Download as PDF khammond on DSKJM1Z7X2PROD with NOTICES 27080 Federal Register / Vol. 86, No. 95 / Wednesday, May 19, 2021 / Notices Filed Date: 5/13/21. Accession Number: 20210513–5021. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–895–001. Applicants: Louisville Gas and Electric Company. Description: Compliance filing: Compliance Filing Transition Mechanism Agreement KYMEA to be effective 3/17/2021. Filed Date: 5/13/21. Accession Number: 20210513–5022. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–896–001. Applicants: Louisville Gas and Electric Company. Description: Compliance filing: Compliance Filing Transition Mechanism Agreement OMU to be effective 3/17/2021. Filed Date: 5/13/21. Accession Number: 20210513–5023. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1176–000; ER21–1177–000. Applicants: Delta’s Edge Solar, LLC, Crosset Solar Energy, LLC. Description: Response to April 19, 2021 Deficiency Letter of Delta’s Edge Solar, LLC et al. Filed Date: 5/12/21. Accession Number: 20210512–5210. Comments Due: 5 p.m. ET 6/2/21. Docket Numbers: ER21–1879–001. Applicants: Farmington Solar, LLC. Description: Tariff Amendment: Farmington Solar, LLC Amendment to the Application for MBR Authority to be effective 7/11/2021. Filed Date: 5/13/21. Accession Number: 20210513–5131. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1881–001. Applicants: Grand Tower Energy Center, LLC. Description: Tariff Amendment: Notice of Cancellation of Reactive Tariff and Request for Waiver to be effective 7/1/2021. Filed Date: 5/11/21. Accession Number: 20210511–5121. Comments Due: 5 p.m. ET 6/1/21. Docket Numbers: ER21–1898–000. Applicants: Commonwealth Edison Company, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: ComEd submits Interconnection Agreement, SA No. 5955 with NIPSCO to be effective 4/2/2021. Filed Date: 5/12/21. Accession Number: 20210512–5206. Comments Due: 5 p.m. ET 6/2/21. Docket Numbers: ER21–1899–000. Applicants: Tri-State Generation and Transmission Association, Inc. Description: § 205(d) Rate Filing: Amendment to Service Agreement No. 804 to be effective 5/11/2021. VerDate Sep<11>2014 16:43 May 18, 2021 Jkt 253001 Filed Date: 5/13/21. Accession Number: 20210513–5071. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1900–000. Applicants: New York Independent System Operator, Inc., Niagara Mohawk Power Corporation. Description: § 205(d) Rate Filing: Joint 205 TIPIA: NYISO, National Grid, NYPA for Segment A, SA 2611, CEII to be effective 4/29/2021. Filed Date: 5/13/21. Accession Number: 20210513–5073. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1901–000. Applicants: Southwestern Public Service Company. Description: Request for Limited Waiver of Tariff Provision, et al. of Southwestern Public Service Company. Filed Date: 5/13/21. Accession Number: 20210513–5081. Comments Due: 5 p.m. ET 5/20/21. Docket Numbers: ER21–1902–000. Applicants: Southern California Edison Company. Description: Tariff Cancellation: Notice of Cancellation Letter Agreement IP Oberon, LLC SA No. 248 to be effective 5/14/2021. Filed Date: 5/13/21. Accession Number: 20210513–5082. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1903–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2021–05–13_Attachment FF removal of RPCE language to be effective 7/13/ 2021. Filed Date: 5/13/21. Accession Number: 20210513–5095. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1904–000. Applicants: Southwestern Electric Power Company. Description: § 205(d) Rate Filing: SWEPCO-Bentonville (POD#6 Sunshine and Sub E) Delivery Point Agreements to be effective 5/5/2021. Filed Date: 5/13/21. Accession Number: 20210513–5127. Comments Due: 5 p.m. ET 6/3/21. Docket Numbers: ER21–1905–000. Applicants: NextEra Energy Transmission MidAtlantic Indiana, Inc., PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: NEET MidAtlantic IN submits Interconnection Agreement, SA No. 5801 with NIPSCO to be effective 10/29/ 2020. Filed Date: 5/13/21. Accession Number: 20210513–5146. Comments Due: 5 p.m. ET 6/3/21. The filings are accessible in the Commission’s eLibrary system (https:// PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 elibrary.ferc.gov/idmws/search/fercgen search.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: May 13, 2021. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2021–10547 Filed 5–18–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No.10934–000] Sugar River Hydro II, LLC; Notice of Authorization for Continued Project Operation The current license for the Sugar River II Project (project) is held by Sugar River Hydro II, LLC (Sugar River Hydro) under Project No. 10934. The project is located on the Sugar River, in Sullivan County, New Hampshire. On April 30, 2019, Sugar River Hydro filed a letter stating that it is not filing an application to relicense the project. On May 8, 2019, the Commission, pursuant to 18 CFR 16.25(a), issued a notice soliciting potential new applicants for the project, which provided until August 6, 2019 for potential applicants to submit a preapplication document (PAD) and notice of intent (NOI). In response to the solicitation notice, New Hampshire Renewable Resources, LLC (New Hampshire Renewable) filed a PAD and NOI to relicense the Sugar River II Project, pursuant to 18 CFR 5.5 and 5.6 of the Commission’s regulations. Commission staff assigned Project No. 15003 for the licensing proceeding initiated by New Hampshire Renewable’s filing. On February 8, 2021, New Hampshire Renewable filed an application for a subsequent license for the Sugar River II Project pursuant to E:\FR\FM\19MYN1.SGM 19MYN1 khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 86, No. 95 / Wednesday, May 19, 2021 / Notices the Federal Power Act (FPA) and the Commission’s regulations thereunder. The license for Project No. 10934 was issued for a period ending April 30, 2021. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 10934 is issued to Sugar River Hydro for a period effective May 1, 2021 through April 30, 2022 or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before April 30, 2022, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that Sugar River Hydro is authorized to continue operation of the Sugar River II Project, until such time as the Commission acts on the application for a subsequent license. Dated: May 13, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–10540 Filed 5–18–21; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 16:43 May 18, 2021 Jkt 253001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL21–73–000] Edgecombe Solar Energy LLC v. Duke Energy Progress, LLC, Duke Energy Carolinas, LLC, and Duke Energy Florida, LLC; Notice of Complaint Take notice that on May 12, 2021, pursuant to sections 206 and 306, of the Federal Power Act, 16 U.S.C. 824e and 825e and Rule 206 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.206 (2020), Edgecombe Solar Energy LLC (Complainant) filed a formal complaint against Duke Energy Progress, LLC, Duke Energy Carolinas, LLC and Duke Energy Florida, LLC (collectively, Duke Companies or Respondents) requesting that the Commission direct the Duke Companies to revise their Affected System Operator Agreement form to include the Commission’s required provisions providing for reimbursement of Network Upgrades that the Duke Companies construct in their role of Affected System Operators,1 as more fully explained in the complaint. The Complainant certifies that copies of the complaint were served on the contacts listed for Respondents in the Commission’s list of Corporate Officials. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondents’ answer and all interventions, or protests must be filed on or before the comment date. The Respondents’ answer, motions to intervene, and protests must be served on the Complainant. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using 1 An Affected System means an electric system other than the Transmission Provider’s Transmission System that may be affected by the proposed interconnection. An Affected System Operator shall mean the entity that operates an Affected System. See pro forma Large Generator Interconnection Agreement, Art. 1 (‘‘LGIA Definitions’’), available at https://www.ferc.gov/ sites/default/files/2020-04/LGIA-agreement.pdf. Other capitalized terms in this document have the meaning set forth in the Commission’s pro forma OATT. PO 00000 Frm 00019 Fmt 4703 Sfmt 4703 27081 the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov, or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on June 1, 2021. Dated: May 13, 2021. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2021–10544 Filed 5–18–21; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY [FRL–10023–10–Region 9] National Oil and Hazardous Substances Pollution Contingency Plan; National Priorities List: Explanation of Significant Differences for the Del Norte County Pesticide Storage Area Superfund Site Environmental Protection Agency (EPA). ACTION: Notice of explanation of significant differences. AGENCY: The U.S. Environmental Protection Agency (EPA) Region 9 is issuing an explanation of significant differences (ESD) for the Del Norte County Pesticide Storage Area Superfund Site (the Site), located at 2650 West Washington Boulevard in Crescent City, Del Norte County, California, and is notifying the public of SUMMARY: E:\FR\FM\19MYN1.SGM 19MYN1

