Download as PDF 23752 Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices in the FOR FURTHER INFORMATION CONTACT section of this document. NUCLEAR REGULATORY COMMISSION [NRC–2021–0074] Environmental Assessments and Findings of No Significant Impact of Independent Spent Fuel Storage Facilities Decommissioning Funding Plans Nuclear Regulatory Commission. ACTION: Environmental assessment and finding of no significant impact; issuance. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) is publishing this notice regarding the issuance of a final Environmental Assessment (EA) and a Finding of No Significant Impact (FONSI) for its review and approval of the initial and updated decommissioning funding plans (DFPs) submitted by independent spent fuel storage installation (ISFSI) licensees for each of the ISFSIs listed in the ‘‘Discussion’’ section of this document. DATES: The EA and FONSI referenced in this document are available on May 4, 2021. ADDRESSES: Please refer to Docket ID NRC–2021–0074 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods: • Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC–2021–0074. Address questions about Docket IDs in Regulations.gov to Stacy Schumann; telephone: 301–415–0624; email: Stacy.Schumann@nrc.gov For technical questions, contact the individual listed SUMMARY: • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301– 415–4737, or by email to pdr.resource@ nrc.gov. The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document. • Attention: The PDR, where you may examine and order copies of public documents, is currently closed. You may submit your request to the PDR via email at pdr.resource@nrc.gov or call 1–800–397–4209 or 301–415–4737, between 8:00 a.m. and 4:00 p.m. (EST), Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: Donald Habib, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001; telephone: 301–415–1035, email: Donald.Habib@ nrc.gov. SUPPLEMENTARY INFORMATION: I. Introduction The NRC is considering the approval of the initial and updated DFPs submitted by ISFSI licensees. The NRC staff has prepared a final EA and FONSI determination for each of the initial and updated ISFSI DFPs in accordance with the NRC regulations in part 51 of title 10 of the Code of Federal Regulations (10 CFR), ‘‘Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions,’’ which implement the National Environmental Policy Act of 1969, as amended (42 U.S.C. 4321 et seq.). The NRC requires its licensees to plan for the eventual decommissioning of their licensed facilities prior to license termination. On June 17, 2011, the NRC published a final rule in the Federal Register amending its decommissioning planning regulations (76 FR 35512). The final rule amended the NRC regulation, 10 CFR 72.30, which concerns financial assurance and decommissioning for ISFSIs. This regulation requires each holder of, or applicant for, a license under 10 CFR part 72 to submit a DFP for the NRC’s review and approval. The DFP is to demonstrate the licensee’s financial assurance, i.e., that funds will be available to decommission the ISFSI. The NRC staff will later publish its financial analyses of the DFP submittals which will be available for public inspection in ADAMS. II. Discussion The table in this notice includes the plant name, docket number, licensee, and ADAMS Accession Number for the final EA and FONSI determination for each of the individual ISFSIs. The table also includes the ADAMS Accession Numbers for other relevant documents, including the initial and updated DFP submittals. For further details with respect to these actions, see the NRC staff’s Final EA and FONSI determinations which are available for public inspection in ADAMS and at https://www.regulations.gov under Docket ID NRC–2021–0074. For additional direction on accessing information related to this document, see the ADDRESSES section of this document. FINDING OF NO SIGNIFICANT IMPACT Facility ................................................................. Docket No. .......................................................... Licensee .............................................................. Proposed Action ................................................. khammond on DSKJM1Z7X2PROD with NOTICES Environmental Impact of Proposed Action ......... VerDate Sep<11>2014 17:13 May 03, 2021 Jkt 253001 Turkey Point Nuclear Generating Units 3 and 4. 72–62. Florida Power & Light Company. The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c). The NRC staff has determined that the proposed action, the review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize changes to licensed operations or maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will not authorize any construction activity, facility modification, or other land-disturbing activity. The NRC staff has concluded that the proposed action is a procedural and administrative action that will not have a significant impact on the environment. PO 00000 Frm 00083 Fmt 4703 Sfmt 4703 E:\FR\FM\04MYN1.SGM 04MYN1 Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices 23753 FINDING OF NO SIGNIFICANT IMPACT—Continued Finding of No Significant Impact ........................ Available Documents .......................................... Facility ................................................................. Docket No. .......................................................... Licensee .............................................................. Proposed Action ................................................. Environmental Impact of Proposed Action ......... khammond on DSKJM1Z7X2PROD with NOTICES Finding of No Significant Impact ........................ Available Documents .......................................... VerDate Sep<11>2014 17:13 May 03, 2021 Jkt 253001 The proposed action does not require changes to the ISFSI’s licensed routine operations, maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs. The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI or for other parts of Turkey Point Nuclear Generating Units 3 and 4. Therefore, the NRC staff determined that approval of the initial and updated DFPs for the Turkey Point Nuclear Generating Units 3 and 4 ISFSI will not significantly affect the quality of the human environment, and accordingly, the staff has concluded that a FONSI is appropriate. The NRC staff further finds that preparation of an environmental impact statement (EIS) is not required. FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134. FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655. FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 30, 2017. ADAMS Accession No. ML17093A722. FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/ NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057. NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 27, 2015. ADAMS Accession No. ML15090A114. U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811. U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated February 1, 2009. ADAMS Accession No. ML090500648. U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS Accession No. ML14143A141. U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the Turkey Point Units 3 and 4 ISFSI DFP, dated June 22, 2016. ADAMS Accession No. ML16174A331. U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062. U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018. ADAMS Package Accession No. ML18058A051. U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s Initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR 72.30(b) and (c) for Turkey Point Nuclear Generating Units 3 and 4 ISFSI, dated April 21, 2021. ADAMS Package Accession No. ML21062A055. St. Lucie Plant Units 1 and 2. 72–61. Florida Power & Light Company. The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c). The NRC staff has determined that the proposed action, the review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize or changes to licensed operations or maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will not authorize any construction activity, facility modification, or other land-disturbing activity. The NRC staff has concluded that the proposed action is a procedural and administrative action that will not have a significant impact on the environment. The proposed action does not require changes to the ISFSI’s licensed routine operations, maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs. The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI or for other parts of the St. Lucie Plant Units 1 and 2. Therefore, the NRC staff determined that approval of the initial and updated DFPs for the St. Lucie Plant Units 1 and 2 ISFSI will not significantly affect the quality of the human environment, and accordingly, the staff has concluded that a FONSI is appropriate. The NRC staff further finds that preparation of an environmental impact statement (EIS) is not required. FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134. FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655. FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 30, 2017. ADAMS Accession No. ML17093A722. FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/ NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057. PO 00000 Frm 00084 Fmt 4703 Sfmt 4703 E:\FR\FM\04MYN1.SGM 04MYN1 23754 Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices FINDING OF NO SIGNIFICANT IMPACT—Continued Facility ................................................................. Docket No. .......................................................... Licensee .............................................................. Proposed Action ................................................. Environmental Impact of Proposed Action ......... Finding of No Significant Impact ........................ khammond on DSKJM1Z7X2PROD with NOTICES Available Documents .......................................... VerDate Sep<11>2014 17:13 May 03, 2021 Jkt 253001 NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 27, 2015. ADAMS Accession No. ML15090A114. U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811. U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated February 1, 2009. ADAMS Accession No. ML090500648. U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS Accession No. ML14143A141. U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the St. Lucie Units 1 and 2 ISFSI DFP, dated June 22, 2016. ADAMS Accession No. ML16174A112. U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062. U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018. ADAMS Package Accession No. ML18058A051. U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR 72.30(b) and (c) for St. Lucie Plant Units 1 and 2 ISFSI, dated April 21, 2021. ADAMS Package Accession No. ML21062A061. Point Beach Nuclear Plant Units 1 and 2. 