Download as PDF 16592 Federal Register / Vol. 86, No. 59 / Tuesday, March 30, 2021 / Notices is hereby given that on April 15, 2021, the eXtensible Business Reporting Language (XBRL) taxonomies, validation rules, and rendering files needed to file FERC Form Nos. 1, 1–F, 3–Q (electric), 2, 2–A, 3–Q (natural gas), 6, 6–Q (oil), 60, and 714 (collectively, Commission Forms),1 will be updated to Release 1.5.2 The updated taxonomies will be available in the Yeti viewer at https://xbrlview.ferc.gov/.3 The updated validation rules and rendering files will be available at https://www.ferc.gov/ ferc-online/ferc-online/filing-forms/ eforms-refresh. The eForms system will incorporate the updated (Release 1.5) taxonomies, validation rules, and rendering files and use them to process filers’ test-only submissions in May 2021. In addition, as noted below, the deadlines for submitting the third quarter 2021 filings of FERC Form Nos. 3–Q (electric), 3–Q (natural gas), and 6–Q (oil) are extended until December 31, 2021. The updated (Release 1.5) taxonomies, validation rules, and rendering files will become effective beginning with the third quarter 2021 filings of FERC Form Nos. 3–Q (electric), 3–Q (natural gas), and 6–Q (oil). The current Visual FoxPro-based system for filing Commission Forms will no longer be available for submissions after September 30, 2021. Therefore, all subsequent filings and any future refilings, i.e., all post-September 30, 2021 filings and refilings, of the FERC Form Nos. 3–Q (electric), 3–Q (natural gas), and 6–Q (oil) and the other Commission Forms (i.e., FERC Form Nos. 1, 1–F, 2, 2–A, 6, 60, and 714) must be made using the applicable taxonomies, validation rules, and rendering files for the relevant form, as indicated on the eForms portal. To provide the additional time necessary to complete the transition to an XBRL-based system, the deadlines for the third quarter filings of the FERC jbell on DSKJLSW7X2PROD with NOTICES 1 The Commission adopted the XBRL process for filing the Commission Forms in Order No. 859. Revisions to the Filing Process for Comm’n Forms, Order No. 859, 167 FERC ¶ 61,241 (2019). 2 The Commission adopted the final XBRL taxonomy, protocols, implementation guide, and other supporting documents, and established the implementation schedule for filing the Commission Forms following a technical conference in this proceeding. Revisions to the Filing Process for Comm’n Forms, 172 FERC ¶ 61,059 (2020). The Commission also stated that technical updates, such as the updates referenced here, will not take effect until at least 60 days after issuance of a notice from the Office of the Secretary. Id. P 26. 3 These technical updates incorporate feedback on the taxonomies submitted by interested parties through various means, including the Yeti review tool. VerDate Sep<11>2014 17:59 Mar 29, 2021 Jkt 253001 Form Nos. 3–Q (electric), 3–Q (natural gas), and 6–Q (oil) are hereby extended. Accordingly, the deadline for filing the FERC Form No. 3–Q (electric) for Major Electric Utilities, Licensees, and Others for the third quarter of 2021 is extended from November 29, 2021 until December 31, 2021. The deadline for filing the FERC Form No. 3–Q (electric) for Non-major Public Utilities and Licensees for the third quarter of 2021 is extended from December 9, 2021 until December 31, 2021. In addition, the deadline for filing the FERC Form No. 3–Q (natural gas) for Major Natural Gas Companies for the third quarter of 2021 is extended from November 29, 2021 until December 31, 2021. The deadline for filing the FERC Form No. 3–Q (natural gas) for Nonmajor Gas Companies for the third quarter of 2021 is extended from December 9, 2021 until December 31, 2021. Finally, the deadline for filing the FERC Form No. 6–Q (oil) for Oil Pipeline Companies for the third quarter of 2021 is extended from December 9, 2021 until December 31, 2021. Dated: March 23, 2021. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2021–06477 Filed 3–29–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 6731–000[ Coneross Power Corporation; Notice of Authorization for Continued Project Operation On February 28, 2019 Coneross Power Corporation, licensee for the Coneross Hydroelectric Project, filed an Application for a New License pursuant to the Federal Power Act (FPA) and the Commission’s regulations thereunder. The Coneross Hydroelectric Project is on the Coneross Creek, in Oconee County, South Carolina The license for Project No.6731 was issued for a period ending February 28, 2021. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No.6731 is issued to the Coneross Power Corporation for a period effective March 1, 2021 through February 28, 2022, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before February 2022, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that the Coneross Power Corporation, is authorized to continue operation of the Coneross Hydroelectric Project, until such time as the Commission acts on its application for a subsequent license. Dated: March 24, 2021. Kimberly D. Bose, Secretary. [FR Doc. 2021–06511 Filed 3–29–21; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC21–67–000. Applicants: Ventura Energy Storage, LLC. Description: Application for Authorization Under Section 203 of the Federal Power Act of Ventura Energy Storage, LLC. Filed Date: 3/22/21. E:\FR\FM\30MRN1.SGM 30MRN1

Agencies

[Federal Register Volume 86, Number 59 (Tuesday, March 30, 2021)]
[Notices]
[Page 16592]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-06511]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 6731-000[


Coneross Power Corporation; Notice of Authorization for Continued 
Project Operation

    On February 28, 2019 Coneross Power Corporation, licensee for the 
Coneross Hydroelectric Project, filed an Application for a New License 
pursuant to the Federal Power Act (FPA) and the Commission's 
regulations thereunder. The Coneross Hydroelectric Project is on the 
Coneross Creek, in Oconee County, South Carolina
    The license for Project No.6731 was issued for a period ending 
February 28, 2021. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year-to-year an annual license to the then licensee under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA. If the project's prior 
license waived the applicability of section 15 of the FPA, then, based 
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), 
and as set forth at 18 CFR 16.21(a), if the licensee of such project 
has filed an application for a subsequent license, the licensee may 
continue to operate the project in accordance with the terms and 
conditions of the license after the minor or minor part license 
expires, until the Commission acts on its application. If the licensee 
of such a project has not filed an application for a subsequent 
license, then it may be required, pursuant to 18 CFR 16.21(b), to 
continue project operations until the Commission issues someone else a 
license for the project or otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No.6731 is issued to 
the Coneross Power Corporation for a period effective March 1, 2021 
through February 28, 2022, or until the issuance of a new license for 
the project or other disposition under the FPA, whichever comes first. 
If issuance of a new license (or other disposition) does not take place 
on or before February 2022, notice is hereby given that, pursuant to 18 
CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is 
renewed automatically without further order or notice by the 
Commission, unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that the Coneross Power Corporation, is authorized to 
continue operation of the Coneross Hydroelectric Project, until such 
time as the Commission acts on its application for a subsequent 
license.

    Dated: March 24, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-06511 Filed 3-29-21; 8:45 am]
BILLING CODE 6717-01-P