Download as PDF 20132 Federal Register / Vol. 86, No. 72 / Friday, April 16, 2021 / Notices Dated: April 12, 2021. Juliana Pearson, PRA Coordinator, Strategic Collections and Clearance Governance and Strategy Division, Office of Chief Data Officer, Office of Planning, Evaluation and Policy Development. [FR Doc. 2021–07799 Filed 4–15–21; 8:45 am] BILLING CODE 4000–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–94–000] jbell on DSKJLSW7X2PROD with NOTICES Transcontinental Gas Pipe Line Company, LLC; Notice of Applcation and Establishing Intervention Deadline Take notice that on March 26, 2021, Transcontinental Gas Pipe Line Company, LLC (Transco), P.O. Box 1396, Houston, Texas 77251, filed in the above referenced docket an application pursuant to section 7(b) and 7(c) of the Natural Gas Act (NGA) and Parts 157 and 284 of the Commission’s regulations to construct, install, modify, operate and maintain its Regional Energy Access Expansion (REAE Project), an expansion of Transco’s existing pipeline system that will enable Transco to provide an additional 829,400 dekatherms per day of firm transportation service to shippers (Project Shippers), and to abandon certain compression facilities. Transco estimates that the REAE Project will cost approximately $950.05 million, all as more fully set forth in the request which is on file with the Commission and open to public inspection. Specifically, Transco proposes to: (1) Construct 22.3 miles of 30-inchdiameter pipeline in Luzerne County, Pennsylvania; (2) construct 13.8 miles of 42-inch-diameter pipeline in Monroe County, Pennsylvania; (3) construct the new 11,107 hp Compressor Station 201 in Gloucester County, New Jersey; (4) construct an additional 15,800 hp at its existing Compressor Station 505 in Somerset County, New Jersey; (5) construct an additional 46,742 hp at its existing Compressor Station 515 in Luzerne County, Pennsylvania; (6) increase the certificated station compression by 5,000 hp at its existing Compressor Station 195 in York County, Pennsylvania; (7) modify its existing Compressor Station 200 in Chester County, Pennsylvania; (8) increase the certificated station compression by 4,100 hp at its existing Compressor Station 207 in Middlesex County, New Jersey; and (9) additional modifications to tie-ins, regulators, and delivery meter VerDate Sep<11>2014 21:13 Apr 15, 2021 Jkt 253001 stations in Pennsylvania, New Jersey, and Maryland. Transco states that it has executed binding precedent agreements with the Project Shippers for 100% of the incremental firm transportation service under the REAE Project. Transco’s application states that a water quality certificate under section 401 of the Clean Water Act is required for the project from the Pennsylvania Department of Environmental Protection. The request for certification must be submitted to the certifying agency and to the Commission concurrently. Proof of the certifying agency’s receipt date must be filed no later than five (5) days after the request is submitted to the certifying agency. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions concerning this application should be directed to Nick Baumann, at (713) 215–3383, P.O. Box 1396, Houston, Texas 77251, or by email at nick.baumann@williams.com. Pursuant to section 157.9 of the Commission’s Rules of Practice and Procedure,1 within 90 days of this Notice the Commission staff will either: Complete its environmental review and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the 1 18 PO 00000 CFR (Code of Federal Regulations) § 157.9. Frm 00019 Fmt 4703 Sfmt 4703 completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Public Participation There are two ways to become involved in the Commission’s review of this project: You can file comments on the project, and you can file a motion to intervene in the proceeding. There is no fee or cost for filing comments or intervening. The deadline for filing a motion to intervene is 5:00 p.m. Eastern Time on April 30, 2021. Comments Any person wishing to comment on the project may do so. Comments may include statements of support or objections to the project as a whole or specific aspects of the project. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please submit your comments on or before April 30, 2021. There are three methods you can use to submit your comments to the Commission. In all instances, please reference the Project docket number (CP21–94–000) in your submission. (1) You may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project; (2) You may file your comments electronically by using the eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address below.2 Your written comments must reference the Project docket number (CP21–94–000). Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426 2 Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. E:\FR\FM\16APN1.SGM 16APN1 Federal Register / Vol. 86, No. 72 / Friday, April 16, 2021 / Notices jbell on DSKJLSW7X2PROD with NOTICES The Commission encourages electronic filing of comments (options 1 and 2 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Persons who comment on the environmental review of this project will be placed on the Commission’s environmental mailing list, and will receive notification when the environmental documents (EA or EIS) are issued for this project and will be notified of meetings associated with the Commission’s environmental review process. The Commission considers all comments received about the project in determining the appropriate action to be taken. However, the filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. For instructions on how to intervene, see below. Interventions Any person, which includes individuals, organizations, businesses, municipalities, and other entities,3 has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 4 and the regulations under the NGA 5 by the intervention deadline for the project, which is April 30, 2021. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the 3 18 CFR 385.102(d). CFR 385.214. 5 18 CFR 157.10. 4 18 VerDate Sep<11>2014 19:57 Apr 15, 2021 Jkt 253001 time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. There are two ways to submit your motion to intervene. In both instances, please reference the Project docket number (CP21–94–000) in your submission. (1) You may file your motion to intervene by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Intervention.’’ The eFiling feature includes a document-less intervention option; for more information, visit https://www.ferc.gov/docsfiling/efiling/ document-less-intervention.pdf; or (2) You can file a paper copy of your motion to intervene, along with three copies, by mailing the documents to the address below.6 Your motion to intervene must reference the Project docket number (CP21–94–000). Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426 The Commission encourages electronic filing of motions to intervene (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Motions to intervene must be served on the applicant either by mail or email at: P.O. Box 1396, Houston, Texas 77251, or by email at nick.baumann@ williams.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Service can be via email with a link to the document. All timely, unopposed 7 motions to intervene are automatically granted by operation of Rule 214(c)(1).8 Motions to 6 Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. 7 The applicant has 15 days from the submittal of a motion to intervene to file a written objection to the intervention. 8 18 CFR 385.214(c)(1). PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 20133 intervene that are filed after the intervention deadline are untimely, and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations.9 A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docsfiling/ esubscription.asp. Intervention Deadline: 5:00 p.m. Eastern Time on April 30, 2021. Dated: April 9, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–07866 Filed 4–15–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. IC21–16–000] Commission Information Collection Activities (FERC–582); Comment Request; Extension Federal Energy Regulatory Commission, Department of Energy. ACTION: Notice of information collection and request for comments. AGENCY: In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal SUMMARY: 9 18 E:\FR\FM\16APN1.SGM CFR 385.214(b)(3) and (d). 16APN1

