Allete, Inc.; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 23951-23952 [2021-09516]

Download as PDF Federal Register / Vol. 86, No. 85 / Wednesday, May 5, 2021 / Notices project to have four smaller Turgo-type turbine-generators in lieu of the approved two Francis-type turbinegenerators. The design change would decrease the project capacity from 1.8 megawatts (MW) to 1.4 MW and decreases the hydraulic capacity from 180 cubic feet per second (cfs) to 150 cfs. The licensee states that this redesign will better align with the existing features of the Flannagan Dam and produce more energy on a yearly basis than the previous design. The licensee states that it is not proposing changes to any other aspects of the project and that the environmental impact of the project will not change from previously analyzed. l. Locations of the Application: This filing may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 VerDate Sep<11>2014 23:06 May 04, 2021 Jkt 253001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: April 29, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–09515 Filed 5–4–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2360–272] Allete, Inc.; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Amendment of Project Boundary. b. Project No: 2360–272. c. Date Filed: December 22, 2020, and supplemented on April 27, 2021. d. Applicant: Allete, Inc. e. Name of Project: St. Louis River Hydroelectric Project. f. Location: Island Lake Reservoir, Fish Lake Reservoir, and Whiteface Reservoir in St. Louis County, Minnesota. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Greg Prom, Minnesota Power, 30 West Superior Street, Duluth, Minnesota 55802–2093, (218) 355–3191. i. FERC Contact: Mark Carter, (678) 245–3083, mark.carter@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: May 31, 2021. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at PO 00000 Frm 00038 Fmt 4703 Sfmt 4703 23951 FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–2360–272. Comments emailed to Commission staff are not considered part of the Commission record. k. Description of Request: Allete, Inc (licensee) is proposing to amend its project boundary at three of the project’s reservoirs (i.e., Island Lake Reservoir, Fish Lake Reservoir, and Whiteface Reservoir) to more accurately reflect the lands needed for project purposes. The licensee would remove approximately 191 acres of land around the reservoirs that are currently leased to individuals for private, residential use, while preserving an upland buffer area around the reservoirs. Additionally, the licensee would add 469 acres of land around the three reservoirs to be managed as Natural Character Areas for scenic and environmental protection uses. The proposed project boundary adjustment would result in a net increase of 423 acres of project lands including the removal of residential lands, addition of environmental protection lands, as well as other additions to reflect actual acreages of islands and recreation areas inside the project boundary. l. Locations of the Application: In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https://www.ferc.gov) using the ‘‘elibrary’’ link. Enter the docket number excluding the last three digits in the document field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3673 or TYY, (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. E:\FR\FM\05MYN1.SGM 05MYN1 23952 Federal Register / Vol. 86, No. 85 / Wednesday, May 5, 2021 / Notices m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: April 29, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–09516 Filed 5–4–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER18–1174–001. Applicants: Imperial Valley Solar 2, LLC. Description: Notice of Non-Material Change in Status of Imperial Valley Solar 2, LLC. Filed Date: 4/28/21. Accession Number: 20210428–5353. Comments Due: 5 p.m. ET 5/19/21. VerDate Sep<11>2014 23:06 May 04, 2021 Jkt 253001 Docket Numbers: ER21–1165–001. Applicants: Purge Energy LLC. Description: Tariff Amendment: Tariffs and Agreements to be effective 4/28/2021. Filed Date: 4/28/21. Accession Number: 20210428–5291. Comments Due: 5 p.m. ET 5/19/21. Docket Numbers: ER21–1789–000. Applicants: Southwest Power Pool, Inc. Description: Notice of cancellation of Network Integration Transmission Service Agreement and Network Operating Agreement of Southwest Power Pool, Inc. Filed Date: 4/28/21. Accession Number: 20210428–5263. Comments Due: 5 p.m. ET 5/19/21. Docket Numbers: ER21–1791–000. Applicants: Mid-Atlantic Interstate Transmission, LLC, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: MAIT submits ECSA No. 5940 to be effective 6/29/2021. Filed Date: 4/29/21. Accession Number: 20210429–5042. Comments Due: 5 p.m. ET 5/20/21. Docket Numbers: ER21–1792–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 2198R30 Kansas Power Pool NITSA NOA to be effective 4/1/2021. Filed Date: 4/29/21. Accession Number: 20210429–5044. Comments Due: 5 p.m. ET 5/20/21. Docket Numbers: ER21–1793–000. Applicants: Southern California Edison Company. Description: § 205(d) Rate Filing: UFA Yellow Pine 2 Project TOT796AFS SA No. 261 to be effective 4/30/2021. Filed Date: 4/29/21. Accession Number: 20210429–5081. Comments Due: 5 p.m. ET 5/20/21. Docket Numbers: ER21–1794–000. Applicants: White Oak Energy LLC. Description: Baseline eTariff Filing: Reactive Power Compensation Filing to be effective 6/28/2021. Filed Date: 4/29/21. Accession Number: 20210429–5128. Comments Due: 5 p.m. ET 5/20/21. Docket Numbers: ER21–1795–000. Applicants: Oakland Power Company LLC. Description: § 205(d) Rate Filing: Request for Authorization of Payment Pursuant to Section 7.5 of RMR Agreement to be effective 6/29/2021. Filed Date: 4/29/21. Accession Number: 20210429–5236. Comments Due: 5 p.m. ET 5/20/21. Docket Numbers: ER21–1796–000. Applicants: Transource Oklahoma, LLC, Southwest Power Pool, Inc. PO 00000 Frm 00039 Fmt 4703 Sfmt 9990 Description: § 205(d) Rate Filing: Transource Oklahoma, LLC Formula Rate to be effective 7/1/2021. Filed Date: 4/29/21. Accession Number: 20210429–5242. Comments Due: 5 p.m. ET 5/20/21. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES21–41–000. Applicants: Southwestern Electric Power Company. Description: Application under Section 204 of the Federal Power Act for Authorization to Issue Securities for Southwestern Electric Power Company. Filed Date: 4/29/21. Accession Number: 20210429–5063. Comments Due: 5 p.m. ET 5/20/21. Take notice that the Commission received the following electric reliability filings: Docket Numbers: RR20–5–001. Applicants: North American Electric Reliability Corporation. Description: Compliance Filing of The North American Electric Reliability Corporation on The Revised Delegation Agreements With Regional Entities. Filed Date: 4/29/21. Accession Number: 20210429–5087. Comments Due: 5 p.m. ET 5/20/21. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: April 29, 2021. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2021–09481 Filed 5–4–21; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\05MYN1.SGM 05MYN1

