Environmental Assessments and Findings of No Significant Impact of Independent Spent Fuel Storage Facilities Decommissioning Funding Plans, 23752-23756 [2021-09293]
Download as PDF
23752
Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices
in the FOR FURTHER INFORMATION
CONTACT section of this document.
NUCLEAR REGULATORY
COMMISSION
[NRC–2021–0074]
Environmental Assessments and
Findings of No Significant Impact of
Independent Spent Fuel Storage
Facilities Decommissioning Funding
Plans
Nuclear Regulatory
Commission.
ACTION: Environmental assessment and
finding of no significant impact;
issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is publishing this
notice regarding the issuance of a final
Environmental Assessment (EA) and a
Finding of No Significant Impact
(FONSI) for its review and approval of
the initial and updated
decommissioning funding plans (DFPs)
submitted by independent spent fuel
storage installation (ISFSI) licensees for
each of the ISFSIs listed in the
‘‘Discussion’’ section of this document.
DATES: The EA and FONSI referenced in
this document are available on May 4,
2021.
ADDRESSES: Please refer to Docket ID
NRC–2021–0074 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2021–0074. Address
questions about Docket IDs in
Regulations.gov to Stacy Schumann;
telephone: 301–415–0624; email:
Stacy.Schumann@nrc.gov For technical
questions, contact the individual listed
SUMMARY:
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced (if it is
available in ADAMS) is provided the
first time that it is mentioned in this
document.
• Attention: The PDR, where you may
examine and order copies of public
documents, is currently closed. You
may submit your request to the PDR via
email at pdr.resource@nrc.gov or call
1–800–397–4209 or 301–415–4737,
between 8:00 a.m. and 4:00 p.m. (EST),
Monday through Friday, except Federal
holidays.
FOR FURTHER INFORMATION CONTACT:
Donald Habib, Office of Nuclear
Material Safety and Safeguards, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–1035, email: Donald.Habib@
nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is considering the approval
of the initial and updated DFPs
submitted by ISFSI licensees. The NRC
staff has prepared a final EA and FONSI
determination for each of the initial and
updated ISFSI DFPs in accordance with
the NRC regulations in part 51 of title
10 of the Code of Federal Regulations
(10 CFR), ‘‘Environmental Protection
Regulations for Domestic Licensing and
Related Regulatory Functions,’’ which
implement the National Environmental
Policy Act of 1969, as amended (42
U.S.C. 4321 et seq.).
The NRC requires its licensees to plan
for the eventual decommissioning of
their licensed facilities prior to license
termination. On June 17, 2011, the NRC
published a final rule in the Federal
Register amending its decommissioning
planning regulations (76 FR 35512). The
final rule amended the NRC regulation,
10 CFR 72.30, which concerns financial
assurance and decommissioning for
ISFSIs. This regulation requires each
holder of, or applicant for, a license
under 10 CFR part 72 to submit a DFP
for the NRC’s review and approval. The
DFP is to demonstrate the licensee’s
financial assurance, i.e., that funds will
be available to decommission the ISFSI.
The NRC staff will later publish its
financial analyses of the DFP submittals
which will be available for public
inspection in ADAMS.
II. Discussion
The table in this notice includes the
plant name, docket number, licensee,
and ADAMS Accession Number for the
final EA and FONSI determination for
each of the individual ISFSIs. The table
also includes the ADAMS Accession
Numbers for other relevant documents,
including the initial and updated DFP
submittals. For further details with
respect to these actions, see the NRC
staff’s Final EA and FONSI
determinations which are available for
public inspection in ADAMS and at
https://www.regulations.gov under
Docket ID NRC–2021–0074. For
additional direction on accessing
information related to this document,
see the ADDRESSES section of this
document.
FINDING OF NO SIGNIFICANT IMPACT
Facility .................................................................
Docket No. ..........................................................
Licensee ..............................................................
Proposed Action .................................................
khammond on DSKJM1Z7X2PROD with NOTICES
Environmental Impact of Proposed Action .........
VerDate Sep<11>2014
17:13 May 03, 2021
Jkt 253001
Turkey Point Nuclear Generating Units 3 and 4.
72–62.
Florida Power & Light Company.
The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c).
The NRC staff has determined that the proposed action, the review and approval of Florida
Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize changes to licensed operations or
maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result
in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will
not authorize any construction activity, facility modification, or other land-disturbing activity.
The NRC staff has concluded that the proposed action is a procedural and administrative
action that will not have a significant impact on the environment.
PO 00000
Frm 00083
Fmt 4703
Sfmt 4703
E:\FR\FM\04MYN1.SGM
04MYN1
Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices
23753
FINDING OF NO SIGNIFICANT IMPACT—Continued
Finding of No Significant Impact ........................
Available Documents ..........................................
Facility .................................................................
Docket No. ..........................................................
Licensee ..............................................................
Proposed Action .................................................
Environmental Impact of Proposed Action .........
khammond on DSKJM1Z7X2PROD with NOTICES
Finding of No Significant Impact ........................
Available Documents ..........................................
VerDate Sep<11>2014
17:13 May 03, 2021
Jkt 253001
The proposed action does not require changes to the ISFSI’s licensed routine operations,
maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and
approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs.
The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI
or for other parts of Turkey Point Nuclear Generating Units 3 and 4. Therefore, the NRC
staff determined that approval of the initial and updated DFPs for the Turkey Point Nuclear
Generating Units 3 and 4 ISFSI will not significantly affect the quality of the human environment, and accordingly, the staff has concluded that a FONSI is appropriate. The NRC staff
further finds that preparation of an environmental impact statement (EIS) is not required.
FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the
ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655.
FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update,
dated March 30, 2017. ADAMS Accession No. ML17093A722.
FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/
NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057.
NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance
Update, dated March 27, 2015. ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review
Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated
February 1, 2009. ADAMS Accession No. ML090500648.
U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the
DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS
Accession No. ML14143A141.
U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the Turkey Point
Units 3 and 4 ISFSI DFP, dated June 22, 2016. ADAMS Accession No. ML16174A331.
U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062.
U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida
Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane
Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018.
ADAMS Package Accession No. ML18058A051.
U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s Initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR
72.30(b) and (c) for Turkey Point Nuclear Generating Units 3 and 4 ISFSI, dated April 21,
2021. ADAMS Package Accession No. ML21062A055.
St. Lucie Plant Units 1 and 2.
72–61.
Florida Power & Light Company.
The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c).
The NRC staff has determined that the proposed action, the review and approval of Florida
Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize or changes to licensed operations or
maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result
in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will
not authorize any construction activity, facility modification, or other land-disturbing activity.
The NRC staff has concluded that the proposed action is a procedural and administrative
action that will not have a significant impact on the environment.
The proposed action does not require changes to the ISFSI’s licensed routine operations,
maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and
approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs.
The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI
or for other parts of the St. Lucie Plant Units 1 and 2. Therefore, the NRC staff determined
that approval of the initial and updated DFPs for the St. Lucie Plant Units 1 and 2 ISFSI will
not significantly affect the quality of the human environment, and accordingly, the staff has
concluded that a FONSI is appropriate. The NRC staff further finds that preparation of an
environmental impact statement (EIS) is not required.
FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the
ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655.
FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update,
dated March 30, 2017. ADAMS Accession No. ML17093A722.
FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/
NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057.
PO 00000
Frm 00084
Fmt 4703
Sfmt 4703
E:\FR\FM\04MYN1.SGM
04MYN1
23754
Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices
FINDING OF NO SIGNIFICANT IMPACT—Continued
Facility .................................................................
Docket No. ..........................................................
Licensee ..............................................................
Proposed Action .................................................
Environmental Impact of Proposed Action .........
Finding of No Significant Impact ........................
khammond on DSKJM1Z7X2PROD with NOTICES
Available Documents ..........................................
VerDate Sep<11>2014
17:13 May 03, 2021
Jkt 253001
NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance
Update, dated March 27, 2015. ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review
Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated
February 1, 2009. ADAMS Accession No. ML090500648.
U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the
DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS
Accession No. ML14143A141.
U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the St. Lucie
Units 1 and 2 ISFSI DFP, dated June 22, 2016. ADAMS Accession No. ML16174A112.
U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062.
U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida
Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane
Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018.
ADAMS Package Accession No. ML18058A051.
U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR
72.30(b) and (c) for St. Lucie Plant Units 1 and 2 ISFSI, dated April 21, 2021. ADAMS
Package Accession No. ML21062A061.
Point Beach Nuclear Plant Units 1 and 2.
72–05.
NextEra Energy Point Beach, LLC.
The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c).
The NRC staff has determined that the proposed action, the review and approval of Florida
Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize changes to licensed operations or
maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result
in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will
not authorize any construction activity, facility modification, or other land-disturbing activity.
The NRC staff has concluded that the proposed action is a procedural and administrative
action that will not have a significant impact on the environment.
The proposed action does not require changes to the ISFSI’s licensed routine operations,
maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and
approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs.
The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI
or for other parts of Point Beach Nuclear Plant Units 1 and 2. Therefore, the NRC staff determined that approval of the initial and updated DFPs for the Point Beach Nuclear Plant
Units 1 and 2 ISFSI will not significantly affect the quality of the human environment, and
accordingly, the staff has concluded that a FONSI is appropriate. The NRC staff further finds
that preparation of an environmental impact statement (EIS) is not required.
FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the
ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655.
FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update,
dated March 30, 2017. ADAMS Accession No. ML17093A722.
FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/
NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057.
NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance
Update, dated March 27, 2015. ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review
Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated
February 1, 2009. ADAMS Accession No. ML090500648.
U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the
DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS
Accession No. ML14143A141.
U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the Point Beach
Nuclear ISFSI DFP, dated October 19, 2016. ADAMS Accession No. ML16293A165.
U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062.
U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida
Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane
Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018.
ADAMS Package Accession No. ML18058A051.
PO 00000
Frm 00085
Fmt 4703
Sfmt 4703
E:\FR\FM\04MYN1.SGM
04MYN1
Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices
23755
FINDING OF NO SIGNIFICANT IMPACT—Continued
Facility .................................................................
Docket No. ..........................................................
Licensee ..............................................................
Proposed Action .................................................
Environmental Impact of Proposed Action .........
Finding of No Significant Impact ........................
Available Documents ..........................................
khammond on DSKJM1Z7X2PROD with NOTICES
Facility .................................................................
Docket Nos. ........................................................
Licensee ..............................................................
Proposed Action .................................................
Environmental Impact of Proposed Action .........
VerDate Sep<11>2014
17:13 May 03, 2021
Jkt 253001
U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s Initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR
72.30(b) and (c) for Point Beach Nuclear Plant Units 1 and 2 ISFSI dated April 21, 2021.
ADAMS Package Accession No. ML21062A069.
Duane Arnold Energy Center.
72–32.
NextEra Energy Duane Arnold, LLC.
The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c).
The NRC staff has determined that the proposed action, the review and approval of Florida
Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize changes to licensed operations or
maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result
in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will
not authorize any construction activity, facility modification, or other land-disturbing activity.
