Southern Nuclear Operating Company Inc; Vogtle Electric Generating Plant Unit 4, 26552-26556 [2021-10254]
Download as PDF
26552
Federal Register / Vol. 86, No. 92 / Friday, May 14, 2021 / Notices
khammond on DSKJM1Z7X2PROD with NOTICES
2198. Additionally, in the current
version of the SHINE QAPD (ADAMS
Accession No. ML20105A316), SHINE
defines safety-related SSCs as ‘‘those
physical SSCs whose intended
functions are to prevent accidents that
could cause undue risk to health and
safety of workers and the public; and to
control or mitigate the consequences of
such accidents.’’ The NRC staff
approved of SHINE’s use of a customdefinition of safety-related SSCs in
NUREG–2198 because the 10 CFR 50.2
definition of ‘‘safety-related structures,
systems, and components’’ did not
apply to a facility that was not a power
reactor and the custom definition was
appropriate for the SHINE facility. The
NRC staff similarly concludes that the
definitions that SHINE proposes to use
(in lieu of the those required by 10 CFR
21.3) are similar to those previously
approved at other facilities and are
appropriate for the SHINE facility,
which has SSCs with unique design or
specification requirements based on
their intended safety function.
Accordingly, the revision of the QAPD
to incorporate the proposed definitions
and the assumption by SHINE (or its
approved sub-contractor) of full
responsibility as the dedicating entity
are appropriate to support procurement
of certain unique items because they
will provide a controlled and safe
approach for item procurement for the
construction of the first-of-its-kind
SHINE facility. Therefore, the NRC finds
that the requested exemption does not
endanger life or property or the common
defense and security.
The NRC staff determined that the
requested exemption is in the public
interest. The requested exemption
would allow SHINE to implement a
controlled and safe approach to item
procurement for the construction of the
SHINE facility. Additionally, consistent
with the American Medical Isotopes
Production Act of 2012 (42 U.S.C. 2065),
construction of the SHINE facility
supports the establishment of a
domestically-produced commercial
supply of molybdenum-99, which is in
the interest of public health. Therefore,
the NRC finds that the requested
exemption is in the public interest.
III. Environmental Considerations
The granting of this exemption is
categorically excluded under 10 CFR
51.22, ‘‘Criterion for categorical
exclusion; identification of licensing
and regulatory actions eligible for
categorical exclusion or otherwise not
requiring environmental review,’’
paragraph (c)(25), and there are no
special circumstances present that
would preclude reliance on this
VerDate Sep<11>2014
19:58 May 13, 2021
Jkt 253001
exclusion. The NRC staff determined,
per 10 CFR 51.22(c)(25)(vi)(I), that the
requirements from which the exemption
is sought involve other requirements of
an administrative, managerial, or
organizational nature. The NRC staff
also determined that approval of this
exemption involves no significant
hazards consideration because
authorizing the use of the specified
definitions that differ from those in 10
CFR 21.3 does not authorize any
physical changes to the facility or any
of its safety systems, does not change
any of the assumptions or limits used in
SHINE’s safety analyses, does not
introduce any new failure modes, and
allows procurement of commercial
grade items, which if properly
dedicated, will have comparable safety
functions. As a result, there is no
significant increase in the probability or
consequences of an accident previously
evaluated, there is no creation of the
possibility of a new or different kind of
accident from any accident previously
evaluated, and there is no significant
reduction in a margin of safety.
In addition, because the SHINE
facility is under construction and an
operating license has not been issued,
there is no significant change in the
types or significant increase in the
amounts of any effluents that may be
released offsite because the exemption
does not affect any effluent release
limits as provided in SHINE’s technical
specifications or by the regulations in 10
CFR part 20, ‘‘Standards for Protection
Against Radiation.’’ There is no
significant increase in individual or
cumulative public or occupational
radiation exposure because the
exemption does not affect the limits on
the release of any radioactive material or
the limits provided in 10 CFR part 20
for radiation exposure to workers or
members of the public. There is no
significant construction impact because
the exemption does not involve any
changes to a construction permit. There
is no significant increase in the
potential for or consequences from
radiological accidents because the
exemption does not alter any of the
assumptions or limits in SHINE’s safety
analysis. Therefore, the NRC has
determined that granting the exemption
would not individually or cumulatively
have a significant effect on the human
environment.
IV. Conclusions
Based on its review, the NRC staff
finds that the use of the SHINEproposed definitions of commercial
grade item, basic component, critical
characteristics, dedication, and
dedicating entity do not adversely affect
PO 00000
Frm 00096
Fmt 4703
Sfmt 4703
public health and safety. Therefore, the
use of commercial grade items by
SHINE, which are properly dedicated, is
acceptable. Further, the NRC staff
considered the requirements of 10 CFR
21.7 and finds that granting this
exemption from certain 10 CFR 21.3
definitions is authorized by law and
will not endanger life or property or the
common defense and security, and is
otherwise in the public’s interest.
Therefore, the NRC grants the
exemption from 10 CFR 21.3 definitions
of commercial grade item, basic
component, critical characteristics,
dedicating entity, and dedication,
subject to the condition that (1) SHINE
revise its QAPD consistent with the
alternate definitions stated above and
prior to assuming full responsibility as
the dedicating entity or otherwise
implementing its commercial grade
procurement strategy and dedication
process, and (2) SHINE shall submit the
revised QAPD to the NRC consistent
with the 10 CFR 50.34(b)(6)(ii)
requirement to include managerial and
administrative controls to be used to
assure safe operation of the facility as
part of the final safety analysis report for
an operating license application.
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 30th day
of April 2021.
For the Nuclear Regulatory Commission.
/RA/
Brian W. Smith,
Deputy Director, Division of Advanced
Reactors and Non-Power, Production and
Utilization Facilities, Office of Nuclear
Reactor Regulation.
[FR Doc. 2021–09903 Filed 5–13–21; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 52–026; NRC–2008–0252]
Southern Nuclear Operating Company
Inc; Vogtle Electric Generating Plant
Unit 4
Nuclear Regulatory
Commission.
ACTION: Exemption; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has issued an
exemption in response to a March 6,
2020, request from Southern Nuclear
Operating Company, Inc. (SNC), as
applicable to Vogtle Electric Generating
Plant (VEGP) Unit 4. Specifically, the
NRC has exempted SNC from the
requirement for VEGP Unit 4 to conduct
an emergency preparedness exercise
prior to its initial fuel load.
SUMMARY:
E:\FR\FM\14MYN1.SGM
14MYN1
Federal Register / Vol. 86, No. 92 / Friday, May 14, 2021 / Notices
This exemption was issued on
July 21, 2020.
ADDRESSES: Please refer to Docket ID
NRC–2008–0252 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2008–0252. Address
questions about Docket IDs in
Regulations.gov to Stacy Schumann;
telephone: 301–415–0624; email:
Stacy.Schumann@nrc.gov. For technical
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced (if it is
available in ADAMS) is provided the
first time that it is mentioned in this
document. The request for the
exemption was submitted by letter
dated March 6, 2020 and is available in
ADAMS under Package Accession No.
