOP)...............               1                937  80 hrs.; $5,615.20.  74,960 hrs.;               5,615.20
                                                                                                                      $5,261,442.4.
VAR-002-4.1 (Requirements R2-R6).  937 (GOP)...............               1                937  120 hrs.; $8,422.80  112,440 hrs.;              8,422.80
                                                                                                                      $7,892,163.6.
                                  ----------------------------------------------------------------------------------------------------------------------
    Total........................  ........................  ..............              2,041  ...................  214,120 hrs.;        ..............
                                                                                                                      $15,029,082.80.
--------------------------------------------------------------------------------------------------------------------------------------------------------

    The burden for the FERC-725X information collection includes 
estimates related to both of the previously approved Reliability 
Standards (VAR-001-4.2 and VAR-002-4.1). The total annual burden and 
cost of the FERC-725X information collection is 214,120 hours and 
$15,029,083 (rounded).
    Comments: Comments are invited on: (1) Whether the collection of 
information is necessary for the proper performance of the functions of 
the Commission, including whether the information will have practical 
utility; (2) the accuracy of the agency's estimate of the burden and 
cost of the collection of information, including the validity of the 
methodology and assumptions used; (3) ways to enhance the quality, 
utility and clarity of the information collection; and (4) ways to 
minimize the burden of the collection of information on those who are 
to respond, including the use of automated collection techniques or 
other forms of information technology.

    Dated: June 8, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-12377 Filed 6-11-21; 8:45 am]
BILLING CODE 6717-01-P