Agencies

[Federal Register Volume 86, Number 85 (Wednesday, May 5, 2021)]
[Notices]
[Pages 23951-23952]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-09516]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2360-272]


Allete, Inc.; Notice of Application Accepted for Filing and 
Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Amendment of Project Boundary.
    b. Project No: 2360-272.
    c. Date Filed: December 22, 2020, and supplemented on April 27, 
2021.
    d. Applicant: Allete, Inc.
    e. Name of Project: St. Louis River Hydroelectric Project.
    f. Location: Island Lake Reservoir, Fish Lake Reservoir, and 
Whiteface Reservoir in St. Louis County, Minnesota.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Greg Prom, Minnesota Power, 30 West Superior 
Street, Duluth, Minnesota 55802-2093, (218) 355-3191.
    i. FERC Contact: Mark Carter, (678) 245-3083, [email protected].
    j. Deadline for filing comments, motions to intervene, and 
protests: May 31, 2021.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, and protests using the Commission's 
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. 
Commenters can submit brief comments up to 6,000 characters, without 
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at [email protected], (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may 
submit a paper copy. Submissions sent via the U.S. Postal Service must 
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852. The first page of any filing should 
include docket number P-2360-272. Comments emailed to Commission staff 
are not considered part of the Commission record.
    k. Description of Request: Allete, Inc (licensee) is proposing to 
amend its project boundary at three of the project's reservoirs (i.e., 
Island Lake Reservoir, Fish Lake Reservoir, and Whiteface Reservoir) to 
more accurately reflect the lands needed for project purposes. The 
licensee would remove approximately 191 acres of land around the 
reservoirs that are currently leased to individuals for private, 
residential use, while preserving an upland buffer area around the 
reservoirs. Additionally, the licensee would add 469 acres of land 
around the three reservoirs to be managed as Natural Character Areas 
for scenic and environmental protection uses. The proposed project 
boundary adjustment would result in a net increase of 423 acres of 
project lands including the removal of residential lands, addition of 
environmental protection lands, as well as other additions to reflect 
actual acreages of islands and recreation areas inside the project 
boundary.
    l. Locations of the Application: In addition to publishing the full 
text of this document in the Federal Register, the Commission provides 
all interested persons an opportunity to view and/or print the contents 
of this document via the internet through the Commission's Home Page 
(https://www.ferc.gov) using the ``elibrary'' link. Enter the docket 
number excluding the last three digits in the document field to access 
the document. At this time, the Commission has suspended access to the 
Commission's Public Reference Room, due to the proclamation declaring a 
National Emergency concerning the Novel Coronavirus Disease (COVID-19), 
issued by the President on March 13, 2020. For assistance, contact FERC 
at [email protected] or call toll-free, (886) 208-3673 or TYY, 
(202) 502-8659. Agencies may obtain copies of the application directly 
from the applicant.

[[Page 23952]]

    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214, respectively. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Filing and Service of Documents: Any filing must (1) bear in all 
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO 
INTERVENE'' as applicable; (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person commenting, protesting or intervening; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis. Any filing made by an intervenor must be accompanied 
by proof of service on all persons listed in the service list prepared 
by the Commission in this proceeding, in accordance with 18 CFR 
385.2010.

    Dated: April 29, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-09516 Filed 5-4-21; 8:45 am]