ML20066G902.
FOR FURTHER INFORMATION CONTACT:
Cayetano Santos Jr., Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
7270; email: Cayetano.Santos@nrc.gov.
• Attention: The PDR, where you may
examine and order copies of public
documents, is currently closed. You
may submit your request to the PDR via
email at pdr.resource@nrc.gov or call 1–
800–397–4209 or 301–415–4737,
between 8:00 a.m. and 4:00 p.m. (EST),
Monday through Friday, except Federal
holidays.
SUPPLEMENTARY INFORMATION:
khammond on DSKJM1Z7X2PROD with NOTICES
DATES:
I. Background
Southern Nuclear Operating
Company, Inc., Georgia Power
Company, Oglethorpe Power
Corporation, MEAG Power SPVM, LLC,
MEAG Power SPVJ, LLC, MEAG Power
SPVP, LLC, and the City of Dalton,
Georgia (collectively SNC) are the
holders of facility Combined License
(COL) Nos. NFP–91 and NPF–92, which
authorize the construction and
VerDate Sep<11>2014
19:58 May 13, 2021
Jkt 253001
operation of VEGP Units 3 and 4. The
COLs, issued under part 52 of title 10
of the Code of Federal Regulations (10
CFR), provide, among other things, that
the facilities are subject to all rules,
regulations, and orders of the NRC or
the Commission now or hereafter in
effect.
Section IV.F.2.a.(iii) of appendix E,
‘‘Emergency Planning and Preparedness
for Production and Utilization
Facilities,’’ to part 50 of 10 CFR states,
in part, that for a combined license
issued under 10 CFR part 52, if the
applicant currently has an operating
reactor at the site, an exercise, either full
or partial participation, shall be
conducted for each subsequent reactor
constructed on the site. VEGP Units 3
and 4 are of the same reactor design
(Westinghouse Electric Company
(Westinghouse) AP1000 pressurizedwater reactor), and VEGP Units 1, 2, 3,
and 4 share the same operating site. In
a letter dated March 6, 2020, SNC
requested an exemption from the
requirement to perform an emergency
preparedness exercise for VEGP Unit 4.
The NRC staff’s evaluation of SNC’s
exemption request for Unit 4 is based on
VEGP Unit 3 first successfully
completing an emergency preparedness
exercise as required by section
IV.F.2.a.(iii) of appendix E, and
establishing an 8-calendar-year
emergency preparedness exercise cycle
that incorporates both VEGP Units 3 and
4 drill and exercise requirements prior
to VEGP Unit 4 commencing initial fuel
load. The justification for the exemption
is that the successful completion of the
VEGP Unit 3 partial participation
exercise demonstrate all aspects of
emergency response capabilities for
both units, thereby making a separate
exercise for VEGP Unit 4 to meet the
requirements of section IV.F.2.a.(iii) of
appendix E unnecessary.
In Part 5, ‘‘Emergency Plan,’’ of its
December 31, 2008, Early Site Permit
(ESP) Application (Revision 5) for VEGP
Units 3 and 4, SNC included a complete
and integrated emergency plan for VEGP
Units 3 and 4, referred to as the ‘‘ESP
Plan’’ (Docket No. 52–011; ADAMS
Accession No. ML091540898). The NRC
staff documented its review of the ESP
Plan in Section 13.3, ‘‘Emergency
Planning,’’ of NUREG–1923, ‘‘Safety
Evaluation Report for an Early Site
Permit (ESP) at the Vogtle Electric
Generating Plant (VEGP) ESP Site,’’ July
2009 (ADAMS Accession No.
ML092290650), and included an
evaluation of the emergency plan’s
description of proposed Units 3 and 4
exercises in Section 13.3.3.2.14,
‘‘Exercises and Drills (10 CFR
PO 00000
Frm 00097
Fmt 4703
Sfmt 4703
26553
50.47(b)(14); NUREG–0654/FEMA–
REP–1, planning standard N).’’
The NRC issued Early Site Permit No.
ESP–004 for the VEGP ESP Site (i.e., for
Units 3 and 4) on August 26, 2009
(ADAMS Accession No. ML092290157).
ESP–004, including the ESP Plan, was
incorporated by reference into SNC’s
June 24, 2011, COL application for
VEGP Units 3 and 4 (Docket Nos. 52–
025 and 52–026, respectively; ADAMS
Accession No. ML11180A086), and the
Units 3 and 4 COLs were issued on
February 10, 2012 (ADAMS Accession
Nos. ML14100A106 and ML14100A135,
respectively). The NRC staff
documented its review of the COL
application in Section 13.3, ‘‘Emergency
Planning,’’ of NUREG–2124, ‘‘Final
Safety Evaluation Report—Related to
the Combined Licenses for Vogtle
Electric Generating Plant, Units 3 and
4,’’ Volume 2, September 2012 (ADAMS
Accession No. ML12271A048).
The NRC staff’s reasonable assurance
finding for the ESP Plan was subject to
the satisfactory completion of the
inspections, tests, analyses, and
acceptance criteria (ITAAC) that were
listed in NUREG–1923 Section [Table]
13.3.6, ‘‘VEGP Unit 4 ITAAC,’’ which
includes ITAAC 8.0, ‘‘Exercises and
Drills.’’ ITAAC 8.0 requires a limited
participation exercise for Unit 4, in
order to demonstrate the various
emergency preparedness capabilities
listed in the associated ITAAC
acceptance criteria. The ESP Plan and
Unit 4 ITAAC were included in SNC’s
Unit 4 COL application, and ITAAC 8.0
(consisting of Unit 4 ITAAC Nos. 870,
E.3.9.08.01.01; 871, E.3.9.08.01.02; and
872, E.3.9.08.01.03) was included in
Appendix C, Table E.3.9–8 of the Unit
4 COL.
Unit 4 COL ITAAC 870, 871, and 872,
which address exercise-related aspects
of emergency preparedness and
response for Unit 4, were subsequently
deleted by Unit 4 License Amendment
No. 161 (September 5, 2018; ADAMS
Package Accession No. ML19213A288).
Prior to their deletion, ITAAC 870, 871,
and 872 had been revised by Unit 4
License Amendment No. 94 (ADAMS
Package Accession No. ML17256A028)
(referenced by SNC in its exemption
request) to change the ITAAC Program
Commitment to conduct a partial
participation exercise, and to
consolidate duplicated or redundant
ITAAC. Finally, while License
Amendment 161 deleted the Unit 4 COL
requirement in ITAAC 870, 871, and
872 to conduct a partial participation
exercise, the separate exercise
requirement in section IV.F.2.a.(iii) of
appendix E to 10 CFR part 50 remained
E:\FR\FM\14MYN1.SGM
14MYN1
26554
Federal Register / Vol. 86, No. 92 / Friday, May 14, 2021 / Notices
applicable to Unit 4 and is the subject
of this exemption request.