72–05. NextEra Energy Point Beach, LLC. The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c). The NRC staff has determined that the proposed action, the review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize changes to licensed operations or maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will not authorize any construction activity, facility modification, or other land-disturbing activity. The NRC staff has concluded that the proposed action is a procedural and administrative action that will not have a significant impact on the environment. The proposed action does not require changes to the ISFSI’s licensed routine operations, maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs. The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI or for other parts of Point Beach Nuclear Plant Units 1 and 2. Therefore, the NRC staff determined that approval of the initial and updated DFPs for the Point Beach Nuclear Plant Units 1 and 2 ISFSI will not significantly affect the quality of the human environment, and accordingly, the staff has concluded that a FONSI is appropriate. The NRC staff further finds that preparation of an environmental impact statement (EIS) is not required. FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134. FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655. FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 30, 2017. ADAMS Accession No. ML17093A722. FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/ NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057. NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 27, 2015. ADAMS Accession No. ML15090A114. U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811. U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated February 1, 2009. ADAMS Accession No. ML090500648. U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS Accession No. ML14143A141. U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the Point Beach Nuclear ISFSI DFP, dated October 19, 2016. ADAMS Accession No. ML16293A165. U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062. U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018. ADAMS Package Accession No. ML18058A051. PO 00000 Frm 00085 Fmt 4703 Sfmt 4703 E:\FR\FM\04MYN1.SGM 04MYN1 Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices 23755 FINDING OF NO SIGNIFICANT IMPACT—Continued Facility ................................................................. Docket No. .......................................................... Licensee .............................................................. Proposed Action ................................................. Environmental Impact of Proposed Action ......... Finding of No Significant Impact ........................ Available Documents .......................................... khammond on DSKJM1Z7X2PROD with NOTICES Facility ................................................................. Docket Nos. ........................................................ Licensee .............................................................. Proposed Action ................................................. Environmental Impact of Proposed Action ......... VerDate Sep<11>2014 17:13 May 03, 2021 Jkt 253001 U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s Initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR 72.30(b) and (c) for Point Beach Nuclear Plant Units 1 and 2 ISFSI dated April 21, 2021. ADAMS Package Accession No. ML21062A069. Duane Arnold Energy Center. 72–32. NextEra Energy Duane Arnold, LLC. The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c). The NRC staff has determined that the proposed action, the review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize changes to licensed operations or maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will not authorize any construction activity, facility modification, or other land-disturbing activity. The NRC staff has concluded that the proposed action is a procedural and administrative action that will not have a significant impact on the environment. The proposed action does not require changes to the ISFSI’s licensed routine operations, maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs. The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI or for other parts of Duane Arnold Energy Center. Therefore, the NRC staff determined that approval of the initial and updated DFPs for the Duane Arnold Energy Center ISFSI will not significantly affect the quality of the human environment, and accordingly, the staff has concluded that a FONSI is appropriate. The NRC staff further finds that preparation of an environmental impact statement (EIS) is not required. FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134. FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655. FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 30, 2017. ADAMS Accession No. ML17093A722. FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/ NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057. NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 27, 2015. ADAMS Accession No. ML15090A114. U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811. U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated February 1, 2009. ADAMS Accession No. ML090500648. U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS Accession No. ML14143A141. U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the Duane Arnold Energy Center ISFSI DFP, dated July 27, 2016. ADAMS Accession No. ML16209A457. U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062. U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018. ADAMS Package Accession No. ML18058A051. U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s Initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR 72.30(b) and (c) for Duane Arnold Energy Center ISFSI, dated April 21, 2021. ADAMS Accession Package No. ML21062A092. Seabrook Station Unit No. 1 72–63 NextEra Energy Seabrook, LLC. The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c). The NRC staff has determined that the proposed action, the review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize changes to licensed operations or maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will not authorize any construction activity, facility modification, or other land-disturbing activity. The NRC staff has concluded that the proposed action is a procedural and administrative action that will not have a significant impact on the environment. PO 00000 Frm 00086 Fmt 4703 Sfmt 4703 E:\FR\FM\04MYN1.SGM 04MYN1 23756 Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices FINDING OF NO SIGNIFICANT IMPACT—Continued Finding of No Significant Impact ........................ Available Documents .......................................... Dated: April 28, 2021. For the Nuclear Regulatory Commission. John B. McKirgan, Chief, Storage and Transportation Licensing Branch, Division of Fuel Management, Office of Nuclear Material Safety and Safeguards. [FR Doc. 2021–09293 Filed 5–3–21; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket Nos. 52–025 and 52–026; NRC– 2008–0252] khammond on DSKJM1Z7X2PROD with NOTICES Southern Nuclear Operating Company, Inc; Vogtle Electric Generating Plant, Units 3 and 4; Inspections, Tests, Analyses, and Acceptance Criteria Nuclear Regulatory Commission. ACTION: Determination of the successful completion of inspections, tests, and analyses. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) staff has determined SUMMARY: VerDate Sep<11>2014 17:13 May 03, 2021 Jkt 253001 The proposed action does not require changes to the ISFSI’s licensed routine operations, maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs. The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI or for other parts of Seabrook Station Unit No. 1. Therefore, the NRC staff determined that approval of the initial and updated DFPs for the Seabrook Station Unit No. 1 ISFSI will not significantly affect the quality of the human environment, and accordingly, the staff has concluded that a FONSI is appropriate. The NRC staff further finds that preparation of an environmental impact statement (EIS) is not required. FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134. FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655. FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 30, 2017. ADAMS Accession No. ML17093A722. FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/ NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057. NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update, dated March 27, 2015. ADAMS Accession No. ML15090A114. U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811. U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated February 1, 2009. ADAMS Accession No. ML090500648. U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS Accession No. ML14143A141. U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062. U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the Seabrook Station ISFSI DFP, dated August 17, 2017. ADAMS Accession No. ML17226A329. U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018. ADAMS Package Accession No. ML18058A051. U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s Initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR 72.30(b) and (c) for Seabrook Station Unit No. 1 ISFSI, dated April 21, 2021. ADAMS Package Accession No. ML21062A145. that specified inspections, tests, and analyses have been successfully completed, and that specified acceptance criteria are met for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4. DATES: Determinations of the successful completion of inspections, tests, and analyses for VEGP Units 3 and 4 are effective on the dates indicated in the NRC staff’s verification evaluation forms for the inspections, tests, analyses, and acceptance criteria (ITAAC). ADDRESSES: Please refer to Docket ID NRC–2008–0252 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods: • Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC–2008–0252. Address questions about Docket IDs to Stacy Schumann; telephone: 301–415–0624; email: Stacy.Schumann@nrc.gov. For technical questions, contact the PO 00000 Frm 00087 Fmt 4703 Sfmt 4703 individual listed in the FOR FURTHER section of this document. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301– 415–4737, or by email to pdr.resource@ nrc.gov. The ADAMS accession number for each document referenced in this document (if that document is available in ADAMS) is provided the first time that a document is referenced. • Attention: The PDR, where you may examine and order copies of public documents, is currently closed. You may submit your request to the PDR via email at pdr.resource@nrc.gov or call 1– 800–397–4209 or 301–415–4737, between 8:00 a.m. and 4:00 p.m. (EST), INFORMATION CONTACT E:\FR\FM\04MYN1.SGM 04MYN1