The NRC staff has concluded that the proposed action is a procedural and administrative
action that will not have a significant impact on the environment.
The proposed action does not require changes to the ISFSI’s licensed routine operations,
maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and
approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs.
The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI
or for other parts of Duane Arnold Energy Center. Therefore, the NRC staff determined that
approval of the initial and updated DFPs for the Duane Arnold Energy Center ISFSI will not
significantly affect the quality of the human environment, and accordingly, the staff has concluded that a FONSI is appropriate. The NRC staff further finds that preparation of an environmental impact statement (EIS) is not required.
FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the
ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655.
FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update,
dated March 30, 2017. ADAMS Accession No. ML17093A722.
FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/
NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057.
NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance
Update, dated March 27, 2015. ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review
Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated
February 1, 2009. ADAMS Accession No. ML090500648.
U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the
DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS
Accession No. ML14143A141.
U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the Duane Arnold Energy Center ISFSI DFP, dated July 27, 2016. ADAMS Accession No. ML16209A457.
U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062.
U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida
Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane
Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018.
ADAMS Package Accession No. ML18058A051.
U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s Initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR
72.30(b) and (c) for Duane Arnold Energy Center ISFSI, dated April 21, 2021. ADAMS Accession Package No. ML21062A092.
Seabrook Station Unit No. 1
72–63
NextEra Energy Seabrook, LLC.
The NRC’s review and approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs submitted in accordance with 10 CFR 72.30(b) and (c).
The NRC staff has determined that the proposed action, the review and approval of Florida
Power & Light Company’s initial and NextEra Energy’s updated DFPs, submitted in accordance with 10 CFR 72.30(b) and (c), will not authorize changes to licensed operations or
maintenance activities, or result in changes in the types, characteristics, or quantities of radiological or non-radiological effluents released into the environment from the ISFSI, or result
in the creation of solid waste. Moreover, the approval of the initial and updated DFPs will
not authorize any construction activity, facility modification, or other land-disturbing activity.
The NRC staff has concluded that the proposed action is a procedural and administrative
action that will not have a significant impact on the environment.
PO 00000
Frm 00086
Fmt 4703
Sfmt 4703
E:\FR\FM\04MYN1.SGM
04MYN1
23756
Federal Register / Vol. 86, No. 84 / Tuesday, May 4, 2021 / Notices
FINDING OF NO SIGNIFICANT IMPACT—Continued
Finding of No Significant Impact ........................
Available Documents ..........................................
Dated: April 28, 2021.
For the Nuclear Regulatory Commission.
John B. McKirgan,
Chief, Storage and Transportation Licensing
Branch, Division of Fuel Management, Office
of Nuclear Material Safety and Safeguards.
[FR Doc. 2021–09293 Filed 5–3–21; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 52–025 and 52–026; NRC–
2008–0252]
khammond on DSKJM1Z7X2PROD with NOTICES
Southern Nuclear Operating Company,
Inc; Vogtle Electric Generating Plant,
Units 3 and 4; Inspections, Tests,
Analyses, and Acceptance Criteria
Nuclear Regulatory
Commission.
ACTION: Determination of the successful
completion of inspections, tests, and
analyses.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) staff has determined
SUMMARY:
VerDate Sep<11>2014
17:13 May 03, 2021
Jkt 253001
The proposed action does not require changes to the ISFSI’s licensed routine operations,
maintenance activities, or monitoring programs, nor does it require new construction or landdisturbing activities. The scope of the proposed action concerns only the NRC’s review and
approval of Florida Power & Light Company’s initial and NextEra Energy’s updated DFPs.
The scope of the proposed action does not include, and will not result in, the review and approval of decontamination or decommissioning activities or license termination for the ISFSI
or for other parts of Seabrook Station Unit No. 1. Therefore, the NRC staff determined that
approval of the initial and updated DFPs for the Seabrook Station Unit No. 1 ISFSI will not
significantly affect the quality of the human environment, and accordingly, the staff has concluded that a FONSI is appropriate. The NRC staff further finds that preparation of an environmental impact statement (EIS) is not required.
FPL, 2012. ISFSI DFPs, dated December 17, 2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for Additional Information for Review of the DFPs Regarding the
ISFSI, dated August 12, 2014. ADAMS Accession No. ML14225A655.
FPL, 2017. Decommissioning Funding Status Reports/ISFSI Financial Assurance Update,
dated March 30, 2017. ADAMS Accession No. ML17093A722.
FPL, 2018. Response to Request for Additional Information Regarding Florida Power & Light/
NextEra Decommissioning Funding Updates for ISFSI, dated April 3, 2018. ADAMS Accession No. ML18095A057.
NextEra Energy, 2015. Decommissioning Funding Status Reports/ISFSI Financial Assurance
Update, dated March 27, 2015. ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/08/31–NUREG–1748, ‘‘Environmental Review
Guidance for Licensing Actions Associated with NMSS Programs, Final Report.’’ Washington, DC, dated August 2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA for Final Rule-Decommissioning Planning, dated
February 1, 2009. ADAMS Accession No. ML090500648.
U.S. Nuclear Regulatory Commission. Request for Additional Information for Review of the
DFPs for Florida Power & Light and NextEra Energy ISFSIs, dated May 23, 2014. ADAMS
Accession No. ML14143A141.
U.S. Nuclear Regulatory Commission. Note to File, Re: ESA Section 7 No Effect Determination for ISFSI DFP Reviews, dated May 15, 2017. ADAMS Accession No. ML17135A062.