II. Request/Action
Pursuant to 10 CFR 50.12, ‘‘Specific
exemptions,’’ SNC requested, by letter
dated March 6, 2020 (ADAMS
Accession No. ML20066G904), an
exemption from the requirements of
section IV.F.2.a.(iii) of appendix E to 10
CFR part 50, as applicable to VEGP Unit
4. Enclosure 1 to this letter includes the
supporting justification for SNC’s
request (ADAMS Accession No.
ML20066G906). Specifically, SNC
requested an exemption for VEGP Unit
4 from the requirement in section
IV.F.2.a.(iii) to appendix E of 10 CFR
part 50 for an applicant who currently
has an operating reactor at the site to
perform an exercise, either full or partial
participation, for each subsequent
reactor constructed on the site. The
exemption removes the requirement to
perform an emergency preparedness
exercise at VEGP Unit 4 prior to its
initial fuel load.
khammond on DSKJM1Z7X2PROD with NOTICES
III. Discussion
Pursuant to 10 CFR 50.12, the
Commission may, upon application by
any interested person or upon its own
initiative, grant exemptions from the
requirements of 10 CFR part 50 when:
(1) The exemptions are authorized by
law, will not present an undue risk to
the health and safety of the public, and
are consistent with the common defense
and security; and (2) special
circumstances are present. These special
circumstances include, among other
things, when the application of the
regulation in the particular
circumstances would not serve the
underlying purpose of the rule or is not
necessary to achieve the underlying
purpose of the rule.
1. The Exemption Is Authorized by Law
The exemption removes the
requirement in section IV.F.2.a.(iii) of
appendix E to 10 CFR part 50 for SNC
to perform an emergency preparedness
exercise, either full or partial
participation, at VEGP Unit 4 prior to
initial fuel load. The VEGP Unit 4
emergency preparedness response
capabilities, emergency response
facilities, and emergency response
organization (ERO) are common to both
VEGP Units 3 and 4 and have been
evaluated during a VEGP Unit 3 partial
participation exercise. These emergency
preparedness response capabilities will
continue to be evaluated under the 8calendar-year emergency preparedness
exercise cycle for the VEGP site (Units
1, 2, 3, and 4). The NRC staff has
determined that granting SNC’s
VerDate Sep<11>2014
19:58 May 13, 2021
Jkt 253001
requested exemption will not result in
a violation of the Atomic Energy Act of
1954, as amended, or the Commission’s
regulations and that no other law
precludes the requested changes.
Therefore, the exemption is authorized
by law.
2. The Exemption Presents No Undue
Risk to Public Health and Safety
The NRC staff considered SNC’s
detailed justification supporting the
proposed exemption from section
IV.F.2.a.(iii) of appendix E to 10 CFR
part 50 for VEGP Unit 4’s exercise prior
to its initial fuel load. Based on its
review of the information submitted
with SNC’s requested exemption, the
NRC staff concluded that VEGP Unit 4
shares emergency preparedness program
response capabilities with Vogtle Unit 3
under a common VEGP Emergency Plan
Annex, which was subsequently
demonstrated during VEGP Unit 3’s
initial partial participation exercise. In
addition, future Unit 4 exercises will be
conducted as part of the 8-calendar-year
exercise cycle for the VEGP site (Units
1, 2, 3, and 4).
The VEGP Unit 4 capabilities that will
have been demonstrated during the
VEGP Unit 3 exercise comprise various
principal functional areas of emergency
response, as they are described in the
applicable exercise-related requirements
and guidance. Specifically, areas of
demonstration during exercises are
described in 10 CFR 50.47(b)(14), which
identifies major portions of emergency
response capabilities, and in sections
IV.F.2.b and IV.F.2.j of appendix E to 10
CFR part 50, which identify key skills
necessary to implement the principal
functional areas of emergency response.
In addition, section IV.F.2.a of appendix
E calls for conducting an exercise that
will test as much of the emergency
plans as is reasonably achievable for
each reactor site without mandatory
public participation. The scope of
exercise demonstrations is also
addressed in related guidance,
consisting of Section II.N.1 of NUREG–
0654, ‘‘Criteria for Preparation and
Evaluation of Radiological Emergency
Response Plans and Preparedness in
Support of Nuclear Power Plants,’’
November 1980 (ADAMS Accession No.
ML040420012), which states that
exercises should test the integrated
capability and a major portion of the
basic elements existing within
emergency preparedness plans and
organizations, and verify the capability
to respond to an accident scenario
requiring response. The successful
completion of the Unit 3 partial
participation exercise means that the
exercise requirements addressed in this
PO 00000
Frm 00098
Fmt 4703
Sfmt 4703
notice have been evaluated, and any
deficiencies have been corrected.
The NRC staff finds that Units 3 and
4 are of the same reactor type and
design (i.e., Westinghouse AP1000
reactor), and that they share the same
resources, requirements, capabilities,
emergency response facilities,
procedures, and ERO, which is
facilitated by VEGP Units 3 and 4 being
located side-by-side on the VEGP site. In
addition, the NRC staff finds that the
identified, shared emergency planning
resources, requirements, capabilities,
etc., are consistent with the
requirements of the applicable
regulations and guidance for
demonstration of the principal
functional areas of emergency response
during an exercise. Further, inclusion of
the VEGP Unit 4 exercise into the 8calendar-year exercise cycle for the
VEGP site would postpone its first
exercise until after initial fuel load. This
option is consistent with section
IV.F.2.a.(iii) of appendix E to 10 CFR
part 50, which states, in part, that this
exercise may be incorporated in the
exercise requirements of sections
IV.F.2.b and IV.F.2.c of appendix E
(which address the timing and
coordination of exercises at reactor
sites). Therefore, the NRC staff has
determined that conducting a VEGP
Unit 4 partial participation exercise
prior to Unit 4’s initial fuel load will not
demonstrate any new aspects of
emergency planning resources,
capabilities, emergency response
facilities, procedures, or ERO used to
accomplish the principal functional
areas of emergency response that were
not already demonstrated during the
VEGP Unit 3 partial participation
exercise.
Because the VEGP Unit 4 emergency
preparedness response capabilities and
ERO were already demonstrated during
a VEGP Unit 3 partial participation
exercise and will continue to be
evaluated under the 8-calendar-year
emergency preparedness exercise cycle
for the VEGP site, there is no change in
risk to public health and safety.
Therefore, the exemption does not
present an undue risk to public health
and safety.
3. The Exemption Is Consistent With the
Common Defense and Security
The exemption from section
IV.F.2.a.(iii) of appendix E to 10 CFR
part 50 removes the requirement for
SNC to perform an emergency
preparedness exercise at VEGP Unit 4
prior to initial fuel load. The licensee’s
successful completion of the Unit 3
partial participation exercise
demonstrates the adequacy of
E:\FR\FM\14MYN1.SGM
14MYN1
Federal Register / Vol. 86, No. 92 / Friday, May 14, 2021 / Notices
khammond on DSKJM1Z7X2PROD with NOTICES
emergency preparedness response
capabilities and ERO for both Units 3
and 4. Units 3 and 4 would also be
incorporated into the 8-calendar-year
emergency preparedness exercise cycle
for the VEGP site. In addition, this
exemption does not involve changes to
the SNC Standard Emergency Plan or
the VEGP Units 3 and 4 Standard
Emergency Plan Annex and has no
impact on plant security or safeguards.