Agencies

[Federal Register Volume 86, Number 84 (Tuesday, May 4, 2021)]
[Notices]
[Pages 23752-23756]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-09293]



[[Page 23752]]

-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2021-0074]


Environmental Assessments and Findings of No Significant Impact 
of Independent Spent Fuel Storage Facilities Decommissioning Funding 
Plans

AGENCY: Nuclear Regulatory Commission.

ACTION: Environmental assessment and finding of no significant impact; 
issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is publishing 
this notice regarding the issuance of a final Environmental Assessment 
(EA) and a Finding of No Significant Impact (FONSI) for its review and 
approval of the initial and updated decommissioning funding plans 
(DFPs) submitted by independent spent fuel storage installation (ISFSI) 
licensees for each of the ISFSIs listed in the ``Discussion'' section 
of this document.

DATES: The EA and FONSI referenced in this document are available on 
May 4, 2021.

ADDRESSES: Please refer to Docket ID NRC-2021-0074 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0074. Address 
questions about Docket IDs in Regulations.gov to Stacy Schumann; 
telephone: 301-415-0624; email: [email protected] For technical 
questions, contact the individual listed in the FOR FURTHER INFORMATION 
CONTACT section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ADAMS accession number for each 
document referenced (if it is available in ADAMS) is provided the first 
time that it is mentioned in this document.
     Attention: The PDR, where you may examine and order copies 
of public documents, is currently closed. You may submit your request 
to the PDR via email at [email protected] or call 1-800-397-4209 or 
301-415-4737, between 8:00 a.m. and 4:00 p.m. (EST), Monday through 
Friday, except Federal holidays.