U.S. Nuclear Regulatory Commission. Review of the Draft EA and FONSI for the Seabrook
Station ISFSI DFP, dated August 17, 2017. ADAMS Accession No. ML17226A329.
U.S. Nuclear Regulatory Commission. Request for Additional Information Regarding Florida
Power & Light/NextEra DFP Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane
Arnold Energy Center; and Point Beach, Units 1 and 2 ISFSIs, dated February 27, 2018.
ADAMS Package Accession No. ML18058A051.
U.S. Nuclear Regulatory Commission. Final EA and FONSI for Florida Power & Light Company’s Initial and NextEra Energy’s Updated DFPs Submitted in Accordance with 10 CFR
72.30(b) and (c) for Seabrook Station Unit No. 1 ISFSI, dated April 21, 2021. ADAMS Package Accession No. ML21062A145.
that specified inspections, tests, and
analyses have been successfully
completed, and that specified
acceptance criteria are met for the
Vogtle Electric Generating Plant (VEGP),
Units 3 and 4.
DATES: Determinations of the successful
completion of inspections, tests, and
analyses for VEGP Units 3 and 4 are
effective on the dates indicated in the
NRC staff’s verification evaluation forms
for the inspections, tests, analyses, and
acceptance criteria (ITAAC).
ADDRESSES: Please refer to Docket ID
NRC–2008–0252 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2008–0252. Address
questions about Docket IDs to Stacy
Schumann; telephone: 301–415–0624;
email: Stacy.Schumann@nrc.gov. For
technical questions, contact the
PO 00000
Frm 00087
Fmt 4703
Sfmt 4703
individual listed in the FOR FURTHER
section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publicly
available documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced in this
document (if that document is available
in ADAMS) is provided the first time
that a document is referenced.
• Attention: The PDR, where you may
examine and order copies of public
documents, is currently closed. You
may submit your request to the PDR via
email at pdr.resource@nrc.gov or call 1–
800–397–4209 or 301–415–4737,
between 8:00 a.m. and 4:00 p.m. (EST),
INFORMATION CONTACT
E:\FR\FM\04MYN1.SGM
04MYN1
Agencies
[Federal Register Volume 86, Number 84 (Tuesday, May 4, 2021)]
[Notices]
[Pages 23752-23756]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-09293]
[[Page 23752]]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2021-0074]
Environmental Assessments and Findings of No Significant Impact
of Independent Spent Fuel Storage Facilities Decommissioning Funding
Plans
AGENCY: Nuclear Regulatory Commission.
ACTION: Environmental assessment and finding of no significant impact;
issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is publishing
this notice regarding the issuance of a final Environmental Assessment
(EA) and a Finding of No Significant Impact (FONSI) for its review and
approval of the initial and updated decommissioning funding plans
(DFPs) submitted by independent spent fuel storage installation (ISFSI)
licensees for each of the ISFSIs listed in the ``Discussion'' section
of this document.
DATES: The EA and FONSI referenced in this document are available on
May 4, 2021.
ADDRESSES: Please refer to Docket ID NRC-2021-0074 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0074. Address
questions about Docket IDs in Regulations.gov to Stacy Schumann;
telephone: 301-415-0624; email: [email protected] For technical
questions, contact the individual listed in the FOR FURTHER INFORMATION
CONTACT section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or
by email to [email protected]. The ADAMS accession number for each
document referenced (if it is available in ADAMS) is provided the first
time that it is mentioned in this document.
Attention: The PDR, where you may examine and order copies
of public documents, is currently closed. You may submit your request
to the PDR via email at [email protected] or call 1-800-397-4209 or
301-415-4737, between 8:00 a.m. and 4:00 p.m. (EST), Monday through
Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: Donald Habib, Office of Nuclear
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001; telephone: 301-415-1035, email:
[email protected].
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is considering the approval of the initial and updated DFPs
submitted by ISFSI licensees. The NRC staff has prepared a final EA and
FONSI determination for each of the initial and updated ISFSI DFPs in
accordance with the NRC regulations in part 51 of title 10 of the Code
of Federal Regulations (10 CFR), ``Environmental Protection Regulations
for Domestic Licensing and Related Regulatory Functions,'' which
implement the National Environmental Policy Act of 1969, as amended (42
U.S.C. 4321 et seq.).
The NRC requires its licensees to plan for the eventual
decommissioning of their licensed facilities prior to license
termination. On June 17, 2011, the NRC published a final rule in the
Federal Register amending its decommissioning planning regulations (76
FR 35512). The final rule amended the NRC regulation, 10 CFR 72.30,
which concerns financial assurance and decommissioning for ISFSIs. This
regulation requires each holder of, or applicant for, a license under
10 CFR part 72 to submit a DFP for the NRC's review and approval. The
DFP is to demonstrate the licensee's financial assurance, i.e., that
funds will be available to decommission the ISFSI. The NRC staff will
later publish its financial analyses of the DFP submittals which will
be available for public inspection in ADAMS.
II. Discussion
The table in this notice includes the plant name, docket number,
licensee, and ADAMS Accession Number for the final EA and FONSI
determination for each of the individual ISFSIs. The table also
includes the ADAMS Accession Numbers for other relevant documents,
including the initial and updated DFP submittals. For further details
with respect to these actions, see the NRC staff's Final EA and FONSI
determinations which are available for public inspection in ADAMS and
at https://www.regulations.gov under Docket ID NRC-2021-0074. For
additional direction on accessing information related to this document,
see the ADDRESSES section of this document.
Finding of No Significant Impact
------------------------------------------------------------------------
------------------------------------------------------------------------
Facility..................... Turkey Point Nuclear Generating Units 3
and 4.