Therefore, the NRC staff has determined
that this exemption does not affect the
common defense and security.
4. Special Circumstances
Special circumstances, in accordance
with 10 CFR 50.12(a)(2)(ii), are present
whenever application of the regulation
in the particular circumstances would
not serve the underlying purpose of the
rule or is not necessary to achieve the
underlying purpose of the rule. Section
IV.F.2.a.(iii) of appendix E to 10 CFR
part 50 requires, in part, that an
emergency preparedness exercise be
conducted for each subsequent reactor
constructed on an existing reactor site.
The underlying purpose of section
IV.F.2.a.(iii) of appendix E to 10 CFR
part 50 for VEGP Unit 4 is to ensure that
an adequate state of emergency
preparedness response capability exists
for VEGP Unit 4 through the conduct of
an emergency preparedness exercise
prior to Unit 4 initial fuel load. In
addition, as the Commission described
in the statement of consideration for the
2007 final rule (72 FR 49351, 49401,
August 28, 2007) that added section
IV.F.2.a.(iii) to appendix E to 10 CFR
part 50, the requirement for emergency
preparedness exercises for each
subsequent reactor constructed at a site
was intended to provide for the
demonstration of ITAAC for various
emergency preparedness requirements
(e.g., programs and facilities) that did
not warrant their own specific, detailed
ITAAC (separate from the exercise).
The exemption removes the
requirement to perform an emergency
preparedness exercise at VEGP Unit 4
prior to initial fuel load. Since all the
emergency preparedness exercise
ITAAC for VEGP Unit 4 were previously
deleted by License Amendment 161,
and the VEGP Unit 4 emergency
preparedness response capabilities and
ERO were demonstrated during the Unit
3 partial participation exercise, the
underlying purpose of section
IV.F.2.a.(iii) for the VEGP Unit 4
exercise is met under the terms of the
exemption. Therefore, the NRC staff has
determined that the special
circumstances required by 10 CFR
50.12(a)(2)(ii) for the granting of the
exemption from section IV.F.2.a.(iii)
VerDate Sep<11>2014
19:58 May 13, 2021
Jkt 253001
exist because requiring a separate
exercise for Unit 4 is not necessary to
meet the underlying purpose of the rule.
5. Environmental Consideration
The NRC staff determined that the
exemption discussed herein meets the
eligibility criteria for the categorical
exclusion set forth in 10 CFR
51.22(c)(25). The requested exemption
seeks to remove the requirement in
section IV.F.2.a.(iii) of appendix E to 10
CFR part 50 to conduct either a full or
partial participation emergency
preparedness exercise for VEGP Unit 4
prior to its initial fuel load, but does not
make any physical changes to the
facility, the approved SNC Standard
Emergency Plan, the VEGP Units 3 and
4 Standard Emergency Plan Annex, or
the facility operating procedures. Under
10 CFR 51.22(c)(25), granting an
exemption from the requirements of any
regulation of chapter I to 10 CFR is a
categorical exclusion provided that (i)
there is no significant hazards
consideration; (ii) there is no significant
change in the types or significant
increase in the amounts of any effluents
that may be released offsite; (iii) there is
no significant increase in individual or
cumulative public or occupational
radiation exposure; (iv) there is no
significant construction impact; (v)
there is no significant increase in the
potential for or consequences from
radiological accidents; and (vi) the
requirements from which an exemption
is sought involve certain categories of
requirements, such as scheduling
requirements related to the performance
of an emergency preparedness exercise.
As required by 10 CFR 51.22(c)(25)(i),
and using the criteria set out in 10 CFR
50.92(c), the NRC staff reviewed
whether the exemption request involves
no significant hazards consideration.
(1) Does the requested exemption
involve a significant increase in the
probability or consequences of an
accident previously evaluated?
No. The exemption to 10 CFR part 50,
appendix E, section IV.F.2.a.(iii)
removes the requirement to perform an
emergency preparedness exercise at
VEGP Unit 4 prior to initial fuel load.
The exemption does not alter the
design, function, or operation of any
plant equipment and does not involve
or interface with any structure, system
or component (SSC) accident initiator or
initiating sequence of events, so the
probabilities of the accidents evaluated
in the Updated Final Safety Analysis
Report (UFSAR) are not affected. The
exemption does not allow for a new
fission product release path, nor does it
result in a new fission product barrier
failure mode or create a new sequence
PO 00000
Frm 00099
Fmt 4703
Sfmt 4703
26555
of events that would result in fuel
cladding failures. The exemption does
not involve any safety-related SSCs or
functions used to mitigate an accident,
thus the consequences of the accidents
evaluated in the UFSAR are not
affected. Therefore, granting this
exemption does not involve a significant
increase in the probability or
consequences of an accident previously
evaluated.
(2) Does the requested exemption
create the possibility of a new or
different kind of accident from any
accident previously evaluated?
No. The exemption does not alter the
design, function, or operation of any
plant equipment. The exemption does
not create any new failure mechanisms,
malfunctions, or accident initiators. The
exemption does not affect the operation
of any systems or equipment such that
a new or different kind of accident,
failure mode, or malfunction is created,
or alter any SSC such that a new
accident initiator or initiating sequence
of events is created. Therefore, granting
this exemption does not create the
possibility of a new or different kind of
accident from any accident previously
evaluated.
(3) Does the requested exemption
involve a significant reduction in a
margin of safety?
No. The exemption does not affect an
SSC, SSC design function, or method of
performing or controlling a design
function. The exemption does not affect
safety-related equipment or fission
product barriers. No safety analysis or
design basis acceptance limit or
criterion is challenged or exceeded by
the exemption. The exemption does not
involve changes to the SNC Standard
Emergency Plan or the VEGP Units 3
and 4 Standard Emergency Plan Annex,
and therefore, there is no reduction in
effectiveness in emergency planning,
pursuant to 10 CFR 50.54(q). Therefore,
granting this exemption does not
involve a significant reduction in a
margin of safety.
As all of the responses to the above
questions are in the negative, under 10
CFR 51.22(c)(25)(i), the NRC staff has
concluded that the exemption involves
no significant hazards consideration.
The exemption does not alter the
design, function, or operation of any
plant equipment. There are no changes
to effluent types, plant radiological or
non-radiological effluent release
quantities, any effluent release path, or
the functionality of any design or
operational features credited with
controlling the release of effluents
during plant operation or construction.
Therefore, under 10 CFR 51.22(c)(25)(ii),
the NRC staff concludes that the
E:\FR\FM\14MYN1.SGM
14MYN1
26556
Federal Register / Vol. 86, No. 92 / Friday, May 14, 2021 / Notices
khammond on DSKJM1Z7X2PROD with NOTICES
exemption does not involve a significant
change in the types or significant
increase in the amounts of any effluents
that may be released offsite.