FOR FURTHER INFORMATION CONTACT: Donald Habib, Office of Nuclear 
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001; telephone: 301-415-1035, email: 
[email protected].

SUPPLEMENTARY INFORMATION:

I. Introduction

    The NRC is considering the approval of the initial and updated DFPs 
submitted by ISFSI licensees. The NRC staff has prepared a final EA and 
FONSI determination for each of the initial and updated ISFSI DFPs in 
accordance with the NRC regulations in part 51 of title 10 of the Code 
of Federal Regulations (10 CFR), ``Environmental Protection Regulations 
for Domestic Licensing and Related Regulatory Functions,'' which 
implement the National Environmental Policy Act of 1969, as amended (42 
U.S.C. 4321 et seq.).
    The NRC requires its licensees to plan for the eventual 
decommissioning of their licensed facilities prior to license 
termination. On June 17, 2011, the NRC published a final rule in the 
Federal Register amending its decommissioning planning regulations (76 
FR 35512). The final rule amended the NRC regulation, 10 CFR 72.30, 
which concerns financial assurance and decommissioning for ISFSIs. This 
regulation requires each holder of, or applicant for, a license under 
10 CFR part 72 to submit a DFP for the NRC's review and approval. The 
DFP is to demonstrate the licensee's financial assurance, i.e., that 
funds will be available to decommission the ISFSI. The NRC staff will 
later publish its financial analyses of the DFP submittals which will 
be available for public inspection in ADAMS.

II. Discussion

    The table in this notice includes the plant name, docket number, 
licensee, and ADAMS Accession Number for the final EA and FONSI 
determination for each of the individual ISFSIs. The table also 
includes the ADAMS Accession Numbers for other relevant documents, 
including the initial and updated DFP submittals. For further details 
with respect to these actions, see the NRC staff's Final EA and FONSI 
determinations which are available for public inspection in ADAMS and 
at https://www.regulations.gov under Docket ID NRC-2021-0074. For 
additional direction on accessing information related to this document, 
see the ADDRESSES section of this document.

                    Finding of No Significant Impact
------------------------------------------------------------------------
 
------------------------------------------------------------------------
Facility.....................  Turkey Point Nuclear Generating Units 3
                                and 4.
Docket No....................  72-62.
Licensee.....................  Florida Power & Light Company.
Proposed Action..............  The NRC's review and approval of Florida
                                Power & Light Company's initial and
                                NextEra Energy's updated DFPs submitted
                                in accordance with 10 CFR 72.30(b) and
                                (c).
Environmental Impact of        The NRC staff has determined that the
 Proposed Action.               proposed action, the review and approval
                                of Florida Power & Light Company's
                                initial and NextEra Energy's updated
                                DFPs, submitted in accordance with 10
                                CFR 72.30(b) and (c), will not authorize
                                changes to licensed operations or
                                maintenance activities, or result in
                                changes in the types, characteristics,
                                or quantities of radiological or non-
                                radiological effluents released into the
                                environment from the ISFSI, or result in
                                the creation of solid waste. Moreover,
                                the approval of the initial and updated
                                DFPs will not authorize any construction
                                activity, facility modification, or
                                other land-disturbing activity. The NRC
                                staff has concluded that the proposed
                                action is a procedural and
                                administrative action that will not have
                                a significant impact on the environment.

[[Page 23753]]