Docket No.................... 72-62.
Licensee..................... Florida Power & Light Company.
Proposed Action.............. The NRC's review and approval of Florida
Power & Light Company's initial and
NextEra Energy's updated DFPs submitted
in accordance with 10 CFR 72.30(b) and
(c).
Environmental Impact of The NRC staff has determined that the
Proposed Action. proposed action, the review and approval
of Florida Power & Light Company's
initial and NextEra Energy's updated
DFPs, submitted in accordance with 10
CFR 72.30(b) and (c), will not authorize
changes to licensed operations or
maintenance activities, or result in
changes in the types, characteristics,
or quantities of radiological or non-
radiological effluents released into the
environment from the ISFSI, or result in
the creation of solid waste. Moreover,
the approval of the initial and updated
DFPs will not authorize any construction
activity, facility modification, or
other land-disturbing activity. The NRC
staff has concluded that the proposed
action is a procedural and
administrative action that will not have
a significant impact on the environment.
[[Page 23753]]
Finding of No Significant The proposed action does not require
Impact. changes to the ISFSI's licensed routine
operations, maintenance activities, or
monitoring programs, nor does it require
new construction or land-disturbing
activities. The scope of the proposed
action concerns only the NRC's review
and approval of Florida Power & Light
Company's initial and NextEra Energy's
updated DFPs. The scope of the proposed
action does not include, and will not
result in, the review and approval of
decontamination or decommissioning
activities or license termination for
the ISFSI or for other parts of Turkey
Point Nuclear Generating Units 3 and 4.
Therefore, the NRC staff determined that
approval of the initial and updated DFPs
for the Turkey Point Nuclear Generating
Units 3 and 4 ISFSI will not
significantly affect the quality of the
human environment, and accordingly, the
staff has concluded that a FONSI is
appropriate. The NRC staff further finds
that preparation of an environmental
impact statement (EIS) is not required.
Available Documents.......... FPL, 2012. ISFSI DFPs, dated December 17,
2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for
Additional Information for Review of the
DFPs Regarding the ISFSI, dated August
12, 2014. ADAMS Accession No.
ML14225A655.
FPL, 2017. Decommissioning Funding Status
Reports/ISFSI Financial Assurance
Update, dated March 30, 2017. ADAMS
Accession No. ML17093A722.
FPL, 2018. Response to Request for
Additional Information Regarding Florida
Power & Light/NextEra Decommissioning
Funding Updates for ISFSI, dated April
3, 2018. ADAMS Accession No.
ML18095A057.
NextEra Energy, 2015. Decommissioning
Funding Status Reports/ISFSI Financial
Assurance Update, dated March 27, 2015.
ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/
08/31-NUREG-1748, ``Environmental Review
Guidance for Licensing Actions
Associated with NMSS Programs, Final
Report.'' Washington, DC, dated August
2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA
for Final Rule-Decommissioning Planning,
dated February 1, 2009. ADAMS Accession
No. ML090500648.
U.S. Nuclear Regulatory Commission.
Request for Additional Information for
Review of the DFPs for Florida Power &
Light and NextEra Energy ISFSIs, dated
May 23, 2014. ADAMS Accession No.
ML14143A141.
U.S. Nuclear Regulatory Commission.
Review of the Draft EA and FONSI for the
Turkey Point Units 3 and 4 ISFSI DFP,
dated June 22, 2016. ADAMS Accession No.
ML16174A331.
U.S. Nuclear Regulatory Commission. Note
to File, Re: ESA Section 7 No Effect
Determination for ISFSI DFP Reviews,
dated May 15, 2017. ADAMS Accession No.
ML17135A062.
U.S. Nuclear Regulatory Commission.
Request for Additional Information
Regarding Florida Power & Light/NextEra
DFP Updates for St. Lucie, Units 1 and
2; Seabrook Station; Duane Arnold Energy
Center; and Point Beach, Units 1 and 2
ISFSIs, dated February 27, 2018. ADAMS
Package Accession No. ML18058A051.
U.S. Nuclear Regulatory Commission. Final
EA and FONSI for Florida Power & Light
Company's Initial and NextEra Energy's
Updated DFPs Submitted in Accordance
with 10 CFR 72.30(b) and (c) for Turkey
Point Nuclear Generating Units 3 and 4
ISFSI, dated April 21, 2021. ADAMS
Package Accession No. ML21062A055.
Facility..................... St. Lucie Plant Units 1 and 2.
Docket No.................... 72-61.
Licensee..................... Florida Power & Light Company.
Proposed Action.............. The NRC's review and approval of Florida
Power & Light Company's initial and
NextEra Energy's updated DFPs submitted
in accordance with 10 CFR 72.30(b) and
(c).
Environmental Impact of The NRC staff has determined that the
Proposed Action. proposed action, the review and approval
of Florida Power & Light Company's
initial and NextEra Energy's updated
DFPs, submitted in accordance with 10
CFR 72.30(b) and (c), will not authorize
or changes to licensed operations or
maintenance activities, or result in
changes in the types, characteristics,
or quantities of radiological or non-
radiological effluents released into the
environment from the ISFSI, or result in
the creation of solid waste. Moreover,
the approval of the initial and updated
DFPs will not authorize any construction
activity, facility modification, or
other land-disturbing activity. The NRC
staff has concluded that the proposed
action is a procedural and
administrative action that will not have
a significant impact on the environment.