Agencies

[Federal Register Volume 86, Number 72 (Friday, April 16, 2021)]
[Notices]
[Pages 20132-20133]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-07866]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP21-94-000]


Transcontinental Gas Pipe Line Company, LLC; Notice of Applcation 
and Establishing Intervention Deadline

    Take notice that on March 26, 2021, Transcontinental Gas Pipe Line 
Company, LLC (Transco), P.O. Box 1396, Houston, Texas 77251, filed in 
the above referenced docket an application pursuant to section 7(b) and 
7(c) of the Natural Gas Act (NGA) and Parts 157 and 284 of the 
Commission's regulations to construct, install, modify, operate and 
maintain its Regional Energy Access Expansion (REAE Project), an 
expansion of Transco's existing pipeline system that will enable 
Transco to provide an additional 829,400 dekatherms per day of firm 
transportation service to shippers (Project Shippers), and to abandon 
certain compression facilities. Transco estimates that the REAE Project 
will cost approximately $950.05 million, all as more fully set forth in 
the request which is on file with the Commission and open to public 
inspection.
    Specifically, Transco proposes to: (1) Construct 22.3 miles of 30-
inch-diameter pipeline in Luzerne County, Pennsylvania; (2) construct 
13.8 miles of 42-inch-diameter pipeline in Monroe County, Pennsylvania; 
(3) construct the new 11,107 hp Compressor Station 201 in Gloucester 
County, New Jersey; (4) construct an additional 15,800 hp at its 
existing Compressor Station 505 in Somerset County, New Jersey; (5) 
construct an additional 46,742 hp at its existing Compressor Station 
515 in Luzerne County, Pennsylvania; (6) increase the certificated 
station compression by 5,000 hp at its existing Compressor Station 195 
in York County, Pennsylvania; (7) modify its existing Compressor 
Station 200 in Chester County, Pennsylvania; (8) increase the 
certificated station compression by 4,100 hp at its existing Compressor 
Station 207 in Middlesex County, New Jersey; and (9) additional 
modifications to tie-ins, regulators, and delivery meter stations in 
Pennsylvania, New Jersey, and Maryland. Transco states that it has 
executed binding precedent agreements with the Project Shippers for 
100% of the incremental firm transportation service under the REAE 
Project.
    Transco's application states that a water quality certificate under 
section 401 of the Clean Water Act is required for the project from the 
Pennsylvania Department of Environmental Protection. The request for 
certification must be submitted to the certifying agency and to the 
Commission concurrently. Proof of the certifying agency's receipt date 
must be filed no later than five (5) days after the request is 
submitted to the certifying agency.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact the Federal Energy 
Regulatory Commission at [email protected] or call toll-free, 
(886) 208-3676 or TYY, (202) 502-8659.
    Any questions concerning this application should be directed to 
Nick Baumann, at (713) 215-3383, P.O. Box 1396, Houston, Texas 77251, 
or by email at [email protected].
    Pursuant to section 157.9 of the Commission's Rules of Practice and 
Procedure,\1\ within 90 days of this Notice the Commission staff will 
either: Complete its environmental review and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or environmental 
assessment (EA) for this proposal. The filing of an EA in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
---------------------------------------------------------------------------

    \1\ 18 CFR (Code of Federal Regulations) Sec.  157.9.
---------------------------------------------------------------------------

Public Participation

    There are two ways to become involved in the Commission's review of 
this project: You can file comments on the project, and you can file a 
motion to intervene in the proceeding. There is no fee or cost for 
filing comments or intervening. The deadline for filing a motion to 
intervene is 5:00 p.m. Eastern Time on April 30, 2021.