 
Finding of No Significant      The proposed action does not require
 Impact.                        changes to the ISFSI's licensed routine
                                operations, maintenance activities, or
                                monitoring programs, nor does it require
                                new construction or land-disturbing
                                activities. The scope of the proposed
                                action concerns only the NRC's review
                                and approval of Florida Power & Light
                                Company's initial and NextEra Energy's
                                updated DFPs. The scope of the proposed
                                action does not include, and will not
                                result in, the review and approval of
                                decontamination or decommissioning
                                activities or license termination for
                                the ISFSI or for other parts of Turkey
                                Point Nuclear Generating Units 3 and 4.
                                Therefore, the NRC staff determined that
                                approval of the initial and updated DFPs
                                for the Turkey Point Nuclear Generating
                                Units 3 and 4 ISFSI will not
                                significantly affect the quality of the
                                human environment, and accordingly, the
                                staff has concluded that a FONSI is
                                appropriate. The NRC staff further finds
                                that preparation of an environmental
                                impact statement (EIS) is not required.
Available Documents..........  FPL, 2012. ISFSI DFPs, dated December 17,
                                2012. ADAMS Accession No. ML12354A134.
                               FPL, 2014. Reply to Request for
                                Additional Information for Review of the
                                DFPs Regarding the ISFSI, dated August
                                12, 2014. ADAMS Accession No.
                                ML14225A655.
                               FPL, 2017. Decommissioning Funding Status
                                Reports/ISFSI Financial Assurance
                                Update, dated March 30, 2017. ADAMS
                                Accession No. ML17093A722.
                               FPL, 2018. Response to Request for
                                Additional Information Regarding Florida
                                Power & Light/NextEra Decommissioning
                                Funding Updates for ISFSI, dated April
                                3, 2018. ADAMS Accession No.
                                ML18095A057.
                               NextEra Energy, 2015. Decommissioning
                                Funding Status Reports/ISFSI Financial
                                Assurance Update, dated March 27, 2015.
                                ADAMS Accession No. ML15090A114.
                               U.S. Nuclear Regulatory Commission. 2003/
                                08/31-NUREG-1748, ``Environmental Review
                                Guidance for Licensing Actions
                                Associated with NMSS Programs, Final
                                Report.'' Washington, DC, dated August
                                2003. ADAMS Accession No. ML032540811.
                               U.S. Nuclear Regulatory Commission. EA
                                for Final Rule-Decommissioning Planning,
                                dated February 1, 2009. ADAMS Accession
                                No. ML090500648.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information for
                                Review of the DFPs for Florida Power &
                                Light and NextEra Energy ISFSIs, dated
                                May 23, 2014. ADAMS Accession No.
                                ML14143A141.
                               U.S. Nuclear Regulatory Commission.
                                Review of the Draft EA and FONSI for the
                                Turkey Point Units 3 and 4 ISFSI DFP,
                                dated June 22, 2016. ADAMS Accession No.
                                ML16174A331.
                               U.S. Nuclear Regulatory Commission. Note
                                to File, Re: ESA Section 7 No Effect
                                Determination for ISFSI DFP Reviews,
                                dated May 15, 2017. ADAMS Accession No.
                                ML17135A062.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information
                                Regarding Florida Power & Light/NextEra
                                DFP Updates for St. Lucie, Units 1 and
                                2; Seabrook Station; Duane Arnold Energy
                                Center; and Point Beach, Units 1 and 2
                                ISFSIs, dated February 27, 2018. ADAMS
                                Package Accession No. ML18058A051.
                               U.S. Nuclear Regulatory Commission. Final
                                EA and FONSI for Florida Power & Light
                                Company's Initial and NextEra Energy's
                                Updated DFPs Submitted in Accordance
                                with 10 CFR 72.30(b) and (c) for Turkey
                                Point Nuclear Generating Units 3 and 4
                                ISFSI, dated April 21, 2021. ADAMS
                                Package Accession No. ML21062A055.
Facility.....................  St. Lucie Plant Units 1 and 2.
Docket No....................  72-61.
Licensee.....................  Florida Power & Light Company.
Proposed Action..............  The NRC's review and approval of Florida
                                Power & Light Company's initial and
                                NextEra Energy's updated DFPs submitted
                                in accordance with 10 CFR 72.30(b) and
                                (c).
Environmental Impact of        The NRC staff has determined that the
 Proposed Action.               proposed action, the review and approval
                                of Florida Power & Light Company's
                                initial and NextEra Energy's updated
                                DFPs, submitted in accordance with 10
                                CFR 72.30(b) and (c), will not authorize
                                or changes to licensed operations or
                                maintenance activities, or result in
                                changes in the types, characteristics,
                                or quantities of radiological or non-
                                radiological effluents released into the
                                environment from the ISFSI, or result in
                                the creation of solid waste. Moreover,
                                the approval of the initial and updated
                                DFPs will not authorize any construction
                                activity, facility modification, or
                                other land-disturbing activity. The NRC
                                staff has concluded that the proposed
                                action is a procedural and
                                administrative action that will not have
                                a significant impact on the environment.
Finding of No Significant      The proposed action does not require
 Impact.                        changes to the ISFSI's licensed routine
                                operations, maintenance activities, or
                                monitoring programs, nor does it require
                                new construction or land-disturbing
                                activities. The scope of the proposed
                                action concerns only the NRC's review
                                and approval of Florida Power & Light
                                Company's initial and NextEra Energy's
                                updated DFPs. The scope of the proposed
                                action does not include, and will not
                                result in, the review and approval of
                                decontamination or decommissioning
                                activities or license termination for
                                the ISFSI or for other parts of the St.
                                Lucie Plant Units 1 and 2. Therefore,
                                the NRC staff determined that approval
                                of the initial and updated DFPs for the
                                St. Lucie Plant Units 1 and 2 ISFSI will
                                not significantly affect the quality of
                                the human environment, and accordingly,
                                the staff has concluded that a FONSI is
                                appropriate. The NRC staff further finds
                                that preparation of an environmental
                                impact statement (EIS) is not required.
Available Documents..........  FPL, 2012. ISFSI DFPs, dated December 17,
                                2012. ADAMS Accession No. ML12354A134.
                               FPL, 2014. Reply to Request for
                                Additional Information for Review of the
                                DFPs Regarding the ISFSI, dated August
                                12, 2014. ADAMS Accession No.
                                ML14225A655.
                               FPL, 2017. Decommissioning Funding Status
                                Reports/ISFSI Financial Assurance
                                Update, dated March 30, 2017. ADAMS
                                Accession No. ML17093A722.
                               FPL, 2018. Response to Request for
                                Additional Information Regarding Florida
                                Power & Light/NextEra Decommissioning
                                Funding Updates for ISFSI, dated April
                                3, 2018. ADAMS Accession No.
                                ML18095A057.

[[Page 23754]]