Agencies

[Federal Register Volume 86, Number 95 (Wednesday, May 19, 2021)]
[Notices]
[Pages 27080-27081]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-10540]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No.10934-000]


Sugar River Hydro II, LLC; Notice of Authorization for Continued 
Project Operation

    The current license for the Sugar River II Project (project) is 
held by Sugar River Hydro II, LLC (Sugar River Hydro) under Project No. 
10934. The project is located on the Sugar River, in Sullivan County, 
New Hampshire. On April 30, 2019, Sugar River Hydro filed a letter 
stating that it is not filing an application to relicense the project. 
On May 8, 2019, the Commission, pursuant to 18 CFR 16.25(a), issued a 
notice soliciting potential new applicants for the project, which 
provided until August 6, 2019 for potential applicants to submit a pre-
application document (PAD) and notice of intent (NOI). In response to 
the solicitation notice, New Hampshire Renewable Resources, LLC (New 
Hampshire Renewable) filed a PAD and NOI to relicense the Sugar River 
II Project, pursuant to 18 CFR 5.5 and 5.6 of the Commission's 
regulations. Commission staff assigned Project No. 15003 for the 
licensing proceeding initiated by New Hampshire Renewable's filing. On 
February 8, 2021, New Hampshire Renewable filed an application for a 
subsequent license for the Sugar River II Project pursuant to

[[Page 27081]]

the Federal Power Act (FPA) and the Commission's regulations 
thereunder.
    The license for Project No. 10934 was issued for a period ending 
April 30, 2021. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year-to-year an annual license to the then licensee(s) under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA. If the project's prior 
license waived the applicability of section 15 of the FPA, then, based 
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), 
and as set forth at 18 CFR 16.21(a), if the licensee of such project 
has filed an application for a subsequent license, the licensee may 
continue to operate the project in accordance with the terms and 
conditions of the license after the minor or minor part license 
expires, until the Commission acts on its application. If the licensee 
of such a project has not filed an application for a subsequent 
license, then it may be required, pursuant to 18 CFR 16.21(b), to 
continue project operations until the Commission issues someone else a 
license for the project or otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 10934 is issued to 
Sugar River Hydro for a period effective May 1, 2021 through April 30, 
2022 or until the issuance of a new license for the project or other 
disposition under the FPA, whichever comes first. If issuance of a new 
license (or other disposition) does not take place on or before April 
30, 2022, notice is hereby given that, pursuant to 18 CFR 16.18(c), an 
annual license under section 15(a)(1) of the FPA is renewed 
automatically without further order or notice by the Commission, unless 
the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that Sugar River Hydro is authorized to continue operation 
of the Sugar River II Project, until such time as the Commission acts 
on the application for a subsequent license.

    Dated: May 13, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-10540 Filed 5-18-21; 8:45 am]