The exemption does not change plant
radiation zones, radiological effluent
release pathways and release quantities,
or cause any changes to the controls
required under 10 CFR part 20 that
preclude a significant increase in public
dose or occupational radiation
exposure. Therefore, under 10 CFR
51.22(c)(25)(iii), the NRC staff concludes
that the exemption does not involve a
significant increase in individual or
cumulative public or occupational
radiation exposure.
The exemption does not alter the
design, function, or operation of any
plant equipment. No change to the
facility is being made as a result of this
exemption. Therefore, under 10 CFR
51.22(c)(25)(iv), the NRC staff concludes
that the exemption does not involve a
significant construction impact.
The exemption does not alter the
design, function, or operation of any
plant equipment, and does not involve
any safety-related SSCs or functions
used to mitigate an accident. No change
to the facility is being made as a result
of this exemption. Therefore, under 10
CFR 51.22(c)(25)(v), the NRC staff
concludes that the exemption does not
involve a significant increase in the
potential for or consequences from
radiological accidents.
The exemption involves scheduling
requirements related to the performance
of an emergency preparedness exercise.
Therefore, under 10 CFR
51.22(c)(25)(vi)(G), the NRC staff
concludes that the exemption involves a
scheduling requirement.
Based on the evaluation above, the
NRC staff concludes that the exemption
meets the criteria of 10 CFR
51.22(c)(25). Therefore, in accordance
with 10 CFR 51.22(b), an environmental
impact statement or environmental
assessment is not required for the NRC
staff’s consideration of this exemption
request.
IV. Conclusion
Based on the above, the NRC staff
concludes that, with the VEGP Unit 4
exemption from section IV.F.2.a.(iii) of
appendix E to 10 CFR part 50, there is
reasonable assurance that adequate
protective measures can, and will, be
taken in the event of a radiological
emergency at VEGP Unit 4, and that
VEGP Unit 4 continues to demonstrate
compliance with 10 CFR 50.47(b)(14)
and appendix E to 10 CFR part 50.
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12, the exemption is authorized by
VerDate Sep<11>2014
19:58 May 13, 2021
Jkt 253001
law, will not present an undue risk to
the health and safety of the public, and
is consistent with the common defense
and security. Also, special
circumstances are present. Therefore,
given that a partial participation
exercise for VEGP Unit 3 was
successfully completed, the
Commission has granted SNC an
exemption from section IV.F.2.a.(iii) of
appendix E to 10 CFR part 50, to
eliminate the requirement to perform an
emergency preparedness exercise at
VEGP Unit 4 prior to its initial fuel load.
Dated: May 11, 2021.
For the Nuclear Regulatory Commission.
Gregory T. Bowman,
Director, Vogtle Project Office, Office of
Nuclear Reactor Regulation.
[FR Doc. 2021–10254 Filed 5–13–21; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2021–0110]
Environmental Assessment and
Findings of No Significant Impact of
Independent Spent Fuel Storage
Facilities Decommissioning Funding
Plans
Nuclear Regulatory
Commission.
ACTION: Environmental assessment and
finding of no significant impact;
issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is publishing this
notice regarding the issuance of a final
Environmental Assessment (EA) and a
Finding of No Significant Impact
(FONSI) for its review and approval of
the initial and updated
decommissioning funding plans (DFPs)
submitted by Sacramento Municipal
Utility District (SMUD) for the Rancho
Seco independent spent fuel storage
installation (ISFSI).
DATES: The EA and FONSI referenced in
this document are available on May 14,
2021.
ADDRESSES: Please refer to Docket ID
NRC–2021–0110 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2021–0110. Address
questions about Docket IDs in
Regulations.gov to Stacy Schumann;
telephone: 301–415–0624; email:
Stacy.Schumann@nrc.gov. For technical
SUMMARY:
PO 00000
Frm 00100
Fmt 4703
Sfmt 4703
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced (if it is
available in ADAMS) is provided the
first time that it is mentioned in this
document.
• Attention: The PDR, where you may
examine and order copies of public
documents, is currently closed. You
may submit your request to the PDR via
email at pdr.resource@nrc.gov or call
1–800–397–4209 or 301–415–4737,
between 8:00 a.m. and 4:00 p.m. (EST),
Monday through Friday, except Federal
holidays.
FOR FURTHER INFORMATION CONTACT:
Chris Allen, Office of Nuclear Material
Safety and Safeguards, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
6877, email: William.Allen@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is considering the approval
of the initial and updated DFPs
submitted by SMUD for the Rancho
Seco ISFSI. The NRC staff has prepared
a final EA and FONSI determination for
SMUDS’s initial and updated DFPs in
accordance with the NRC regulations in
Part 51 of title 10 of the Code of Federal
Regulations (10 CFR), ‘‘Environmental
Protection Regulations for Domestic
Licensing and Related Regulatory
Functions,’’ which implement the
National Environmental Policy Act of
1969, as amended (42 U.S.C. 4321 et
seq.).
The NRC requires its licensees to plan
for the eventual decommissioning of
their licensed facilities prior to license
termination. On June 17, 2011, the NRC
published a final rule in the Federal
Register amending its decommissioning
planning regulations (76 FR 35511). The
final rule amended the NRC regulation,
10 CFR 72.30, which concerns financial
assurance and decommissioning for
ISFSIs. This regulation requires each
holder of, or applicant for, a license
under 10 CFR part 72 to submit a DFP
for the NRC’s review and approval. The
DFP is to demonstrate the licensee’s
E:\FR\FM\14MYN1.SGM
14MYN1
Agencies
[Federal Register Volume 86, Number 92 (Friday, May 14, 2021)]
[Notices]
[Pages 26552-26556]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-10254]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 52-026; NRC-2008-0252]
Southern Nuclear Operating Company Inc; Vogtle Electric
Generating Plant Unit 4
AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued an
exemption in response to a March 6, 2020, request from Southern Nuclear
Operating Company, Inc. (SNC), as applicable to Vogtle Electric
Generating Plant (VEGP) Unit 4. Specifically, the NRC has exempted SNC
from the requirement for VEGP Unit 4 to conduct an emergency
preparedness exercise prior to its initial fuel load.
[[Page 26553]]
DATES: This exemption was issued on July 21, 2020.
ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2008-0252. Address
questions about Docket IDs in Regulations.gov to Stacy Schumann;
telephone: 301-415-0624; email: [email protected]. For technical
questions, contact the individual listed in the FOR FURTHER INFORMATION
CONTACT section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or
by email to [email protected]. The ADAMS accession number for each
document referenced (if it is available in ADAMS) is provided the first
time that it is mentioned in this document. The request for the
exemption was submitted by letter dated March 6, 2020 and is available
in ADAMS under Package Accession No. ML20066G902.
FOR FURTHER INFORMATION CONTACT: Cayetano Santos Jr., Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-7270; email: [email protected].
Attention: The PDR, where you may examine and order copies
of public documents, is currently closed. You may submit your request
to the PDR via email at [email protected] or call 1-800-397-4209 or
301-415-4737, between 8:00 a.m. and 4:00 p.m. (EST), Monday through
Friday, except Federal holidays.