 
                               NextEra Energy, 2015. Decommissioning
                                Funding Status Reports/ISFSI Financial
                                Assurance Update, dated March 27, 2015.
                                ADAMS Accession No. ML15090A114.
                               U.S. Nuclear Regulatory Commission. 2003/
                                08/31-NUREG-1748, ``Environmental Review
                                Guidance for Licensing Actions
                                Associated with NMSS Programs, Final
                                Report.'' Washington, DC, dated August
                                2003. ADAMS Accession No. ML032540811.
                               U.S. Nuclear Regulatory Commission. EA
                                for Final Rule-Decommissioning Planning,
                                dated February 1, 2009. ADAMS Accession
                                No. ML090500648.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information for
                                Review of the DFPs for Florida Power &
                                Light and NextEra Energy ISFSIs, dated
                                May 23, 2014. ADAMS Accession No.
                                ML14143A141.
                               U.S. Nuclear Regulatory Commission.
                                Review of the Draft EA and FONSI for the
                                St. Lucie Units 1 and 2 ISFSI DFP, dated
                                June 22, 2016. ADAMS Accession No.
                                ML16174A112.
                               U.S. Nuclear Regulatory Commission. Note
                                to File, Re: ESA Section 7 No Effect
                                Determination for ISFSI DFP Reviews,
                                dated May 15, 2017. ADAMS Accession No.
                                ML17135A062.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information
                                Regarding Florida Power & Light/NextEra
                                DFP Updates for St. Lucie, Units 1 and
                                2; Seabrook Station; Duane Arnold Energy
                                Center; and Point Beach, Units 1 and 2
                                ISFSIs, dated February 27, 2018. ADAMS
                                Package Accession No. ML18058A051.
                               U.S. Nuclear Regulatory Commission. Final
                                EA and FONSI for Florida Power & Light
                                Company's initial and NextEra Energy's
                                Updated DFPs Submitted in Accordance
                                with 10 CFR 72.30(b) and (c) for St.
                                Lucie Plant Units 1 and 2 ISFSI, dated
                                April 21, 2021. ADAMS Package Accession
                                No. ML21062A061.
Facility.....................  Point Beach Nuclear Plant Units 1 and 2.
Docket No....................  72-05.
Licensee.....................  NextEra Energy Point Beach, LLC.
Proposed Action..............  The NRC's review and approval of Florida
                                Power & Light Company's initial and
                                NextEra Energy's updated DFPs submitted
                                in accordance with 10 CFR 72.30(b) and
                                (c).
Environmental Impact of        The NRC staff has determined that the
 Proposed Action.               proposed action, the review and approval
                                of Florida Power & Light Company's
                                initial and NextEra Energy's updated
                                DFPs, submitted in accordance with 10
                                CFR 72.30(b) and (c), will not authorize
                                changes to licensed operations or
                                maintenance activities, or result in
                                changes in the types, characteristics,
                                or quantities of radiological or non-
                                radiological effluents released into the
                                environment from the ISFSI, or result in
                                the creation of solid waste. Moreover,
                                the approval of the initial and updated
                                DFPs will not authorize any construction
                                activity, facility modification, or
                                other land-disturbing activity. The NRC
                                staff has concluded that the proposed
                                action is a procedural and
                                administrative action that will not have
                                a significant impact on the environment.
Finding of No Significant      The proposed action does not require
 Impact.                        changes to the ISFSI's licensed routine
                                operations, maintenance activities, or
                                monitoring programs, nor does it require
                                new construction or land-disturbing
                                activities. The scope of the proposed
                                action concerns only the NRC's review
                                and approval of Florida Power & Light
                                Company's initial and NextEra Energy's
                                updated DFPs. The scope of the proposed
                                action does not include, and will not
                                result in, the review and approval of
                                decontamination or decommissioning
                                activities or license termination for
                                the ISFSI or for other parts of Point
                                Beach Nuclear Plant Units 1 and 2.
                                Therefore, the NRC staff determined that
                                approval of the initial and updated DFPs
                                for the Point Beach Nuclear Plant Units
                                1 and 2 ISFSI will not significantly
                                affect the quality of the human
                                environment, and accordingly, the staff
                                has concluded that a FONSI is
                                appropriate. The NRC staff further finds
                                that preparation of an environmental
                                impact statement (EIS) is not required.
Available Documents..........  FPL, 2012. ISFSI DFPs, dated December 17,
                                2012. ADAMS Accession No. ML12354A134.
                               FPL, 2014. Reply to Request for
                                Additional Information for Review of the
                                DFPs Regarding the ISFSI, dated August
                                12, 2014. ADAMS Accession No.
                                ML14225A655.
                               FPL, 2017. Decommissioning Funding Status
                                Reports/ISFSI Financial Assurance
                                Update, dated March 30, 2017. ADAMS
                                Accession No. ML17093A722.
                               FPL, 2018. Response to Request for
                                Additional Information Regarding Florida
                                Power & Light/NextEra Decommissioning
                                Funding Updates for ISFSI, dated April
                                3, 2018. ADAMS Accession No.
                                ML18095A057.
                               NextEra Energy, 2015. Decommissioning
                                Funding Status Reports/ISFSI Financial
                                Assurance Update, dated March 27, 2015.
                                ADAMS Accession No. ML15090A114.
                               U.S. Nuclear Regulatory Commission. 2003/
                                08/31-NUREG-1748, ``Environmental Review
                                Guidance for Licensing Actions
                                Associated with NMSS Programs, Final
                                Report.'' Washington, DC, dated August
                                2003. ADAMS Accession No. ML032540811.
                               U.S. Nuclear Regulatory Commission. EA
                                for Final Rule-Decommissioning Planning,
                                dated February 1, 2009. ADAMS Accession
                                No. ML090500648.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information for
                                Review of the DFPs for Florida Power &
                                Light and NextEra Energy ISFSIs, dated
                                May 23, 2014. ADAMS Accession No.
                                ML14143A141.
                               U.S. Nuclear Regulatory Commission.
                                Review of the Draft EA and FONSI for the
                                Point Beach Nuclear ISFSI DFP, dated
                                October 19, 2016. ADAMS Accession No.
                                ML16293A165.
                               U.S. Nuclear Regulatory Commission. Note
                                to File, Re: ESA Section 7 No Effect
                                Determination for ISFSI DFP Reviews,
                                dated May 15, 2017. ADAMS Accession No.
                                ML17135A062.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information
                                Regarding Florida Power & Light/NextEra
                                DFP Updates for St. Lucie, Units 1 and
                                2; Seabrook Station; Duane Arnold Energy
                                Center; and Point Beach, Units 1 and 2
                                ISFSIs, dated February 27, 2018. ADAMS
                                Package Accession No. ML18058A051.

