Verdant Power, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 30458-30459 [2021-11955]

Download as PDF 30458 Federal Register / Vol. 86, No. 108 / Tuesday, June 8, 2021 / Notices must be filed with the Commission at least 24 months prior to the expiration of the existing license. All applications for license for this project must be filed by April 30, 2024. o. Register online at https:// ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Dated: June 2, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–11951 Filed 6–7–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12611–014] jbell on DSKJLSW7X2PROD with NOTICES Verdant Power, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent Minor License. b. Project No.: P–12611–014. c. Date filed: December 30, 2019. d. Applicant: Verdant Power, LLC (Verdant Power). e. Name of Project: Roosevelt Island Tidal Energy Project (RITE Project). f. Location: On the East River in New York County, New York. The project does not occupy federal land. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Ronald F. Smith, President and Chief Operating Officer, Verdant Power, LLC, P.O. Box 282, Roosevelt Island, New York, New York 10044. Phone: (703) 328–6842. Email: rsmith@verdantpower.com. i. FERC Contact: Andy Bernick at (202) 502–8660, or andrew.bernick@ ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the Commission’s eFiling system at https:// ferconline.ferc.gov/FERCOnline.aspx. VerDate Sep<11>2014 16:36 Jun 07, 2021 Jkt 253001 Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/ QuickComment.aspx. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–12611–014. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted and is now ready for environmental analysis. The Council on Environmental Quality (CEQ) issued a final rule on July 15, 2020, revising the regulations under 40 CFR parts 1500–1518 that federal agencies use to implement NEPA (see Update to the Regulations Implementing the Procedural Provisions of the National Environmental Policy Act, 85 FR 43304). The Final Rule became effective on and applies to any NEPA process begun after September 14, 2020. An agency may also apply the regulations to ongoing activities and environmental documents begun before September 14, 2020, which includes the RITE Project. Commission staff intends to conduct its NEPA review in accordance with CEQ’s new regulations. l. The existing pilot project license, which expires on December 31, 2021, authorizes the following project facilities: (a) Thirty 35-kilowatt, 5meter-diameter axial flow turbinegenerator units; (b) ten triframe mounts, each supporting three turbine-generator units; (c) 480-volt underwater cables from each triframe mount to five shoreline switchgear vaults that interconnect to a control room and interconnection points; and (d) PO 00000 Frm 00058 Fmt 4703 Sfmt 4703 appurtenant facilities for navigation safety and operation. On October 22, 2020, Verdant installed three turbine-generator units attached to one tri-frame mount under the existing pilot project license. Between October 2020 and January 2021, the pilot project generated about 90 megawatt-hours. Under the current pilot project license, Verdant is required to remove all project facilities, including triframe mounts and turbines, prior to the expiration of its pilot project license. The proposed project would consist of a maximum of fifteen 35-kilowatt, 5meter-diameter axial flow turbinegenerator units with a total installed capacity of 0.525 megawatt, with underwater cables connecting five triframe mounts to two shoreline switchgear vaults. The project would operate using the natural tidal currents of the East River, during both ebb and flood tidal periods. As the direction of tidal flow changes, each turbinegenerator unit would rotate (or yaw) to align the rotor to the direction of flow, through a passive system caused by hydrodynamic forces on the turbinegenerator unit. The annual generation is expected to be from 840 to 1,200 megawatt-hours. m. A copy of the application can be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. All filings must (1) bear in all capital letters the title ‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’ ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via E:\FR\FM\08JNN1.SGM 08JNN1 Federal Register / Vol. 86, No. 108 / Tuesday, June 8, 2021 / Notices email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. The applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. Please note that the certification request must comply with 40 CFR 121.5(b), including documentation that a pre-filing meeting request was submitted to the certifying authority at least 30 days prior to submitting the certification request. Please also note that the certification request must be sent to the certifying authority and to the Commission concurrently. o. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Milestone Deadline for Filing Comments, Recommendations, and Agency Terms and Conditions/Prescriptions. Deadline for Filing Reply Comments. Target date August 2021. September 2021. Dated: June 2, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–11955 Filed 6–7–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL21–79–000] jbell on DSKJLSW7X2PROD with NOTICES Illinois Municipal Electric Agency v. PJM Interconnection, L.L.C.; Notice of Complaint Take notice that on May 28, 2021, pursuant to sections 206, 306, and 309 of the Federal Power Act, 16 U.S.C. 824e, 825e, and 825h and Rule 206 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.206, Illinois Municipal Electric Agency (IMEA or Complainant) filed a formal complaint against PJM Interconnection, L.L.C. (PJM or Respondent), requesting that PJM properly administer the payment of Incremental Capacity Transfer Rights to IMEA without reduction in the 2021/2022 Delivery VerDate Sep<11>2014 17:46 Jun 07, 2021 Jkt 253001 Year and future Delivery Years, in accordance with PJM’s Open Access Transmission Tariff and in a just and reasonable manner, all as more fully explained in its complaint. The Complainant certify that copies of the complaint were served on the contacts listed for Respondent in the Commission’s list of Corporate Officials. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainant. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov, or call toll-free, (886) 208–3676 or TTY, (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on June 17, 2021. PO 00000 Frm 00059 Fmt 4703 Sfmt 4703 30459 Dated: June 2, 2021. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2021–11995 Filed 6–7–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER21–1953–000] Heartland Divide Wind II, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Heartland Divide Wind II, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is June 22, 2021. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. E:\FR\FM\08JNN1.SGM 08JNN1

