Download as PDF Federal Register / Vol. 86, No. 95 / Wednesday, May 19, 2021 / Notices For assistance, contact FERC Online Support. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Issue Deficiency Letter (if necessary)— July 2021 Request Additional Information—July 2021 Issue Acceptance Letter—October 2021 Issue Scoping Document 1—October 2021 Comments on Scoping Document 1 due—November 2021 Issue Scoping Document 2 (if necessary)—January 2022 Issue Notice of Ready for Environmental Analysis—February 2022 Commission issues EA—July 2022 Comments on EA—August 2022 q. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: May 13, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–10541 Filed 5–18–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL21–72–000] khammond on DSKJM1Z7X2PROD with NOTICES LS Power Development, LLC, Doswell Limited Partnership v. PJM Interconnection, L.L.C.; Notice of Complaint Take notice that on May 7, 2021, pursuant to sections 206, and 306 of the Federal Power Act, 16 U.S.C. 824e, 825e and Rule 206 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.206, LS Power Development, LLC and Doswell Limited Partnership (Complainants) filed a formal complaint against PJM Interconnection, L.L.C., (Respondent or PJM) alleging that the Respondent violated the Reliability Assurance Agreement among Load Serving Entities in the PJM Region by approving FRR Alternative elections by entities whose FRR Capacity Plans did not demonstrate the commitment of capacity resources to meet their capacity obligations for the full term of the elections, all as more fully explained in the complaint. The Complainant certifies that copies of the complaint were served on the VerDate Sep<11>2014 16:43 May 18, 2021 Jkt 253001 contacts listed for Respondent in the Commission’s list of Corporate Officials, and on the Independent Market Monitor for PJM. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov, or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on May 27, 2021. Dated: May 13, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–10538 Filed 5–18–21; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 27079 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG21–142–000. Applicants: Bluestone Wind, LLC. Description: Notice of SelfCertification of Exempt Wholesale Generator Status of Bluestone Wind, LLC. Filed Date: 5/12/21. Accession Number: 20210512–5222. Comments Due: 5 p.m. ET 6/2/21. Docket Numbers: EG21–143–000. Applicants: Ball Hill Wind Energy, LLC. Description: Notice of SelfCertification of Exempt Wholesale Generator Status of Ball Hill Wind Energy, LLC. Filed Date: 5/12/21. Accession Number: 20210512–5223. Comments Due: 5 p.m. ET 6/2/21. Docket Numbers: EG21–144–000. Applicants: White Mesa Wind, LLC. Description: Notice of SelfCertification of Exempt Wholesale Generator Status of White Mesa Wind, LLC. Filed Date: 5/10/21. Accession Number: 20210510–5231. Comments Due: 5 p.m. ET 6/1/21. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–2641–038; ER10–1852–051. Applicants: Florida Power & Light Company, Oleander Power Project, Limited Partnership. Description: Notice of Change in Status of Florida Power & Light Company, et al. Filed Date: 5/3/21. Accession Number: 20210503–5115. Comments Due: 5 p.m. ET 5/24/21. Docket Numbers: ER19–2858–005. Applicants: East Coast Power Linden Holding, L.L.C. Description: Compliance filing: Informational Filing Under PJM Tariff Schedule 2 and Request for Partial Waiver to be effective N/A. Filed Date: 1/29/21. Accession Number: 20210129–5271. Comments Due: 5 p.m. ET 5/24/21. Docket Numbers: ER21–894–001. Applicants: Louisville Gas and Electric Company. Description: Compliance filing: Compliance Filing Transition Mechanism Agreement KMPA to be effective 3/17/2021. E:\FR\FM\19MYN1.SGM 19MYN1 khammond on DSKJM1Z7X2PROD with NOTICES 27080 Federal Register / Vol. 86, No. 95 / Wednesday, May 19, 2021 / Notices Filed Date: 5/13/21. Accession Number: 20210513–5021. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–895–001. Applicants: Louisville Gas and Electric Company. Description: Compliance filing: Compliance Filing Transition Mechanism Agreement KYMEA to be effective 3/17/2021. Filed Date: 5/13/21. Accession Number: 20210513–5022. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–896–001. Applicants: Louisville Gas and Electric Company. Description: Compliance filing: Compliance Filing Transition Mechanism Agreement OMU to be effective 3/17/2021. Filed Date: 5/13/21. Accession Number: 20210513–5023. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1176–000; ER21–1177–000. Applicants: Delta’s Edge Solar, LLC, Crosset Solar Energy, LLC. Description: Response to April 19, 2021 Deficiency Letter of Delta’s Edge Solar, LLC et al. Filed Date: 5/12/21. Accession Number: 20210512–5210. Comments Due: 5 p.m. ET 6/2/21. Docket Numbers: ER21–1879–001. Applicants: Farmington Solar, LLC. Description: Tariff Amendment: Farmington Solar, LLC Amendment to the Application for MBR Authority to be effective 7/11/2021. Filed Date: 5/13/21. Accession Number: 20210513–5131. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1881–001. Applicants: Grand Tower Energy Center, LLC. Description: Tariff Amendment: Notice of Cancellation of Reactive Tariff and Request for Waiver to be effective 7/1/2021. Filed Date: 5/11/21. Accession Number: 20210511–5121. Comments Due: 5 p.m. ET 6/1/21. Docket Numbers: ER21–1898–000. Applicants: Commonwealth Edison Company, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: ComEd submits Interconnection Agreement, SA No. 5955 with NIPSCO to be effective 4/2/2021. Filed Date: 5/12/21. Accession Number: 20210512–5206. Comments Due: 5 p.m. ET 6/2/21. Docket Numbers: ER21–1899–000. Applicants: Tri-State Generation and Transmission Association, Inc. Description: § 205(d) Rate Filing: Amendment to Service Agreement No. 804 to be effective 5/11/2021. VerDate Sep<11>2014 16:43 May 18, 2021 Jkt 253001 Filed Date: 5/13/21. Accession Number: 20210513–5071. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1900–000. Applicants: New York Independent System Operator, Inc., Niagara Mohawk Power Corporation. Description: § 205(d) Rate Filing: Joint 205 TIPIA: NYISO, National Grid, NYPA for Segment A, SA 2611, CEII to be effective 4/29/2021. Filed Date: 5/13/21. Accession Number: 20210513–5073. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1901–000. Applicants: Southwestern Public Service Company. Description: Request for Limited Waiver of Tariff Provision, et al. of Southwestern Public Service Company. Filed Date: 5/13/21. Accession Number: 20210513–5081. Comments Due: 5 p.m. ET 5/20/21. Docket Numbers: ER21–1902–000. Applicants: Southern California Edison Company. Description: Tariff Cancellation: Notice of Cancellation Letter Agreement IP Oberon, LLC SA No. 248 to be effective 5/14/2021. Filed Date: 5/13/21. Accession Number: 20210513–5082. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1903–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2021–05–13_Attachment FF removal of RPCE language to be effective 7/13/ 2021. Filed Date: 5/13/21. Accession Number: 20210513–5095. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1904–000. Applicants: Southwestern Electric Power Company. Description: § 205(d) Rate Filing: SWEPCO-Bentonville (POD#6 Sunshine and Sub E) Delivery Point Agreements to be effective 5/5/2021. Filed Date: 5/13/21. Accession Number: 20210513–5127. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1905–000. Applicants: NextEra Energy Transmission MidAtlantic Indiana, Inc., PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: NEET MidAtlantic IN submits Interconnection Agreement, SA No. 5801 with NIPSCO to be effective 10/29/ 2020. Filed Date: 5/13/21. Accession Number: 20210513–5146. Comments Due: 5 p.m. ET 6/3/21. The filings are accessible in the Commission’s eLibrary system (https:// PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 elibrary.ferc.gov/idmws/search/fercgen search.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: May 13, 2021. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2021–10547 Filed 5–18–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No.10934–000] Sugar River Hydro II, LLC; Notice of Authorization for Continued Project Operation The current license for the Sugar River II Project (project) is held by Sugar River Hydro II, LLC (Sugar River Hydro) under Project No. 10934. The project is located on the Sugar River, in Sullivan County, New Hampshire. On April 30, 2019, Sugar River Hydro filed a letter stating that it is not filing an application to relicense the project. On May 8, 2019, the Commission, pursuant to 18 CFR 16.25(a), issued a notice soliciting potential new applicants for the project, which provided until August 6, 2019 for potential applicants to submit a preapplication document (PAD) and notice of intent (NOI). In response to the solicitation notice, New Hampshire Renewable Resources, LLC (New Hampshire Renewable) filed a PAD and NOI to relicense the Sugar River II Project, pursuant to 18 CFR 5.5 and 5.6 of the Commission’s regulations. Commission staff assigned Project No. 15003 for the licensing proceeding initiated by New Hampshire Renewable’s filing. On February 8, 2021, New Hampshire Renewable filed an application for a subsequent license for the Sugar River II Project pursuant to E:\FR\FM\19MYN1.SGM 19MYN1