[[Page 23755]]

 
                               U.S. Nuclear Regulatory Commission. Final
                                EA and FONSI for Florida Power & Light
                                Company's Initial and NextEra Energy's
                                Updated DFPs Submitted in Accordance
                                with 10 CFR 72.30(b) and (c) for Point
                                Beach Nuclear Plant Units 1 and 2 ISFSI
                                dated April 21, 2021. ADAMS Package
                                Accession No. ML21062A069.
Facility.....................  Duane Arnold Energy Center.
Docket No....................  72-32.
Licensee.....................  NextEra Energy Duane Arnold, LLC.
Proposed Action..............  The NRC's review and approval of Florida
                                Power & Light Company's initial and
                                NextEra Energy's updated DFPs submitted
                                in accordance with 10 CFR 72.30(b) and
                                (c).
Environmental Impact of        The NRC staff has determined that the
 Proposed Action.               proposed action, the review and approval
                                of Florida Power & Light Company's
                                initial and NextEra Energy's updated
                                DFPs, submitted in accordance with 10
                                CFR 72.30(b) and (c), will not authorize
                                changes to licensed operations or
                                maintenance activities, or result in
                                changes in the types, characteristics,
                                or quantities of radiological or non-
                                radiological effluents released into the
                                environment from the ISFSI, or result in
                                the creation of solid waste. Moreover,
                                the approval of the initial and updated
                                DFPs will not authorize any construction
                                activity, facility modification, or
                                other land-disturbing activity. The NRC
                                staff has concluded that the proposed
                                action is a procedural and
                                administrative action that will not have
                                a significant impact on the environment.
Finding of No Significant      The proposed action does not require
 Impact.                        changes to the ISFSI's licensed routine
                                operations, maintenance activities, or
                                monitoring programs, nor does it require
                                new construction or land-disturbing
                                activities. The scope of the proposed
                                action concerns only the NRC's review
                                and approval of Florida Power & Light
                                Company's initial and NextEra Energy's
                                updated DFPs. The scope of the proposed
                                action does not include, and will not
                                result in, the review and approval of
                                decontamination or decommissioning
                                activities or license termination for
                                the ISFSI or for other parts of Duane
                                Arnold Energy Center. Therefore, the NRC
                                staff determined that approval of the
                                initial and updated DFPs for the Duane
                                Arnold Energy Center ISFSI will not
                                significantly affect the quality of the
                                human environment, and accordingly, the
                                staff has concluded that a FONSI is
                                appropriate. The NRC staff further finds
                                that preparation of an environmental
                                impact statement (EIS) is not required.
Available Documents..........  FPL, 2012. ISFSI DFPs, dated December 17,
                                2012. ADAMS Accession No. ML12354A134.
                               FPL, 2014. Reply to Request for
                                Additional Information for Review of the
                                DFPs Regarding the ISFSI, dated August
                                12, 2014. ADAMS Accession No.
                                ML14225A655.
                               FPL, 2017. Decommissioning Funding Status
                                Reports/ISFSI Financial Assurance
                                Update, dated March 30, 2017. ADAMS
                                Accession No. ML17093A722.
                               FPL, 2018. Response to Request for
                                Additional Information Regarding Florida
                                Power & Light/NextEra Decommissioning
                                Funding Updates for ISFSI, dated April
                                3, 2018. ADAMS Accession No.
                                ML18095A057.
                               NextEra Energy, 2015. Decommissioning
                                Funding Status Reports/ISFSI Financial
                                Assurance Update, dated March 27, 2015.
                                ADAMS Accession No. ML15090A114.
                               U.S. Nuclear Regulatory Commission. 2003/
                                08/31-NUREG-1748, ``Environmental Review
                                Guidance for Licensing Actions
                                Associated with NMSS Programs, Final
                                Report.'' Washington, DC, dated August
                                2003. ADAMS Accession No. ML032540811.
                               U.S. Nuclear Regulatory Commission. EA
                                for Final Rule-Decommissioning Planning,
                                dated February 1, 2009. ADAMS Accession
                                No. ML090500648.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information for
                                Review of the DFPs for Florida Power &
                                Light and NextEra Energy ISFSIs, dated
                                May 23, 2014. ADAMS Accession No.
                                ML14143A141.
                               U.S. Nuclear Regulatory Commission.
                                Review of the Draft EA and FONSI for the
                                Duane Arnold Energy Center ISFSI DFP,
                                dated July 27, 2016. ADAMS Accession No.
                                ML16209A457.
                               U.S. Nuclear Regulatory Commission. Note
                                to File, Re: ESA Section 7 No Effect
                                Determination for ISFSI DFP Reviews,
                                dated May 15, 2017. ADAMS Accession No.
                                ML17135A062.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information
                                Regarding Florida Power & Light/NextEra
                                DFP Updates for St. Lucie, Units 1 and
                                2; Seabrook Station; Duane Arnold Energy
                                Center; and Point Beach, Units 1 and 2
                                ISFSIs, dated February 27, 2018. ADAMS
                                Package Accession No. ML18058A051.
                               U.S. Nuclear Regulatory Commission. Final
                                EA and FONSI for Florida Power & Light
                                Company's Initial and NextEra Energy's
                                Updated DFPs Submitted in Accordance
                                with 10 CFR 72.30(b) and (c) for Duane
                                Arnold Energy Center ISFSI, dated April
                                21, 2021. ADAMS Accession Package No.
                                ML21062A092.
Facility.....................  Seabrook Station Unit No. 1
Docket Nos...................  72-63
Licensee.....................  NextEra Energy Seabrook, LLC.
Proposed Action..............  The NRC's review and approval of Florida
                                Power & Light Company's initial and
                                NextEra Energy's updated DFPs submitted
                                in accordance with 10 CFR 72.30(b) and
                                (c).
Environmental Impact of        The NRC staff has determined that the
 Proposed Action.               proposed action, the review and approval
                                of Florida Power & Light Company's
                                initial and NextEra Energy's updated
                                DFPs, submitted in accordance with 10
                                CFR 72.30(b) and (c), will not authorize
                                changes to licensed operations or
                                maintenance activities, or result in
                                changes in the types, characteristics,
                                or quantities of radiological or non-
                                radiological effluents released into the
                                environment from the ISFSI, or result in
                                the creation of solid waste. Moreover,
                                the approval of the initial and updated
                                DFPs will not authorize any construction
                                activity, facility modification, or
                                other land-disturbing activity. The NRC
                                staff has concluded that the proposed
                                action is a procedural and
                                administrative action that will not have
                                a significant impact on the environment.