Agencies

[Federal Register Volume 86, Number 108 (Tuesday, June 8, 2021)]
[Notices]
[Pages 30458-30459]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-11955]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 12611-014]


Verdant Power, LLC; Notice of Application Ready for Environmental 
Analysis and Soliciting Comments, Recommendations, Terms and 
Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: P-12611-014.
    c. Date filed: December 30, 2019.
    d. Applicant: Verdant Power, LLC (Verdant Power).
    e. Name of Project: Roosevelt Island Tidal Energy Project (RITE 
Project).
    f. Location: On the East River in New York County, New York. The 
project does not occupy federal land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Mr. Ronald F. Smith, President and Chief 
Operating Officer, Verdant Power, LLC, P.O. Box 282, Roosevelt Island, 
New York, New York 10044. Phone: (703) 328-6842. Email: 
[email protected].
    i. FERC Contact: Andy Bernick at (202) 502-8660, or 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://ferconline.ferc.gov/QuickComment.aspx. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Washington, DC 20426. Submissions sent via any other 
carrier must be addressed to: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852. The first page of any filing should include docket number P-
12611-014.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is now ready for 
environmental analysis.
    The Council on Environmental Quality (CEQ) issued a final rule on 
July 15, 2020, revising the regulations under 40 CFR parts 1500-1518 
that federal agencies use to implement NEPA (see Update to the 
Regulations Implementing the Procedural Provisions of the National 
Environmental Policy Act, 85 FR 43304). The Final Rule became effective 
on and applies to any NEPA process begun after September 14, 2020. An 
agency may also apply the regulations to ongoing activities and 
environmental documents begun before September 14, 2020, which includes 
the RITE Project. Commission staff intends to conduct its NEPA review 
in accordance with CEQ's new regulations.
    l. The existing pilot project license, which expires on December 
31, 2021, authorizes the following project facilities: (a) Thirty 35-
kilowatt, 5-meter-diameter axial flow turbine-generator units; (b) ten 
triframe mounts, each supporting three turbine-generator units; (c) 
480-volt underwater cables from each triframe mount to five shoreline 
switchgear vaults that interconnect to a control room and 
interconnection points; and (d) appurtenant facilities for navigation 
safety and operation.
    On October 22, 2020, Verdant installed three turbine-generator 
units attached to one tri-frame mount under the existing pilot project 
license. Between October 2020 and January 2021, the pilot project 
generated about 90 megawatt-hours. Under the current pilot project 
license, Verdant is required to remove all project facilities, 
including triframe mounts and turbines, prior to the expiration of its 
pilot project license.
    The proposed project would consist of a maximum of fifteen 35-
kilowatt, 5-meter-diameter axial flow turbine-generator units with a 
total installed capacity of 0.525 megawatt, with underwater cables 
connecting five triframe mounts to two shoreline switchgear vaults. The 
project would operate using the natural tidal currents of the East 
River, during both ebb and flood tidal periods. As the direction of 
tidal flow changes, each turbine-generator unit would rotate (or yaw) 
to align the rotor to the direction of flow, through a passive system 
caused by hydrodynamic forces on the turbine-generator unit. The annual 
generation is expected to be from 840 to 1,200 megawatt-hours.
    m. A copy of the application can be viewed on the Commission's 
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document. For assistance, contact FERC Online 
Support.
    All filings must (1) bear in all capital letters the title 
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person submitting the filing; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicant. Each filing must be 
accompanied by proof of service on all persons listed on the service 
list prepared by the Commission in this proceeding, in accordance with 
18 CFR 4.34(b) and 385.2010.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via

[[Page 30459]]

email of new filings and issuances related to this or other pending 
projects. For assistance, contact FERC Online Support.
    n. The applicant must file no later than 60 days following the date 
of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification. Please note 
that the certification request must comply with 40 CFR 121.5(b), 
including documentation that a pre-filing meeting request was submitted 
to the certifying authority at least 30 days prior to submitting the 
certification request. Please also note that the certification request 
must be sent to the certifying authority and to the Commission 
concurrently.
    o. Procedural schedule: The application will be processed according 
to the following schedule. Revisions to the schedule will be made as 
appropriate.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Deadline for Filing Comments,            August 2021.
 Recommendations, and Agency Terms and
 Conditions/Prescriptions.
Deadline for Filing Reply Comments.....  September 2021.
------------------------------------------------------------------------


    Dated: June 2, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-11955 Filed 6-7-21; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.