Finding of No Significant The proposed action does not require
Impact. changes to the ISFSI's licensed routine
operations, maintenance activities, or
monitoring programs, nor does it require
new construction or land-disturbing
activities. The scope of the proposed
action concerns only the NRC's review
and approval of Florida Power & Light
Company's initial and NextEra Energy's
updated DFPs. The scope of the proposed
action does not include, and will not
result in, the review and approval of
decontamination or decommissioning
activities or license termination for
the ISFSI or for other parts of the St.
Lucie Plant Units 1 and 2. Therefore,
the NRC staff determined that approval
of the initial and updated DFPs for the
St. Lucie Plant Units 1 and 2 ISFSI will
not significantly affect the quality of
the human environment, and accordingly,
the staff has concluded that a FONSI is
appropriate. The NRC staff further finds
that preparation of an environmental
impact statement (EIS) is not required.
Available Documents.......... FPL, 2012. ISFSI DFPs, dated December 17,
2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for
Additional Information for Review of the
DFPs Regarding the ISFSI, dated August
12, 2014. ADAMS Accession No.
ML14225A655.
FPL, 2017. Decommissioning Funding Status
Reports/ISFSI Financial Assurance
Update, dated March 30, 2017. ADAMS
Accession No. ML17093A722.
FPL, 2018. Response to Request for
Additional Information Regarding Florida
Power & Light/NextEra Decommissioning
Funding Updates for ISFSI, dated April
3, 2018. ADAMS Accession No.
ML18095A057.
[[Page 23754]]
NextEra Energy, 2015. Decommissioning
Funding Status Reports/ISFSI Financial
Assurance Update, dated March 27, 2015.
ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/
08/31-NUREG-1748, ``Environmental Review
Guidance for Licensing Actions
Associated with NMSS Programs, Final
Report.'' Washington, DC, dated August
2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA
for Final Rule-Decommissioning Planning,
dated February 1, 2009. ADAMS Accession
No. ML090500648.
U.S. Nuclear Regulatory Commission.
Request for Additional Information for
Review of the DFPs for Florida Power &
Light and NextEra Energy ISFSIs, dated
May 23, 2014. ADAMS Accession No.
ML14143A141.
U.S. Nuclear Regulatory Commission.
Review of the Draft EA and FONSI for the
St. Lucie Units 1 and 2 ISFSI DFP, dated
June 22, 2016. ADAMS Accession No.
ML16174A112.
U.S. Nuclear Regulatory Commission. Note
to File, Re: ESA Section 7 No Effect
Determination for ISFSI DFP Reviews,
dated May 15, 2017. ADAMS Accession No.
ML17135A062.
U.S. Nuclear Regulatory Commission.
Request for Additional Information
Regarding Florida Power & Light/NextEra
DFP Updates for St. Lucie, Units 1 and
2; Seabrook Station; Duane Arnold Energy
Center; and Point Beach, Units 1 and 2
ISFSIs, dated February 27, 2018. ADAMS
Package Accession No. ML18058A051.
U.S. Nuclear Regulatory Commission. Final
EA and FONSI for Florida Power & Light
Company's initial and NextEra Energy's
Updated DFPs Submitted in Accordance
with 10 CFR 72.30(b) and (c) for St.
Lucie Plant Units 1 and 2 ISFSI, dated
April 21, 2021. ADAMS Package Accession
No. ML21062A061.
Facility..................... Point Beach Nuclear Plant Units 1 and 2.
Docket No.................... 72-05.
Licensee..................... NextEra Energy Point Beach, LLC.
Proposed Action.............. The NRC's review and approval of Florida
Power & Light Company's initial and
NextEra Energy's updated DFPs submitted
in accordance with 10 CFR 72.30(b) and
(c).
Environmental Impact of The NRC staff has determined that the
Proposed Action. proposed action, the review and approval
of Florida Power & Light Company's
initial and NextEra Energy's updated
DFPs, submitted in accordance with 10
CFR 72.30(b) and (c), will not authorize
changes to licensed operations or
maintenance activities, or result in
changes in the types, characteristics,
or quantities of radiological or non-
radiological effluents released into the
environment from the ISFSI, or result in
the creation of solid waste. Moreover,
the approval of the initial and updated
DFPs will not authorize any construction
activity, facility modification, or
other land-disturbing activity. The NRC
staff has concluded that the proposed
action is a procedural and
administrative action that will not have
a significant impact on the environment.
Finding of No Significant The proposed action does not require
Impact. changes to the ISFSI's licensed routine
operations, maintenance activities, or
monitoring programs, nor does it require
new construction or land-disturbing
activities. The scope of the proposed
action concerns only the NRC's review
and approval of Florida Power & Light
Company's initial and NextEra Energy's
updated DFPs. The scope of the proposed
action does not include, and will not
result in, the review and approval of
decontamination or decommissioning
activities or license termination for
the ISFSI or for other parts of Point
Beach Nuclear Plant Units 1 and 2.
Therefore, the NRC staff determined that
approval of the initial and updated DFPs
for the Point Beach Nuclear Plant Units
1 and 2 ISFSI will not significantly
affect the quality of the human
environment, and accordingly, the staff
has concluded that a FONSI is
appropriate. The NRC staff further finds
that preparation of an environmental
impact statement (EIS) is not required.
Available Documents.......... FPL, 2012. ISFSI DFPs, dated December 17,
2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for
Additional Information for Review of the
DFPs Regarding the ISFSI, dated August
12, 2014. ADAMS Accession No.
ML14225A655.
FPL, 2017. Decommissioning Funding Status
Reports/ISFSI Financial Assurance
Update, dated March 30, 2017. ADAMS
Accession No. ML17093A722.
FPL, 2018. Response to Request for
Additional Information Regarding Florida
Power & Light/NextEra Decommissioning
Funding Updates for ISFSI, dated April
3, 2018. ADAMS Accession No.