[[Page 23756]]

 
Finding of No Significant      The proposed action does not require
 Impact.                        changes to the ISFSI's licensed routine
                                operations, maintenance activities, or
                                monitoring programs, nor does it require
                                new construction or land-disturbing
                                activities. The scope of the proposed
                                action concerns only the NRC's review
                                and approval of Florida Power & Light
                                Company's initial and NextEra Energy's
                                updated DFPs. The scope of the proposed
                                action does not include, and will not
                                result in, the review and approval of
                                decontamination or decommissioning
                                activities or license termination for
                                the ISFSI or for other parts of Seabrook
                                Station Unit No. 1. Therefore, the NRC
                                staff determined that approval of the
                                initial and updated DFPs for the
                                Seabrook Station Unit No. 1 ISFSI will
                                not significantly affect the quality of
                                the human environment, and accordingly,
                                the staff has concluded that a FONSI is
                                appropriate. The NRC staff further finds
                                that preparation of an environmental
                                impact statement (EIS) is not required.
Available Documents..........  FPL, 2012. ISFSI DFPs, dated December 17,
                                2012. ADAMS Accession No. ML12354A134.
                               FPL, 2014. Reply to Request for
                                Additional Information for Review of the
                                DFPs Regarding the ISFSI, dated August
                                12, 2014. ADAMS Accession No.
                                ML14225A655.
                               FPL, 2017. Decommissioning Funding Status
                                Reports/ISFSI Financial Assurance
                                Update, dated March 30, 2017. ADAMS
                                Accession No. ML17093A722.
                               FPL, 2018. Response to Request for
                                Additional Information Regarding Florida
                                Power & Light/NextEra Decommissioning
                                Funding Updates for ISFSI, dated April
                                3, 2018. ADAMS Accession No.
                                ML18095A057.
                               NextEra Energy, 2015. Decommissioning
                                Funding Status Reports/ISFSI Financial
                                Assurance Update, dated March 27, 2015.
                                ADAMS Accession No. ML15090A114.
                               U.S. Nuclear Regulatory Commission. 2003/
                                08/31-NUREG-1748, ``Environmental Review
                                Guidance for Licensing Actions
                                Associated with NMSS Programs, Final
                                Report.'' Washington, DC, dated August
                                2003. ADAMS Accession No. ML032540811.
                               U.S. Nuclear Regulatory Commission. EA
                                for Final Rule-Decommissioning Planning,
                                dated February 1, 2009. ADAMS Accession
                                No. ML090500648.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information for
                                Review of the DFPs for Florida Power &
                                Light and NextEra Energy ISFSIs, dated
                                May 23, 2014. ADAMS Accession No.
                                ML14143A141.
                               U.S. Nuclear Regulatory Commission. Note
                                to File, Re: ESA Section 7 No Effect
                                Determination for ISFSI DFP Reviews,
                                dated May 15, 2017. ADAMS Accession No.
                                ML17135A062.
                               U.S. Nuclear Regulatory Commission.
                                Review of the Draft EA and FONSI for the
                                Seabrook Station ISFSI DFP, dated August
                                17, 2017. ADAMS Accession No.
                                ML17226A329.
                               U.S. Nuclear Regulatory Commission.
                                Request for Additional Information
                                Regarding Florida Power & Light/NextEra
                                DFP Updates for St. Lucie, Units 1 and
                                2; Seabrook Station; Duane Arnold Energy
                                Center; and Point Beach, Units 1 and 2
                                ISFSIs, dated February 27, 2018. ADAMS
                                Package Accession No. ML18058A051.
                               U.S. Nuclear Regulatory Commission. Final
                                EA and FONSI for Florida Power & Light
                                Company's Initial and NextEra Energy's
                                Updated DFPs Submitted in Accordance
                                with 10 CFR 72.30(b) and (c) for
                                Seabrook Station Unit No. 1 ISFSI, dated
                                April 21, 2021. ADAMS Package Accession
                                No. ML21062A145.
------------------------------------------------------------------------


    Dated: April 28, 2021.

    For the Nuclear Regulatory Commission.
John B. McKirgan,
Chief, Storage and Transportation Licensing Branch, Division of Fuel 
Management, Office of Nuclear Material Safety and Safeguards.
[FR Doc. 2021-09293 Filed 5-3-21; 8:45 am]
BILLING CODE 7590-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.