Comments

    Any person wishing to comment on the project may do so. Comments 
may include statements of support or objections to the project as a 
whole or specific aspects of the project. The more specific your 
comments, the more useful they will be. To ensure that your comments 
are timely and properly recorded, please submit your comments on or 
before April 30, 2021.
    There are three methods you can use to submit your comments to the 
Commission. In all instances, please reference the Project docket 
number (CP21-94-000) in your submission.
    (1) You may file your comments electronically by using the eComment 
feature, which is located on the Commission's website at www.ferc.gov 
under the link to Documents and Filings. Using eComment is an easy 
method for interested persons to submit brief, text-only comments on a 
project;
    (2) You may file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. With eFiling, you can provide 
comments in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; first select ``General'' and then select ``Comment on a 
Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address below.\2\ Your written comments must reference 
the Project docket number (CP21-94-000).
---------------------------------------------------------------------------

    \2\ Hand delivered submissions in docketed proceedings should be 
delivered to Health and Human Services, 12225 Wilkins Avenue, 
Rockville, Maryland 20852.

Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
---------------------------------------------------------------------------
First Street NE, Washington, DC 20426


[[Page 20133]]


    The Commission encourages electronic filing of comments (options 1 
and 2 above) and has eFiling staff available to assist you at (202) 
502-8258 or [email protected]
    Persons who comment on the environmental review of this project 
will be placed on the Commission's environmental mailing list, and will 
receive notification when the environmental documents (EA or EIS) are 
issued for this project and will be notified of meetings associated 
with the Commission's environmental review process.
    The Commission considers all comments received about the project in 
determining the appropriate action to be taken. However, the filing of 
a comment alone will not serve to make the filer a party to the 
proceeding. To become a party, you must intervene in the proceeding. 
For instructions on how to intervene, see below.

Interventions

    Any person, which includes individuals, organizations, businesses, 
municipalities, and other entities,\3\ has the option to file a motion 
to intervene in this proceeding. Only intervenors have the right to 
request rehearing of Commission orders issued in this proceeding and to 
subsequently challenge the Commission's orders in the U.S. Circuit 
Courts of Appeal.
---------------------------------------------------------------------------

    \3\ 18 CFR 385.102(d).
---------------------------------------------------------------------------

    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \4\ and the regulations under the NGA \5\ by the 
intervention deadline for the project, which is April 30, 2021. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \4\ 18 CFR 385.214.
    \5\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.
    There are two ways to submit your motion to intervene. In both 
instances, please reference the Project docket number (CP21-94-000) in 
your submission.
    (1) You may file your motion to intervene by using the Commission's 
eFiling feature, which is located on the Commission's website 
(www.ferc.gov) under the link to Documents and Filings. New eFiling 
users must first create an account by clicking on ``eRegister.'' You 
will be asked to select the type of filing you are making; first select 
``General'' and then select ``Intervention.'' The eFiling feature 
includes a document-less intervention option; for more information, 
visit https://www.ferc.gov/docsfiling/efiling/document-less-intervention.pdf; or
    (2) You can file a paper copy of your motion to intervene, along 
with three copies, by mailing the documents to the address below.\6\ 
Your motion to intervene must reference the Project docket number 
(CP21-94-000).

Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Washington, DC 20426

    \6\ Hand delivered submissions in docketed proceedings should be 
delivered to Health and Human Services, 12225 Wilkins Avenue, 
Rockville, Maryland 20852.
---------------------------------------------------------------------------

    The Commission encourages electronic filing of motions to intervene 
(option 1 above) and has eFiling staff available to assist you at (202) 
502-8258 or [email protected]
    Motions to intervene must be served on the applicant either by mail 
or email at: P.O. Box 1396, Houston, Texas 77251, or by email at 
[email protected]. Any subsequent submissions by an intervenor 
must be served on the applicant and all other parties to the 
proceeding. Contact information for parties can be downloaded from the 
service list at the eService link on FERC Online. Service can be via 
email with a link to the document.
    All timely, unopposed \7\ motions to intervene are automatically 
granted by operation of Rule 214(c)(1).\8\ Motions to intervene that 
are filed after the intervention deadline are untimely, and may be 
denied. Any late-filed motion to intervene must show good cause for 
being late and must explain why the time limitation should be waived 
and provide justification by reference to factors set forth in Rule 
214(d) of the Commission's Rules and Regulations.\9\ A person obtaining 
party status will be placed on the service list maintained by the 
Secretary of the Commission and will receive copies (paper or 
electronic) of all documents filed by the applicant and by all other 
parties.
---------------------------------------------------------------------------

    \7\ The applicant has 15 days from the submittal of a motion to 
intervene to file a written objection to the intervention.
    \8\ 18 CFR 385.214(c)(1).
    \9\ 18 CFR 385.214(b)(3) and (d).
---------------------------------------------------------------------------

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docsfiling/esubscription.asp.
    Intervention Deadline: 5:00 p.m. Eastern Time on April 30, 2021.

    Dated: April 9, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-07866 Filed 4-15-21; 8:45 am]
BILLING CODE 6717-01-P