ML18095A057.
NextEra Energy, 2015. Decommissioning
Funding Status Reports/ISFSI Financial
Assurance Update, dated March 27, 2015.
ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/
08/31-NUREG-1748, ``Environmental Review
Guidance for Licensing Actions
Associated with NMSS Programs, Final
Report.'' Washington, DC, dated August
2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA
for Final Rule-Decommissioning Planning,
dated February 1, 2009. ADAMS Accession
No. ML090500648.
U.S. Nuclear Regulatory Commission.
Request for Additional Information for
Review of the DFPs for Florida Power &
Light and NextEra Energy ISFSIs, dated
May 23, 2014. ADAMS Accession No.
ML14143A141.
U.S. Nuclear Regulatory Commission.
Review of the Draft EA and FONSI for the
Point Beach Nuclear ISFSI DFP, dated
October 19, 2016. ADAMS Accession No.
ML16293A165.
U.S. Nuclear Regulatory Commission. Note
to File, Re: ESA Section 7 No Effect
Determination for ISFSI DFP Reviews,
dated May 15, 2017. ADAMS Accession No.
ML17135A062.
U.S. Nuclear Regulatory Commission.
Request for Additional Information
Regarding Florida Power & Light/NextEra
DFP Updates for St. Lucie, Units 1 and
2; Seabrook Station; Duane Arnold Energy
Center; and Point Beach, Units 1 and 2
ISFSIs, dated February 27, 2018. ADAMS
Package Accession No. ML18058A051.
[[Page 23755]]
U.S. Nuclear Regulatory Commission. Final
EA and FONSI for Florida Power & Light
Company's Initial and NextEra Energy's
Updated DFPs Submitted in Accordance
with 10 CFR 72.30(b) and (c) for Point
Beach Nuclear Plant Units 1 and 2 ISFSI
dated April 21, 2021. ADAMS Package
Accession No. ML21062A069.
Facility..................... Duane Arnold Energy Center.
Docket No.................... 72-32.
Licensee..................... NextEra Energy Duane Arnold, LLC.
Proposed Action.............. The NRC's review and approval of Florida
Power & Light Company's initial and
NextEra Energy's updated DFPs submitted
in accordance with 10 CFR 72.30(b) and
(c).
Environmental Impact of The NRC staff has determined that the
Proposed Action. proposed action, the review and approval
of Florida Power & Light Company's
initial and NextEra Energy's updated
DFPs, submitted in accordance with 10
CFR 72.30(b) and (c), will not authorize
changes to licensed operations or
maintenance activities, or result in
changes in the types, characteristics,
or quantities of radiological or non-
radiological effluents released into the
environment from the ISFSI, or result in
the creation of solid waste. Moreover,
the approval of the initial and updated
DFPs will not authorize any construction
activity, facility modification, or
other land-disturbing activity. The NRC
staff has concluded that the proposed
action is a procedural and
administrative action that will not have
a significant impact on the environment.
Finding of No Significant The proposed action does not require
Impact. changes to the ISFSI's licensed routine
operations, maintenance activities, or
monitoring programs, nor does it require
new construction or land-disturbing
activities. The scope of the proposed
action concerns only the NRC's review
and approval of Florida Power & Light
Company's initial and NextEra Energy's
updated DFPs. The scope of the proposed
action does not include, and will not
result in, the review and approval of
decontamination or decommissioning
activities or license termination for
the ISFSI or for other parts of Duane
Arnold Energy Center. Therefore, the NRC
staff determined that approval of the
initial and updated DFPs for the Duane
Arnold Energy Center ISFSI will not
significantly affect the quality of the
human environment, and accordingly, the
staff has concluded that a FONSI is
appropriate. The NRC staff further finds
that preparation of an environmental
impact statement (EIS) is not required.
Available Documents.......... FPL, 2012. ISFSI DFPs, dated December 17,
2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for
Additional Information for Review of the
DFPs Regarding the ISFSI, dated August
12, 2014. ADAMS Accession No.
ML14225A655.
FPL, 2017. Decommissioning Funding Status
Reports/ISFSI Financial Assurance
Update, dated March 30, 2017. ADAMS
Accession No. ML17093A722.
FPL, 2018. Response to Request for
Additional Information Regarding Florida
Power & Light/NextEra Decommissioning
Funding Updates for ISFSI, dated April
3, 2018. ADAMS Accession No.
ML18095A057.
NextEra Energy, 2015. Decommissioning
Funding Status Reports/ISFSI Financial
Assurance Update, dated March 27, 2015.
ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/
08/31-NUREG-1748, ``Environmental Review
Guidance for Licensing Actions
Associated with NMSS Programs, Final
Report.'' Washington, DC, dated August
2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA
for Final Rule-Decommissioning Planning,
dated February 1, 2009. ADAMS Accession
No. ML090500648.
U.S. Nuclear Regulatory Commission.
Request for Additional Information for
Review of the DFPs for Florida Power &
Light and NextEra Energy ISFSIs, dated
May 23, 2014. ADAMS Accession No.
ML14143A141.
U.S. Nuclear Regulatory Commission.
Review of the Draft EA and FONSI for the
Duane Arnold Energy Center ISFSI DFP,
dated July 27, 2016. ADAMS Accession No.
ML16209A457.
U.S. Nuclear Regulatory Commission. Note
to File, Re: ESA Section 7 No Effect
Determination for ISFSI DFP Reviews,
dated May 15, 2017. ADAMS Accession No.
ML17135A062.
U.S. Nuclear Regulatory Commission.