Agencies

[Federal Register Volume 86, Number 95 (Wednesday, May 19, 2021)]
[Notices]
[Pages 27079-27080]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-10547]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Combined Notice of Filings #1

    Take notice that the Commission received the following exempt 
wholesale generator filings:

    Docket Numbers: EG21-142-000.
    Applicants: Bluestone Wind, LLC.
    Description: Notice of Self-Certification of Exempt Wholesale 
Generator Status of Bluestone Wind, LLC.
    Filed Date: 5/12/21.
    Accession Number: 20210512-5222.
    Comments Due: 5 p.m. ET 6/2/21.

    Docket Numbers: EG21-143-000.
    Applicants: Ball Hill Wind Energy, LLC.
    Description: Notice of Self-Certification of Exempt Wholesale 
Generator Status of Ball Hill Wind Energy, LLC.
    Filed Date: 5/12/21.
    Accession Number: 20210512-5223.
    Comments Due: 5 p.m. ET 6/2/21.

    Docket Numbers: EG21-144-000.
    Applicants: White Mesa Wind, LLC.
    Description: Notice of Self-Certification of Exempt Wholesale 
Generator Status of White Mesa Wind, LLC.
    Filed Date: 5/10/21.
    Accession Number: 20210510-5231.
    Comments Due: 5 p.m. ET 6/1/21.

    Take notice that the Commission received the following electric 
rate filings:

    Docket Numbers: ER10-2641-038; ER10-1852-051.
    Applicants: Florida Power & Light Company, Oleander Power Project, 
Limited Partnership.
    Description: Notice of Change in Status of Florida Power & Light 
Company, et al.
    Filed Date: 5/3/21.
    Accession Number: 20210503-5115.
    Comments Due: 5 p.m. ET 5/24/21.

    Docket Numbers: ER19-2858-005.
    Applicants: East Coast Power Linden Holding, L.L.C.
    Description: Compliance filing: Informational Filing Under PJM 
Tariff Schedule 2 and Request for Partial Waiver to be effective N/A.
    Filed Date: 1/29/21.
    Accession Number: 20210129-5271.
    Comments Due: 5 p.m. ET 5/24/21.

    Docket Numbers: ER21-894-001.
    Applicants: Louisville Gas and Electric Company.
    Description: Compliance filing: Compliance Filing Transition 
Mechanism Agreement KMPA to be effective 3/17/2021.

[[Page 27080]]

    Filed Date: 5/13/21.
    Accession Number: 20210513-5021.
    Comments Due: 5 p.m. ET 6/3/21.

    Docket Numbers: ER21-895-001.
    Applicants: Louisville Gas and Electric Company.
    Description: Compliance filing: Compliance Filing Transition 
Mechanism Agreement KYMEA to be effective 3/17/2021.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5022.
    Comments Due: 5 p.m. ET 6/3/21.

    Docket Numbers: ER21-896-001.
    Applicants: Louisville Gas and Electric Company.
    Description: Compliance filing: Compliance Filing Transition 
Mechanism Agreement OMU to be effective 3/17/2021.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5023.
    Comments Due: 5 p.m. ET 6/3/21.

    Docket Numbers: ER21-1176-000; ER21-1177-000.
    Applicants: Delta's Edge Solar, LLC, Crosset Solar Energy, LLC.
    Description: Response to April 19, 2021 Deficiency Letter of 
Delta's Edge Solar, LLC et al.
    Filed Date: 5/12/21.
    Accession Number: 20210512-5210.
    Comments Due: 5 p.m. ET 6/2/21.

