Transcontinental Gas Pipe Line Company, LLC; Notice of Request for Extension of Time, 20491 [2021-08071]
Download as PDF
Federal Register / Vol. 86, No. 74 / Tuesday, April 20, 2021 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–16–000]
Transcontinental Gas Pipe Line
Company, LLC; Notice of Request for
Extension of Time
Take notice that on April 12, 2021,
Transcontinental Gas Pipe Line
Company, LLC, (Transco) requested that
the Federal Energy Regulatory
Commission (Commission) grant an
extension of time, until May 1, 2023, to
complete, in part, approximately
thirteen miles of pipeline looping
needed to complete Phase III of its
Hillabee Expansion Project, as
authorized in the February 2, 2016
Order Issuing Certificates and
Approving Abandonment (February 2
Order).1 Ordering Paragraph (F)(1) of the
February 2 Order, as amended, provides
a deadline of May 1, 2021, for Transco
to construct the remaining facilities and
place them into service.2
Transco states that, due to unforeseen
delays caused by current economic
conditions, additional time is now
required in order to complete the
construction of the authorized project
facilities.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on the applicant’s request for
an extension of time may do so. No
reply comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).3
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
1 Florida Southeast Connection, LLC, et al., 154
FERC ¶ 61,080 (2016) (February 2 Order), order on
reh’g, Florida Southeast Connection, LLC, et al., 156
FERC ¶ 61,160 (2016), order on remand, Florida
Southeast Connection, LLC, et al., 162 FERC
¶ 61,233 (2018).
2 Florida Southeast Connection, LLC, et al., 156
FERC ¶ 61,160, P 50.
3 Only motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC ¶ 61,144, at P 39 (2020).
VerDate Sep<11>2014
17:10 Apr 19, 2021
Jkt 253001
contested,4 the Commission will aim to
issue an order acting on the request
within 45 days.5 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.6 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.7 At the time
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.8 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments in lieu of
paper using the ‘‘eFile’’ link at https://
www.ferc.gov. In lieu of electronic filing,
you may submit a paper copy.
Submissions sent via the U.S. Postal
Service must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier
4 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
5 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
6 Id. at P 40.
7 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
8 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
PO 00000
Frm 00016
Fmt 4703
Sfmt 9990
20491
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern
Time on April 29, 2021.
Dated: April 14, 2021.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2021–08071 Filed 4–19–21; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Numbers: RP21–543–001.
Applicants: Northwest Pipeline LLC.
Description: Compliance filing
Compliance Filing for Rate Schedule
TPAL to be effective 4/1/2021.
Filed Date: 4/12/21.
Accession Number: 20210412–5557.
Comments Due: 5 p.m. ET 4/26/21.
Docket Numbers: RP21–734–000.
Applicants: Sea Robin Pipeline
Company, LLC.
Description: § 4(d) Rate Filing:
Revised Fuel Percentage to be effective
6/1/2021.
Filed Date: 4/12/21.
Accession Number: 20210412–5781.
Comments Due: 5 p.m. ET 4/26/21.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: April 14, 2021.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2021–08070 Filed 4–19–21; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\20APN1.SGM
20APN1
Agencies
[Federal Register Volume 86, Number 74 (Tuesday, April 20, 2021)]
[Notices]
[Page 20491]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-08071]
[[Page 20491]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-16-000]
Transcontinental Gas Pipe Line Company, LLC; Notice of Request
for Extension of Time
Take notice that on April 12, 2021, Transcontinental Gas Pipe Line
Company, LLC, (Transco) requested that the Federal Energy Regulatory
Commission (Commission) grant an extension of time, until May 1, 2023,
to complete, in part, approximately thirteen miles of pipeline looping
needed to complete Phase III of its Hillabee Expansion Project, as
authorized in the February 2, 2016 Order Issuing Certificates and
Approving Abandonment (February 2 Order).\1\ Ordering Paragraph (F)(1)
of the February 2 Order, as amended, provides a deadline of May 1,
2021, for Transco to construct the remaining facilities and place them
into service.\2\
---------------------------------------------------------------------------
\1\ Florida Southeast Connection, LLC, et al., 154 FERC ] 61,080
(2016) (February 2 Order), order on reh'g, Florida Southeast
Connection, LLC, et al., 156 FERC ] 61,160 (2016), order on remand,
Florida Southeast Connection, LLC, et al., 162 FERC ] 61,233 (2018).
\2\ Florida Southeast Connection, LLC, et al., 156 FERC ]
61,160, P 50.
---------------------------------------------------------------------------
Transco states that, due to unforeseen delays caused by current
economic conditions, additional time is now required in order to
complete the construction of the authorized project facilities.
This notice establishes a 15-calendar day intervention and comment
period deadline. Any person wishing to comment on the applicant's
request for an extension of time may do so. No reply comments or
answers will be considered. If you wish to obtain legal status by
becoming a party to the proceedings for this request, you should, on or
before the comment date stated below, file a motion to intervene in
accordance with the requirements of the Commission's Rules of Practice
and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
Natural Gas Act (18 CFR 157.10).\3\
---------------------------------------------------------------------------
\3\ Only motions to intervene from entities that were party to
the underlying proceeding will be accepted. Algonquin Gas
Transmission, LLC, 170 FERC ] 61,144, at P 39 (2020).
---------------------------------------------------------------------------
As a matter of practice, the Commission itself generally acts on
requests for extensions of time to complete construction for Natural
Gas Act facilities when such requests are contested before order
issuance. For those extension requests that are contested,\4\ the
Commission will aim to issue an order acting on the request within 45
days.\5\ The Commission will address all arguments relating to whether
the applicant has demonstrated there is good cause to grant the
extension.\6\ The Commission will not consider arguments that re-
litigate the issuance of the certificate order, including whether the
Commission properly found the project to be in the public convenience
and necessity and whether the Commission's environmental analysis for
the certificate complied with the National Environmental Policy Act.\7\
At the time a pipeline requests an extension of time, orders on
certificates of public convenience and necessity are final and the
Commission will not re-litigate their issuance.\8\ The OEP Director, or
his or her designee, will act on all of those extension requests that
are uncontested.
---------------------------------------------------------------------------
\4\ Contested proceedings are those where an intervenor disputes
any material issue of the filing. 18 CFR 385.2201(c)(1) (2019).
\5\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
\6\ Id. at P 40.
\7\ Similarly, the Commission will not re-litigate the issuance
of an NGA section 3 authorization, including whether a proposed
project is not inconsistent with the public interest and whether the
Commission's environmental analysis for the permit order complied
with NEPA.
\8\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://www.ferc.gov) using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to Commission's Public Reference
Room, due to the proclamation declaring a National Emergency concerning
the Novel Coronavirus Disease (COVID-19), issued by the President on
March 13, 2020. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
The Commission strongly encourages electronic filings of comments
in lieu of paper using the ``eFile'' link at https://www.ferc.gov. In
lieu of electronic filing, you may submit a paper copy. Submissions
sent via the U.S. Postal Service must be addressed to: Kimberly D.
Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426. Submissions sent via any other
carrier must be addressed to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland
20852.
Comment Date: 5:00 p.m. Eastern Time on April 29, 2021.
Dated: April 14, 2021.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2021-08071 Filed 4-19-21; 8:45 am]
BILLING CODE 6717-01-P