Request for Additional Information
Regarding Florida Power & Light/NextEra
DFP Updates for St. Lucie, Units 1 and
2; Seabrook Station; Duane Arnold Energy
Center; and Point Beach, Units 1 and 2
ISFSIs, dated February 27, 2018. ADAMS
Package Accession No. ML18058A051.
U.S. Nuclear Regulatory Commission. Final
EA and FONSI for Florida Power & Light
Company's Initial and NextEra Energy's
Updated DFPs Submitted in Accordance
with 10 CFR 72.30(b) and (c) for Duane
Arnold Energy Center ISFSI, dated April
21, 2021. ADAMS Accession Package No.
ML21062A092.
Facility..................... Seabrook Station Unit No. 1
Docket Nos................... 72-63
Licensee..................... NextEra Energy Seabrook, LLC.
Proposed Action.............. The NRC's review and approval of Florida
Power & Light Company's initial and
NextEra Energy's updated DFPs submitted
in accordance with 10 CFR 72.30(b) and
(c).
Environmental Impact of The NRC staff has determined that the
Proposed Action. proposed action, the review and approval
of Florida Power & Light Company's
initial and NextEra Energy's updated
DFPs, submitted in accordance with 10
CFR 72.30(b) and (c), will not authorize
changes to licensed operations or
maintenance activities, or result in
changes in the types, characteristics,
or quantities of radiological or non-
radiological effluents released into the
environment from the ISFSI, or result in
the creation of solid waste. Moreover,
the approval of the initial and updated
DFPs will not authorize any construction
activity, facility modification, or
other land-disturbing activity. The NRC
staff has concluded that the proposed
action is a procedural and
administrative action that will not have
a significant impact on the environment.
[[Page 23756]]
Finding of No Significant The proposed action does not require
Impact. changes to the ISFSI's licensed routine
operations, maintenance activities, or
monitoring programs, nor does it require
new construction or land-disturbing
activities. The scope of the proposed
action concerns only the NRC's review
and approval of Florida Power & Light
Company's initial and NextEra Energy's
updated DFPs. The scope of the proposed
action does not include, and will not
result in, the review and approval of
decontamination or decommissioning
activities or license termination for
the ISFSI or for other parts of Seabrook
Station Unit No. 1. Therefore, the NRC
staff determined that approval of the
initial and updated DFPs for the
Seabrook Station Unit No. 1 ISFSI will
not significantly affect the quality of
the human environment, and accordingly,
the staff has concluded that a FONSI is
appropriate. The NRC staff further finds
that preparation of an environmental
impact statement (EIS) is not required.
Available Documents.......... FPL, 2012. ISFSI DFPs, dated December 17,
2012. ADAMS Accession No. ML12354A134.
FPL, 2014. Reply to Request for
Additional Information for Review of the
DFPs Regarding the ISFSI, dated August
12, 2014. ADAMS Accession No.
ML14225A655.
FPL, 2017. Decommissioning Funding Status
Reports/ISFSI Financial Assurance
Update, dated March 30, 2017. ADAMS
Accession No. ML17093A722.
FPL, 2018. Response to Request for
Additional Information Regarding Florida
Power & Light/NextEra Decommissioning
Funding Updates for ISFSI, dated April
3, 2018. ADAMS Accession No.
ML18095A057.
NextEra Energy, 2015. Decommissioning
Funding Status Reports/ISFSI Financial
Assurance Update, dated March 27, 2015.
ADAMS Accession No. ML15090A114.
U.S. Nuclear Regulatory Commission. 2003/
08/31-NUREG-1748, ``Environmental Review
Guidance for Licensing Actions
Associated with NMSS Programs, Final
Report.'' Washington, DC, dated August
2003. ADAMS Accession No. ML032540811.
U.S. Nuclear Regulatory Commission. EA
for Final Rule-Decommissioning Planning,
dated February 1, 2009. ADAMS Accession
No. ML090500648.
U.S. Nuclear Regulatory Commission.
Request for Additional Information for
Review of the DFPs for Florida Power &
Light and NextEra Energy ISFSIs, dated
May 23, 2014. ADAMS Accession No.
ML14143A141.
U.S. Nuclear Regulatory Commission. Note
to File, Re: ESA Section 7 No Effect
Determination for ISFSI DFP Reviews,
dated May 15, 2017. ADAMS Accession No.
ML17135A062.
U.S. Nuclear Regulatory Commission.
Review of the Draft EA and FONSI for the
Seabrook Station ISFSI DFP, dated August
17, 2017. ADAMS Accession No.
ML17226A329.
U.S. Nuclear Regulatory Commission.
Request for Additional Information
Regarding Florida Power & Light/NextEra
DFP Updates for St. Lucie, Units 1 and
2; Seabrook Station; Duane Arnold Energy
Center; and Point Beach, Units 1 and 2
ISFSIs, dated February 27, 2018. ADAMS
Package Accession No. ML18058A051.
U.S. Nuclear Regulatory Commission. Final
EA and FONSI for Florida Power & Light
Company's Initial and NextEra Energy's
Updated DFPs Submitted in Accordance
with 10 CFR 72.30(b) and (c) for
Seabrook Station Unit No. 1 ISFSI, dated
April 21, 2021. ADAMS Package Accession
No. ML21062A145.
------------------------------------------------------------------------
Dated: April 28, 2021.
For the Nuclear Regulatory Commission.
John B. McKirgan,
Chief, Storage and Transportation Licensing Branch, Division of Fuel
Management, Office of Nuclear Material Safety and Safeguards.
[FR Doc. 2021-09293 Filed 5-3-21; 8:45 am]