    Docket Numbers: ER21-1879-001.
    Applicants: Farmington Solar, LLC.
    Description: Tariff Amendment: Farmington Solar, LLC Amendment to 
the Application for MBR Authority to be effective 7/11/2021.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5131.
    Comments Due: 5 p.m. ET 6/3/21.

    Docket Numbers: ER21-1881-001.
    Applicants: Grand Tower Energy Center, LLC.
    Description: Tariff Amendment: Notice of Cancellation of Reactive 
Tariff and Request for Waiver to be effective 7/1/2021.
    Filed Date: 5/11/21.
    Accession Number: 20210511-5121.
    Comments Due: 5 p.m. ET 6/1/21.

    Docket Numbers: ER21-1898-000.
    Applicants: Commonwealth Edison Company, PJM Interconnection, 
L.L.C.
    Description: Sec.  205(d) Rate Filing: ComEd submits 
Interconnection Agreement, SA No. 5955 with NIPSCO to be effective 4/2/
2021.
    Filed Date: 5/12/21.
    Accession Number: 20210512-5206.
    Comments Due: 5 p.m. ET 6/2/21.

    Docket Numbers: ER21-1899-000.
    Applicants: Tri-State Generation and Transmission Association, Inc.
    Description: Sec.  205(d) Rate Filing: Amendment to Service 
Agreement No. 804 to be effective 5/11/2021.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5071.
    Comments Due: 5 p.m. ET 6/3/21.

    Docket Numbers: ER21-1900-000.
    Applicants: New York Independent System Operator, Inc., Niagara 
Mohawk Power Corporation.
    Description: Sec.  205(d) Rate Filing: Joint 205 TIPIA: NYISO, 
National Grid, NYPA for Segment A, SA 2611, CEII to be effective 4/29/
2021.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5073.
    Comments Due: 5 p.m. ET 6/3/21.

    Docket Numbers: ER21-1901-000.
    Applicants: Southwestern Public Service Company.
    Description: Request for Limited Waiver of Tariff Provision, et al. 
of Southwestern Public Service Company.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5081.
    Comments Due: 5 p.m. ET 5/20/21.

    Docket Numbers: ER21-1902-000.
    Applicants: Southern California Edison Company.
    Description: Tariff Cancellation: Notice of Cancellation Letter 
Agreement IP Oberon, LLC SA No. 248 to be effective 5/14/2021.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5082.
    Comments Due: 5 p.m. ET 6/3/21.

    Docket Numbers: ER21-1903-000.
    Applicants: Midcontinent Independent System Operator, Inc.
    Description: Sec.  205(d) Rate Filing: 2021-05-13_Attachment FF 
removal of RPCE language to be effective 7/13/2021.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5095.
    Comments Due: 5 p.m. ET 6/3/21.

    Docket Numbers: ER21-1904-000.
    Applicants: Southwestern Electric Power Company.
    Description: Sec.  205(d) Rate Filing: SWEPCO-Bentonville (POD#6 
Sunshine and Sub E) Delivery Point Agreements to be effective 5/5/2021.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5127.
    Comments Due: 5 p.m. ET 6/3/21.

    Docket Numbers: ER21-1905-000.
    Applicants: NextEra Energy Transmission MidAtlantic Indiana, Inc., 
PJM Interconnection, L.L.C.
    Description: Sec.  205(d) Rate Filing: NEET MidAtlantic IN submits 
Interconnection Agreement, SA No. 5801 with NIPSCO to be effective 10/
29/2020.
    Filed Date: 5/13/21.
    Accession Number: 20210513-5146.
    Comments Due: 5 p.m. ET 6/3/21.

    The filings are accessible in the Commission's eLibrary system 
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying 
the docket number.
    Any person desiring to intervene or protest in any of the above 
proceedings must file in accordance with Rules 211 and 214 of the 
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00 
p.m. Eastern time on the specified comment date. Protests may be 
considered, but intervention is necessary to become a party to the 
proceeding.
    eFiling is encouraged. More detailed information relating to filing 
requirements, interventions, protests, service, and qualifying 
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676 
(toll free). For TTY, call (202) 502-8659.

    Dated: May 13, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021-10547 Filed 5-18-21; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.