SUPPLEMENTARY INFORMATION:
I. Background
Southern Nuclear Operating Company, Inc., Georgia Power Company,
Oglethorpe Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ,
LLC, MEAG Power SPVP, LLC, and the City of Dalton, Georgia
(collectively SNC) are the holders of facility Combined License (COL)
Nos. NFP-91 and NPF-92, which authorize the construction and operation
of VEGP Units 3 and 4. The COLs, issued under part 52 of title 10 of
the Code of Federal Regulations (10 CFR), provide, among other things,
that the facilities are subject to all rules, regulations, and orders
of the NRC or the Commission now or hereafter in effect.
Section IV.F.2.a.(iii) of appendix E, ``Emergency Planning and
Preparedness for Production and Utilization Facilities,'' to part 50 of
10 CFR states, in part, that for a combined license issued under 10 CFR
part 52, if the applicant currently has an operating reactor at the
site, an exercise, either full or partial participation, shall be
conducted for each subsequent reactor constructed on the site. VEGP
Units 3 and 4 are of the same reactor design (Westinghouse Electric
Company (Westinghouse) AP1000 pressurized-water reactor), and VEGP
Units 1, 2, 3, and 4 share the same operating site. In a letter dated
March 6, 2020, SNC requested an exemption from the requirement to
perform an emergency preparedness exercise for VEGP Unit 4.
The NRC staff's evaluation of SNC's exemption request for Unit 4 is
based on VEGP Unit 3 first successfully completing an emergency
preparedness exercise as required by section IV.F.2.a.(iii) of appendix
E, and establishing an 8-calendar-year emergency preparedness exercise
cycle that incorporates both VEGP Units 3 and 4 drill and exercise
requirements prior to VEGP Unit 4 commencing initial fuel load. The
justification for the exemption is that the successful completion of
the VEGP Unit 3 partial participation exercise demonstrate all aspects
of emergency response capabilities for both units, thereby making a
separate exercise for VEGP Unit 4 to meet the requirements of section
IV.F.2.a.(iii) of appendix E unnecessary.
In Part 5, ``Emergency Plan,'' of its December 31, 2008, Early Site
Permit (ESP) Application (Revision 5) for VEGP Units 3 and 4, SNC
included a complete and integrated emergency plan for VEGP Units 3 and
4, referred to as the ``ESP Plan'' (Docket No. 52-011; ADAMS Accession
No. ML091540898). The NRC staff documented its review of the ESP Plan
in Section 13.3, ``Emergency Planning,'' of NUREG-1923, ``Safety
Evaluation Report for an Early Site Permit (ESP) at the Vogtle Electric
Generating Plant (VEGP) ESP Site,'' July 2009 (ADAMS Accession No.
ML092290650), and included an evaluation of the emergency plan's
description of proposed Units 3 and 4 exercises in Section 13.3.3.2.14,
``Exercises and Drills (10 CFR 50.47(b)(14); NUREG-0654/FEMA-REP-1,
planning standard N).''
The NRC issued Early Site Permit No. ESP-004 for the VEGP ESP Site
(i.e., for Units 3 and 4) on August 26, 2009 (ADAMS Accession No.
ML092290157). ESP-004, including the ESP Plan, was incorporated by
reference into SNC's June 24, 2011, COL application for VEGP Units 3
and 4 (Docket Nos. 52-025 and 52-026, respectively; ADAMS Accession No.
ML11180A086), and the Units 3 and 4 COLs were issued on February 10,
2012 (ADAMS Accession Nos. ML14100A106 and ML14100A135, respectively).
The NRC staff documented its review of the COL application in Section
13.3, ``Emergency Planning,'' of NUREG-2124, ``Final Safety Evaluation
Report--Related to the Combined Licenses for Vogtle Electric Generating
Plant, Units 3 and 4,'' Volume 2, September 2012 (ADAMS Accession No.
ML12271A048).
The NRC staff's reasonable assurance finding for the ESP Plan was
subject to the satisfactory completion of the inspections, tests,
analyses, and acceptance criteria (ITAAC) that were listed in NUREG-
1923 Section [Table] 13.3.6, ``VEGP Unit 4 ITAAC,'' which includes
ITAAC 8.0, ``Exercises and Drills.'' ITAAC 8.0 requires a limited
participation exercise for Unit 4, in order to demonstrate the various
emergency preparedness capabilities listed in the associated ITAAC
acceptance criteria. The ESP Plan and Unit 4 ITAAC were included in
SNC's Unit 4 COL application, and ITAAC 8.0 (consisting of Unit 4 ITAAC
Nos. 870, E.3.9.08.01.01; 871, E.3.9.08.01.02; and 872, E.3.9.08.01.03)
was included in Appendix C, Table E.3.9-8 of the Unit 4 COL.
Unit 4 COL ITAAC 870, 871, and 872, which address exercise-related
aspects of emergency preparedness and response for Unit 4, were
subsequently deleted by Unit 4 License Amendment No. 161 (September 5,
2018; ADAMS Package Accession No. ML19213A288). Prior to their
deletion, ITAAC 870, 871, and 872 had been revised by Unit 4 License
Amendment No. 94 (ADAMS Package Accession No. ML17256A028) (referenced
by SNC in its exemption request) to change the ITAAC Program Commitment
to conduct a partial participation exercise, and to consolidate
duplicated or redundant ITAAC. Finally, while License Amendment 161
deleted the Unit 4 COL requirement in ITAAC 870, 871, and 872 to
conduct a partial participation exercise, the separate exercise
requirement in section IV.F.2.a.(iii) of appendix E to 10 CFR part 50
remained
[[Page 26554]]
applicable to Unit 4 and is the subject of this exemption request.
II. Request/Action
Pursuant to 10 CFR 50.12, ``Specific exemptions,'' SNC requested,
by letter dated March 6, 2020 (ADAMS Accession No. ML20066G904), an
exemption from the requirements of section IV.F.2.a.(iii) of appendix E
to 10 CFR part 50, as applicable to VEGP Unit 4. Enclosure 1 to this
letter includes the supporting justification for SNC's request (ADAMS
Accession No. ML20066G906). Specifically, SNC requested an exemption
for VEGP Unit 4 from the requirement in section IV.F.2.a.(iii) to
appendix E of 10 CFR part 50 for an applicant who currently has an
operating reactor at the site to perform an exercise, either full or
partial participation, for each subsequent reactor constructed on the
site. The exemption removes the requirement to perform an emergency
preparedness exercise at VEGP Unit 4 prior to its initial fuel load.
III. Discussion
Pursuant to 10 CFR 50.12, the Commission may, upon application by
any interested person or upon its own initiative, grant exemptions from
the requirements of 10 CFR part 50 when: (1) The exemptions are
authorized by law, will not present an undue risk to the health and
safety of the public, and are consistent with the common defense and
security; and (2) special circumstances are present. These special
circumstances include, among other things, when the application of the
regulation in the particular circumstances would not serve the
underlying purpose of the rule or is not necessary to achieve the
underlying purpose of the rule.
