Green Mountain Power Corporation, City of Somersworth, New Hampshire; Notice of Intent To Prepare an Environmental Assessment, 22405 [2021-08830]

Download as PDF Federal Register / Vol. 86, No. 80 / Wednesday, April 28, 2021 / Notices 22405 FERC–516, ELECTRIC RATE SCHEDULES AND TARIFF FILINGS—Continued Requirements Total Burden for FERC–516 Number of respondents Annual number of responses per respondent Total number of responses Average burden & cost per response Total annual burden hours & cost Cost per respondent (1) (2) (1) x (2) = (3) (4) (3) * (4) = (5) (5) / (1) = (5) .................... .................... Comments: Comments are invited on: (1) Whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology. Dated: April 22, 2021. Kimberly D. Bose, Secretary. 6,396 does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to license the Lower Great Falls Project. The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission’s final licensing decision. The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate. Milestone Target date August 2021. 1 September 2021. Commission issues EA Comments on EA ......... [FR Doc. 2021–08828 Filed 4–27–21; 8:45 am] BILLING CODE 6717–01–P ............................... Any questions regarding this notice may be directed to Amanda Gill at (202) 502–6773 or amanda.gill@ferc.gov. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Dated: April 22, 2021. Kimberly D. Bose, Secretary. [Project No. 4451–024] [FR Doc. 2021–08830 Filed 4–27–21; 8:45 am] BILLING CODE 6717–01–P jbell on DSKJLSW7X2PROD with NOTICES Green Mountain Power Corporation, City of Somersworth, New Hampshire; Notice of Intent To Prepare an Environmental Assessment On April 30, 2020, Green Mountain Power Corporation and the City of Somersworth, New Hampshire filed an application for a subsequent license to continue operating the existing 1.28megawatt Lower Great Falls Hydroelectric Project No. 4451 (Lower Great Falls Project or project). The project is located on the Salmon Falls River in Strafford County, New Hampshire and York County, Maine. The project does not occupy federal land. In accordance with the Commission’s regulations, on February 10, 2021, Commission staff issued a notice that the project was ready for environmental analysis (REA notice). Based on the information in the record, including comments filed on the REA notice, staff VerDate Sep<11>2014 19:17 Apr 27, 2021 Jkt 253001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AD21–10–000] Modernizing Electricity Market Design Notice of Technical Conference on Resource Adequacy in the Evolving Electricity Sector: ISO New England Inc Take notice that the Federal Energy Regulatory Commission (Commission) will convene a Commissioner-led 1 The Council on Environmental Quality’s (CEQ) regulations under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 year of the federal action agency’s decision to prepare an EA. This notice establishes the Commission’s intent to prepare an EA for the Lower Great Falls Project. Therefore, in accordance with CEQ’s regulations, the EA must be issued within 1 year of the issuance date of this notice. PO 00000 Frm 00022 Fmt 4703 Sfmt 9990 502,987.66 hrs.; $41,747,945.07. 188,326.88 technical conference regarding wholesale markets administered by ISO New England Inc. in the abovereferenced proceeding on Tuesday, May 25, 2021, from approximately 9:00 a.m. to 5:00 p.m. Eastern time. The conference will be held remotely. The Commission will issue a supplemental notice providing the agenda for the technical conference. The conference will be open for the public to attend remotely. There is no fee for attendance. Information on this event will be posted on the Calendar of Events on the Commission’s website, www.ferc.gov, prior to the event. The conference will be transcribed. Transcripts will be available for a fee from Ace Reporting at (202) 347–3700. Commission conferences are accessible under section 508 of the Rehabilitation Act of 1973. For accessibility accommodations, please send an email to accessibility@ferc.gov or call toll free (866) 208–3372 (voice) or (202) 208–8659 (TTY), or send a fax to (202) 208–2106 with the required accommodations. For more information about this technical conference, please contact David Rosner at david.rosner@ferc.gov or (202) 502–8479, or Emma Nicholson at emma.nicholson@ferc.gov or (202) 502–8741. For legal information, please contact Meghan O’Brien at meghan.o’brien@ferc.gov or (202) 502– 6137. For information related to logistics, please contact Sarah McKinley at sarah.mckinley@ferc.gov or (202) 502–8368. Dated: April 22, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–08831 Filed 4–27–21; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\28APN1.SGM 28APN1

Agencies

[Federal Register Volume 86, Number 80 (Wednesday, April 28, 2021)]
[Notices]
[Page 22405]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-08830]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 4451-024]


Green Mountain Power Corporation, City of Somersworth, New 
Hampshire; Notice of Intent To Prepare an Environmental Assessment

    On April 30, 2020, Green Mountain Power Corporation and the City of 
Somersworth, New Hampshire filed an application for a subsequent 
license to continue operating the existing 1.28-megawatt Lower Great 
Falls Hydroelectric Project No. 4451 (Lower Great Falls Project or 
project). The project is located on the Salmon Falls River in Strafford 
County, New Hampshire and York County, Maine. The project does not 
occupy federal land.
    In accordance with the Commission's regulations, on February 10, 
2021, Commission staff issued a notice that the project was ready for 
environmental analysis (REA notice). Based on the information in the 
record, including comments filed on the REA notice, staff does not 
anticipate that licensing the project would constitute a major federal 
action significantly affecting the quality of the human environment. 
Therefore, staff intends to prepare an Environmental Assessment (EA) on 
the application to license the Lower Great Falls Project.
    The EA will be issued and circulated for review by all interested 
parties. All comments filed on the EA will be analyzed by staff and 
considered in the Commission's final licensing decision.
    The application will be processed according to the following 
schedule. Revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
              Milestone                           Target date
------------------------------------------------------------------------
Commission issues EA.................  August 2021. \1\
Comments on EA.......................  September 2021.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Amanda Gill 
at (202) 502-6773 or [email protected].
---------------------------------------------------------------------------

    \1\ The Council on Environmental Quality's (CEQ) regulations 
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 
year of the federal action agency's decision to prepare an EA. This 
notice establishes the Commission's intent to prepare an EA for the 
Lower Great Falls Project. Therefore, in accordance with CEQ's 
regulations, the EA must be issued within 1 year of the issuance 
date of this notice.

    Dated: April 22, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-08830 Filed 4-27-21; 8:45 am]