Marlow Hydro, LLC; Notice of Effectiveness of Withdrawal of License Application, 28825 [2021-11337]
Download as PDF
Federal Register / Vol. 86, No. 102 / Friday, May 28, 2021 / Notices
eFiling feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to Documents and
Filings. New eFiling users must first
create an account by clicking on
‘‘eRegister.’’ You will be asked to select
the type of filing you are making; first
select ‘‘General’’ and then select
‘‘Intervention.’’ The eFiling feature
includes a document-less intervention
option; for more information, visit
https://www.ferc.gov/docsfiling/efiling/
document-less-intervention.pdf.; or
(2) You can file a paper copy of your
motion to intervene, along with three
copies, by mailing the documents to the
address below.6 Your motion to
intervene must reference the project
docket number CP21–446–000.
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC
20426.
The Commission encourages
electronic filing of motions to intervene
(option 1 above) and has eFiling staff
available to assist you at (202) 502–8258
or FercOnlineSupport@ferc.gov.
Motions to intervene must be served
on the applicant either by mail or email
at: 700 Louisiana Street, Suite 1300,
Houston, Texas, or by email at john_
ryan@tcenergy.com. Any subsequent
submissions by an intervenor must be
served on the applicant and all other
parties to the proceeding. Contact
information for parties can be
downloaded from the service list at the
eService link on FERC Online. Service
can be via email with a link to the
document.
All timely, unopposed 7 motions to
intervene are automatically granted by
operation of Rule 214(c)(1).8 Motions to
intervene that are filed after the
intervention deadline are untimely and
may be denied. Any late-filed motion to
intervene must show good cause for
being late and must explain why the
time limitation should be waived and
provide justification by reference to
factors set forth in Rule 214(d) of the
Commission’s Rules and Regulations.9
A person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies (paper or electronic)
of all documents filed by the applicant
and by all other parties.
6 Hand delivered submissions in docketed
proceedings should be delivered to Health and
Human Services, 12225 Wilkins Avenue, Rockville,
Maryland 20852.
7 The applicant has 15 days from the submittal of
a motion to intervene to file a written objection to
the intervention.
8 18 CFR 385.214(c)(1).
9 18 CFR 385.214(b)(3) and (d).
VerDate Sep<11>2014
17:28 May 27, 2021
Jkt 253001
Tracking the Proceeding
DEPARTMENT OF ENERGY
Throughout the proceeding,
additional information about the project
will be available from the Commission’s
Office of External Affairs, at (866) 208–
FERC, or on the FERC website at
www.ferc.gov using the ‘‘eLibrary’’ link
as described above. The eLibrary link
also provides access to the texts of all
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. For more information and to
register, go to www.ferc.gov/docsfiling/
esubscription.asp.
Intervention Deadline: 5:00 p.m.
Eastern Time on June 10, 2021.
Dated: May 20, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–11348 Filed 5–27–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3309–021]
Marlow Hydro, LLC; Notice of
Effectiveness of Withdrawal of License
Application
On December 1, 2020, Marlow Hydro,
LLC (Marlow Hydro) filed an
application for a subsequent license for
the 225-kilowatt Nash Mill Dam
Hydroelectric Project No. 3309. On May
5, 2020, Marlow Hydro filed a notice of
withdrawal of its application.
No motion in opposition to the notice
of withdrawal has been filed, and the
Commission has taken no action to
disallow the withdrawal. Pursuant to
Rule 216(b) of the Commission’s Rules
of Practice and Procedure,1 the
withdrawal of the application became
effective on May 21, 2021, and this
proceeding is hereby terminated.
Dated: May 21, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021–11337 Filed 5–27–21; 8:45 am]
BILLING CODE 6717–01–P
28825
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Numbers: RP21–832–000.
Applicants: Tapstone Energy, LLC, FP
Wheeler Midstream, LLC.
Description: Joint Petition for Limited
Waiver of Capacity Release Regulations,
et al. of Tapstone Energy, LLC, et al.
Filed Date: 5/19/21.
Accession Number: 20210519–5150.
Comments Due: 5 p.m. ET 6/1/21.
Docket Numbers: RP21–833–000.
Applicants: ETC Tiger Pipeline, LLC.
Description: § 4(d) Rate Filing: Filed
Agreements Housekeeping to be
effective 6/21/2021.
Filed Date: 5/21/21.
Accession Number: 20210521–5054.
Comments Due: 5 p.m. ET 6/2/21.
Docket Numbers: RP21–834–000.
Applicants: Natural Gas Pipeline
Company of America.
Description: § 4(d) Rate Filing:
Amendment to a Negotiated Rate
Agreement Filing—La Frontera
Holdings, LLC to be effective 6/1/2021.
Filed Date: 5/21/21.
Accession Number: 20210521–5218.
Comments Due: 5 p.m. ET 6/2/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: May 24, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021–11363 Filed 5–27–21; 8:45 am]
1 18
PO 00000
CFR 385.216(b) (2020).
Frm 00079
Fmt 4703
Sfmt 9990
BILLING CODE 6717–01–P
E:\FR\FM\28MYN1.SGM
28MYN1
Agencies
[Federal Register Volume 86, Number 102 (Friday, May 28, 2021)]
[Notices]
[Page 28825]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-11337]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3309-021]
Marlow Hydro, LLC; Notice of Effectiveness of Withdrawal of
License Application
On December 1, 2020, Marlow Hydro, LLC (Marlow Hydro) filed an
application for a subsequent license for the 225-kilowatt Nash Mill Dam
Hydroelectric Project No. 3309. On May 5, 2020, Marlow Hydro filed a
notice of withdrawal of its application.
No motion in opposition to the notice of withdrawal has been filed,
and the Commission has taken no action to disallow the withdrawal.
Pursuant to Rule 216(b) of the Commission's Rules of Practice and
Procedure,\1\ the withdrawal of the application became effective on May
21, 2021, and this proceeding is hereby terminated.
---------------------------------------------------------------------------
\1\ 18 CFR 385.216(b) (2020).
Dated: May 21, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-11337 Filed 5-27-21; 8:45 am]