1. The Exemption Is Authorized by Law
The exemption removes the requirement in section IV.F.2.a.(iii) of
appendix E to 10 CFR part 50 for SNC to perform an emergency
preparedness exercise, either full or partial participation, at VEGP
Unit 4 prior to initial fuel load. The VEGP Unit 4 emergency
preparedness response capabilities, emergency response facilities, and
emergency response organization (ERO) are common to both VEGP Units 3
and 4 and have been evaluated during a VEGP Unit 3 partial
participation exercise. These emergency preparedness response
capabilities will continue to be evaluated under the 8-calendar-year
emergency preparedness exercise cycle for the VEGP site (Units 1, 2, 3,
and 4). The NRC staff has determined that granting SNC's requested
exemption will not result in a violation of the Atomic Energy Act of
1954, as amended, or the Commission's regulations and that no other law
precludes the requested changes. Therefore, the exemption is authorized
by law.
2. The Exemption Presents No Undue Risk to Public Health and Safety
The NRC staff considered SNC's detailed justification supporting
the proposed exemption from section IV.F.2.a.(iii) of appendix E to 10
CFR part 50 for VEGP Unit 4's exercise prior to its initial fuel load.
Based on its review of the information submitted with SNC's requested
exemption, the NRC staff concluded that VEGP Unit 4 shares emergency
preparedness program response capabilities with Vogtle Unit 3 under a
common VEGP Emergency Plan Annex, which was subsequently demonstrated
during VEGP Unit 3's initial partial participation exercise. In
addition, future Unit 4 exercises will be conducted as part of the 8-
calendar-year exercise cycle for the VEGP site (Units 1, 2, 3, and 4).
The VEGP Unit 4 capabilities that will have been demonstrated
during the VEGP Unit 3 exercise comprise various principal functional
areas of emergency response, as they are described in the applicable
exercise-related requirements and guidance. Specifically, areas of
demonstration during exercises are described in 10 CFR 50.47(b)(14),
which identifies major portions of emergency response capabilities, and
in sections IV.F.2.b and IV.F.2.j of appendix E to 10 CFR part 50,
which identify key skills necessary to implement the principal
functional areas of emergency response. In addition, section IV.F.2.a
of appendix E calls for conducting an exercise that will test as much
of the emergency plans as is reasonably achievable for each reactor
site without mandatory public participation. The scope of exercise
demonstrations is also addressed in related guidance, consisting of
Section II.N.1 of NUREG-0654, ``Criteria for Preparation and Evaluation
of Radiological Emergency Response Plans and Preparedness in Support of
Nuclear Power Plants,'' November 1980 (ADAMS Accession No.
ML040420012), which states that exercises should test the integrated
capability and a major portion of the basic elements existing within
emergency preparedness plans and organizations, and verify the
capability to respond to an accident scenario requiring response. The
successful completion of the Unit 3 partial participation exercise
means that the exercise requirements addressed in this notice have been
evaluated, and any deficiencies have been corrected.
The NRC staff finds that Units 3 and 4 are of the same reactor type
and design (i.e., Westinghouse AP1000 reactor), and that they share the
same resources, requirements, capabilities, emergency response
facilities, procedures, and ERO, which is facilitated by VEGP Units 3
and 4 being located side-by-side on the VEGP site. In addition, the NRC
staff finds that the identified, shared emergency planning resources,
requirements, capabilities, etc., are consistent with the requirements
of the applicable regulations and guidance for demonstration of the
principal functional areas of emergency response during an exercise.
Further, inclusion of the VEGP Unit 4 exercise into the 8-calendar-year
exercise cycle for the VEGP site would postpone its first exercise
until after initial fuel load. This option is consistent with section
IV.F.2.a.(iii) of appendix E to 10 CFR part 50, which states, in part,
that this exercise may be incorporated in the exercise requirements of
sections IV.F.2.b and IV.F.2.c of appendix E (which address the timing
and coordination of exercises at reactor sites). Therefore, the NRC
staff has determined that conducting a VEGP Unit 4 partial
participation exercise prior to Unit 4's initial fuel load will not
demonstrate any new aspects of emergency planning resources,
capabilities, emergency response facilities, procedures, or ERO used to
accomplish the principal functional areas of emergency response that
were not already demonstrated during the VEGP Unit 3 partial
participation exercise.
Because the VEGP Unit 4 emergency preparedness response
capabilities and ERO were already demonstrated during a VEGP Unit 3
partial participation exercise and will continue to be evaluated under
the 8-calendar-year emergency preparedness exercise cycle for the VEGP
site, there is no change in risk to public health and safety.
Therefore, the exemption does not present an undue risk to public
health and safety.
3. The Exemption Is Consistent With the Common Defense and Security
The exemption from section IV.F.2.a.(iii) of appendix E to 10 CFR
part 50 removes the requirement for SNC to perform an emergency
preparedness exercise at VEGP Unit 4 prior to initial fuel load. The
licensee's successful completion of the Unit 3 partial participation
exercise demonstrates the adequacy of
[[Page 26555]]
emergency preparedness response capabilities and ERO for both Units 3
and 4. Units 3 and 4 would also be incorporated into the 8-calendar-
year emergency preparedness exercise cycle for the VEGP site. In
addition, this exemption does not involve changes to the SNC Standard
Emergency Plan or the VEGP Units 3 and 4 Standard Emergency Plan Annex
and has no impact on plant security or safeguards. Therefore, the NRC
staff has determined that this exemption does not affect the common
defense and security.
4. Special Circumstances
Special circumstances, in accordance with 10 CFR 50.12(a)(2)(ii),
are present whenever application of the regulation in the particular
circumstances would not serve the underlying purpose of the rule or is
not necessary to achieve the underlying purpose of the rule. Section
IV.F.2.a.(iii) of appendix E to 10 CFR part 50 requires, in part, that
an emergency preparedness exercise be conducted for each subsequent
reactor constructed on an existing reactor site. The underlying purpose
of section IV.F.2.a.(iii) of appendix E to 10 CFR part 50 for VEGP Unit
4 is to ensure that an adequate state of emergency preparedness
response capability exists for VEGP Unit 4 through the conduct of an
emergency preparedness exercise prior to Unit 4 initial fuel load. In
addition, as the Commission described in the statement of consideration
for the 2007 final rule (72 FR 49351, 49401, August 28, 2007) that
added section IV.F.2.a.(iii) to appendix E to 10 CFR part 50, the
requirement for emergency preparedness exercises for each subsequent
reactor constructed at a site was intended to provide for the
demonstration of ITAAC for various emergency preparedness requirements
(e.g., programs and facilities) that did not warrant their own
specific, detailed ITAAC (separate from the exercise).
The exemption removes the requirement to perform an emergency
preparedness exercise at VEGP Unit 4 prior to initial fuel load. Since
all the emergency preparedness exercise ITAAC for VEGP Unit 4 were
previously deleted by License Amendment 161, and the VEGP Unit 4
emergency preparedness response capabilities and ERO were demonstrated
during the Unit 3 partial participation exercise, the underlying
purpose of section IV.F.2.a.(iii) for the VEGP Unit 4 exercise is met
under the terms of the exemption. Therefore, the NRC staff has
determined that the special circumstances required by 10 CFR
50.12(a)(2)(ii) for the granting of the exemption from section
IV.F.2.a.(iii) exist because requiring a separate exercise for Unit 4
is not necessary to meet the underlying purpose of the rule.
