Download as PDF Federal Register / Vol. 86, No. 95 / Wednesday, May 19, 2021 / Notices For assistance, contact FERC Online Support. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Issue Deficiency Letter (if necessary)— July 2021 Request Additional Information—July 2021 Issue Acceptance Letter—October 2021 Issue Scoping Document 1—October 2021 Comments on Scoping Document 1 due—November 2021 Issue Scoping Document 2 (if necessary)—January 2022 Issue Notice of Ready for Environmental Analysis—February 2022 Commission issues EA—July 2022 Comments on EA—August 2022 q. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: May 13, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–10541 Filed 5–18–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL21–72–000] khammond on DSKJM1Z7X2PROD with NOTICES LS Power Development, LLC, Doswell Limited Partnership v. PJM Interconnection, L.L.C.; Notice of Complaint Take notice that on May 7, 2021, pursuant to sections 206, and 306 of the Federal Power Act, 16 U.S.C. 824e, 825e and Rule 206 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.206, LS Power Development, LLC and Doswell Limited Partnership (Complainants) filed a formal complaint against PJM Interconnection, L.L.C., (Respondent or PJM) alleging that the Respondent violated the Reliability Assurance Agreement among Load Serving Entities in the PJM Region by approving FRR Alternative elections by entities whose FRR Capacity Plans did not demonstrate the commitment of capacity resources to meet their capacity obligations for the full term of the elections, all as more fully explained in the complaint. The Complainant certifies that copies of the complaint were served on the VerDate Sep<11>2014 16:43 May 18, 2021 Jkt 253001 contacts listed for Respondent in the Commission’s list of Corporate Officials, and on the Independent Market Monitor for PJM. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. The Respondent’s answer and all interventions, or protests must be filed on or before the comment date. The Respondent’s answer, motions to intervene, and protests must be served on the Complainants. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov, or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on May 27, 2021. Dated: May 13, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–10538 Filed 5–18–21; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 27079 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG21–142–000. Applicants: Bluestone Wind, LLC. Description: Notice of SelfCertification of Exempt Wholesale Generator Status of Bluestone Wind, LLC. Filed Date: 5/12/21. Accession Number: 20210512–5222. Comments Due: 5 p.m. ET 6/2/21. Docket Numbers: EG21–143–000. Applicants: Ball Hill Wind Energy, LLC. Description: Notice of SelfCertification of Exempt Wholesale Generator Status of Ball Hill Wind Energy, LLC. Filed Date: 5/12/21. Accession Number: 20210512–5223. Comments Due: 5 p.m. ET 6/2/21. Docket Numbers: EG21–144–000. Applicants: White Mesa Wind, LLC. Description: Notice of SelfCertification of Exempt Wholesale Generator Status of White Mesa Wind, LLC. Filed Date: 5/10/21. Accession Number: 20210510–5231. Comments Due: 5 p.m. ET 6/1/21. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–2641–038; ER10–1852–051. Applicants: Florida Power & Light Company, Oleander Power Project, Limited Partnership. Description: Notice of Change in Status of Florida Power & Light Company, et al. Filed Date: 5/3/21. Accession Number: 20210503–5115. Comments Due: 5 p.m. ET 5/24/21. Docket Numbers: ER19–2858–005. Applicants: East Coast Power Linden Holding, L.L.C. Description: Compliance filing: Informational Filing Under PJM Tariff Schedule 2 and Request for Partial Waiver to be effective N/A. Filed Date: 1/29/21. Accession Number: 20210129–5271. Comments Due: 5 p.m. ET 5/24/21. Docket Numbers: ER21–894–001. Applicants: Louisville Gas and Electric Company. Description: Compliance filing: Compliance Filing Transition Mechanism Agreement KMPA to be effective 3/17/2021. E:\FR\FM\19MYN1.SGM 19MYN1

Agencies

[Federal Register Volume 86, Number 95 (Wednesday, May 19, 2021)]
[Notices]
[Page 27079]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-10538]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL21-72-000]


LS Power Development, LLC, Doswell Limited Partnership v. PJM 
Interconnection, L.L.C.; Notice of Complaint

    Take notice that on May 7, 2021, pursuant to sections 206, and 306 
of the Federal Power Act, 16 U.S.C. 824e, 825e and Rule 206 of the 
Federal Energy Regulatory Commission's (Commission) Rules of Practice 
and Procedure, 18 CFR 385.206, LS Power Development, LLC and Doswell 
Limited Partnership (Complainants) filed a formal complaint against PJM 
Interconnection, L.L.C., (Respondent or PJM) alleging that the 
Respondent violated the Reliability Assurance Agreement among Load 
Serving Entities in the PJM Region by approving FRR Alternative 
elections by entities whose FRR Capacity Plans did not demonstrate the 
commitment of capacity resources to meet their capacity obligations for 
the full term of the elections, all as more fully explained in the 
complaint.
    The Complainant certifies that copies of the complaint were served 
on the contacts listed for Respondent in the Commission's list of 
Corporate Officials, and on the Independent Market Monitor for PJM.
    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. The Respondent's 
answer and all interventions, or protests must be filed on or before 
the comment date. The Respondent's answer, motions to intervene, and 
protests must be served on the Complainants.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically may mail 
similar pleadings to the Federal Energy Regulatory Commission, 888 
First Street NE, Washington, DC 20426. Hand delivered submissions in 
docketed proceedings should be delivered to Health and Human Services, 
12225 Wilkins Avenue, Rockville, Maryland 20852.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://www.ferc.gov) using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact the Federal Energy 
Regulatory Commission at [email protected], or call toll-free, 
(886) 208-3676 or TYY, (202) 502-8659.
    Comment Date: 5:00 p.m. Eastern Time on May 27, 2021.

    Dated: May 13, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-10538 Filed 5-18-21; 8:45 am]
BILLING CODE 6717-01-P