5. Environmental Consideration
The NRC staff determined that the exemption discussed herein meets
the eligibility criteria for the categorical exclusion set forth in 10
CFR 51.22(c)(25). The requested exemption seeks to remove the
requirement in section IV.F.2.a.(iii) of appendix E to 10 CFR part 50
to conduct either a full or partial participation emergency
preparedness exercise for VEGP Unit 4 prior to its initial fuel load,
but does not make any physical changes to the facility, the approved
SNC Standard Emergency Plan, the VEGP Units 3 and 4 Standard Emergency
Plan Annex, or the facility operating procedures. Under 10 CFR
51.22(c)(25), granting an exemption from the requirements of any
regulation of chapter I to 10 CFR is a categorical exclusion provided
that (i) there is no significant hazards consideration; (ii) there is
no significant change in the types or significant increase in the
amounts of any effluents that may be released offsite; (iii) there is
no significant increase in individual or cumulative public or
occupational radiation exposure; (iv) there is no significant
construction impact; (v) there is no significant increase in the
potential for or consequences from radiological accidents; and (vi) the
requirements from which an exemption is sought involve certain
categories of requirements, such as scheduling requirements related to
the performance of an emergency preparedness exercise.
As required by 10 CFR 51.22(c)(25)(i), and using the criteria set
out in 10 CFR 50.92(c), the NRC staff reviewed whether the exemption
request involves no significant hazards consideration.
(1) Does the requested exemption involve a significant increase in
the probability or consequences of an accident previously evaluated?
No. The exemption to 10 CFR part 50, appendix E, section
IV.F.2.a.(iii) removes the requirement to perform an emergency
preparedness exercise at VEGP Unit 4 prior to initial fuel load. The
exemption does not alter the design, function, or operation of any
plant equipment and does not involve or interface with any structure,
system or component (SSC) accident initiator or initiating sequence of
events, so the probabilities of the accidents evaluated in the Updated
Final Safety Analysis Report (UFSAR) are not affected. The exemption
does not allow for a new fission product release path, nor does it
result in a new fission product barrier failure mode or create a new
sequence of events that would result in fuel cladding failures. The
exemption does not involve any safety-related SSCs or functions used to
mitigate an accident, thus the consequences of the accidents evaluated
in the UFSAR are not affected. Therefore, granting this exemption does
not involve a significant increase in the probability or consequences
of an accident previously evaluated.
(2) Does the requested exemption create the possibility of a new or
different kind of accident from any accident previously evaluated?
No. The exemption does not alter the design, function, or operation
of any plant equipment. The exemption does not create any new failure
mechanisms, malfunctions, or accident initiators. The exemption does
not affect the operation of any systems or equipment such that a new or
different kind of accident, failure mode, or malfunction is created, or
alter any SSC such that a new accident initiator or initiating sequence
of events is created. Therefore, granting this exemption does not
create the possibility of a new or different kind of accident from any
accident previously evaluated.
(3) Does the requested exemption involve a significant reduction in
a margin of safety?
No. The exemption does not affect an SSC, SSC design function, or
method of performing or controlling a design function. The exemption
does not affect safety-related equipment or fission product barriers.
No safety analysis or design basis acceptance limit or criterion is
challenged or exceeded by the exemption. The exemption does not involve
changes to the SNC Standard Emergency Plan or the VEGP Units 3 and 4
Standard Emergency Plan Annex, and therefore, there is no reduction in
effectiveness in emergency planning, pursuant to 10 CFR 50.54(q).
Therefore, granting this exemption does not involve a significant
reduction in a margin of safety.
As all of the responses to the above questions are in the negative,
under 10 CFR 51.22(c)(25)(i), the NRC staff has concluded that the
exemption involves no significant hazards consideration.
The exemption does not alter the design, function, or operation of
any plant equipment. There are no changes to effluent types, plant
radiological or non-radiological effluent release quantities, any
effluent release path, or the functionality of any design or
operational features credited with controlling the release of effluents
during plant operation or construction. Therefore, under 10 CFR
51.22(c)(25)(ii), the NRC staff concludes that the
[[Page 26556]]
exemption does not involve a significant change in the types or
significant increase in the amounts of any effluents that may be
released offsite.
The exemption does not change plant radiation zones, radiological
effluent release pathways and release quantities, or cause any changes
to the controls required under 10 CFR part 20 that preclude a
significant increase in public dose or occupational radiation exposure.
Therefore, under 10 CFR 51.22(c)(25)(iii), the NRC staff concludes that
the exemption does not involve a significant increase in individual or
cumulative public or occupational radiation exposure.
The exemption does not alter the design, function, or operation of
any plant equipment. No change to the facility is being made as a
result of this exemption. Therefore, under 10 CFR 51.22(c)(25)(iv), the
NRC staff concludes that the exemption does not involve a significant
construction impact.
The exemption does not alter the design, function, or operation of
any plant equipment, and does not involve any safety-related SSCs or
functions used to mitigate an accident. No change to the facility is
being made as a result of this exemption. Therefore, under 10 CFR
51.22(c)(25)(v), the NRC staff concludes that the exemption does not
involve a significant increase in the potential for or consequences
from radiological accidents.
The exemption involves scheduling requirements related to the
performance of an emergency preparedness exercise. Therefore, under 10
CFR 51.22(c)(25)(vi)(G), the NRC staff concludes that the exemption
involves a scheduling requirement.
Based on the evaluation above, the NRC staff concludes that the
exemption meets the criteria of 10 CFR 51.22(c)(25). Therefore, in
accordance with 10 CFR 51.22(b), an environmental impact statement or
environmental assessment is not required for the NRC staff's
consideration of this exemption request.
IV. Conclusion
Based on the above, the NRC staff concludes that, with the VEGP
Unit 4 exemption from section IV.F.2.a.(iii) of appendix E to 10 CFR
part 50, there is reasonable assurance that adequate protective
measures can, and will, be taken in the event of a radiological
emergency at VEGP Unit 4, and that VEGP Unit 4 continues to demonstrate
compliance with 10 CFR 50.47(b)(14) and appendix E to 10 CFR part 50.
Accordingly, the Commission has determined that, pursuant to 10 CFR
50.12, the exemption is authorized by law, will not present an undue
risk to the health and safety of the public, and is consistent with the
common defense and security. Also, special circumstances are present.
Therefore, given that a partial participation exercise for VEGP Unit 3
was successfully completed, the Commission has granted SNC an exemption
from section IV.F.2.a.(iii) of appendix E to 10 CFR part 50, to
eliminate the requirement to perform an emergency preparedness exercise
at VEGP Unit 4 prior to its initial fuel load.
Dated: May 11, 2021.
For the Nuclear Regulatory Commission.
Gregory T. Bowman,
Director, Vogtle Project Office, Office of Nuclear Reactor Regulation.
[FR Doc. 2021-10254 Filed 5-13-21; 8:45 am]
BILLING CODE 7590-01-P